IR 05000498/2017005: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
| (10 intermediate revisions by the same user not shown) | |||
| Line 2: | Line 2: | ||
| number = ML17242A182 | | number = ML17242A182 | ||
| issue date = 08/28/2017 | | issue date = 08/28/2017 | ||
| title = | | title = Updated Inspection Plan (Reports 05000498/2017005 and 05000499/2017005) | ||
| author name = Taylor N | | author name = Taylor N | ||
| author affiliation = NRC/RGN-IV/DRP/RPB-B | | author affiliation = NRC/RGN-IV/DRP/RPB-B | ||
| addressee name = Powell G | | addressee name = Powell G | ||
| addressee affiliation = South Texas Project Nuclear Operating Co | | addressee affiliation = South Texas Project Nuclear Operating Co | ||
| docket = 05000498, 05000499 | | docket = 05000498, 05000499 | ||
| Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter | {{#Wiki_filter:August 28, 2017 | ||
==SUBJECT:== | |||
UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 AND 2 (REPORTS 05000498/2017005 AND 05000499/2017005) | |||
==Dear Mr. Powell:== | |||
The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for South Texas Project Electric Generating Station Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence. | |||
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. This inspection will be conducted at South Texas Project Electric Generating Station Units 1 and 2 to confirm the stations full implementation of Commission Orders EA-12-049 and EA-12-051. | |||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION | |||
==REGION IV== | |||
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Please contact me at (817) 200-1141 with any questions you have regarding this letter. | |||
Sincerely, | |||
/RA D. Proulx for/ | |||
Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket Nos. 50-498 and 50-499 License Nos. NPF-76 and NPF-80 Enclosure: | |||
South Texas Project Electric Generating Station Inspection Plan | |||
SUNSI Review ADAMS: | |||
Non-Publicly Available Non-Sensitive Keyword:NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE | |||
/RA/ | |||
/RA/DProulx for DATE 8/28/17 8/28/17 | |||
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site South Texas Project Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 1 of 2 08/25/2017 08:24:16 EXAM | |||
- INITIAL EXAM | |||
1 INITIAL EXAM STP U1 (09/2017) | |||
X02592 08/14/2017 08/18/2017 | |||
INITIAL EXAM STP U2 (09/2017) | |||
X02593 08/14/2017 08/18/2017 | |||
INITIAL EXAM STP U1 (09/2017) | |||
X02592 09/25/2017 10/04/2017 | |||
INITIAL EXAM STP U2 (09/2017) | |||
X02593 09/25/2017 10/04/2017 RS 24 | |||
- RADIATION SAFETY | |||
1, 2 IP Occupational ALARA Planning and Controls 71124.02 07/31/2017 08/04/2017 1, 2 IP Occupational Dose Assessment 71124.04 07/31/2017 08/04/2017 TI-191 | |||
- MITIGATING STRATEGIES/SFP INST FOR BDBEE | |||
1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 10/23/2017 10/27/2017 BRQ | |||
- BRQ INSPECTION | |||
1, 2 IP Licensed Operator Requalification Program 7111111B 10/16/2017 10/20/2017 RS 12PI | |||
- RAD SAFETY | |||
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/26/2018 03/30/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/26/2018 03/30/2018 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 03/26/2018 03/30/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 03/26/2018 03/30/2018 7111108 | |||
- INSERVICE INSPECTION UNIT 2 | |||
2 IP Inservice Inspection Activities - PWR 7111108P 04/02/2018 04/13/2018 EXAM | |||
- INITIAL EXAM | |||
1 INITIAL EXAM STP U1(11/18) | |||
X02626 09/17/2018 09/21/2018 | |||
INITIAL EXAM STP U2(11/2018) | |||
X02627 09/17/2018 09/21/2018 | |||
INITIAL EXAM STP U1(11/18) | |||
X02626 10/22/2018 11/01/2018 | |||
INITIAL EXAM STP U2(11/2018) | |||
X02627 10/22/2018 11/01/2018 EB1-07T | |||
- STP HEAT SINK PERFORMANCE | |||
1, 2 IP Heat Sink Performance 7111107T 06/11/2018 06/15/2018 EP-1 | |||
- EP EXERCISE INSPECTION | |||
1, 2 IP Exercise Evaluation 7111401 06/11/2018 06/15/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 06/11/2018 06/15/2018 1, 2 IP Drill/Exercise Performance 71151-EP01 06/11/2018 06/15/2018 1, 2 IP ERO Readiness 71151-EP02 06/11/2018 06/15/2018 1, 2 IP Alert & Notification System Reliability 71151-EP03 06/11/2018 06/15/2018 This report does not include INPO and OUTAGE activities. | |||
This report shows only on-site and announced inspection procedures. | |||
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site South Texas Project Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 2 of 2 08/25/2017 08:24:16 RS 5678 | |||
- RAD SAFETY | |||
1, 2 IP Radiation Monitoring Instrumentation 71124.05 07/23/2018 07/27/2018 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 07/23/2018 07/27/2018 1, 2 IP Radiological Environmental Monitoring Program 71124.07 07/23/2018 07/27/2018 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 07/23/2018 07/27/2018 PI&R | |||
- BIENNIAL PI&R INSPECTION | |||
1, 2 IP Problem Identification and Resolution 71152B 08/06/2018 08/10/2018 1, 2 IP Problem Identification and Resolution 71152B 08/20/2018 08/24/2018 7111108 | |||
- INSERVICE INSPECTION UNIT 1 | |||
1 IP Inservice Inspection Activities - PWR 7111108P 10/15/2018 10/26/2018 RS 24 | |||
- RP INSPECTION | |||
1, 2 IP Occupational ALARA Planning and Controls 71124.02 01/28/2019 02/01/2019 1, 2 IP Occupational Dose Assessment 71124.04 01/28/2019 02/01/2019 EB1-21M | |||
- SOUTH TEXAS DBA TEAM INSPECTION | |||
1, 2 IP Design Bases Assurance Inspection (Teams) | |||
7111121M 03/25/2019 04/12/2019 This report does not include INPO and OUTAGE activities. | |||
This report shows only on-site and announced inspection procedures. | |||
}} | }} | ||
Latest revision as of 12:31, 8 January 2025
| ML17242A182 | |
| Person / Time | |
|---|---|
| Site: | South Texas |
| Issue date: | 08/28/2017 |
| From: | Nick Taylor NRC/RGN-IV/DRP/RPB-B |
| To: | Gerry Powell South Texas |
| NICK TAYLOR | |
| References | |
| IR 2017005 | |
| Download: ML17242A182 (5) | |
Text
August 28, 2017
SUBJECT:
UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 AND 2 (REPORTS 05000498/2017005 AND 05000499/2017005)
Dear Mr. Powell:
The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for South Texas Project Electric Generating Station Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans. This inspection will be conducted at South Texas Project Electric Generating Station Units 1 and 2 to confirm the stations full implementation of Commission Orders EA-12-049 and EA-12-051.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION
REGION IV
1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1141 with any questions you have regarding this letter.
