IR 05000498/2017005: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML17242A182
| number = ML17242A182
| issue date = 08/28/2017
| issue date = 08/28/2017
| title = South Texas Project, Units 1 and 2, Updated Inspection Plan (Reports 05000498/2017005 and 05000499/2017005)
| title = Project, Units 1 and 2, Updated Inspection Plan (Reports 05000498/2017005 and 05000499/2017005)
| author name = Taylor N H
| author name = Taylor N H
| author affiliation = NRC/RGN-IV/DRP/RPB-B
| author affiliation = NRC/RGN-IV/DRP/RPB-B

Revision as of 05:20, 6 April 2019

Project, Units 1 and 2, Updated Inspection Plan (Reports 05000498/2017005 and 05000499/2017005)
ML17242A182
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 08/28/2017
From: Taylor N H
NRC/RGN-IV/DRP/RPB-B
To: Powell G T
South Texas
NICK TAYLOR
References
IR 2017005
Download: ML17242A182 (5)


Text

August 28, 2017

Mr. G. Executive Vice President and Chief Nuclear Officer STP Nuclear Operating Company P.O. Box 289 Wadsworth, TX 77483

SUBJECT: UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNITS 1 AND 2 (REPORTS 05000498/2017005 AND 05000499/2017005)

Dear Mr. Powell:

The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for South Texas Project Electric Generating Station Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include the plan for security

-related inspections, which will be sent via separate, non

-publicly available correspondence.

Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi

-Unit Dose Assessment Plans." This inspection will be conducted at South Texas Project Electric Generating Station Units 1 and 2 to confirm the station's full implementation of Commission Orders EA

-12-049 and EA

-12-051. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011

-4511 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading

-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (817) 200-1141 with any questions you have regarding this letter.

Sincerely,/RA D. Proulx for/

Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket Nos.

50-498 and 50

-499 License Nos. NPF-76 and NPF

-80

Enclosure:

South Texas Project Electric Generating Station Inspection Plan

SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword: NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE /RA/ /RA/DProulx for DATE 8/28/17 8/28/17 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteSouth Texas ProjectInspection / Activity Plan 07/01/2017

-06/30/2019 Page 1 of 2 08/25/2017 08:24:16EXAM-INITIAL EXAM 4 1 INITIAL EXAM STP U1 (09/2017)

X02592 08/14/2017 08/18/2017 2 INITIAL EXAM STP U2 (09/2017)

X02593 08/14/2017 08/18/2017 1 INITIAL EXAM STP U1 (09/2017)

X02592 09/25/2017 10/04/2017 2 INITIAL EXAM STP U2 (09/2017)

X02593 09/25/2017 10/04/2017 RS 24-RADIATION SAFETY 2 1, 2 IP Occupational ALARA Planning and Controls71124.02 07/31/2017 08/04/2017 1, 2 IP Occupational Dose Assessment71124.04 07/31/2017 08/04/2017TI-191-MITIGATING STRATEGIES/SFP INST FOR BDBEE 4 1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 10/23/2017 10/27/2017 BRQ-BRQ INSPECTION 2 1, 2 IP Licensed Operator Requalification Program7111111B 10/16/2017 10/20/2017 RS 12PI-RAD SAFETY 2 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 03/26/2018 03/30/2018 1, 2 IP Occupational ALARA Planning and Controls71124.02 03/26/2018 03/30/2018 1, 2 IP Occupational Exposure Control Effectiveness71151-OR01 03/26/2018 03/30/2018 1, 2 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 03/26/2018 03/30/20187111108-INSERVICE INSPECTION UNIT 2 1 2 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/13/2018EXAM-INITIAL EXAM 4 1 INITIAL EXAM STP U1(11/18)

X02626 09/17/2018 09/21/2018 2 INITIAL EXAM STP U2(11/2018)

X02627 09/17/2018 09/21/2018 1 INITIAL EXAM STP U1(11/18)

X02626 10/22/201811/01/2018 2 INITIAL EXAM STP U2(11/2018)

X02627 10/22/201811/01/2018 EB1-07T-STP HEAT SINK PERFORMANCE 2 1, 2 IP Heat Sink Performance7111107T06/11/2018 06/15/2018 EP-1-EP EXERCISE INSPECTION 5 1, 2 IP Exercise Evaluation711140106/11/2018 06/15/2018 1, 2 IP Emergency Action Level and Emergency Plan Changes711140406/11/2018 06/15/2018 1, 2 IP Drill/Exercise Performance71151-EP0106/11/2018 06/15/2018 1, 2 IP ERO Readiness71151-EP0206/11/2018 06/15/2018 1, 2 IP A lert & Notification System Reliability71151-EP0306/11/2018 06/15/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.

Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteSouth Texas ProjectInspection / Activity Plan 07/01/2017

-06/30/2019 Page 2 of 2 08/25/2017 08:24:16 RS 5678-RAD SAFETY 4 1, 2 IP Radiation Monitoring Instrumentation71124.05 07/23/2018 07/27/2018 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 07/23/2018 07/27/2018 1, 2 IP Radiological Environmental Monitoring Program71124.07 07/23/2018 07/27/2018 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 07/23/2018 07/27/2018 PI&R-BIENNIAL PI&R INSPECTION 4 1, 2 IP Problem Identification and Resolution71152B 08/06/2018 08/10/2018 1, 2 IP Problem Identification and Resolution71152B 08/20/2018 08/24/20187111108-INSERVICE INSPECTION UNIT 1 1 1 IP Inservice Inspection Activities - PWR7111108P 10/15/2018 10/26/2018 RS 24-RP INSPECTION 2 1, 2 IP Occupational ALARA Planning and Controls71124.02 01/28/2019 02/01/2019 1, 2 IP Occupational Dose Assessment71124.04 01/28/2019 02/01/2019 EB1-21M-SOUTH TEXAS DBA TEAM INSPECTION 6 1, 2 IP Design Bases Assurance Inspection (Teams)7111121M 03/25/2019 04/12/2019 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.