{{#Wiki_filter:Attachment 3 to ULNRC-06780 Page 1 of 11 Revised Technical Specification Pages (Markup)
{{#Wiki_filter:Attachment 3 to ULNRC-06780 Page 1 of 11 Revised Technical Specification Pages (Markup)
(10 pages follow this cover sheet)
(10 pages follow this cover sheet)  


CompletionTimes 1.3 1.3 Completion Times EXAMPLES          EXAMPLE 1.3-3 (continued)
CompletionTimes 1.3 1.3 Completion Times (continued)
ACTIONS COMPLETION CONDITION       REQUIRED ACTION           TIME A   One         A.1 Restore Function X 7 days Function X       train to OPERABLE train            status.            AND inoperable.
Amendment 133 CALLAWAY PLANT 1.3-6 EXAMPLE 1.3-3 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A
10 days from discovery of failure to meet the LCO B. One         B.1 Restore Function Y 72 hours Function Y       train to OPERABLE train           status.            AND inoperable.
One A.1 Restore Function X train to OPERABLE status.
10 days from discovery of failure to meet the LCO C. One         C.1 Restore Function X 72 hours Function X      train to OPERABLE train            status.
7 days Function X train AND inoperable.
inoperable.
10 days from discovery of failure to meet the LCO B.
OR AND C.2 Restore Function Y 72 hours One              train to OPERABLE Function Y      status.
One B.1 Restore Function Y train to OPERABLE status.
train inoperable.
72 hours Function Y train AND inoperable.
(continued)
10 days from discovery of failure to meet the LCO C.
CALLAWAY                              1.3-6                      Amendment 133 PLANT
One C.1 Restore Function X train to OPERABLE status.
OR C.2 Restore Function Y train to OPERABLE status.
72 hours Function X train inoperable.
AND 72 hours One Function Y train inoperable.
EXAMPLES (continued)


RTS Instrumentation 3.3.1 TABLE 3.3.1-1 (page 5 of 8)
RTS Instrumentation 3.3.1 CALLAWAY PLANT 3.3-23 Amendment No. 202 TABLE 3.3.1-1 (page 5 of 8)
Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED         REQUIRED                         SURVEILLANCE         ALLOWABLE FUNCTION              CONDITIONS        CHANNELS        CONDITIONS      REQUIREMENTS        VALUE(a)
Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED CONDITIONS REQUIRED CHANNELS SURVEILLANCE REQUIREMENTS ALLOWABLE VALUE(a)
: 16. Turbine Trip
FUNCTION CONDITIONS 16.
: a. Low Fluid Oil   1(j)               3               OM               SR 3.3.1.10           539.42 psig Pressure                                                            SR 3.3.1.15
Turbine Trip a.
: b. Turbine Stop 1(j)                 4               PN               SR 3.3.1.10           1% open Valve Closure                                                      SR 3.3.1.15
Low Fluid Oil Pressure 1(j) 3 OM SR 3.3.1.10 SR 3.3.1.15 539.42 psig b.
: 17. Safety Injection       1, 2               2 trains       QP               SR 3.3.1.14         NA (SI) Input from Engineered Safety Feature Actuation System (ESFAS)
Turbine Stop Valve Closure 1(j) 4 PN SR 3.3.1.10 SR 3.3.1.15 1% open 17.
: 18. Reactor Trip System Interlocks
Safety Injection (SI) Input from Engineered Safety Feature Actuation System (ESFAS) 1, 2 2 trains QP SR 3.3.1.14 NA 18.
: a. Intermediate 2(e)                 2               SR               SR 3.3.1.11           6E-11 amp Range                                                              SR 3.3.1.13 Neutron Flux, P-6
Reactor Trip System Interlocks a.
: b. Low Power       1                 1 per train     TS               SR 3.3.1.5           NA Reactor Trips Block, P-7
Intermediate Range Neutron Flux, P-6 2(e) 2 SR SR 3.3.1.11 SR 3.3.1.13 6E-11 amp b.
: c. Power Range 1                     4               TS               SR 3.3.1.11           51.3% RTP Neutron Flux,                                                      SR 3.3.1.13 P-8
Low Power Reactor Trips Block, P-7 1
: d. Power Range 1                     4               TS               SR 3.3.1.11           53.3% RTP Neutron Flux,                                                      SR 3.3.1.13 P-9 (a) The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.
1 per train TS SR 3.3.1.5 NA c.
(e) Below the P-6 (Intermediate Range Neutron Flux) interlock.
Power Range Neutron Flux, P-8 1
(j) Above the P-9 (Power Range Neutron Flux) interlock.
4 TS SR 3.3.1.11 SR 3.3.1.13 51.3% RTP d.
CALLAWAY PLANT                                            3.3-23                                Amendment No. 202
Power Range Neutron Flux, P-9 1
4 TS SR 3.3.1.11 SR 3.3.1.13 53.3% RTP (a)
The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.
(e)
Below the P-6 (Intermediate Range Neutron Flux) interlock.
(j)
Above the P-9 (Power Range Neutron Flux) interlock.


