ML12305A251: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:8/10/71 SAFETY GUIDE 9 SELECTION OF DIESEL GENERATOR SET CAPACITY FOR STANDBY POWER SUPPLIES A. Introduction General Design Criterion 17 requires that the onsite (standby) power supply for a nuclear power plant be of sufficient capacity and capa-bility to assure that (1) specified acceptable fuel design limits and design conditions of the reactor coolant pressure boundary are not ex-ceeded as a result of anticipated operational occurrences and (2) the core is cooled and con-tainment integrity and other vital functions are maintained in the event of postulated acci-dents. Diesel generator sets have been widely used as the power source for the standby power supplies.
{{#Wiki_filter:8/10/71 SAFETY GUIDE 9 SELECTION OF DIESEL GENERATOR SET CAPACITY FOR STANDBY POWER SUPPLIES A. Introduction                                       large increases in current drawn from the die-sel generator resulting from the startup of General Design Criterion 17 requires that induction motors can result in substantial volt-the onsite (standby) power supply for a nuclear age reductions. The lower voltage could pre-power plant be of sufficient capacity and capa-vent a motor from starting or cause a running bility to assure that (1) specified acceptable motor to coast down. Other loads also might be fuel design limits and design conditions of the lost if their contactors drop out. Recovery reactor coolant pressure boundary are not ex-from the transient caused by starting large ceeded as a result of anticipated operational motors or from the loss of a large load could occurrences and (2) the core is cooled and con-cause diesel engine overspeed which, if exces-tainment integrity and other vital functions sive, might result in a trip of the machine.
This safety guide describes an accept-able basis for the selection of diesel generator sets of sufficient capacity and margin to imple-ment General Design Criterion 17.B. Discussion A diesel generator set selected for use as a standby power supply should have the capabil-ity to (1) start and accelerate a number of large motor loads in rapid succession, and be able to sustain the loss of any such load, and (2) supply continuously the sum of the loads needed to be powered at any one time. This guide provides an acceptable way of assuring these objectives are met. The considerations involved in the need for the diesel generator to start and achieve rated conditions in a short period of time are evaluated on an individual case basis.A knowledge of the characteristics of each load is essential in establishing the bases for the selection of a diesel generator set that is able to accelerate large loads in rapid succes-sion. The majority of the emergency loads are large induction motors. This type of motor draws, at full voltage, a starting current five to ten times its rated load current. The sudden, large increases in current drawn from the die-sel generator resulting from the startup of induction motors can result in substantial volt-age reductions.
are maintained in the event of postulated acci-These same consequences also can result from dents. Diesel generator sets have been widely the cumulative effect of a sequence of more used as the power source for the standby power moderate transients if the system is not per-supplies. This safety guide describes an accept-mitted to recover sufficiently between succes-able basis for the selection of diesel generator sive steps in a loading sequence.
The lower voltage could pre-vent a motor from starting or cause a running motor to coast down. Other loads also might be lost if their contactors drop out. Recovery from the transient caused by starting large motors or from the loss of a large load could cause diesel engine overspeed which, if exces-sive, might result in a trip of the machine.These same consequences also can result from the cumulative effect of a sequence of more moderate transients if the system is not per-mitted to recover sufficiently between succes-sive steps in a loading sequence.Generally it has been industry practice to specify a maximum voltage reduction of 15 percent when starting large motors from large capacity power systems and a 25 to 30 percent voltage reduction when starting these motors from limited capacity power sources such as diesel generator sets. Large induction motors supplied with nominal voltage can achieve rated.speed in less than 5 seconds when pow-ered from adequately sized diesel generator sets which are capable of restoring the voltage to 90 percent of nominal in about 1 second.Protection of the diesel generator set from excessive overspeed, which can result from a loss of load, is afforded by the provision of a diesel generator set trip, usually set at 115 per-cent of nominal speed.A problem arises in assessing whether the goal of continuously supplying the sum of the needed loads is achieved with sufficient capacity and margin, because of the various interpreta-tions of load ratings quoted by diesel generator suppliers.
