{{#Wiki_filter:May 14, 2018
[[Issue date::May 14, 2018]]


Mr. Brian Sullivan Site Vice President Pilgrim Nuclear Power Station Entergy Nuclear Operations, Inc.
==SUBJECT:==
 
PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000293/2018001
600 Rocky Hill Road Plymouth, MA 02360-5508
 
SUBJECT: PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000293/2018001


==Dear Mr. Sullivan:==
==Dear Mr. Sullivan:==
Line 32: Line 28:
The NRC inspectors did not identify any finding or violation of more than minor significance.
The NRC inspectors did not identify any finding or violation of more than minor significance.


This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.


Sincerely,
Sincerely,
/RA/ Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Number: 50-293 License Number: DPR-35
/RA/  
 
Enclosure: Inspection Report 05000293/2018001


cc w/encl: Distribution via ListServ
Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects


ML18134A225 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME ECarfang via email LCline via email ADimitriadis DATE 5/14/18 5/14/18 5/14/18
Docket Number: 50-293 License Number: DPR-35


1 Enclosure U.S. NUCLEAR REGULATORY COMMISSION
===Enclosure:===
Inspection Report 05000293/2018001


==Inspection Report==
==Inspection Report==
Docket Number:
50-293


Docket Number: 50-293 License Number: DPR-35
License Number:
DPR-35  


Report Number: 05000293/2018001  
Report Number:
05000293/2018001  


Enterprise Identifier: I-2018-001-0047  
Enterprise Identifier: I-2018-001-0047  


Licensee: Entergy Nuclear Operations, Inc. (Entergy)
Licensee:
Entergy Nuclear Operations, Inc. (Entergy)  


Facility: Pilgrim Nuclear Power Station (PNPS)
Facility:
Pilgrim Nuclear Power Station (PNPS)  


Location: Plymouth, Massachusetts
Location:
Plymouth, Massachusetts  


Inspection Dates: January 1, 2018 to March 31, 2018
Inspection Dates:
January 1, 2018 to March 31, 2018  


Inspectors: E. Carfang, Senior Resident Inspector J. Krafty, Acting Senior Resident Inspector B. Pinson, Resident Inspector J. Pfingsten, Project Engineer E. DiPaolo, Senior Reactor Inspector  
Inspectors:
E. Carfang, Senior Resident Inspector  


Approved By: A. Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects
J. Krafty, Acting Senior Resident Inspector


2
B. Pinson, Resident Inspector
 
J. Pfingsten, Project Engineer
 
E. DiPaolo, Senior Reactor Inspector
 
Approved By:
A. Dimitriadis, Chief
 
Reactor Projects Branch 5
 
Division of Reactor Projects


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergy's performance at PNPS by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergys performance at PNPS by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.


No findings or more-than-minor violations were identified.
No findings or more-than-minor violations were identified.


3
=PLANT STATUS=


=PLANT STATUS=
The unit began the inspection period at rated thermal power. On January 4, 2018, operators scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators down powered the unit to 45 percent for a planned repair to a drain valve in the moisture separator drain tank. The operators returned the unit to rated thermal power the same day. On March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the main condenser after the March 2, 2018 noreaster. Operators returned the unit to rated thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating current power during a noreaster while the unit was in cold shutdown, and the startup transformer experienced an electrical fault during the storm. The unit remained in cold shutdown for the remainder of the inspection period to address issues in the switchyard.
The unit began the inspection period at rated thermal power. On January 4, 2018, operators scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators down powered the unit to 45 percent for a planned repair to a drain valve in the moisture separator drain tank. The operators returned the unit to rated thermal power the same day. On March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the main condenser after the March 2, 2018 nor'easter. Operators returned the unit to rated thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating current power during a nor'easter while the unit was in cold shutdown, and the startup transformer experienced an electrical fault during the storm. The unit remained in cold shutdown for the remainder of the inspection period to address issues in the switchyard.


==INSPECTION SCOPES==
==INSPECTION SCOPES==
Inspections were conducted using the appropriate portions of the inspection procedures in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the inspection procedure requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, "Light-Water Reactor Inspection Program - Operations Phase."
Inspections were conducted using the appropriate portions of the inspection procedures in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.


The inspectors performed plant status activities described in Inspection Manual Chapter 2515, Appendix D, "Plant Status," and conducted routine reviews using Inspection Procedure 71152, "Problem Identification and Resolution.The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Entergy's performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Samples were declared complete when the inspection procedure requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, and conducted routine reviews using Inspection Procedure 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Entergys performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.


==REACTOR SAFETY==
==REACTOR SAFETY==
==71111.01 - Adverse Weather Protection==
==71111.01 - Adverse Weather Protection==
===Impending Severe Weather (4 Samples)===
===Impending Severe Weather (4 Samples)===
 
The inspectors evaluated readiness for impending adverse weather conditions for the following:
The inspectors evaluated readiness for impendi ng adverse weather conditions for the following:
: (1) Severe cold weather on January 2, 2018
: (1) Severe cold weather on January 2, 2018
: (2) Blizzard conditions on January 3, 2018
: (2) Blizzard conditions on January 3, 2018
: (3) Nor'easter on March 2-3, 2018
: (3) Noreaster on March 2-3, 2018
: (4) Blizzard conditions on March 12-13, 2018
: (4) Blizzard conditions on March 12-13, 2018  


===External Flooding (1 Sample)===
===External Flooding (1 Sample)===
The inspectors evaluated readiness to cope with external flooding the week of February 26, 2018.
The inspectors evaluated readiness to cope with external flooding the week of February 26, 2018.


==71111.04 - Equipment Alignment==
==71111.04 - Equipment Alignment==
===Partial Walkdown (4 Samples)===
===Partial Walkdown (4 Samples)===
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
: (1) Reactor core isolation cooling system walkdown with high pressure coolant injection system out of service for planned maintenance on February 7, 2018
: (1) Reactor core isolation cooling system walkdown with high pressure coolant injection system out of service for planned maintenance on February 7, 2018
: (2) Control rod drive system 'B' walkdown with c ontrol rod drive system 'A' out of service for planned maintenance on February 26, 2018
: (2) Control rod drive system B walkdown with control rod drive system A out of service for planned maintenance on February 26, 2018
: (3) Emergency diesel generators 'A' and 'B' during loss of offsite power from March 13-16, 2018
: (3) Emergency diesel generators A and B during loss of offsite power from March 13-16, 2018
: (4) Offsite power backfeed alignment on March 22-23, 2018  
: (4) Offsite power backfeed alignment on March 22-23, 2018  


===Complete Walkdown (1 Sample)===
===Complete Walkdown (1 Sample)===
The inspectors evaluated system configurations during a complete walkdown of the station blackout diesel generator system on March 1, 2018.
The inspectors evaluated system configurations during a complete walkdown of the station blackout diesel generator system on March 1, 2018.