RTS Instrumentation 3.3.1 TABLE 3.3.1-1 (page 6 of 8)
RTS Instrumentation 3.3.1 CALLAWAY PLANT 3.3-24 Amendment No. 202 TABLE 3.3.1-1 (page 6 of 8)
Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED           REQUIRED                       SURVEILLANCE         ALLOWABLE FUNCTION            CONDITIONS          CHANNELS        CONDITIONS      REQUIREMENTS        VALUE(a)
Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED CONDITIONS REQUIRED CHANNELS SURVEILLANCE REQUIREMENTS ALLOWABLE VALUE(a)
: 18. Reactor Trip System Interlocks
FUNCTION CONDITIONS 18.
: e. Power       1, 2               4               SR             SR 3.3.1.11           6.7% RTP and Range                                                          SR 3.3.1.13         12.4% RTP Neutron Flux, P-10
Reactor Trip System Interlocks e.
: f. Turbine      1                  2               TS             SR 3.3.1.10           12.4% turbine Impulse                                                        SR 3.3.1.13         power Pressure, P-13
Power Range Neutron Flux, P-10 1, 2 4
: 19. Reactor Trip           1, 2               2 trains       RQ             SR 3.3.1.4           NA Breakers (RTBs)(k) 3(b), 4(b), 5(b)   2 trains       C               SR 3.3.1.4           NA
SR SR 3.3.1.11 SR 3.3.1.13 6.7% RTP and 12.4% RTP f.
: 20. Reactor Trip           1, 2               1 each per     U               SR 3.3.1.4           NA Breaker                                  RTB Undervoltage and Shunt Trip            3(b), 4(b), 5(b)   1 each per     C               SR 3.3.1.4           NA Mechanisms(k)                            RTB
Turbine Impulse
: 21. Automatic Trip         1, 2               2 trains       QP             SR 3.3.1.5           NA Logic 3(b), 4(b), 5(b)   2 trains       C               SR 3.3.1.5           NA (a) The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.
: Pressure, P-13 1
(b) With Rod Control System capable of rod withdrawal or one or more rods not fully inserted.
2 TS SR 3.3.1.10 SR 3.3.1.13 12.4% turbine power 19.
(k) Including any reactor trip bypass breakers that are racked in and closed for bypassing an RTB.
Reactor Trip Breakers (RTBs)(k) 1, 2 2 trains RQ SR 3.3.1.4 NA 3(b), 4(b), 5(b) 2 trains C
CALLAWAY PLANT                                            3.3-24                                Amendment No. 202
SR 3.3.1.4 NA 20.
Reactor Trip Breaker Undervoltage and Shunt Trip Mechanisms(k) 1, 2 1 each per RTB U
SR 3.3.1.4 NA 3(b), 4(b), 5(b) 1 each per RTB C
SR 3.3.1.4 NA 21.
Automatic Trip Logic 1, 2 2 trains QP SR 3.3.1.5 NA 3(b), 4(b), 5(b) 2 trains C
SR 3.3.1.5 NA (a)
The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.
(b)
With Rod Control System capable of rod withdrawal or one or more rods not fully inserted.
(k)
Including any reactor trip bypass breakers that are racked in and closed for bypassing an RTB.


