ML17170A091: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 21: | Line 21: | ||
NUCLEAR REGULATORY COMMISSION | NUCLEAR REGULATORY COMMISSION | ||
REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX | REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX | ||
76011-4511 June 19, | 76011-4511 June 19, 201 7 Mr. Fadi Diya, Senior Vice President | ||
and Chief Nuclear Officer | and Chief Nuclear Officer | ||
Ameren Missouri | Ameren Missouri | ||
| Line 37: | Line 37: | ||
Callaway Plant | Callaway Plant | ||
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors from the NRC | from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors from the NRC | ||
's Region IV | 's Region IV office, plus one of the assigned Resident Inspectors at the Callaway Plant for one week. The inspection will be conducted in accordance with | ||
the NRC's Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi | |||
. The inspection will be conducted in accordance with | |||
the NRC's Temporary Instruction 2515/191 | |||
, "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi | |||
-Unit Dose Assessment Plans." | -Unit Dose Assessment Plans." | ||
Experience has shown that this inspection is resource intensive both for the NRC inspectors | Experience has shown that this inspection is resource intensive both for the NRC inspectors | ||
| Line 50: | Line 47: | ||
. During the onsite inspection, inspectors will verify that plans for complying with NRC Orders | . During the onsite inspection, inspectors will verify that plans for complying with NRC Orders | ||
EA-12-049 and EA | EA-12-049 and EA | ||
-12-051 are in place and are being implemented. Inspectors will also verify the establishment of staffing and communications plans provided in response to the March 12, 2012, request for information letter, and multi | -12-051 are in place and are being implemented. Inspectors will also verify the establishment of staffing and communications plans provided in response to the March 12, 2012, request for information letter, and multi-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in the site specific submittals, which were subsequently reviewed by the NRC staff for | ||
-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in the site specific submittals, which were subsequently reviewed by the NRC staff for | |||
understanding and documented in the NRC's plant safety evaluations (SEs) and safety | understanding and documented in the NRC's plant safety evaluations (SEs) and safety | ||
assessments. Therefore, | assessments. Therefore, appropriate personnel knowledgeable of | ||
the station's FLEX | the station's FLEX | ||
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements | strategies, spent fuel pool instrumentation, and emergency preparedness enhancements | ||
should be available to support the inspector | should be available to support the inspector s at the site during the inspection. | ||
s at the site during the inspection. | |||
| Line 65: | Line 59: | ||
y with your staff and understand that our regulatory contact for this inspection will be | y with your staff and understand that our regulatory contact for this inspection will be | ||
Elizabeth Ptasznik | Elizabeth Ptasznik | ||
of your licensing organization. If there are any questions about this inspection or the material requested, please contact the | of your licensing organization. If there are any questions about this inspection or the material requested, please contact the l ead inspector , Ryan D. Alexander | ||
, Ryan D. Alexander | |||
, by telephone | , by telephone | ||
at 817-200-1195 or by e-mail at ryan.alexander@nrc.gov. | at 817-200-1195 or by e-mail at ryan.alexander@nrc.gov. | ||
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection | ||
requirements were approved by the Office of Management and Budget, control number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control | requirements were approved by the Office of Management and Budget, control number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control | ||
| Line 77: | Line 69: | ||
-rm/adams.html | -rm/adams.html | ||
(the Public Electronic Reading Room). | (the Public Electronic Reading Room). | ||
Sincerely, | Sincerely, /RA/ John L. Dixon , Acting Chief Project Branch B | ||
Division of Reactor Projects | Division of Reactor Projects | ||
Docket No. 50 | Docket No. 50 | ||
-483 License No. NPF | -483 License No. NPF | ||
-30 | -30 | ||
Enclosure | Enclosure: FLEX Strategies, Spent Fuel Pool | ||
: FLEX Strategies, Spent Fuel Pool | |||
Instrumentation | Instrumentation | ||
, & EP Enhancements | , & EP Enhancements | ||
| Line 90: | Line 80: | ||
Request for Information | Request for Information | ||
1 Enclosure | 1 Enclosure Request for Information | ||
FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements | FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements | ||
Inspection | Inspection | ||