==71111.05A/Q - Fire Protection Annual/Quarterly==
==71111.05A/Q - Fire Protection Annual/Quarterly==
===Quarterly Inspection (5 Samples)===
===Quarterly Inspection (5 Samples)===
The inspectors evaluated fire protection program implementation in the following selected areas:
The inspectors evaluated fire protection program implementation in the following selected areas:
: (1) High pressure coolant injection on February 13, 2018
: (1) High pressure coolant injection on February 13, 2018
Line 124: Line 129:


===Annual Inspection (1 Sample)===
===Annual Inspection (1 Sample)===
The inspectors evaluated fire brigade performance on January 23, 2018.
The inspectors evaluated fire brigade performance on January 23, 2018.


==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
===Operator Requalification (1 Sample)===
===Operator Requalification (1 Sample)===
The inspectors observed and evaluated licensed operator requalification training, in accordance with 10 CFR 55.59, at PNPS on February 8, 2018.
The inspectors observed and evaluated licensed operator requalification training, in accordance with 10 CFR 55.59, at PNPS on February 8, 2018.


===Operator Performance (1 Sample)===
===Operator Performance (1 Sample)===
The inspectors observed and evaluated licensed operator performance in the control room during plant startup following a forced outage on January 10, 2018.
The inspectors observed and evaluated licensed operator performance in the control room during plant startup following a forced outage on January 10, 2018.


==71111.12 - Maintenance Effectiveness==
==71111.12 - Maintenance Effectiveness==
===Routine Maintenance Effectiveness (3 Samples)===
===Routine Maintenance Effectiveness (3 Samples)===
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
: (1) Instrument air system on February 2, 2018
: (1) Instrument air system on February 2, 2018
: (2) Reactor protection system on February 2, 2018
: (2) Reactor protection system on February 2, 2018
: (3) Reactor building 23' level structural monitoring the weeks of March 19 and March 26, 2018
: (3) Reactor building 23 level structural monitoring the weeks of March 19 and March 26, 2018


==71111.13 - Maintenance Risk Assessments and Emergent Work Control==
==71111.13 - Maintenance Risk Assessments and Emergent Work Control==
Line 151: Line 151:
: (1) Decay heat removal short time to boil on January 5, 2018
: (1) Decay heat removal short time to boil on January 5, 2018
: (2) Testing of the station blackout diesel generator halon system on January 19, 2018
: (2) Testing of the station blackout diesel generator halon system on January 19, 2018
: (3) Logic system functional testing of emergency diesel generator 'A' on January 23, 2018
: (3) Logic system functional testing of emergency diesel generator A on January 23, 2018
: (4) Station blackout diesel generator and instrument air compressor unavailability on February 21, 2018
: (4) Station blackout diesel generator and instrument air compressor unavailability on February 21, 2018
: (5) Low pressure core injection diagnostic valve testing on March 8, 2018
: (5) Low pressure core injection diagnostic valve testing on March 8, 2018
Line 161: Line 161:
The inspectors evaluated the following operability determinations and functionality assessments:
The inspectors evaluated the following operability determinations and functionality assessments:
: (1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018
: (1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018
: (2) Control room high efficiency air filtration system train 'B' filter testing identified bypass around the downstream high efficiency particulate air filter on February 6, 2018
: (2) Control room high efficiency air filtration system train B filter testing identified bypass around the downstream high efficiency particulate air filter on February 6, 2018
: (3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed surveillance on February 20, 2018
: (3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed surveillance on February 20, 2018
: (4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018
: (4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018
Line 174: Line 174:
{{IP sample|IP=IP 71111.19|count=5}}
{{IP sample|IP=IP 71111.19|count=5}}


The inspectors evaluated post maintenance testing for the following maintenance/repair  
The inspectors evaluated post maintenance testing for the following maintenance/repair activities:
 
activities:
: (1) Safety relief valve 3B pilot valve replacement on January 10, 2018
: (1) Safety relief valve 3B pilot valve replacement on January 10, 2018
: (2) K-111 instrument air compressor motor replacement on January 30, 2018 6
: (2) K-111 instrument air compressor motor replacement on January 30, 2018
: (3) High pressure coolant injection steam line drain line level control switch replacement on February 8, 2018
: (3) High pressure coolant injection steam line drain line level control switch replacement on February 8, 2018
: (4) Salt service water pump 'E' baseplate injection performed on February 8, 2018
: (4) Salt service water pump E baseplate injection performed on February 8, 2018
: (5) K-110 instrument air compressor motor replacement performed on February 22, 2018
: (5) K-110 instrument air compressor motor replacement performed on February 22, 2018


Line 186: Line 184:
{{IP sample|IP=IP 71111.20|count=2}}
{{IP sample|IP=IP 71111.20|count=2}}


The inspectors evaluated Entergy's forced outage activities from:
The inspectors evaluated Entergys forced outage activities from:
: (1) January 4 to January 10, 2018
: (1) January 4 to January 10, 2018
: (2) March 6 to March 31, 2018
: (2) March 6 to March 31, 2018


==71111.22 - Surveillance Testing==
==71111.22 - Surveillance Testing==
The inspectors evaluated the following surveillance tests:  
The inspectors evaluated the following surveillance tests:  


===Routine (4 Samples)===
===Routine===
{{IP sample|IP=IP 71111.22|count=4}}
: (1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test on January 19, 2018
: (1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test on January 19, 2018
: (2) 8.M.2-2.10.8.1, Diesel Generator 'A' Initiation by Residual Heat Removal Logic on January 23, 2018
: (2) 8.M.2-2.10.8.1, Diesel Generator A Initiation by Residual Heat Removal Logic on January 23, 2018
: (3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018
: (3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018
: (4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on February 22, 2018
: (4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on February 22, 2018  


===Reactor Coolant System Leak Detection (1 Sample)===
===Reactor Coolant System Leak Detection (1 Sample)===
: (1) 2.1.15, Daily Surveillance Log on February 27, 2018
: (1) 2.1.15, Daily Surveillance Log on February 27,


==OTHER ACTIVITIES - BASELINE==
==OTHER ACTIVITIES - BASELINE==
71151 - Performance Indicator Verification  
===71151 - Performance Indicator Verification  


===The inspectors verified Entergy's performance indicators submittals listed below for the period from January 1, 2017 through December 31, 2017. (3 Samples)===
The inspectors verified Entergys performance indicators submittals listed below for the period from January 1, 2017 through December 31, 2017.===
{{IP sample|IP=IP 71151|count=3}}
: (1) Reactor coolant system specific activity
: (1) Reactor coolant system specific activity
: (2) Reactor coolant system leak rate
: (2) Reactor coolant system leak rate
Line 212: Line 211:


==71152 - Problem Identification and Resolution==
==71152 - Problem Identification and Resolution==
===Annual Follow-up of Selected Issues (1 Sample)===
===Annual Follow-up of Selected Issues (1 Sample)===
The inspectors reviewed Entergys implementation of its corrective action program related to the following issues:
: (1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15)deficiencies discovered during thermography