ESFAS Instrumentation 3.3.2 ACTIONS (continued)
ESFAS Instrumentation 3.3.2 CALLAWAY PLANT 3.3-31 Amendment No. 202 ACTIONS (continued)
CONDITION                         REQUIRED ACTION                             COMPLETION TIME H. One or more trains     --------------------------NOTE-----------------------
CONDITION REQUIRED ACTION COMPLETION TIME H.
inoperable.            One train may be bypassed for up to 4 hours for surveillance testing provided the other train is OPERABLE.
One or more trains inoperable.
H.1               Declare associated                     Immediately Pressurizer PORV(s) inoperable.
--------------------------NOTE-----------------------
I. One channel inoperable. --------------------------NOTE-----------------------
One train may be bypassed for up to 4 hours for surveillance testing provided the other train is OPERABLE.
H.1 Declare associated Pressurizer PORV(s) inoperable.
Immediately I.
One channel inoperable.
--------------------------NOTE-----------------------
The inoperable channel may be bypassed for up to 12 hours for surveillance testing of other channels.
The inoperable channel may be bypassed for up to 12 hours for surveillance testing of other channels.
I.1               Place channel in trip.                 72 hours OR In accordance with the Risk Informed Completion Time Program OR I.2               Be in MODE 3.                           78 hours J. One channel inoperable. --------------------------NOTE-----------------------
I.1 Place channel in trip.
72 hours OR In accordance with the Risk Informed Completion Time Program OR I.2 Be in MODE 3.
78 hours J.
One channel inoperable.
--------------------------NOTE-----------------------
The inoperable channel may be bypassed for up to 2 hours for surveillance testing of other channels.
The inoperable channel may be bypassed for up to 2 hours for surveillance testing of other channels.
J.1               Place channel in trip.                 24 hours OR In accordance with the Risk Informed Completion Time Program OR J.2               Be in MODE 3.                           30 hours CALLAWAY PLANT                        3.3-31                                  Amendment No. 202
J.1 Place channel in trip.
24 hours OR In accordance with the Risk Informed Completion Time Program OR J.2 Be in MODE 3.
30 hours  


ECCS - Operating 3.5.2 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS - Operating LCO 3.5.2             Two ECCS trains shall be OPERABLE.
ECCS - Operating 3.5.2 CALLAWAY PLANT 3.5-4 Amendment No. 202 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS - Operating ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A.
                      ------------------------------------------- NOTES --------------------------------------------
One or more trains inoperable.
: 1.       In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours to perform pressure isolation valve testing per SR 3.4.14.1.
AND At least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available.
: 2.       Operation in MODE 3 with ECCS pumps made incapable of injecting, pursuant to LCO 3.4.12, Cold Overpressure Mitigation System, is allowed for up to 4 hours or until the temperature of all RCS cold legs exceeds 375°F, whichever comes first.
A.1 Restore train(s) to OPERABLE status.
APPLICABILITY:       MODES 1, 2, and 3.
72 hours OR In accordance with the Risk Informed Completion Time Program B.
ACTIONS CONDITION                                  REQUIRED ACTION                                COMPLETION TIME A. One or more trains                A.1              Restore train(s) to                      72 hours inoperable.                                          OPERABLE status.
Required Action and associated Completion Time not met.
OR AND In accordance with At least 100% of the ECCS                                                                    the Risk Informed flow equivalent to a single                                                                  Completion Time OPERABLE ECCS train                                                                          Program available.
B.1 Be in MODE 3.
B. Required Action and                  B.1              Be in MODE 3.                            6 hours associated Completion Time not met.
6 hours AND B.2 Be in MODE 4.
AND B.2              Be in MODE 4.                            12 hours CALLAWAY PLANT                                        3.5-4                                  Amendment No. 202
12 hours LCO 3.5.2 Two ECCS trains shall be OPERABLE.
------------------------------------------- NOTES --------------------------------------------
1.
In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours to perform pressure isolation valve testing per SR 3.4.14.1.
2.
Operation in MODE 3 with ECCS pumps made incapable of injecting, pursuant to LCO 3.4.12, Cold Overpressure Mitigation System, is allowed for up to 4 hours or until the temperature of all RCS cold legs exceeds 375°F, whichever comes first.
APPLICABILITY:
MODES 1, 2, and 3.  