Callaway Plant | Callaway Plant | ||
Inspection Report: | Inspection Report: | ||
050004 83/2017 008 Inspection Dates: | |||
August 28 | August 28 | ||
- September 1 | - September 1 | ||
, 2017 | , 2017 | ||
Inspection Procedure: | Inspection Procedure: | ||
Temporary Instruction 2515/191 | Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi | ||
, "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi | |||
-Unit Dose Assessment Plans" | -Unit Dose Assessment Plans" | ||
Inspect o r s: Ryan D. Alexander | |||
, Team Lead, Sr. | , Team Lead, Sr. | ||
Project Engineer, Region IV | Project Engineer, Region IV | ||
Dan Bradley | Dan Bradley , Callaway Plant | ||
, Callaway Plant | |||
Senior Resident Inspector | Senior Resident Inspector | ||
Steve Alferink, Reactor Inspector, Region IV | Steve Alferink, Reactor Inspector, Region IV | ||
| Line 116: | Line 103: | ||
The following information should be sent to the Region IV office in hard copy or electronic format (use of the Certrec IMS | The following information should be sent to the Region IV office in hard copy or electronic format (use of the Certrec IMS | ||
information portal is preferred), to the attention | information portal is preferred), to the attention | ||
of Ryan Alexander | of Ryan Alexander , by August 11, 2017. The inspector s will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week. Also, we request that you categorize the documents in your response with the numbered list below. | ||
, by August 11, 2017. The inspector | |||
s will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week. Also, we request that you categorize the documents in your response with the numbered list below. | |||
Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the | Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the | ||
lead inspector, and provide | lead inspector, and provide | ||
| Line 126: | Line 111: | ||
- Appendix A | - Appendix A | ||
A. Provide current revision of the FLEX Final Integrated Plan | A. Provide current revision of the FLEX Final Integrated Plan | ||
(i.e., current FLEX Program Document), including any revisions since July 2016 | (i.e., current FLEX Program Document), including any revisions since July 2016 submission to the NRC | ||
. B. Provide the FLEX Strategy Basis Document. | . B. Provide the FLEX Strategy Basis Document. | ||
C. Provide each operating, off | C. Provide each operating, off | ||
| Line 188: | Line 172: | ||
K. Provide documents/procedures | K. Provide documents/procedures | ||
which describe the programmatic controls in place | which describe the programmatic controls in place | ||
to ensure that if equipment and applicable connections are unavailable (e.g., due to maintenance | to ensure that if equipment and applicable connections are unavailable (e.g., due to maintenance , non-functionality), then compensatory measures are implemented in accordance with guidance outlined NEI 12 | ||
, non-functionality), then compensatory measures are implemented in accordance with guidance outlined NEI 12 | |||
-06. L. Provide the station | -06. L. Provide the station | ||
-specific National SAFER Center "Playbook" | -specific National SAFER Center "Playbook" | ||
| Line 201: | Line 184: | ||
during the onsite inspection week.] | during the onsite inspection week.] | ||
N. A current copy of administrative procedure(s) for the CAP, modification program, operations | N. A current copy of administrative procedure(s) for the CAP, modification program, operations | ||
procedure writing and implementation, and top | procedure writing and implementation, and top-level documents for the work control and work scheduling programs. | ||
-level documents for the work control and work scheduling programs. | |||
(If FLEX related procedures such as FSGs or the FIP are maintained under a different process | (If FLEX related procedures such as FSGs or the FIP are maintained under a different process | ||
, please include copies of those | , please include copies of those | ||
| Line 212: | Line 194: | ||
TI 2515/191 | TI 2515/191 | ||
- Appendix B | - Appendix B | ||
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the primary and backup Spent Fuel Pool (SFP) | R. Provide the procedures implemented for maintenance, testing, calibration, and use of the primary and backup Spent Fuel Pool (SFP) instrumentation channels. | ||
S. Provide lesson plans/training documents which describe the training program that address the use, maintenance, calibration, surveillance, and the use of alternate power to the primary and backup SFP instrument channels. | S. Provide lesson plans/training documents which describe the training program that address the use, maintenance, calibration, surveillance, and the use of alternate power to the primary and backup SFP instrument channels. | ||
| Line 231: | Line 212: | ||