The inspectors reviewed Entergy's implementation of its corrective action program related to the following issues:
===71153 - Follow-up of Events and Notices of Enforcement Discretion Personnel Performance===
: (1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15) deficiencies discovered during thermography 7 71153 - Follow-up of Events and Notices of Enforcement Discretion  
{{IP sample|IP=IP 71153|count=2}}
 
===Personnel Performance (2 Sample)===


The inspectors evaluated response during the following non-routine evolutions or transients:
The inspectors evaluated response during the following non-routine evolutions or transients:
: (1) Reactor scram due to loss of one offsite power line on January 4, 2018
: (1) Reactor scram due to loss of one offsite power line on January 4, 2018
: (2) Loss of offsite alternating current power on March 13, 2018
: (2) Loss of offsite alternating current power on March 13,


==INSPECTION RESULTS==
==INSPECTION RESULTS==
Observation 71152 Annual Follow-up of Selected Issues The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the past operability regarding the deficiencies discovered on the 23 kilovolt offsite power supply to shutdown transformer circuit switcher during thermography. The inspectors concluded that the cause analysis was thorough, the extent of condition was reasonable, and the corrective actions were timely.
Observation 71152 Annual Follow-up of Selected Issues The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the past operability regarding the deficiencies discovered on the 23 kilovolt offsite power supply to shutdown transformer circuit switcher during thermography. The inspectors concluded that the cause analysis was thorough, the extent of condition was reasonable, and the corrective actions were timely.


==EXIT MEETINGS AND DEBRIEFS==
==EXIT MEETINGS AND DEBRIEFS==
Line 234: Line 232:
On April 25, 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.
On April 25, 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.


THIRD PARTY REVIEWS Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the inspection period.
THIRD PARTY REVIEWS  


8
Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the inspection period.


=DOCUMENTS REVIEWED=
=DOCUMENTS REVIEWED=


71111.15
71111.15
Procedure EN-OP-104, Operability Determination Process, Revision 15
Procedure
71111.18 Procedures EN-LI-100, Process Applicability Determination, Revision 22 EN-DC-136, Temporary Modifications, Revision 17
EN-OP-104, Operability Determination Process, Revision 15
71111.19 Procedure EN-WM-107, Post Maintenance Testing, Revision 5
71111.18
71152 Procedures EN-LI-102, Corrective Action Program, Revision 33
Procedures
EN-LI-100, Process Applicability Determination, Revision 22
EN-DC-136, Temporary Modifications, Revision 17
71111.19
Procedure
EN-WM-107, Post Maintenance Testing, Revision 5
71152
Procedures
EN-LI-102, Corrective Action Program, Revision 33
EN-LI-118, Cause Evaluation Process, Revision 26  
EN-LI-118, Cause Evaluation Process, Revision 26  


UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713
UNITED STATES
May 14, 2018
NUCLEAR REGULATORY COMMISSION
Mr. Brian Sullivan Site Vice President
REGION I
2100 RENAISSANCE BOULEVARD, SUITE 100
KING OF PRUSSIA, PENNSLYVANIA 19406-2713  
 
May 14, 2018  
 
Mr. Brian Sullivan
Site Vice President
Pilgrim Nuclear Power Station
Pilgrim Nuclear Power Station
Entergy Nuclear Operations, Inc.
Entergy Nuclear Operations, Inc.
600 Rocky Hill Road Plymouth, MA 02360-5508  
600 Rocky Hill Road
 
Plymouth, MA 02360-5508  
SUBJECT: PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000293/2018001
Dear Mr. Sullivan:


SUBJECT:
PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION
REPORT 05000293/2018001
Dear Mr. Sullivan:
On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection
at Pilgrim Nuclear Power Station (PNPS). On April 25, 2018, the NRC inspectors discussed the
at Pilgrim Nuclear Power Station (PNPS). On April 25, 2018, the NRC inspectors discussed the
results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
results of this inspection with you and other members of your staff. The results of this
The NRC inspectors did not identify any finding or violation of more than minor significance.  
inspection are documented in the enclosed report.
 
The NRC inspectors did not identify any finding or violation of more than minor significance.
This letter, its enclosure, and your response (if any) will be made available for public inspection
This letter, its enclosure, and your response (if any) will be made available for public inspection
and copying at
and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room
http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public
Inspections, Exemptions, Requests for Withholding.
Sincerely,  
Sincerely,  
          /RA/   Anthony Dimitriadis, Chief
 
/RA/
Anthony Dimitriadis, Chief
Reactor Projects Branch 5
Reactor Projects Branch 5
Division of Reactor Projects
Division of Reactor Projects
Docket Number:   50-293
Docket Number: 50-293
License Number: DPR-35  
License Number: DPR-35
 
Enclosure:
Enclosure: Inspection Report 05000293/2018001
Inspection Report 05000293/2018001
cc w/encl: Distribution via ListServ
cc w/encl: Distribution via ListServ
ML18134A225
ML18134A225
SUNSI Review
SUNSI Review
Non-Sensitive Sensitive
Non-Sensitive
Publicly Available Non-Publicly Available
Sensitive
OFFICE RI/DRP RI/DRP RI/DRP   NAME ECarfang via email LCline via email ADimitriadis   DATE 5/14/18 5/14/18 5/14/18
Publicly Available
Enclosure U.S. NUCLEAR REGULATORY COMMISSION
Non-Publicly Available
Inspection Report
OFFICE
RI/DRP
RI/DRP
RI/DRP  
 
NAME
ECarfang via email
LCline via email
ADimitriadis  


Docket Number: 50-293
DATE
License Number: DPR-35
5/14/18
5/14/18
5/14/18
 
U.S. NUCLEAR REGULATORY COMMISSION
Inspection Report
 
Docket Number:
50-293  
 
License Number:
DPR-35  


Report Number: 05000293/2018001  
Report Number:
05000293/2018001  


Enterprise Identifier: I-2018-001-0047  
Enterprise Identifier: I-2018-001-0047  


Licensee: Entergy Nuclear Operations, Inc. (Entergy)
Licensee:
Entergy Nuclear Operations, Inc. (Entergy)  


Facility: Pilgrim Nuclear Power Station (PNPS)
Facility:
Pilgrim Nuclear Power Station (PNPS)  


Location: Plymouth, Massachusetts
Location:
Plymouth, Massachusetts  


Inspection Dates: January 1, 2018
Inspection Dates:
to March 31, 2018
January 1, 2018 to March 31, 2018  


Inspectors:  
Inspectors:  
: [[contact::E. Carfang]], Senior Resident Inspector  
: [[contact::E. Carfang]], Senior Resident Inspector  
: [[contact::J. Krafty]], Acting Senior Resident Inspector  
: [[contact::J. Krafty]], Acting Senior Resident Inspector  
: [[contact::B. Pinson]], Resident Inspector  
: [[contact::B. Pinson]], Resident Inspector  
Line 306: Line 347:


Approved By:  
Approved By:  
: [[contact::A. Dimitriadis]], Chief
: [[contact::A. Dimitriadis]], Chief  
Reactor Projects Branch 5   Division of Reactor Projects  
 
Reactor Projects Branch 5  
 
Division of Reactor Projects  


SUMMARY The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergy's performance at PNPS by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to
SUMMARY
https://www.nrc.gov/reactors/operating/oversight.html
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergys performance
for more information.
at PNPS by conducting the baseline inspections described in this report in accordance with the
Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for
overseeing the safe operation of commercial nuclear power reactors. Refer to
https://www.nrc.gov/reactors/operating/oversight.html for more information.
No findings or more-than-minor violations were identified.  
No findings or more-than-minor violations were identified.  