sets of sufficient capacity and margin to imple-Generally it has been industry practice to ment General Design Criterion 17.
The load ratings represent the loads at which the set can operate continuously with a high availability, if various specified mainte-9.1 nance programs are followed.
specify a maximum voltage reduction of 15 B. Discussion                                         percent when starting large motors from large capacity power systems and a 25 to 30 percent A diesel generator set selected for use as a     voltage reduction when starting these motors standby power supply should have the capabil-         from limited capacity power sources such as ity to (1) start and accelerate a number of           diesel generator sets. Large induction motors large motor loads in rapid succession, and be         supplied with nominal voltage can achieve able to sustain the loss of any such load, and       rated.speed in less than 5 seconds when pow-(2) supply continuously the sum of the loads         ered from adequately sized diesel generator sets needed to be powered at any one time. This           which are capable of restoring the voltage to guide provides an acceptable way of assuring         90 percent of nominal in about 1 second.
The nominal rating, used as a datum for the overload rat-ings, has been termed variously the "continu-ous," "guaranteed," or "long term" rating. The definition used throughout this guide for "con-tinuous rating" is "that load for which the sup-plier guarantees continuous operation at a high availability (expected to be about 95%) with an annual maintenance interval".
these objectives are met. The considerations             Protection of the diesel generator set from involved in the need for the diesel generator to     excessive overspeed, which can result from a start and achieve rated conditions in a short         loss of load, is afforded by the provision of a period of time are evaluated on an individual         diesel generator set trip, usually set at 115 per-case basis.                                           cent of nominal speed.
The over-load ratings are similarly defined except that the specified maintenance intervals are shorter.For example, the following are the load ratings of a typical diesel generator set: mating the loads conservatively and by select-ing the continuous rating of the diesel genera-tor set so that it exceeds the sum of the loadsI needed at any one time. A more accurate esti-mate of safety loads is possible during the operating license stage of review due to the completion of the detailed designs and the availability of preoperational test data. This permits the consideration of a somewhat less conservative approach, such as operation with safety loads within the 2000 hour overload rating of the diesel generator set. A conserva-tive estimate of safety loads based on design or measurements taken during preoperational testing of engineered safety features does not, however, represent with certainty the actual loads experienced under accident conditions.
A knowledge of the characteristics of each           A problem arises in assessing whether the load is essential in establishing the bases for       goal of continuously supplying the sum of the the selection of a diesel generator set that is       needed loads is achieved with sufficient capacity able to accelerate large loads in rapid succes-      and margin, because of the various interpreta-sion. The majority of the emergency loads are         tions of load ratings quoted by diesel generator large induction motors. This type of motor           suppliers. The load ratings represent the loads draws, at full voltage, a starting current five       at which the set can operate continuously with to ten times its rated load current. The sudden,     a high availability, if various specified mainte-9.1
Therefore, an adequate margin is still essential.
 