to demonstrate the ERO's ability to utilize the communications systems and/or equipment. | to demonstrate the ERO's ability to utilize the communications systems and/or equipment. | ||
V. Provide documents and procedures which show that your dose | V. Provide documents and procedures which show that your dose | ||
assessment is capable of analyzing concurrent radiological releases from all on-site significant sources, including | assessment is capable of analyzing concurrent radiological releases from all on-site significant sources, including releases from spent fuel pools (i.e., multi | ||
-unit/multi | -unit/multi | ||
-source dose assessment capability) | -source dose assessment capability) | ||
. Lead Inspector Contact Information: | . Lead Inspector Contact Information: | ||
Ryan D. Alexander | Ryan D. Alexander , Sr. Project Engineer | ||
, Sr. Project Engineer | |||
Mailing Address | Mailing Address | ||
: 817-200- | : 817-200-11 95 U.S. NRC, Region IV | ||
Ryan.Alexander@nrc.gov | Ryan.Alexander@nrc.gov | ||
Attn: Ryan Alexander, DRP | Attn: Ryan Alexander, DRP | ||
| Line 248: | Line 227: | ||
ML17170A091 | ML17170A091 | ||
SUNSI Review By: RDA/rdr ADAMS: Yes No Sensitive | SUNSI Review By: RDA/rdr ADAMS: Yes No Sensitive | ||
Non-Sensitive | Non-Sensitive Non-Publicly Available | ||
Publicly Available | Publicly Available | ||
Keyword NRC-002 OFFICE DRP/RPBA C:DRP/RPBB | Keyword NRC-002 OFFICE DRP/RPBA C:DRP/RPBB | ||
NAME RAlexander | NAME RAlexander | ||
JDixon SIGNATURE | JDixon SIGNATURE /RA/-E /RA/ DATE 06/14/2017 | ||
06/19/2017 | 06/19/2017 | ||
}} | }} | ||
Revision as of 19:33, 7 July 2018
| ML17170A091 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 06/19/2017 |
| From: | Alexander R D, Dixon J L NRC/RGN-IV/DRP/RPB-B |
| To: | Diya F Ameren Corp |
| Dixon J L | |
| References | |
| TI-2515/191 IR 2017008 | |
| Download: ML17170A091 (7) | |
See also: IR 05000483/2017008
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX
76011-4511 June 19, 201 7 Mr. Fadi Diya, Senior Vice President
and Chief Nuclear Officer
Ameren Missouri
Callaway Plant
P.O. Box 620 Fulton, MO 65251
SUBJECT: CALLAWAY PLANT - NOTIFICATION OF NRC INSPECTION OF THE IMPLEMENTATION OF MITIGATION STRATEGIES AND SPENT FUEL POOL
INSTRUMENTATION ORDERS AND EMERGENCY PREPAREDNESS
COMMUNICATION/
STAFFING/MULTI
-UNIT DOSE ASSESSMENT PLANS
(05000483/2017008) AND REQUEST FOR INFORMATION
Dear Mr. Diya: The purpose of this letter is to notify you that
the U.S. Nuclear Regulatory Commission (NRC) staff will conduct a mitigation strategies for beyond
-design-basis external events, spent fuel pool instrumentation, and emergency preparedness enhancements inspection at the
Callaway Plant
from August 28 - September 1, 2017. The inspection will consist of three reactor inspectors from the NRC
's Region IV office, plus one of the assigned Resident Inspectors at the Callaway Plant for one week. The inspection will be conducted in accordance with
the NRC's Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi
-Unit Dose Assessment Plans."
Experience has shown that this inspection is resource intensive both for the NRC inspectors
and licensee staff. In order to minimize the impact to your onsite resources and to ensure a productive inspection, we have enclosed a request for documents needed for this inspection
activity. Please note that the documents
are requested to be provided by
August 11, 2017
. During the onsite inspection, inspectors will verify that plans for complying with NRC Orders
-12-051 are in place and are being implemented. Inspectors will also verify the establishment of staffing and communications plans provided in response to the March 12, 2012, request for information letter, and multi-unit dose assessment information provided per COMSECY-13-0010, Schedule and Plans for Tier 2 Order on Emergency Preparedness for Japan Lessons Learned, dated March 27, 2013. These plans and information were provided in the site specific submittals, which were subsequently reviewed by the NRC staff for
understanding and documented in the NRC's plant safety evaluations (SEs) and safety
assessments. Therefore, appropriate personnel knowledgeable of
the station's FLEX
strategies, spent fuel pool instrumentation, and emergency preparedness enhancements
should be available to support the inspector s at the site during the inspection.
F. Diya 2 We have discussed the schedule for th
is inspection activit
y with your staff and understand that our regulatory contact for this inspection will be
Elizabeth Ptasznik
of your licensing organization. If there are any questions about this inspection or the material requested, please contact the l ead inspector , Ryan D. Alexander
, by telephone
at 817-200-1195 or by e-mail at ryan.alexander@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, control number 3150 0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC
's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html
(the Public Electronic Reading Room).