PLANT STATUS The unit began the inspection period at rated thermal power. On January 4, 2018, operators scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators
PLANT STATUS
The unit began the inspection period at rated thermal power. On January 4, 2018, operators
scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit
was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators
down powered the unit to 45 percent for a planned repair to a drain valve in the moisture
down powered the unit to 45 percent for a planned repair to a drain valve in the moisture
separator drain tank. The operators returned the unit to rated thermal power the same day. On
separator drain tank. The operators returned the unit to rated thermal power the same day. On
March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the
March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the
main condenser after the March 2, 2018 nor'easter. Operators returned the unit to rated thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating
main condenser after the March 2, 2018 noreaster. Operators returned the unit to rated
current power during a nor'easter while the unit was in cold shutdown, and the startup
thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform
repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating
current power during a noreaster while the unit was in cold shutdown, and the startup
transformer experienced an electrical fault during the storm. The unit remained in cold
transformer experienced an electrical fault during the storm. The unit remained in cold
shutdown for the remainder of the inspection period to address issues in the switchyard.
shutdown for the remainder of the inspection period to address issues in the switchyard.
INSPECTION SCOPES
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection
Inspections were conducted using the appropriate portions of the inspection procedures in effect
at the beginning of the inspection unless otherwise noted. Currently approved inspection
procedures with their attached revision histories are located on the public website at
procedures with their attached revision histories are located on the public website at
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the inspection procedure requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515,  
http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.
"Light-Water Reactor Inspection Program - Operations Phase."
Samples were declared complete when the inspection procedure requirements most
The inspectors performed plant status activities described in Inspection Manual Chapter 2515, Appendix D, "Plant Status," and
appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515,
conducted routine reviews using Inspection Procedure 71152, "Problem Identification and
Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant
Resolution.The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Entergy's
status activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, and
performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
conducted routine reviews using Inspection Procedure 71152, Problem Identification and
Resolution. The inspectors reviewed selected procedures and records, observed activities,
and interviewed personnel to assess Entergys performance and compliance with Commission
rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
REACTOR SAFETY
71111.01 - Adverse Weather Protection
71111.01 - Adverse Weather Protection
Impending Severe Weather (4 Samples)
Impending Severe Weather (4 Samples)
The inspectors evaluated readiness for impendi
The inspectors evaluated readiness for impending adverse weather conditions for the
ng adverse weather conditions for the
following:  
following:  
(1) Severe cold weather on January 2, 2018
(1) Severe cold weather on January 2, 2018  
(2) Blizzard conditions on January 3, 2018
(2) Blizzard conditions on January 3, 2018  
(3) Nor'easter on March 2-3, 2018  
(3) Noreaster on March 2-3, 2018  
(4) Blizzard conditions on March 12-13, 2018
(4) Blizzard conditions on March 12-13, 2018
External Flooding (1 Sample)
External Flooding (1 Sample)
The inspectors evaluated readiness to cope with external flooding the week of February 26,
The inspectors evaluated readiness to cope with external flooding the week of February 26,
2018.
2018.  
 
71111.04 - Equipment Alignment
71111.04 - Equipment Alignment
Partial Walkdown (4 Samples)
Partial Walkdown (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following
The inspectors evaluated system configurations during partial walkdowns of the following
systems/trains:  
systems/trains:  
 
(1) Reactor core isolation cooling system walkdown with high pressure coolant injection
(1) Reactor core isolation cooling system walkdown with high pressure coolant injection system out of service for planned maintenance on February 7, 2018
system out of service for planned maintenance on February 7, 2018  
(2) Control rod drive system 'B' walkdown with c
(2) Control rod drive system B walkdown with control rod drive system A out of service for
ontrol rod drive system 'A' out of service for planned maintenance on February 26, 2018
planned maintenance on February 26, 2018  
(3) Emergency diesel generators 'A' and 'B' during loss of offsite power from March 13-16, 2018 (4) Offsite power backfeed alignment on March 22-23, 2018
(3) Emergency diesel generators A and B during loss of offsite power from March 13-16,
2018  
(4) Offsite power backfeed alignment on March 22-23, 2018
Complete Walkdown (1 Sample)
Complete Walkdown (1 Sample)
The inspectors evaluated system configurations during a complete walkdown of the station
The inspectors evaluated system configurations during a complete walkdown of the station
Line 359: Line 417:
Quarterly Inspection (5 Samples)
Quarterly Inspection (5 Samples)
The inspectors evaluated fire protection program implementation in the following selected
The inspectors evaluated fire protection program implementation in the following selected
areas:
areas:  
(1) High pressure coolant injection on February 13, 2018
(1) High pressure coolant injection on February 13, 2018  
(2) Main condenser bay on March 10, 2018
(2) Main condenser bay on March 10, 2018  
(3) Condensate pump on March 21, 2018 (4) Radioactive waste control corridor on March 21, 2018 (5) Turbine building truck lock and hydrogen seal oil area on March 22, 2018
(3) Condensate pump on March 21, 2018  
(4) Radioactive waste control corridor on March 21, 2018  
(5) Turbine building truck lock and hydrogen seal oil area on March 22, 2018
Annual Inspection (1 Sample)
Annual Inspection (1 Sample)
The inspectors evaluated fire brigade performance on January 23, 2018.
The inspectors evaluated fire brigade performance on January 23, 2018.
71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance
71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance
Operator Requalification (1 Sample)
Operator Requalification (1 Sample)
The inspectors observed and evaluated licensed operator requalification training, in accordance with 10 CFR 55.59, at PNPS on February 8, 2018.  
The inspectors observed and evaluated licensed operator requalification training, in
 
accordance with 10 CFR 55.59, at PNPS on February 8, 2018.
Operator Performance (1 Sample)
Operator Performance (1 Sample)
The inspectors observed and evaluated licensed operator performance in the control room during plant startup following a forced outage on January 10, 2018.  
The inspectors observed and evaluated licensed operator performance in the control room
during plant startup following a forced outage on January 10, 2018.  