Ratings Continuous 2500 kW Overload 2850 kW 2950 kW 3050 kW Maintenance Interval Annual (8760 hr)2000 hr 7 day 30 min If the power output is increased into the over-load ratings, wearout is accelerated and the maintenance interval needed to assure high reliability is reduced. This discussion assumes that the diesel generator set is utilized solely as a standby power supply and that it does not serve a secondary function such as power gen-eration for peak demand periods of a transmis-sion network. The secondary functions, since they would affect wearout and availability of the diesel generator set, will be evaluated on an individual case basis. If found acceptable, the total amount of operation between mainte-nance intervals will be limited by the technical specifications.
nance programs are followed. The nominal              mating the loads conservatively and by select-rating, used as a datum for the overload rat-        ing the continuous rating of the diesel genera-ings, has been termed variously the "continu-        tor set so that it exceeds the sum of the loadsI ous," "guaranteed," or "long term" rating. The      needed at any one time. A more accurate esti-definition used throughout this guide for "con-     mate of safety loads is possible during the tinuous rating" is "that load for which the sup-    operating license stage of review due to the plier guarantees continuous operation at a high      completion of the detailed designs and the availability (expected to be about 95%) with         availability of preoperational test data. This an annual maintenance interval". The over-           permits the consideration of a somewhat less load ratings are similarly defined except that        conservative approach, such as operation with the specified maintenance intervals are shorter.     safety loads within the 2000 hour overload For example, the following are the load ratings      rating of the diesel generator set. A conserva-of a typical diesel generator set:                  tive estimate of safety loads based on design or measurements taken during preoperational Ratings            Maintenance Interval testing of engineered safety features does not, Continuous 2500 kW          Annual (8760 hr)      however, represent with certainty the actual Overload    2850 kW        2000 hr loads experienced under accident conditions.
This guide covers diesel gen-erator sets used solely as a standby power sup-ply which is the design most widely adopted.The tabulation illustrates the sensitivity of the deterioration rate to increases in load above the continuous rating. For example, if the design basis loading were that corresponding to the 2000-hour rating, an error of only 8 per-cent in estimating the loads could result in operation at the 30-minute rating. Although operation at the 30-minute rating would not be expected to stall the engine, such operation could lead to the danger of early failure.The uncertainties inherent in estimates of safety loads at the construction permit stage of design are of such magnitude that it is pru-dent to provide a substantial margin in the selection of the diesel generator set load capa-bility. This margin can be provided by esti-C. Regulatory Position 1. At a time when the characteristics of loads are not accurately known, such as during the construction permit stage of design, each diesel generator set on a standby (onsite) power supply should be selected to have a continuous load rating equal to or greater than the sum of the conservatively estimated loads needed to be powered at any one time. In the absence of fully substan-tiated performance characteristics for mechanical equipment such as pumps, the electric motor drive ratings should be calculated using conservative esti-mates of these characteristics. (For example, pump run-out conditions and motor efficiencies of 90% or less.)2. At the operating license stage of re-view, the predicted loads should not exceed the smaller of the 2000-hour rating, or 90 percent of the 30-minute rating of the set.3. During preoperational testing, the pre-dicted loads should be verified by tests.4. Each diesel generator set should be ca-pable of starting and accelerating to rated speed, in the required sequence, all the needed engineered safety fea-ture and emergency shutdown loads. At no time during the loading sequence should the frequency and voltage de-9.2 crease to less than 95 percent of nomi-nal and 75 percent of nominal, respec-tively. During recovery from transients caused by step load increases or result-ing from the disconnection of the larg-est single load, the speed of the diesel generator set should not exceed 75 per-cent of the difference between nominal speed and the overspeed trip set point or 115 percent of nominal, whichever is lower. Voltage should be restored to within 10 percent of nominal and fre-quency should be restored to within 2 percent of nominal in less than 40 per-cent of each load sequence time inter-val.5. The suitability of each diesel generator set of the standby power supply should be confirmed by prototype qualification test data and preoperational tests.9.3}}
2950 kW            7 day 3050 kW            30 min              Therefore, an adequate margin is still essential.
If the power output is increased into the over-     C. Regulatory Position load ratings, wearout is accelerated and the maintenance interval needed to assure high                1. At a time when the characteristics of reliability is reduced. This discussion assumes                loads are not accurately known, such as that the diesel generator set is utilized solely              during the construction permit stage of as a standby power supply and that it does not                design, each diesel generator set on a serve a secondary function such as power gen-                  standby (onsite) power supply should eration for peak demand periods of a transmis-                 be selected to have a continuous load sion network. The secondary functions, since                  rating equal to or greater than the they would affect wearout and availability of                  sum of the conservatively estimated loads needed to be powered at any one the diesel generator set, will be evaluated on an individual case basis. If found acceptable,                time. In the absence of fully substan-the total amount of operation between mainte-                 tiated performance characteristics for mechanical equipment such as pumps, nance intervals will be limited by the technical specifications. This guide covers diesel gen-                 the electric motor drive ratings should erator sets used solely as a standby power sup-               be calculated using conservative esti-mates of these characteristics. (For ply which is the design most widely adopted.
example, pump run-out conditions and The tabulation illustrates the sensitivity of               motor efficiencies of 90% or less.)
the deterioration rate to increases in load above the continuous rating. For example, if the                2. At the operating license stage of re-design basis loading were that corresponding                  view, the predicted loads should not to the 2000-hour rating, an error of only 8 per-              exceed the smaller of the 2000-hour cent in estimating the loads could result in                  rating, or 90 percent of the 30-minute rating of the set.
operation at the 30-minute rating. Although operation at the 30-minute rating would not               3. During preoperational testing, the pre-be expected to stall the engine, such operation                dicted loads should be verified by tests.
could lead to the danger of early failure.                4. Each diesel generator set should be ca-The uncertainties inherent in estimates of                pable of starting and accelerating to safety loads at the construction permit stage                rated speed, in the required sequence, of design are of such magnitude that it is pru-               all the needed engineered safety fea-dent to provide a substantial margin in the                   ture and emergency shutdown loads. At selection of the diesel generator set load capa-              no time during the loading sequence bility. This margin can be provided by esti-                  should the frequency and voltage de-9.2
 