Sincerely, /RA/ John L. Dixon , Acting Chief Project Branch B
Division of Reactor Projects
Docket No. 50
-483 License No. NPF
-30
Enclosure: FLEX Strategies, Spent Fuel Pool
Instrumentation
, & EP Enhancements
Inspection
Request for Information
1 Enclosure Request for Information
FLEX Strategies, Spent Fuel Pool Instrumentation, & EP Enhancements
Inspection
Callaway Plant
Inspection Report:
050004 83/2017 008 Inspection Dates:
August 28
- September 1
, 2017
Inspection Procedure:
Temporary Instruction 2515/191 , "Inspection of the Implementation of Mitigating Strategies and Spent Fuel Pool Instrumentation Orders, and Emergency Preparedness Communication/Staffing/Multi
-Unit Dose Assessment Plans"
Inspect o r s: Ryan D. Alexander
, Team Lead, Sr.
Project Engineer, Region IV
Dan Bradley , Callaway Plant
Senior Resident Inspector
Steve Alferink, Reactor Inspector, Region IV
Michael Stafford, Project Engineer, Region IV
Information Requested for the In-Office Preparation Week
The following information should be sent to the Region IV office in hard copy or electronic format (use of the Certrec IMS
information portal is preferred), to the attention
of Ryan Alexander , by August 11, 2017. The inspector s will select specific items from the information requested below and then request from your staff additional documents needed during the onsite inspection week. Also, we request that you categorize the documents in your response with the numbered list below.
Please provide requested documentation electronically if possible. If requested documents are large and only hard copy formats are available, please inform the
lead inspector, and provide
subject documentation during the first day of the onsite inspection. If you have any questions regarding this information request, please call the lead
inspector as soon as possible.
- Appendix A
A. Provide current revision of the FLEX Final Integrated Plan
(i.e., current FLEX Program Document), including any revisions since July 2016 submission to the NRC
. B. Provide the FLEX Strategy Basis Document.
C. Provide each operating, off
-normal, abnormal, and/or emergency procedures where entry into one or more
FLEX Support Guideline(s) are initiated
. D. Provide a list
and copies of every FLEX Support Guideline (FSG) or equivalent procedure which you developed or revised to implement your mitigating strategies.
E. Provide a list of key piece
s of equipment that directly perform a FLEX mitigation strategy for core cooling (RCS and Steam Generators), containment, and/or spent fuel pool
cooling. F. Provide a listing/summaries
of plant modifications completed related to the FLEX program.
G. Provide a listing of calculations, evaluations, and 50.59 reviews related to the FLEX program
and modifications
.
2 H. Applicable site specific hazards for the Callaway Plant
- 1) Provide documents which show the locations and configuration of structure(s) which store FLEX equipment
. 2) Seismic (a) Provide the travel route(s) for FLEX equipment from storage location(s) to their location(s) of use, AND evaluation(s) which demonstrate that for the potential for soil liquefaction is not of a concern for these travel route(s).
(b) Seismic concerns for water source(s)
(1) If the FLEX water sources are seismically robust, then provide the assessment that shows that they are.
(2) If the FLEX water sources are not seismically robust, then provide:
(a) an assessment of alternate water sources, and
(b) the procedure(s) which describe when and how to access those sources.
3) External Flooding {"Screened Out
" for Callaway Plant
- no documents requested}
4) Severe storms with high winds
(a) Provide evaluation/evidence as to how FLEX equipment is stored relative to protection from severe storms with high winds:
(1) In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety
-related structure); OR
(2) In a structure that meets the design requirements as described in ASCE 7-10, "Minimum Design Loads for Buildings and Other Structures," given the limiting tornado wind speeds
from Regulatory Guide 1.76, and/or design
-basis hurricane wind speeds.
(b) Provide pathways via which you plan to move FLEX equipment from onsite storage areas to final deployment locations.
(1) Show how you designated and evaluated those pathways for post
-storm accessibility for staging and connecting FLEX equipment.
5) Snow, Ice, and Extreme Cold
For each key piece of equipment described in Item 5
(above) that directly performs or implements a FLEX mitigation strategy:
(a) Provide procedures/documents
demonstrating that the FLEX equipment is maintained at a temperature within a range to ensure that it will function when called
upon. (b) Provide procedures/documents
demonstrating how the FLEX equipment can be moved from the storage location to its deployment location during extreme snowfall and ice storms.
