{{#Wiki_filter:December 21, 2023 LICENSEE:       n/a FACILITY:       n/a
{{#Wiki_filter:December 21, 2023 LICENSEE:
n/a FACILITY:
n/a  


==SUBJECT:==
==SUBJECT:==
==SUMMARY==
==SUMMARY==
OF NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)
OF NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)
Line 28: Line 29:
The NRC staff informed the meeting participants that public comments on the draft revision would not be collected during the public meeting. The NRC staff informed the meeting participants that public comments should be provided through regulations.gov using the Docket ID NRC-2023-0181. The NRC staff informed the meeting participants that the public comment period on the draft revision ends on November 24, 2023.
The NRC staff informed the meeting participants that public comments on the draft revision would not be collected during the public meeting. The NRC staff informed the meeting participants that public comments should be provided through regulations.gov using the Docket ID NRC-2023-0181. The NRC staff informed the meeting participants that the public comment period on the draft revision ends on November 24, 2023.
The NRC staff provided a high-level overview of the direction to the NRC staff in SRM-SECY-22-0076, Expansion of Current Policy on Potential Common-Cause Failures in Digital Instrumentation and Control Systems (ML23145A176). The NRC staff informed external stakeholders that the revisions to the BTP 7-19 were limited to the changes needed to implement the direction in SRM-SECY-22-0076. The NRC staff described the substantive changes in the draft Revision 9 to BTP 7-19. The substantive changes included:
The NRC staff provided a high-level overview of the direction to the NRC staff in SRM-SECY-22-0076, Expansion of Current Policy on Potential Common-Cause Failures in Digital Instrumentation and Control Systems (ML23145A176). The NRC staff informed external stakeholders that the revisions to the BTP 7-19 were limited to the changes needed to implement the direction in SRM-SECY-22-0076. The NRC staff described the substantive changes in the draft Revision 9 to BTP 7-19. The substantive changes included:
Revisions to Section B.1.1 to reflect the updated four points in SRM-SECY-22-0076 Revisions to Section B.1.2 for clarification of critical safety functions Revisions to Section B.3.1.3 for evaluation of alternative approaches Addition of Section B.3.4 for evaluation of risk-informed D3 assessment
Revisions to Section B.1.1 to reflect the updated four points in SRM-SECY-22-0076 Revisions to Section B.1.2 for clarification of critical safety functions Revisions to Section B.3.1.3 for evaluation of alternative approaches Addition of Section B.3.4 for evaluation of risk-informed D3 assessment Revisions to Section B.4 for evaluation of different approaches for meeting Point 4 Addition, at the end, of four flowcharts to facilitate NRC staff review Members of the public were in attendance. During the question-and-answer portion of the meeting, the following statements1 were made to and questions were asked of the NRC staff:
 
Revisions to Section B.4 for evaluation of different approaches for meeting Point 4 Addition, at the end, of four flowcharts to facilitate NRC staff review Members of the public were in attendance. During the question-and-answer portion of the meeting, the following statements1 were made to and questions were asked of the NRC staff:
BTP 7-19 is complex and challenging to navigate.
BTP 7-19 is complex and challenging to navigate.
Multiple terms are used interchangeably, which can create confusion.
Multiple terms are used interchangeably, which can create confusion.
Line 44: Line 43:
The graded approach discussed seems to be limited to the new risk-informed approach.
The graded approach discussed seems to be limited to the new risk-informed approach.
1 Statements and questions are paraphrased.
1 Statements and questions are paraphrased.
 
Public meeting feedback forms were not received. No regulatory decisions were made during the meeting. Please direct any inquiries to me at 301-415-2871, or michael.marshall@nrc.gov.  
Public meeting feedback forms were not received. No regulatory decisions were made during the meeting. Please direct any inquiries to me at 301-415-2871, or michael.marshall@nrc.gov.
/RA/
                                            /RA/
Michael L. Marshall, Jr, Senior Project Manager Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation  
Michael L. Marshall, Jr, Senior Project Manager Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation


==Enclosure:==
==Enclosure:==
List of Attendees


List of Attendees
Enclosure LIST OF ATTENDEES NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)
 