71111.12 - Maintenance Effectiveness
71111.12 - Maintenance Effectiveness
Line 376: Line 437:
The inspectors evaluated the effectiveness of routine maintenance activities associated
The inspectors evaluated the effectiveness of routine maintenance activities associated
with the following equipment and/or safety significant functions:  
with the following equipment and/or safety significant functions:  
(1) Instrument air system on February 2, 2018  
(1) Instrument air system on February 2, 2018  
(2) Reactor protection system on February 2, 2018 (3) Reactor building 23' level structural monitoring the weeks of March 19 and March 26, 2018
(2) Reactor protection system on February 2, 2018  
(3) Reactor building 23 level structural monitoring the weeks of March 19 and March 26,
2018
71111.13 - Maintenance Risk Assessments and Emergent Work Control (6 Samples)
71111.13 - Maintenance Risk Assessments and Emergent Work Control (6 Samples)
The inspectors evaluated the risk assessments for the following planned and emergent
The inspectors evaluated the risk assessments for the following planned and emergent
work activities:  
work activities:  
(1) Decay heat removal short time to boil on January 5, 2018
(1) Decay heat removal short time to boil on January 5, 2018  
(2) Testing of the station blackout diesel generator halon system on January 19, 2018
(2) Testing of the station blackout diesel generator halon system on January 19, 2018  
(3) Logic system functional testing of emergency diesel generator 'A' on January 23, 2018
(3) Logic system functional testing of emergency diesel generator A on January 23, 2018  
(4) Station blackout diesel generator and instrument air compressor unavailability on
(4) Station blackout diesel generator and instrument air compressor unavailability on
February 21, 2018
February 21, 2018  
(5) Low pressure core injection diagnostic valve testing on March 8, 2018
(5) Low pressure core injection diagnostic valve testing on March 8, 2018  
(6) Movement of the spare startup transformer into the switchyard on March 29, 2018
(6) Movement of the spare startup transformer into the switchyard on March 29, 2018
71111.15 - Operability Determinations and Functionality Assessments (4 Samples)
71111.15 - Operability Determinations and Functionality Assessments (4 Samples)
The inspectors evaluated the following operability determinations and functionality
The inspectors evaluated the following operability determinations and functionality
assessments:  
assessments:  
(1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018
(1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018  
(2) Control room high efficiency air filtration system train 'B' filter testing identified bypass around the downstream high efficiency particulate air filter on February 6, 2018
(2) Control room high efficiency air filtration system train B filter testing identified bypass
(3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed surveillance on February 20, 2018
around the downstream high efficiency particulate air filter on February 6, 2018  
(4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018
(3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed
surveillance on February 20, 2018  
(4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018
71111.18 - Plant Modifications (1 Sample)
71111.18 - Plant Modifications (1 Sample)
The inspectors evaluated the following temporary or permanent modifications:  
The inspectors evaluated the following temporary or permanent modifications:  
(1) Temporary heating to fire water storage tanks on March 15, 2018
(1) Temporary heating to fire water storage tanks on March 15, 2018
71111.19 - Post Maintenance Testing (5 Samples)
71111.19 - Post Maintenance Testing (5 Samples)
The inspectors evaluated post maintenance testing for the following maintenance/repair
The inspectors evaluated post maintenance testing for the following maintenance/repair
activities:  
activities:  
(1) Safety relief valve 3B pilot valve replacement on January 10, 2018
(1) Safety relief valve 3B pilot valve replacement on January 10, 2018  
(2) K-111 instrument air compressor motor replacement on January 30, 2018  
(2) K-111 instrument air compressor motor replacement on January 30, 2018  
(3) High pressure coolant injection steam line drain line level control switch replacement on
 
February 8, 2018
(3) High pressure coolant injection steam line drain line level control switch replacement on
(4) Salt service water pump 'E' baseplate injection performed on February 8, 2018
February 8, 2018  
(5) K-110 instrument air compressor motor replacement performed on February 22, 2018
(4) Salt service water pump E baseplate injection performed on February 8, 2018  
(5) K-110 instrument air compressor motor replacement performed on February 22, 2018
71111.20 - Refueling and Other Outage Activities (2 Samples)
71111.20 - Refueling and Other Outage Activities (2 Samples)
The inspectors evaluated Entergy's forced outage activities from:  
The inspectors evaluated Entergys forced outage activities from:  
(1) January 4 to January 10, 2018 (2) March 6 to March 31, 2018
(1) January 4 to January 10, 2018  
(2) March 6 to March 31, 2018
71111.22 - Surveillance Testing
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
The inspectors evaluated the following surveillance tests:
Routine (4 Samples)  
Routine (4 Samples)  
(1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test
(1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test
on January 19, 2018
on January 19, 2018  
(2) 8.M.2-2.10.8.1, Diesel Generator 'A' Initiation by Residual Heat Removal Logic on
(2) 8.M.2-2.10.8.1, Diesel Generator A Initiation by Residual Heat Removal Logic on
January 23, 2018
January 23, 2018  
(3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018
(3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018  
  (4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on
(4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment
Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on
February 22, 2018
February 22, 2018
Reactor Coolant System Leak Detection (1 Sample)  
Reactor Coolant System Leak Detection (1 Sample)  
(1) 2.1.15, Daily Surveillance Log on February 27, 2018
(1) 2.1.15, Daily Surveillance Log on February 27, 2018
OTHER ACTIVITIES - BASELINE
OTHER ACTIVITIES - BASELINE
71151 - Performance Indicator Verification
71151 - Performance Indicator Verification
The inspectors verified Entergy's performance indicators submittals listed below for the period from January 1, 2017 through December 31, 2017. (3 Samples)  
The inspectors verified Entergys performance indicators submittals listed below for the
(1) Reactor coolant system specific activity
period from January 1, 2017 through December 31, 2017. (3 Samples)  
  (2) Reactor coolant system leak rate
(1) Reactor coolant system specific activity  
(3) Safety system functional failures
(2) Reactor coolant system leak rate  
(3) Safety system functional failures
71152 - Problem Identification and Resolution
71152 - Problem Identification and Resolution
Annual Follow-up of Selected Issues (1 Sample)
Annual Follow-up of Selected Issues (1 Sample)
The inspectors reviewed Entergy's implementation of its corrective action program related to the following issues:  
The inspectors reviewed Entergys implementation of its corrective action program related to
(1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15) deficiencies discovered during thermography
the following issues:  
(1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15)
deficiencies discovered during thermography
71153 - Follow-up of Events and Notices of Enforcement Discretion
71153 - Follow-up of Events and Notices of Enforcement Discretion
Personnel Performance (2 Sample)
Personnel Performance (2 Sample)
The inspectors evaluated response during the following non-routine evolutions or transients:  
The inspectors evaluated response during the following non-routine evolutions or transients:  
(1) Reactor scram due to loss of one offsite power line on January 4, 2018  
(1) Reactor scram due to loss of one offsite power line on January 4, 2018  
(2) Loss of offsite alternating current power on March 13, 2018
(2) Loss of offsite alternating current power on March 13, 2018
INSPECTION RESULTS
INSPECTION RESULTS
Observation 71152 Annual Follow-up of
Observation
Selected Issues The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the
71152
Annual Follow-up of
Selected Issues
The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the
past operability regarding the deficiencies discovered on the 23 kilovolt offsite power
past operability regarding the deficiencies discovered on the 23 kilovolt offsite power
supply to shutdown transformer circuit switcher during thermography. The inspectors concluded that the cause analysis was thorough, the extent of condition was reasonable, and the corrective actions were timely.
supply to shutdown transformer circuit switcher during thermography. The inspectors
concluded that the cause analysis was thorough, the extent of condition was reasonable,
and the corrective actions were timely.
EXIT MEETINGS AND DEBRIEFS
EXIT MEETINGS AND DEBRIEFS
Inspectors verified no proprietary information was retained or documented in this report.
Inspectors verified no proprietary information was retained or documented in this report.  
On January 11, 2018, the inspectors debriefed the inspection of the annual problem identification and resolution sample associated with the 23 kilovolt power offsite supply deficiencies with Mr.  
 