MSIVs, MSIVBVs, and MSLPDIVs 3.7.2 3.7 PLANT SYSTEMS 3.7.2 Main Steam Isolation Valves (MSIVs), Main Steam Isolation Valve Bypass Valves (MSIVBVs), and Main Steam Low Point Drain Isolation Valves (MSLPDIVs)
MSIVs, MSIVBVs, and MSLPDIVs 3.7.2 CALLAWAY PLANT 3.7-5 Amendment No. 197 3.7 PLANT SYSTEMS 3.7.2 Main Steam Isolation Valves (MSIVs), Main Steam Isolation Valve Bypass Valves (MSIVBVs), and Main Steam Low Point Drain Isolation Valves (MSLPDIVs)
LCO 3.7.2           The MSIV and its associated actuator trains, the MSIVBV, and the MSLPDIV in each of the four main steam lines shall be OPERABLE.
LCO 3.7.2 APPLICABILITY:
APPLICABILITY:      For the MSIV and its associated actuator trains in each main steam line:
The MSIV and its associated actuator trains, the MSIVBV, and the MSLPDIV in each of the four main steam lines shall be OPERABLE.
For the MSIV and its associated actuator trains in each main steam line:
MODE 1, MODE 2 and 3 except when the MSIV is closed and de-activated.
MODE 1, MODE 2 and 3 except when the MSIV is closed and de-activated.
For the MSIVBV in each main steam line:
For the MSIVBV in each main steam line:
MODES 1, 2, and 3 except when:
MODES 1, 2, and 3 except when:
: a. MSIVBV is closed and de-activated, or
: a. MSIVBV is closed and de-activated, or
: b. MSIVBV is closed and isolated by a closed manual valve, or
: b. MSIVBV is closed and isolated by a closed manual valve, or c.
: c. MSIVBV is isolated by two closed manual valves.
MSIVBV is isolated by two closed manual valves.
For the MSLPDIV in each main steam line:
For the MSLPDIV in each main steam line:
MODES 1, 2, and 3 except when:
MODES 1, 2, and 3 except when:
: a. MSLPDIV is closed and de-activated, or
: a. MSLPDIV is closed and de-activated, or
: b. MSLPDIV is closed and isolated by a closed manual valve, or
: b. MSLPDIV is closed and isolated by a closed manual valve, or c.
: c. MSLPDIV is isolated by two closed manual valves.
MSLPDIV is isolated by two closed manual valves.
ACTIONS CONDITION                     REQUIRED ACTION                     COMPLETION TIME A. One MSIV actuator train     A.1           Restore MSIV actuator       72 hours inoperable.                              train to OPERABLE OR status.
ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One MSIV actuator train inoperable.
In accordance with the Risk Informed Completion Time Program (continued)
A.1 Restore MSIV actuator train to OPERABLE status.
CALLAWAY PLANT                              3.7-5                          Amendment No. 197
72 hours OR In accordance with the Risk Informed Completion Time Program (continued)  


AFW System 3.7.5 3.7 PLANT SYSTEMS 3.7.5 Auxiliary Feedwater (AFW) System LCO 3.7.5                     Three AFW trains shall be OPERABLE.
AFW System 3.7.5 CALLAWAY PLANT 3.7-15 Amendment No. 198 3.7 PLANT SYSTEMS 3.7.5 Auxiliary Feedwater (AFW) System LCO 3.7.5 Three AFW trains shall be OPERABLE.
APPLICABILITY:               MODE 1, 2, and 3.
APPLICABILITY:
ACTIONS
MODE 1, 2, and 3.
ACTIONS  
-----------------------------------------------------------------NOTE-----------------------------------------------------------------
-----------------------------------------------------------------NOTE-----------------------------------------------------------------
LCO 3.0.4.b is not applicable when entering MODE 1.
LCO 3.0.4.b is not applicable when entering MODE 1.
CONDITION                                   REQUIRED ACTION                               COMPLETION TIME A. One steam supply to                       A.1               Restore steam supply to           7 days turbine driven AFW pump                                    OPERABLE status.
CONDITION REQUIRED ACTION COMPLETION TIME A. One steam supply to turbine driven AFW pump inoperable.
OR inoperable.
A.1 Restore steam supply to OPERABLE status.
In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO B. One ESW supply to turbine                 B.1               Restore ESW supply to             72 hours driven AFW pump                                          OPERABLE status.
7 days OR In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO B. One ESW supply to turbine driven AFW pump inoperable.
OR inoperable.
B.1 Restore ESW supply to OPERABLE status.
In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO (continued)
72 hours OR In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO (continued)  
CALLAWAY PLANT                                            3.7-15                                  Amendment No. 198