crease to less than 95 percent of nomi-         lower. Voltage should be restored to nal and 75 percent of nominal, respec-          within 10 percent of nominal and fre-tively. During recovery from transients        quency should be restored to within 2 caused by step load increases or result-        percent of nominal in less than 40 per-ing from the disconnection of the larg-        cent of each load sequence time inter-est single load, the speed of the diesel       val.
generator set should not exceed 75 per-     5. The suitability of each diesel generator cent of the difference between nominal          set of the standby power supply should speed and the overspeed trip set point          be confirmed by prototype qualification or 115 percent of nominal, whichever is        test data and preoperational tests.
9.3}}

Revision as of 20:46, 11 November 2019

Safety Guide 9, Selection of Diesel Set Capacity for Standby Power Supplies
ML12305A251
Person / Time
Issue date: 08/31/1971
From:
Office of Nuclear Regulatory Research
To:
References
Safety Guide 9 RG 1.9
Download: ML12305A251 (3)


Text

8/10/71 SAFETY GUIDE 9 SELECTION OF DIESEL GENERATOR SET CAPACITY FOR STANDBY POWER SUPPLIES A. Introduction large increases in current drawn from the die-sel generator resulting from the startup of General Design Criterion 17 requires that induction motors can result in substantial volt-the onsite (standby) power supply for a nuclear age reductions. The lower voltage could pre-power plant be of sufficient capacity and capa-vent a motor from starting or cause a running bility to assure that (1) specified acceptable motor to coast down. Other loads also might be fuel design limits and design conditions of the lost if their contactors drop out. Recovery reactor coolant pressure boundary are not ex-from the transient caused by starting large ceeded as a result of anticipated operational motors or from the loss of a large load could occurrences and (2) the core is cooled and con-cause diesel engine overspeed which, if exces-tainment integrity and other vital functions sive, might result in a trip of the machine.

are maintained in the event of postulated acci-These same consequences also can result from dents. Diesel generator sets have been widely the cumulative effect of a sequence of more used as the power source for the standby power moderate transients if the system is not per-supplies. This safety guide describes an accept-mitted to recover sufficiently between succes-able basis for the selection of diesel generator sive steps in a loading sequence.

sets of sufficient capacity and margin to imple-Generally it has been industry practice to ment General Design Criterion 17.

specify a maximum voltage reduction of 15 B. Discussion percent when starting large motors from large capacity power systems and a 25 to 30 percent A diesel generator set selected for use as a voltage reduction when starting these motors standby power supply should have the capabil- from limited capacity power sources such as ity to (1) start and accelerate a number of diesel generator sets. Large induction motors large motor loads in rapid succession, and be supplied with nominal voltage can achieve able to sustain the loss of any such load, and rated.speed in less than 5 seconds when pow-(2) supply continuously the sum of the loads ered from adequately sized diesel generator sets needed to be powered at any one time. This which are capable of restoring the voltage to guide provides an acceptable way of assuring 90 percent of nominal in about 1 second.

these objectives are met. The considerations Protection of the diesel generator set from involved in the need for the diesel generator to excessive overspeed, which can result from a start and achieve rated conditions in a short loss of load, is afforded by the provision of a period of time are evaluated on an individual diesel generator set trip, usually set at 115 per-case basis. cent of nominal speed.