: [[contact::R. Byrne. On April 25]], 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.
On January 11, 2018, the inspectors debriefed the inspection of the annual problem
identification and resolution sample associated with the 23 kilovolt power offsite supply
deficiencies with Mr. R. Byrne.
On April 25, 2018, the inspectors presented the quarterly resident inspector inspection
results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.
THIRD PARTY REVIEWS
THIRD PARTY REVIEWS
Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the inspection period.  
Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the
inspection period.  


DOCUMENTS REVIEWED
DOCUMENTS REVIEWED
71111.15
71111.15
Procedure EN-OP-104, Operability Determination Process, Revision 15
Procedure
71111.18 Procedures EN-LI-100, Process Applicability Determination, Revision 22 EN-DC-136, Temporary Modifications, Revision 17
EN-OP-104, Operability Determination Process, Revision 15
71111.19 Procedure EN-WM-107, Post Maintenance Testing, Revision 5
71111.18
71152 Procedures EN-LI-102, Corrective Action Program, Revision 33
Procedures
EN-LI-100, Process Applicability Determination, Revision 22
EN-DC-136, Temporary Modifications, Revision 17
71111.19
Procedure
EN-WM-107, Post Maintenance Testing, Revision 5
71152
Procedures
EN-LI-102, Corrective Action Program, Revision 33
EN-LI-118, Cause Evaluation Process, Revision 26
EN-LI-118, Cause Evaluation Process, Revision 26
}}
}}

Latest revision as of 21:53, 5 January 2025

Integrated Inspection Report 05000293/2018001
ML18134A225
Person / Time
Site: Pilgrim
Issue date: 05/14/2018
From: Anthony Dimitriadis
NRC/RGN-I/DRP/PB5
To: Brian Sullivan
Entergy Nuclear Operations
Dimitriadis A
References
IR 2018001
Download: ML18134A225 (10)


Text

May 14, 2018

SUBJECT:

PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION REPORT 05000293/2018001

Dear Mr. Sullivan:

On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Pilgrim Nuclear Power Station (PNPS). On April 25, 2018, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects

Docket Number: 50-293 License Number: DPR-35

Enclosure:

Inspection Report 05000293/2018001

Inspection Report

Docket Number:

50-293

License Number:

DPR-35

Report Number:

05000293/2018001

Enterprise Identifier: I-2018-001-0047

Licensee:

Entergy Nuclear Operations, Inc. (Entergy)

Facility:

Pilgrim Nuclear Power Station (PNPS)

Location:

Plymouth, Massachusetts

Inspection Dates:

January 1, 2018 to March 31, 2018

Inspectors:

E. Carfang, Senior Resident Inspector

J. Krafty, Acting Senior Resident Inspector

B. Pinson, Resident Inspector

J. Pfingsten, Project Engineer

E. DiPaolo, Senior Reactor Inspector

Approved By:

A. Dimitriadis, Chief

Reactor Projects Branch 5

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergys performance at PNPS by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

No findings or more-than-minor violations were identified.

PLANT STATUS

The unit began the inspection period at rated thermal power. On January 4, 2018, operators scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators down powered the unit to 45 percent for a planned repair to a drain valve in the moisture separator drain tank. The operators returned the unit to rated thermal power the same day. On March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the main condenser after the March 2, 2018 noreaster. Operators returned the unit to rated thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating current power during a noreaster while the unit was in cold shutdown, and the startup transformer experienced an electrical fault during the storm. The unit remained in cold shutdown for the remainder of the inspection period to address issues in the switchyard.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures in effect at the beginning of the inspection unless otherwise noted. Currently approved inspection procedures with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the inspection procedure requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, and conducted routine reviews using Inspection Procedure 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Entergys performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather (4 Samples)

The inspectors evaluated readiness for impending adverse weather conditions for the following:

(1) Severe cold weather on January 2, 2018
(2) Blizzard conditions on January 3, 2018
(3) Noreaster on March 2-3, 2018
(4) Blizzard conditions on March 12-13, 2018

External Flooding (1 Sample)

The inspectors evaluated readiness to cope with external flooding the week of February 26, 2018.

71111.04 - Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Reactor core isolation cooling system walkdown with high pressure coolant injection system out of service for planned maintenance on February 7, 2018
(2) Control rod drive system B walkdown with control rod drive system A out of service for planned maintenance on February 26, 2018
(3) Emergency diesel generators A and B during loss of offsite power from March 13-16, 2018
(4) Offsite power backfeed alignment on March 22-23, 2018

Complete Walkdown (1 Sample)

The inspectors evaluated system configurations during a complete walkdown of the station blackout diesel generator system on March 1, 2018.

71111.05A/Q - Fire Protection Annual/Quarterly

Quarterly Inspection (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) High pressure coolant injection on February 13, 2018
(2) Main condenser bay on March 10, 2018
(3) Condensate pump on March 21, 2018
(4) Radioactive waste control corridor on March 21, 2018
(5) Turbine building truck lock and hydrogen seal oil area on March 22, 2018

Annual Inspection (1 Sample)

The inspectors evaluated fire brigade performance on January 23, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed and evaluated licensed operator requalification training, in accordance with 10 CFR 55.59, at PNPS on February 8, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated licensed operator performance in the control room during plant startup following a forced outage on January 10, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (3 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Instrument air system on February 2, 2018
(2) Reactor protection system on February 2, 2018
(3) Reactor building 23 level structural monitoring the weeks of March 19 and March 26, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Decay heat removal short time to boil on January 5, 2018
(2) Testing of the station blackout diesel generator halon system on January 19, 2018
(3) Logic system functional testing of emergency diesel generator A on January 23, 2018
(4) Station blackout diesel generator and instrument air compressor unavailability on February 21, 2018
(5) Low pressure core injection diagnostic valve testing on March 8, 2018
(6) Movement of the spare startup transformer into the switchyard on March 29, 2018