AC Sources - Operating 3.8.1 ACTIONS (continued)
AC Sources - Operating 3.8.1 CALLAWAY PLANT 3.8.5 Amendment No. 186 CONDITION REQUIRED ACTION COMPLETION TIME C.
CONDITION                   REQUIRED ACTION                             COMPLETION TIME C. Two offsite circuits C.2                Restore one offsite circuit 24 hours inoperable.                            to OPERABLE status.
Two offsite circuits inoperable.
OR (continued)
In accordance with the Risk Informed Completion Time Program D. One offsite circuit  ----------------------NOTE-------------------
inoperable.
Enter applicable Conditions and Required Actions of LCO 3.8.9, AND Distribution Systems - Operating, when Condition D is entered with no One DG inoperable.
AC power source to any train.
D.1                Restore offsite circuit to      12 hours OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program OR D.2                Restore DG to                    12 hours OPERABLE status.
OR In accordance with the Risk Informed Completion Time Program E. Two DGs inoperable. E.1                Restore one DG to                2 hours OPERABLE status.
(continued)
(continued)
CALLAWAY PLANT                          3.8.5                                Amendment No. 186
C.2 Restore one offsite circuit to OPERABLE status.
24 hours OR In accordance with the Risk Informed Completion Time Program D. One offsite circuit inoperable.
----------------------NOTE-------------------
Enter applicable Conditions and Required Actions of LCO 3.8.9, Distribution Systems - Operating, when Condition D is entered with no AC power source to any train.
AND One DG inoperable.
D.1 Restore offsite circuit to OPERABLE status.
12 hours OR In accordance with the Risk Informed Completion Time Program OR D.2 Restore DG to OPERABLE status.
12 hours OR In accordance with the Risk Informed Completion Time Program E. Two DGs inoperable.
E.1 Restore one DG to OPERABLE status.
2 hours (continued)
ACTIONS (continued)


AC Sources - Operating 3.8.1 ACTIONS (continued)
AC Sources - Operating 3.8.1 CALLAWAY PLANT 3.8-6 Amendment No. 202 ACTIONS (continued)
CONDITION                               REQUIRED ACTION                       COMPLETION TIME F. One required LSELS                 F.1             Declare the affected DG       Immediately inoperable.                                        and offsite circuit inoperable.
CONDITION REQUIRED ACTION COMPLETION TIME F. One required LSELS inoperable.
AND F.2             Restore required LSELS         12 hours to OPERABLE status.
F.1 Declare the affected DG and offsite circuit inoperable.
OR In accordance with the Risk Informed Completion Time Program G. Required Action and                 G.1              Be in MODE 3.                6 hours associated Completion Time of Condition A, B, C, D, E,       AND or F not met.
Immediately AND F.2 Restore required LSELS to OPERABLE status.
G.2             Be in MODE 5.                 36 hours H. Three or more AC sources           H.1             Enter LCO 3.0.3.             Immediately inoperable.
12 hours OR In accordance with the Risk Informed Completion Time Program G. Required Action and associated Completion Time of Condition A, B, C, D, E, or F not met.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                                           FREQUENCY SR 3.8.1.1   Verify correct breaker alignment and indicated power             In accordance availability for each required offsite circuit.                   with the Surveillance Frequency Control Program (continued)
G.1 Be in MODE 3.
CALLAWAY PLANT                                3.8-6                              Amendment No. 202
6 hours AND G.2 Be in MODE 5.
36 hours H. Three or more AC sources inoperable.
H.1 Enter LCO 3.0.3.
Immediately SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.1.1 Verify correct breaker alignment and indicated power availability for each required offsite circuit.
In accordance with the Surveillance Frequency Control Program (continued)  