Sincerely,
/RA D. Proulx for/
Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket Nos. 50-498 and 50-499 License Nos. NPF-76 and NPF-80 Enclosure:
South Texas Project Electric Generating Station Inspection Plan
SUNSI Review ADAMS:
Non-Publicly Available Non-Sensitive Keyword:NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE
/RA/
/RA/DProulx for DATE 8/28/17 8/28/17
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site South Texas Project Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 1 of 2 08/25/2017 08:24:16 EXAM
- INITIAL EXAM
1 INITIAL EXAM STP U1 (09/2017)
X02592 08/14/2017 08/18/2017
INITIAL EXAM STP U2 (09/2017)
X02593 08/14/2017 08/18/2017
INITIAL EXAM STP U1 (09/2017)
X02592 09/25/2017 10/04/2017
INITIAL EXAM STP U2 (09/2017)
X02593 09/25/2017 10/04/2017 RS 24
- RADIATION SAFETY
1, 2 IP Occupational ALARA Planning and Controls 71124.02 07/31/2017 08/04/2017 1, 2 IP Occupational Dose Assessment 71124.04 07/31/2017 08/04/2017 TI-191
- MITIGATING STRATEGIES/SFP INST FOR BDBEE
1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 10/23/2017 10/27/2017 BRQ
- BRQ INSPECTION
1, 2 IP Licensed Operator Requalification Program 7111111B 10/16/2017 10/20/2017 RS 12PI
- RAD SAFETY
1, 2 IP Radiological Hazard Assessment and Exposure Controls 71124.01 03/26/2018 03/30/2018 1, 2 IP Occupational ALARA Planning and Controls 71124.02 03/26/2018 03/30/2018 1, 2 IP Occupational Exposure Control Effectiveness 71151-OR01 03/26/2018 03/30/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences 71151-PR01 03/26/2018 03/30/2018 7111108
- INSERVICE INSPECTION UNIT 2
2 IP Inservice Inspection Activities - PWR 7111108P 04/02/2018 04/13/2018 EXAM
- INITIAL EXAM
1 INITIAL EXAM STP U1(11/18)
X02626 09/17/2018 09/21/2018
INITIAL EXAM STP U2(11/2018)
X02627 09/17/2018 09/21/2018
INITIAL EXAM STP U1(11/18)
X02626 10/22/2018 11/01/2018
INITIAL EXAM STP U2(11/2018)
X02627 10/22/2018 11/01/2018 EB1-07T
- STP HEAT SINK PERFORMANCE
1, 2 IP Heat Sink Performance 7111107T 06/11/2018 06/15/2018 EP-1
- EP EXERCISE INSPECTION
1, 2 IP Exercise Evaluation 7111401 06/11/2018 06/15/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes 7111404 06/11/2018 06/15/2018 1, 2 IP Drill/Exercise Performance 71151-EP01 06/11/2018 06/15/2018 1, 2 IP ERO Readiness 71151-EP02 06/11/2018 06/15/2018 1, 2 IP Alert & Notification System Reliability 71151-EP03 06/11/2018 06/15/2018 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site South Texas Project Inspection / Activity Plan 07/01/2017 - 06/30/2019 Page 2 of 2 08/25/2017 08:24:16 RS 5678
- RAD SAFETY
1, 2 IP Radiation Monitoring Instrumentation 71124.05 07/23/2018 07/27/2018 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 07/23/2018 07/27/2018 1, 2 IP Radiological Environmental Monitoring Program 71124.07 07/23/2018 07/27/2018 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 07/23/2018 07/27/2018 PI&R
- BIENNIAL PI&R INSPECTION
1, 2 IP Problem Identification and Resolution 71152B 08/06/2018 08/10/2018 1, 2 IP Problem Identification and Resolution 71152B 08/20/2018 08/24/2018 7111108
- INSERVICE INSPECTION UNIT 1
1 IP Inservice Inspection Activities - PWR 7111108P 10/15/2018 10/26/2018 RS 24
- RP INSPECTION
1, 2 IP Occupational ALARA Planning and Controls 71124.02 01/28/2019 02/01/2019 1, 2 IP Occupational Dose Assessment 71124.04 01/28/2019 02/01/2019 EB1-21M
- SOUTH TEXAS DBA TEAM INSPECTION
1, 2 IP Design Bases Assurance Inspection (Teams)
7111121M 03/25/2019 04/12/2019 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.