3 6) Extreme high temperatures
For each key piece of equipment described in Item
5 (above) that directly performs or implements a FLEX mitigation strategy
- (a) Provide procedures/documents
which describes the high
-temperature limit of the range within which the equipment will function.
(b) Provide procedures/documents
which describe how the equipment is maintained below that limit in its storage location.
I. Provide the station
-specific FLEX strategies time validation study(ies)
. J. Provide the relevant station procedure(s)/guideline(s) which describe
the testing and maintenance program for FLEX equipment.
As applicable, provide a listing of the model work orders established to conduct period testing and maintenance activities for FLEX equipment. [A sample of records for completed maintenance/testing activities
may be requested for review
during the onsite inspection week.]
K. Provide documents/procedures
which describe the programmatic controls in place
to ensure that if equipment and applicable connections are unavailable (e.g., due to maintenance , non-functionality), then compensatory measures are implemented in accordance with guidance outlined NEI 12
-06. L. Provide the station
-specific National SAFER Center "Playbook"
M. Relative to personnel training on FLEX strategies, provide:
1) FLEX training bases document(s)
2) Lesson plans/training documents
for site emergency response leaders responsible for the implementation of FLEX strategies. [Records for staff completing this training may be requested for review
during the onsite inspection week.]
3) Lesson plans/training documents
for site personnel responsible for the execution of mitigating strategies for BDBEEs (i.e., operators, craft personnel, security, radiation protection, etc.). [Records for staff completing this training may be requested for review
during the onsite inspection week.]
N. A current copy of administrative procedure(s) for the CAP, modification program, operations
procedure writing and implementation, and top-level documents for the work control and work scheduling programs.
(If FLEX related procedures such as FSGs or the FIP are maintained under a different process
, please include copies of those
procedures.
) O. A current copy of the U/FSAR, Technical Specifications, and Technical Specification Bases documents.
P. Listing of corrective action program document summaries generated related to FLEX equipment, strategies, procedures, and/or training.
Q. A copy of any audits/self
-assessments related to your preparation for this inspection, as well as any related to the implementation or maintenance of the FLEX program.
- Appendix B
R. Provide the procedures implemented for maintenance, testing, calibration, and use of the primary and backup Spent Fuel Pool (SFP) instrumentation channels.
S. Provide lesson plans/training documents which describe the training program that address the use, maintenance, calibration, surveillance, and the use of alternate power to the primary and backup SFP instrument channels.
- Appendix C
T. Communications:
1) Provide documents which show that
the communications system(s), technologies, equipment and power supplies would be available from the beginning of the event and operate during an ELAP.
2) Provide the procedures and/or guidance used to implement the communication capabilities
. 3) Provide documents which show that you have added any new communications equipment, portable power supplies and/or systems have been added to ongoing testing and preventative maintenance programs.
U. Staffing: 1) Provide documents which show that onsite and augmented staff will be available to
implement the strategies
in response to a large scale natural event that results an ELAP and impedes access to the site, and that functions/tasks have been appropriately
staffed. 2) Provide documents which show that the site access methods (e.g., roadways, navigable bodies of water and dockage, airlift, etc.) expected to be available
following the event and available to the Emergency Response Organization (ERO) [as described in the Phase 1 and 2 staffing assessments and NRC safety assessment]. 3) Provide documents which show the testing, training, and drills/exercises performed by
the station
to demonstrate the ERO's ability to utilize the communications systems and/or equipment.
V. Provide documents and procedures which show that your dose
assessment is capable of analyzing concurrent radiological releases from all on-site significant sources, including releases from spent fuel pools (i.e., multi
-unit/multi
-source dose assessment capability)
. Lead Inspector Contact Information:
Ryan D. Alexander , Sr. Project Engineer
Mailing Address
- 817-200-11 95 U.S. NRC, Region IV
Ryan.Alexander@nrc.gov
Attn: Ryan Alexander, DRP
1600 East Lamar Blvd.
Arlington, TX 76011
-4511
SUNSI Review By: RDA/rdr ADAMS: Yes No Sensitive
Non-Sensitive Non-Publicly Available
Publicly Available
Keyword NRC-002 OFFICE DRP/RPBA C:DRP/RPBB
NAME RAlexander
JDixon SIGNATURE /RA/-E /RA/ DATE 06/14/2017
06/19/2017