Distribution Systems - Operating 3.8.9 ACTIONS (continued)
Distribution Systems - Operating 3.8.9 CALLAWAY PLANT 3.8-39 Amendment No. 202 ACTIONS (continued)
CONDITION                           REQUIRED ACTION                   COMPLETION TIME C. One DC electrical power         C.1           Restore DC electrical       2 hours distribution subsystem                        power distribution OR inoperable.                                    subsystem to OPERABLE status.           In accordance with the Risk Informed Completion Time Program AND 16 hours from discovery of failure to meet LCO D. Required Action and             D.1           Be in MODE 3.               6 hours associated Completion Time not met.                    AND D.2           Be in MODE 5.               36 hours E. Two trains with inoperable       E.1           Enter LCO 3.0.3.             Immediately distribution subsystems that result in a loss of safety function.
CONDITION REQUIRED ACTION COMPLETION TIME C.
SURVEILLANCE REQUIREMENTS SURVEILLANCE                                     FREQUENCY SR 3.8.9.1       Verify correct breaker alignments and voltage to         In accordance required AC, DC, and AC vital bus electrical power       with the distribution subsystems.                                 Surveillance Frequency Control Program CALLAWAY PLANT                                3.8-39                        Amendment No. 202}}
One DC electrical power distribution subsystem inoperable.
C.1 Restore DC electrical power distribution subsystem to OPERABLE status.
2 hours OR In accordance with the Risk Informed Completion Time Program AND 16 hours from discovery of failure to meet LCO D.
Required Action and associated Completion Time not met.
D.1 Be in MODE 3.
6 hours AND D.2 Be in MODE 5.
36 hours E.
Two trains with inoperable distribution subsystems that result in a loss of safety function.
E.1 Enter LCO 3.0.3.
Immediately SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.9.1 Verify correct breaker alignments and voltage to required AC, DC, and AC vital bus electrical power distribution subsystems.
In accordance with the Surveillance Frequency Control Program}}

Latest revision as of 12:01, 27 November 2024

Revised Technical Specification Pages (Markup)
ML22334A259
Person / Time
Site: Callaway Ameren icon.png
Issue date: 11/30/2022
From:
Ameren Missouri, Union Electric Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML22334A255 List:
References
ULNRC-06780
Download: ML22334A259 (1)


Text

Attachment 3 to ULNRC-06780 Page 1 of 11 Revised Technical Specification Pages (Markup)

(10 pages follow this cover sheet)

CompletionTimes 1.3 1.3 Completion Times (continued)

Amendment 133 CALLAWAY PLANT 1.3-6 EXAMPLE 1.3-3 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A

One A.1 Restore Function X train to OPERABLE status.

7 days Function X train AND inoperable.

10 days from discovery of failure to meet the LCO B.

One B.1 Restore Function Y train to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Function Y train AND inoperable.

10 days from discovery of failure to meet the LCO C.

One C.1 Restore Function X train to OPERABLE status.

OR C.2 Restore Function Y train to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Function X train inoperable.

AND 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> One Function Y train inoperable.

EXAMPLES (continued)

RTS Instrumentation 3.3.1 CALLAWAY PLANT 3.3-23 Amendment No. 202 TABLE 3.3.1-1 (page 5 of 8)

Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED CONDITIONS REQUIRED CHANNELS SURVEILLANCE REQUIREMENTS ALLOWABLE VALUE(a)

FUNCTION CONDITIONS 16.

Turbine Trip a.

Low Fluid Oil Pressure 1(j) 3 OM SR 3.3.1.10 SR 3.3.1.15 539.42 psig b.

Turbine Stop Valve Closure 1(j) 4 PN SR 3.3.1.10 SR 3.3.1.15 1% open 17.

Safety Injection (SI) Input from Engineered Safety Feature Actuation System (ESFAS) 1, 2 2 trains QP SR 3.3.1.14 NA 18.

Reactor Trip System Interlocks a.

Intermediate Range Neutron Flux, P-6 2(e) 2 SR SR 3.3.1.11 SR 3.3.1.13 6E-11 amp b.

Low Power Reactor Trips Block, P-7 1

1 per train TS SR 3.3.1.5 NA c.

Power Range Neutron Flux, P-8 1

4 TS SR 3.3.1.11 SR 3.3.1.13 51.3% RTP d.

Power Range Neutron Flux, P-9 1

4 TS SR 3.3.1.11 SR 3.3.1.13 53.3% RTP (a)

The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.

(e)

Below the P-6 (Intermediate Range Neutron Flux) interlock.

(j)

Above the P-9 (Power Range Neutron Flux) interlock.