Name Organization Samir Darbali U.S. Nuclear Regulatory Commission (NRC)
LIST OF ATTENDEES NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)
Michael Marshall NRC Carla Roque-Cruz NRC Kate Lenning NRC Mary Presley Electric Power Research Institute James Chamberlain Southern Nuclear Company Shilp Vasavada NRC David Herrell MPR Associates Frank Hope Jensen Hughes Jana Bergman Curtiss Wright Christina Antonescu NRC Steven Alferink NRC Joseph Ashcraft NRC Christopher Phillips Paragon Philip Tarpinian Constellation Nuclear Eric Bowman NRC David Desaulniers NRC Steven Pope David Heinig Sargent & Lundy Geno Keller Talen Energy Undine Shoop NRC Mike Wiwel Ismael Garcia NRC Paul Hunton Idaho National Laboratory Tony Nakanishi NRC Michael Swim NRC Daniel Silverstein NRC Brayden Gordy Sergiu Basturescu NRC Robert Chenkovich Dominion Energy Steve Wyman NRC Alexander Bowman Tennessee Valley Authority Alan Campbell Nuclear Energy Institute Jason Paige NRC Brian Mount Dominion Energy Sunil Weerakkody NRC Francis Mascitelli Constellation Nuclear Ming Li NRC Doug Eskins NRC Ho Thu Dominion Energy Name Organization Warren Odess-Gillett Westinghouse Dinesh Taneja NRC Gerond George NRC Calvin Cheung NRC Jack Zhao NRC Sunwoo Park NRC Christopher Cook NRC Bradley Dolan Tennessee Valley Authority Richard Supler ENERCON Ron Jarrett Paragon Golub, Pareez Sargent & Lundy Derek Halverson NRC Sheldon Clark NRC Han Bao Idaho National Laboratory John Lane NRC Andrea Kock NRC Mary Miller Dominion Energy Norbert Carte NRC William Catullo Paragon Mauricio Gutierrez NRC Ian Jung NRC Eric Benner NRC Khoi Nguyen NRC  
Name                               Organization Samir Darbali                           U.S. Nuclear Regulatory Commission (NRC)
Michael Marshall                       NRC Carla Roque-Cruz                       NRC Kate Lenning                           NRC Mary Presley                           Electric Power Research Institute James Chamberlain                       Southern Nuclear Company Shilp Vasavada                         NRC David Herrell                           MPR Associates Frank Hope                             Jensen Hughes Jana Bergman                           Curtiss Wright Christina Antonescu                     NRC Steven Alferink                         NRC Joseph Ashcraft                         NRC Christopher Phillips                   Paragon Philip Tarpinian                       Constellation Nuclear Eric Bowman                             NRC David Desaulniers                       NRC Steven Pope                             -----
David Heinig                           Sargent & Lundy Geno Keller                             Talen Energy Undine Shoop                           NRC Mike Wiwel                             -----
Ismael Garcia                           NRC Paul Hunton                             Idaho National Laboratory Tony Nakanishi                         NRC Michael Swim                           NRC Daniel Silverstein                     NRC Brayden Gordy                           -----
Sergiu Basturescu                       NRC Robert Chenkovich                       Dominion Energy Steve Wyman                             NRC Alexander Bowman                       Tennessee Valley Authority Alan Campbell                           Nuclear Energy Institute Jason Paige                             NRC Brian Mount                             Dominion Energy Sunil Weerakkody                       NRC Francis Mascitelli                     Constellation Nuclear Ming Li                                 NRC Doug Eskins                             NRC Ho Thu                                 Dominion Energy Enclosure
 
Name                   Organization Warren Odess-Gillett     Westinghouse Dinesh Taneja             NRC Gerond George             NRC Calvin Cheung             NRC Jack Zhao                 NRC Sunwoo Park               NRC Christopher Cook         NRC Bradley Dolan             Tennessee Valley Authority Richard Supler           ENERCON Ron Jarrett               Paragon Golub, Pareez             Sargent & Lundy Derek Halverson           NRC Sheldon Clark             NRC Han Bao                   Idaho National Laboratory John Lane                 NRC Andrea Kock               NRC Mary Miller               Dominion Energy Norbert Carte             NRC William Catullo           Paragon Mauricio Gutierrez       NRC Ian Jung                 NRC Eric Benner               NRC Khoi Nguyen               NRC