71111.15 - Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018
(2) Control room high efficiency air filtration system train B filter testing identified bypass around the downstream high efficiency particulate air filter on February 6, 2018
(3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed surveillance on February 20, 2018
(4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018

71111.18 - Plant Modifications

The inspectors evaluated the following temporary or permanent modifications:

(1) Temporary heating to fire water storage tanks on March 15, 2018

71111.19 - Post Maintenance Testing

The inspectors evaluated post maintenance testing for the following maintenance/repair activities:

(1) Safety relief valve 3B pilot valve replacement on January 10, 2018
(2) K-111 instrument air compressor motor replacement on January 30, 2018
(3) High pressure coolant injection steam line drain line level control switch replacement on February 8, 2018
(4) Salt service water pump E baseplate injection performed on February 8, 2018
(5) K-110 instrument air compressor motor replacement performed on February 22, 2018

71111.20 - Refueling and Other Outage Activities

The inspectors evaluated Entergys forced outage activities from:

(1) January 4 to January 10, 2018
(2) March 6 to March 31, 2018

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine

(1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test on January 19, 2018
(2) 8.M.2-2.10.8.1, Diesel Generator A Initiation by Residual Heat Removal Logic on January 23, 2018
(3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018
(4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on February 22, 2018

Reactor Coolant System Leak Detection (1 Sample)

(1) 2.1.15, Daily Surveillance Log on February 27,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified Entergys performance indicators submittals listed below for the period from January 1, 2017 through December 31, 2017.===

(1) Reactor coolant system specific activity
(2) Reactor coolant system leak rate
(3) Safety system functional failures

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (1 Sample)

The inspectors reviewed Entergys implementation of its corrective action program related to the following issues:

(1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15)deficiencies discovered during thermography

71153 - Follow-up of Events and Notices of Enforcement Discretion Personnel Performance

The inspectors evaluated response during the following non-routine evolutions or transients:

(1) Reactor scram due to loss of one offsite power line on January 4, 2018
(2) Loss of offsite alternating current power on March 13,

INSPECTION RESULTS

Observation 71152 Annual Follow-up of Selected Issues The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the past operability regarding the deficiencies discovered on the 23 kilovolt offsite power supply to shutdown transformer circuit switcher during thermography. The inspectors concluded that the cause analysis was thorough, the extent of condition was reasonable, and the corrective actions were timely.

EXIT MEETINGS AND DEBRIEFS

Inspectors verified no proprietary information was retained or documented in this report.

On January 11, 2018, the inspectors debriefed the inspection of the annual problem identification and resolution sample associated with the 23 kilovolt power offsite supply deficiencies with Mr. R. Byrne.

On April 25, 2018, the inspectors presented the quarterly resident inspector inspection results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.

THIRD PARTY REVIEWS

Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the inspection period.

DOCUMENTS REVIEWED

71111.15

Procedure

EN-OP-104, Operability Determination Process, Revision 15

71111.18

Procedures

EN-LI-100, Process Applicability Determination, Revision 22

EN-DC-136, Temporary Modifications, Revision 17

71111.19

Procedure

EN-WM-107, Post Maintenance Testing, Revision 5

71152

Procedures

EN-LI-102, Corrective Action Program, Revision 33

EN-LI-118, Cause Evaluation Process, Revision 26

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BOULEVARD, SUITE 100

KING OF PRUSSIA, PENNSLYVANIA 19406-2713

May 14, 2018

Mr. Brian Sullivan

Site Vice President

Pilgrim Nuclear Power Station

Entergy Nuclear Operations, Inc.

600 Rocky Hill Road

Plymouth, MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - INTEGRATED INSPECTION

REPORT 05000293/2018001

Dear Mr. Sullivan:

On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at Pilgrim Nuclear Power Station (PNPS). On April 25, 2018, the NRC inspectors discussed the

results of this inspection with you and other members of your staff. The results of this

inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection

and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room

in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public

Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Anthony Dimitriadis, Chief

Reactor Projects Branch 5

Division of Reactor Projects

Docket Number: 50-293

License Number: DPR-35

Enclosure:

Inspection Report 05000293/2018001

cc w/encl: Distribution via ListServ

ML18134A225

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RI/DRP

RI/DRP

RI/DRP

NAME

ECarfang via email

LCline via email

ADimitriadis

DATE

5/14/18

5/14/18

5/14/18

U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number:

50-293

License Number:

DPR-35

Report Number:

05000293/2018001

Enterprise Identifier: I-2018-001-0047

Licensee:

Entergy Nuclear Operations, Inc. (Entergy)

Facility:

Pilgrim Nuclear Power Station (PNPS)

Location:

Plymouth, Massachusetts

Inspection Dates:

January 1, 2018 to March 31, 2018

Inspectors:

E. Carfang, Senior Resident Inspector
J. Krafty, Acting Senior Resident Inspector
B. Pinson, Resident Inspector
J. Pfingsten, Project Engineer
E. DiPaolo, Senior Reactor Inspector

Approved By:

A. Dimitriadis, Chief

Reactor Projects Branch 5

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Entergys performance

at PNPS by conducting the baseline inspections described in this report in accordance with the

Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for

overseeing the safe operation of commercial nuclear power reactors. Refer to

https://www.nrc.gov/reactors/operating/oversight.html for more information.

No findings or more-than-minor violations were identified.

PLANT STATUS

The unit began the inspection period at rated thermal power. On January 4, 2018, operators

scrammed the unit based on an anticipated loss of offsite power during a winter storm. The unit

was returned to rated thermal power on January 11, 2018. On January 25, 2018, operators

down powered the unit to 45 percent for a planned repair to a drain valve in the moisture

separator drain tank. The operators returned the unit to rated thermal power the same day. On

March 4, 2018, operators lowered power to 50 percent to perform a thermal backwash of the

main condenser after the March 2, 2018 noreaster. Operators returned the unit to rated

thermal power on March 5, 2018. On March 6, 2018, operators shutdown the unit to perform

repairs to the fifth point feedwater heater. On March 13, 2018, the site lost all offsite alternating

current power during a noreaster while the unit was in cold shutdown, and the startup

transformer experienced an electrical fault during the storm. The unit remained in cold

shutdown for the remainder of the inspection period to address issues in the switchyard.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures in effect

at the beginning of the inspection unless otherwise noted. Currently approved inspection

procedures with their attached revision histories are located on the public website at

http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the inspection procedure requirements most

appropriate to the inspection activity were met consistent with Inspection Manual Chapter 2515,

Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant

status activities described in Inspection Manual Chapter 2515, Appendix D, Plant Status, and

conducted routine reviews using Inspection Procedure 71152, Problem Identification and

Resolution. The inspectors reviewed selected procedures and records, observed activities,

and interviewed personnel to assess Entergys performance and compliance with Commission

rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather (4 Samples)

The inspectors evaluated readiness for impending adverse weather conditions for the

following:

(1) Severe cold weather on January 2, 2018

(2) Blizzard conditions on January 3, 2018

(3) Noreaster on March 2-3, 2018

(4) Blizzard conditions on March 12-13, 2018

External Flooding (1 Sample)

The inspectors evaluated readiness to cope with external flooding the week of February 26,

2018.