RTS Instrumentation 3.3.1 CALLAWAY PLANT 3.3-24 Amendment No. 202 TABLE 3.3.1-1 (page 6 of 8)

Reactor Trip System Instrumentation APPLICABLE MODES OR OTHER SPECIFIED CONDITIONS REQUIRED CHANNELS SURVEILLANCE REQUIREMENTS ALLOWABLE VALUE(a)

FUNCTION CONDITIONS 18.

Reactor Trip System Interlocks e.

Power Range Neutron Flux, P-10 1, 2 4

SR SR 3.3.1.11 SR 3.3.1.13 6.7% RTP and 12.4% RTP f.

Turbine Impulse

Pressure, P-13 1

2 TS SR 3.3.1.10 SR 3.3.1.13 12.4% turbine power 19.

Reactor Trip Breakers (RTBs)(k) 1, 2 2 trains RQ SR 3.3.1.4 NA 3(b), 4(b), 5(b) 2 trains C

SR 3.3.1.4 NA 20.

Reactor Trip Breaker Undervoltage and Shunt Trip Mechanisms(k) 1, 2 1 each per RTB U

SR 3.3.1.4 NA 3(b), 4(b), 5(b) 1 each per RTB C

SR 3.3.1.4 NA 21.

Automatic Trip Logic 1, 2 2 trains QP SR 3.3.1.5 NA 3(b), 4(b), 5(b) 2 trains C

SR 3.3.1.5 NA (a)

The Allowable Value defines the limiting safety system setting except for Trip Functions 14.a and 14.b (the Nominal Trip Setpoint defines the limiting safety system setting for these Trip Functions). See the Bases for the Nominal Trip Setpoints.

(b)

With Rod Control System capable of rod withdrawal or one or more rods not fully inserted.

(k)

Including any reactor trip bypass breakers that are racked in and closed for bypassing an RTB.

ESFAS Instrumentation 3.3.2 CALLAWAY PLANT 3.3-31 Amendment No. 202 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME H.

One or more trains inoperable.


NOTE-----------------------

One train may be bypassed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> for surveillance testing provided the other train is OPERABLE.

H.1 Declare associated Pressurizer PORV(s) inoperable.

Immediately I.

One channel inoperable.


NOTE-----------------------

The inoperable channel may be bypassed for up to 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> for surveillance testing of other channels.

I.1 Place channel in trip.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program OR I.2 Be in MODE 3.

78 hours9.027778e-4 days <br />0.0217 hours <br />1.289683e-4 weeks <br />2.9679e-5 months <br /> J.

One channel inoperable.


NOTE-----------------------

The inoperable channel may be bypassed for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> for surveillance testing of other channels.

J.1 Place channel in trip.

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OR In accordance with the Risk Informed Completion Time Program OR J.2 Be in MODE 3.

30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />

ECCS - Operating 3.5.2 CALLAWAY PLANT 3.5-4 Amendment No. 202 3.5 EMERGENCY CORE COOLING SYSTEMS (ECCS) 3.5.2 ECCS - Operating ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A.

One or more trains inoperable.

AND At least 100% of the ECCS flow equivalent to a single OPERABLE ECCS train available.

A.1 Restore train(s) to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program B.

Required Action and associated Completion Time not met.

B.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> AND B.2 Be in MODE 4.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> LCO 3.5.2 Two ECCS trains shall be OPERABLE.


NOTES --------------------------------------------

1.

In MODE 3, both safety injection (SI) pump flow paths may be isolated by closing the isolation valves for up to 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> to perform pressure isolation valve testing per SR 3.4.14.1.

2.

Operation in MODE 3 with ECCS pumps made incapable of injecting, pursuant to LCO 3.4.12, Cold Overpressure Mitigation System, is allowed for up to 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> or until the temperature of all RCS cold legs exceeds 375°F, whichever comes first.

APPLICABILITY:

MODES 1, 2, and 3.

MSIVs, MSIVBVs, and MSLPDIVs 3.7.2 CALLAWAY PLANT 3.7-5 Amendment No. 197 3.7 PLANT SYSTEMS 3.7.2 Main Steam Isolation Valves (MSIVs), Main Steam Isolation Valve Bypass Valves (MSIVBVs), and Main Steam Low Point Drain Isolation Valves (MSLPDIVs)

LCO 3.7.2 APPLICABILITY:

The MSIV and its associated actuator trains, the MSIVBV, and the MSLPDIV in each of the four main steam lines shall be OPERABLE.