Package, ML23325A066 Meeting Notice, ML23296A080 Handouts, ML23305A167 Meeting Summary, ML23325A063 OFFICE   NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA     NRR/DEX/ELTB/BC     NRR/DORL/LPMB/BC NAME     MMarshall         KZeleznock         JPaige (DTaneja for) UShoop DATE     11/20/2023         12/04/2023         12/13/2023         12/20/2023 OFFICE   NRR/DORL/LPL1/PM NAME     MMarshall DATE     12/21/2023}}
Package, ML23325A066 Meeting Notice, ML23296A080 Handouts, ML23305A167 Meeting Summary, ML23325A063 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DEX/ELTB/BC NRR/DORL/LPMB/BC NAME MMarshall KZeleznock JPaige (DTaneja for)
UShoop DATE 11/20/2023 12/04/2023 12/13/2023 12/20/2023 OFFICE NRR/DORL/LPL1/PM NAME MMarshall DATE 12/21/2023}}

Latest revision as of 07:45, 25 November 2024

"Draft Meeting" is not in the list (Request, Draft Request, Supplement, Acceptance Review, Meeting, Withholding Request, Withholding Request Acceptance, RAI, Draft RAI, Draft Response to RAI, ...) of allowed values for the "Project stage" property.

Summary of November 14, 2023, Information Public Meeting on Draft Revision 9 to Branch Technical Position 7-19
ML23325A063
Person / Time
Issue date: 12/21/2023
From: Marshall M
NRC/NRR/DORL/LPL1
To:
Shared Package
ML23325A066 List:
References
EPID L-2023-NNR-0007
Download: ML23325A063 (1)


Text

December 21, 2023 LICENSEE:

n/a FACILITY:

n/a

SUBJECT:

SUMMARY

OF NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)

On November 14, 2023, an information meeting with a question-and-answer session was held between the U.S. Nuclear Regulatory Commission (NRC) and external stakeholders through video conference. The purpose of the meeting was to provide external stakeholders an opportunity to ask NRC staff questions about the draft revision to Branch Technical Position (BTP) 7-19, Guidance for Evaluation of Defense in Depth and Diversity to Address Common-Cause Failure Due to Latent Design Defects in Digital Safety Systems. The draft revision was published and made available for public comment on October 24, 2023. The meeting notice and agenda, dated October 24, 2023, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML23296A080. A list of attendees is provided as Enclosure 1. Copies of the draft revisions were made available to external stakeholders prior to the meeting at ADAMS Accession Nos. ML23222A237 and ML23222A219. A copy of the presentation used by the NRC staff during the meeting is available at ADAMS Accession No. ML23305A167.

The NRC staff informed the meeting participants that public comments on the draft revision would not be collected during the public meeting. The NRC staff informed the meeting participants that public comments should be provided through regulations.gov using the Docket ID NRC-2023-0181. The NRC staff informed the meeting participants that the public comment period on the draft revision ends on November 24, 2023.

The NRC staff provided a high-level overview of the direction to the NRC staff in SRM-SECY-22-0076, Expansion of Current Policy on Potential Common-Cause Failures in Digital Instrumentation and Control Systems (ML23145A176). The NRC staff informed external stakeholders that the revisions to the BTP 7-19 were limited to the changes needed to implement the direction in SRM-SECY-22-0076. The NRC staff described the substantive changes in the draft Revision 9 to BTP 7-19. The substantive changes included:

Revisions to Section B.1.1 to reflect the updated four points in SRM-SECY-22-0076 Revisions to Section B.1.2 for clarification of critical safety functions Revisions to Section B.3.1.3 for evaluation of alternative approaches Addition of Section B.3.4 for evaluation of risk-informed D3 assessment Revisions to Section B.4 for evaluation of different approaches for meeting Point 4 Addition, at the end, of four flowcharts to facilitate NRC staff review Members of the public were in attendance. During the question-and-answer portion of the meeting, the following statements1 were made to and questions were asked of the NRC staff:

BTP 7-19 is complex and challenging to navigate.

