| issue date = 03/28/2019
| issue date = 03/28/2019
| title = Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 10 (EPID No. L-2018-RNW-0002) - Email
| title = Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 10 (EPID No. L-2018-RNW-0002) - Email
| author name = James L M
| author name = James L
| author affiliation = NRC/NRR/DMLR/MRPB
| author affiliation = NRC/NRR/DMLR/MRPB
| addressee name = Nazar M
| addressee name = Nazar M

Revision as of 08:43, 12 June 2019

Requests for Additional Information for the Safety Review of the Turkey Point Subsequent License Renewal Application - Set 10 (EPID No. L-2018-RNW-0002) - Email
ML19087A209
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/28/2019
From: Lois James
NRC/NRR/DMLR/MRPB
To: Nazar M
Florida Power & Light Co
Lois James, 301-415-3306
Shared Package
ML19087A204 List:
References
EPID L-2018-RNW-0002
Download: ML19087A209 (1)


Text

ML18053A123), March 1, 2018 (ADAMS Accession No.

ML18072A224), and April 10, 2018 (ADAMS Accession Nos. ML18102A521 and ML18113A132), Florida Power & Light Company (FPL) submitted an application for subsequent license renewal of Renewed Facility Operating License Nos. DPR-31 and DPR-41 for the Turkey Point Nuclear Generating Unit Nos. 3 and 4 (Turkey Point) to the U.S. Nuclear Regulatory Commission (NRC) pursuant to Section 103 of the Atomic Energy Act of 1954, as amended, and Part 54 of Title 10 of the Code of Federal Regulations, "

Requirements for renewal of operating licenses for nuclear power plants"

. The NRC staff from the Divisions of Materials and License Renewal (DMLR) is reviewing the information contained in the subsequent license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

These requests for additional information were discussed with Steve Franzone of your staff, and a mutually agreeable date for the response is within 21 days from the date of this e-mail.

If you have any questions, please contact me by e-mail Lois.Jame@nrc.gov

. Sincerely, Lois James, Senior Project Manager License Renewal Projects Branch Division of Materials and License Renewal Office of Nuclear Reactor Regulation 50-250 and 50-251

Enclosure:

Requests for Additional Information cc w/encl:

Listserv ADAMS Accession Nos:

ML19087A204 (package);

ML19087A209 (email); ML19087A211 (RAIs)*concurrence via e-mail OFFICE PM:MRPB:DMLR BC:MCCB:DMLR BC:MRPB:NRR PM:MRPB:NRR NAME LJames SBloom*EOesterle*

LJames DATE 03/28/2019 03/13/2019 03/13/2019 03/28/2019