A knowledge of the characteristics of each A problem arises in assessing whether the load is essential in establishing the bases for goal of continuously supplying the sum of the the selection of a diesel generator set that is needed loads is achieved with sufficient capacity able to accelerate large loads in rapid succes- and margin, because of the various interpreta-sion. The majority of the emergency loads are tions of load ratings quoted by diesel generator large induction motors. This type of motor suppliers. The load ratings represent the loads draws, at full voltage, a starting current five at which the set can operate continuously with to ten times its rated load current. The sudden, a high availability, if various specified mainte-9.1

nance programs are followed. The nominal mating the loads conservatively and by select-rating, used as a datum for the overload rat- ing the continuous rating of the diesel genera-ings, has been termed variously the "continu- tor set so that it exceeds the sum of the loadsI ous," "guaranteed," or "long term" rating. The needed at any one time. A more accurate esti-definition used throughout this guide for "con- mate of safety loads is possible during the tinuous rating" is "that load for which the sup- operating license stage of review due to the plier guarantees continuous operation at a high completion of the detailed designs and the availability (expected to be about 95%) with availability of preoperational test data. This an annual maintenance interval". The over- permits the consideration of a somewhat less load ratings are similarly defined except that conservative approach, such as operation with the specified maintenance intervals are shorter. safety loads within the 2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> overload For example, the following are the load ratings rating of the diesel generator set. A conserva-of a typical diesel generator set: tive estimate of safety loads based on design or measurements taken during preoperational Ratings Maintenance Interval testing of engineered safety features does not, Continuous 2500 kW Annual (8760 hr) however, represent with certainty the actual Overload 2850 kW 2000 hr loads experienced under accident conditions.

2950 kW 7 day 3050 kW 30 min Therefore, an adequate margin is still essential.

If the power output is increased into the over- C. Regulatory Position load ratings, wearout is accelerated and the maintenance interval needed to assure high 1. At a time when the characteristics of reliability is reduced. This discussion assumes loads are not accurately known, such as that the diesel generator set is utilized solely during the construction permit stage of as a standby power supply and that it does not design, each diesel generator set on a serve a secondary function such as power gen- standby (onsite) power supply should eration for peak demand periods of a transmis- be selected to have a continuous load sion network. The secondary functions, since rating equal to or greater than the they would affect wearout and availability of sum of the conservatively estimated loads needed to be powered at any one the diesel generator set, will be evaluated on an individual case basis. If found acceptable, time. In the absence of fully substan-the total amount of operation between mainte- tiated performance characteristics for mechanical equipment such as pumps, nance intervals will be limited by the technical specifications. This guide covers diesel gen- the electric motor drive ratings should erator sets used solely as a standby power sup- be calculated using conservative esti-mates of these characteristics. (For ply which is the design most widely adopted.

example, pump run-out conditions and The tabulation illustrates the sensitivity of motor efficiencies of 90% or less.)

the deterioration rate to increases in load above the continuous rating. For example, if the 2. At the operating license stage of re-design basis loading were that corresponding view, the predicted loads should not to the 2000-hour rating, an error of only 8 per- exceed the smaller of the 2000-hour cent in estimating the loads could result in rating, or 90 percent of the 30-minute rating of the set.

operation at the 30-minute rating. Although operation at the 30-minute rating would not 3. During preoperational testing, the pre-be expected to stall the engine, such operation dicted loads should be verified by tests.

could lead to the danger of early failure. 4. Each diesel generator set should be ca-The uncertainties inherent in estimates of pable of starting and accelerating to safety loads at the construction permit stage rated speed, in the required sequence, of design are of such magnitude that it is pru- all the needed engineered safety fea-dent to provide a substantial margin in the ture and emergency shutdown loads. At selection of the diesel generator set load capa- no time during the loading sequence bility. This margin can be provided by esti- should the frequency and voltage de-9.2

crease to less than 95 percent of nomi- lower. Voltage should be restored to nal and 75 percent of nominal, respec- within 10 percent of nominal and fre-tively. During recovery from transients quency should be restored to within 2 caused by step load increases or result- percent of nominal in less than 40 per-ing from the disconnection of the larg- cent of each load sequence time inter-est single load, the speed of the diesel val.

generator set should not exceed 75 per- 5. The suitability of each diesel generator cent of the difference between nominal set of the standby power supply should speed and the overspeed trip set point be confirmed by prototype qualification or 115 percent of nominal, whichever is test data and preoperational tests.

9.3