For the MSIV and its associated actuator trains in each main steam line:

MODE 1, MODE 2 and 3 except when the MSIV is closed and de-activated.

For the MSIVBV in each main steam line:

MODES 1, 2, and 3 except when:

a. MSIVBV is closed and de-activated, or
b. MSIVBV is closed and isolated by a closed manual valve, or c.

MSIVBV is isolated by two closed manual valves.

For the MSLPDIV in each main steam line:

MODES 1, 2, and 3 except when:

a. MSLPDIV is closed and de-activated, or
b. MSLPDIV is closed and isolated by a closed manual valve, or c.

MSLPDIV is isolated by two closed manual valves.

ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME A. One MSIV actuator train inoperable.

A.1 Restore MSIV actuator train to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program (continued)

AFW System 3.7.5 CALLAWAY PLANT 3.7-15 Amendment No. 198 3.7 PLANT SYSTEMS 3.7.5 Auxiliary Feedwater (AFW) System LCO 3.7.5 Three AFW trains shall be OPERABLE.

APPLICABILITY:

MODE 1, 2, and 3.

ACTIONS


NOTE-----------------------------------------------------------------

LCO 3.0.4.b is not applicable when entering MODE 1.

CONDITION REQUIRED ACTION COMPLETION TIME A. One steam supply to turbine driven AFW pump inoperable.

A.1 Restore steam supply to OPERABLE status.

7 days OR In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO B. One ESW supply to turbine driven AFW pump inoperable.

B.1 Restore ESW supply to OPERABLE status.

72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> OR In accordance with the Risk Informed Completion Time Program AND 10 days from discovery of failure to meet the LCO (continued)

AC Sources - Operating 3.8.1 CALLAWAY PLANT 3.8.5 Amendment No. 186 CONDITION REQUIRED ACTION COMPLETION TIME C.

Two offsite circuits inoperable.

(continued)

C.2 Restore one offsite circuit to OPERABLE status.

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OR In accordance with the Risk Informed Completion Time Program D. One offsite circuit inoperable.


NOTE-------------------

Enter applicable Conditions and Required Actions of LCO 3.8.9, Distribution Systems - Operating, when Condition D is entered with no AC power source to any train.

AND One DG inoperable.

D.1 Restore offsite circuit to OPERABLE status.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OR In accordance with the Risk Informed Completion Time Program OR D.2 Restore DG to OPERABLE status.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OR In accordance with the Risk Informed Completion Time Program E. Two DGs inoperable.

E.1 Restore one DG to OPERABLE status.

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> (continued)

ACTIONS (continued)

AC Sources - Operating 3.8.1 CALLAWAY PLANT 3.8-6 Amendment No. 202 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME F. One required LSELS inoperable.

F.1 Declare the affected DG and offsite circuit inoperable.

Immediately AND F.2 Restore required LSELS to OPERABLE status.

12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OR In accordance with the Risk Informed Completion Time Program G. Required Action and associated Completion Time of Condition A, B, C, D, E, or F not met.

G.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> AND G.2 Be in MODE 5.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> H. Three or more AC sources inoperable.

H.1 Enter LCO 3.0.3.

Immediately SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.1.1 Verify correct breaker alignment and indicated power availability for each required offsite circuit.

In accordance with the Surveillance Frequency Control Program (continued)

Distribution Systems - Operating 3.8.9 CALLAWAY PLANT 3.8-39 Amendment No. 202 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME C.

One DC electrical power distribution subsystem inoperable.

C.1 Restore DC electrical power distribution subsystem to OPERABLE status.

2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> OR In accordance with the Risk Informed Completion Time Program AND 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> from discovery of failure to meet LCO D.

Required Action and associated Completion Time not met.

D.1 Be in MODE 3.

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> AND D.2 Be in MODE 5.

36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> E.

Two trains with inoperable distribution subsystems that result in a loss of safety function.

E.1 Enter LCO 3.0.3.

Immediately SURVEILLANCE REQUIREMENTS SURVEILLANCE FREQUENCY SR 3.8.9.1 Verify correct breaker alignments and voltage to required AC, DC, and AC vital bus electrical power distribution subsystems.

In accordance with the Surveillance Frequency Control Program