71111.04 - Equipment Alignment

Partial Walkdown (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following

systems/trains:

(1) Reactor core isolation cooling system walkdown with high pressure coolant injection

system out of service for planned maintenance on February 7, 2018

(2) Control rod drive system B walkdown with control rod drive system A out of service for

planned maintenance on February 26, 2018

(3) Emergency diesel generators A and B during loss of offsite power from March 13-16,

2018

(4) Offsite power backfeed alignment on March 22-23, 2018

Complete Walkdown (1 Sample)

The inspectors evaluated system configurations during a complete walkdown of the station

blackout diesel generator system on March 1, 2018.

71111.05A/Q - Fire Protection Annual/Quarterly

Quarterly Inspection (5 Samples)

The inspectors evaluated fire protection program implementation in the following selected

areas:

(1) High pressure coolant injection on February 13, 2018

(2) Main condenser bay on March 10, 2018

(3) Condensate pump on March 21, 2018

(4) Radioactive waste control corridor on March 21, 2018

(5) Turbine building truck lock and hydrogen seal oil area on March 22, 2018

Annual Inspection (1 Sample)

The inspectors evaluated fire brigade performance on January 23, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed and evaluated licensed operator requalification training, in

accordance with 10 CFR 55.59, at PNPS on February 8, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated licensed operator performance in the control room

during plant startup following a forced outage on January 10, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (3 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated

with the following equipment and/or safety significant functions:

(1) Instrument air system on February 2, 2018

(2) Reactor protection system on February 2, 2018

(3) Reactor building 23 level structural monitoring the weeks of March 19 and March 26,

2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control (6 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent

work activities:

(1) Decay heat removal short time to boil on January 5, 2018

(2) Testing of the station blackout diesel generator halon system on January 19, 2018

(3) Logic system functional testing of emergency diesel generator A on January 23, 2018

(4) Station blackout diesel generator and instrument air compressor unavailability on

February 21, 2018

(5) Low pressure core injection diagnostic valve testing on March 8, 2018

(6) Movement of the spare startup transformer into the switchyard on March 29, 2018

71111.15 - Operability Determinations and Functionality Assessments (4 Samples)

The inspectors evaluated the following operability determinations and functionality

assessments:

(1) Safety relief valve 3B elevated tailpipe temperature on January 11, 2018

(2) Control room high efficiency air filtration system train B filter testing identified bypass

around the downstream high efficiency particulate air filter on February 6, 2018

(3) Reactor water cleanup valve, MO-1201-5, following discovery of a never performed

surveillance on February 20, 2018

(4) Low pressure core injection diagnostic and stem rotation testing on March 8, 2018

71111.18 - Plant Modifications (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Temporary heating to fire water storage tanks on March 15, 2018

71111.19 - Post Maintenance Testing (5 Samples)

The inspectors evaluated post maintenance testing for the following maintenance/repair

activities:

(1) Safety relief valve 3B pilot valve replacement on January 10, 2018

(2) K-111 instrument air compressor motor replacement on January 30, 2018

(3) High pressure coolant injection steam line drain line level control switch replacement on

February 8, 2018

(4) Salt service water pump E baseplate injection performed on February 8, 2018

(5) K-110 instrument air compressor motor replacement performed on February 22, 2018

71111.20 - Refueling and Other Outage Activities (2 Samples)

The inspectors evaluated Entergys forced outage activities from:

(1) January 4 to January 10, 2018

(2) March 6 to March 31, 2018

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine (4 Samples)

(1) 8.M.2-3.6.5, Neutron Monitoring System Flow Converter Functional and Calibration Test

on January 19, 2018

(2) 8.M.2-2.10.8.1, Diesel Generator A Initiation by Residual Heat Removal Logic on

January 23, 2018

(3) 7.1.30, HEPA Filter and Charcoal Performance Test on February 6, 2018

(4) 8.M.2-1.5.8.3, Logic System Functional Test of System A Standby Gas Treatment

Initiation - Reactor Building Isolation and Inboard Drywell Isolation Valves on

February 22, 2018

Reactor Coolant System Leak Detection (1 Sample)

(1) 2.1.15, Daily Surveillance Log on February 27, 2018

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified Entergys performance indicators submittals listed below for the

period from January 1, 2017 through December 31, 2017. (3 Samples)

(1) Reactor coolant system specific activity

(2) Reactor coolant system leak rate

(3) Safety system functional failures

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (1 Sample)

The inspectors reviewed Entergys implementation of its corrective action program related to

the following issues:

(1) 23 kilovolt offsite power supply to shutdown transformer circuit switcher (X-15)

deficiencies discovered during thermography

71153 - Follow-up of Events and Notices of Enforcement Discretion

Personnel Performance (2 Sample)

The inspectors evaluated response during the following non-routine evolutions or transients:

(1) Reactor scram due to loss of one offsite power line on January 4, 2018

(2) Loss of offsite alternating current power on March 13, 2018

INSPECTION RESULTS

Observation

71152

Annual Follow-up of

Selected Issues

The inspectors reviewed the apparent cause analysis, the corrective actions taken, and the

past operability regarding the deficiencies discovered on the 23 kilovolt offsite power

supply to shutdown transformer circuit switcher during thermography. The inspectors

concluded that the cause analysis was thorough, the extent of condition was reasonable,

and the corrective actions were timely.

EXIT MEETINGS AND DEBRIEFS

Inspectors verified no proprietary information was retained or documented in this report.

On January 11, 2018, the inspectors debriefed the inspection of the annual problem

identification and resolution sample associated with the 23 kilovolt power offsite supply

deficiencies with Mr. R. Byrne.

On April 25, 2018, the inspectors presented the quarterly resident inspector inspection

results to Mr. Brian Sullivan, Site Vice President, and other members of Entergy staff.

THIRD PARTY REVIEWS

Inspectors reviewed Institute of Nuclear Power Operations reports that were issued during the

inspection period.

DOCUMENTS REVIEWED

71111.15

Procedure

EN-OP-104, Operability Determination Process, Revision 15

71111.18

Procedures

EN-LI-100, Process Applicability Determination, Revision 22

EN-DC-136, Temporary Modifications, Revision 17

71111.19

Procedure

EN-WM-107, Post Maintenance Testing, Revision 5

71152

Procedures

EN-LI-102, Corrective Action Program, Revision 33

EN-LI-118, Cause Evaluation Process, Revision 26