Multiple terms are used interchangeably, which can create confusion.

What is the intended scope of BTP 7-19? Is it intended to cover non-safety systems?

The title of BTP 7-19 does not indicate that non-safety systems can fall within the scope of the document.

The acceptance criteria in Section B.3.1.3 does not appear to be consistent. The words correct and complete should be replaced with credible and bounding.

Guidance for advanced reactors and operating reactors seem to be mixed in BTP 7-19.

Is the review guidance in BTP 7-19 applicable to advanced reactors?

Can the NRC staff explain the use of probabilistic risk assessment (PRA) model, PRA maintenance, and PRA upgrade in Section B.3.4.2? Should definitions of those terms be included in BTP 7-19?

The review of intersystem common cause failure modelling would go beyond the requirements in the American Nuclear Society standards for PRA.

Assuming an intersystem common cause failure would lead to over conservatism in the analysis.

There appears to be three different approaches in BTP 7 not one graded approach.

The graded approach discussed seems to be limited to the new risk-informed approach.

1 Statements and questions are paraphrased.

Public meeting feedback forms were not received. No regulatory decisions were made during the meeting. Please direct any inquiries to me at 301-415-2871, or michael.marshall@nrc.gov.

/RA/

Michael L. Marshall, Jr, Senior Project Manager Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

Enclosure:

List of Attendees

Enclosure LIST OF ATTENDEES NOVEMBER 14, 2023, INFORMATION PUBLIC MEETING ON DRAFT REVISION 9 TO BRANCH TECHNICAL POSITION 7-19 (EPID L-2023-NNR-0007)

Name Organization Samir Darbali U.S. Nuclear Regulatory Commission (NRC)

Michael Marshall NRC Carla Roque-Cruz NRC Kate Lenning NRC Mary Presley Electric Power Research Institute James Chamberlain Southern Nuclear Company Shilp Vasavada NRC David Herrell MPR Associates Frank Hope Jensen Hughes Jana Bergman Curtiss Wright Christina Antonescu NRC Steven Alferink NRC Joseph Ashcraft NRC Christopher Phillips Paragon Philip Tarpinian Constellation Nuclear Eric Bowman NRC David Desaulniers NRC Steven Pope David Heinig Sargent & Lundy Geno Keller Talen Energy Undine Shoop NRC Mike Wiwel Ismael Garcia NRC Paul Hunton Idaho National Laboratory Tony Nakanishi NRC Michael Swim NRC Daniel Silverstein NRC Brayden Gordy Sergiu Basturescu NRC Robert Chenkovich Dominion Energy Steve Wyman NRC Alexander Bowman Tennessee Valley Authority Alan Campbell Nuclear Energy Institute Jason Paige NRC Brian Mount Dominion Energy Sunil Weerakkody NRC Francis Mascitelli Constellation Nuclear Ming Li NRC Doug Eskins NRC Ho Thu Dominion Energy Name Organization Warren Odess-Gillett Westinghouse Dinesh Taneja NRC Gerond George NRC Calvin Cheung NRC Jack Zhao NRC Sunwoo Park NRC Christopher Cook NRC Bradley Dolan Tennessee Valley Authority Richard Supler ENERCON Ron Jarrett Paragon Golub, Pareez Sargent & Lundy Derek Halverson NRC Sheldon Clark NRC Han Bao Idaho National Laboratory John Lane NRC Andrea Kock NRC Mary Miller Dominion Energy Norbert Carte NRC William Catullo Paragon Mauricio Gutierrez NRC Ian Jung NRC Eric Benner NRC Khoi Nguyen NRC

Package, ML23325A066 Meeting Notice, ML23296A080 Handouts, ML23305A167 Meeting Summary, ML23325A063 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DEX/ELTB/BC NRR/DORL/LPMB/BC NAME MMarshall KZeleznock JPaige (DTaneja for)

UShoop DATE 11/20/2023 12/04/2023 12/13/2023 12/20/2023 OFFICE NRR/DORL/LPL1/PM NAME MMarshall DATE 12/21/2023