IR 05000305/2011003: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
| Line 154: | Line 154: | ||
The inspectors also reviewed corrective action program (CAP) items to verify that the licensee was identifying adverse weather issues at an appropriate threshold and entering them into the CAP in accordance with station corrective action (CA) procedures. | The inspectors also reviewed corrective action program (CAP) items to verify that the licensee was identifying adverse weather issues at an appropriate threshold and entering them into the CAP in accordance with station corrective action (CA) procedures. | ||
This inspection constituted one readiness of offsite and alternate AC power systems sample as defined in Inspection Procedure (IP)71111.01-05. b. No findings were identified. | This inspection constituted one readiness of offsite and alternate AC power systems sample as defined in Inspection Procedure (IP) | ||
==71111.01 - 05.== | |||
b. No findings were identified. | |||
Findings | Findings | ||
| Line 166: | Line 169: | ||
Documents reviewed are listed in the Attachment to this report. | Documents reviewed are listed in the Attachment to this report. | ||
Inspection Scope This inspection constituted one external flooding sample as defined in IP 71111.01-05. | Inspection Scope This inspection constituted one external flooding sample as defined in IP | ||
==71111.01 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 179: | Line 184: | ||
. | . | ||
These activities constituted two partial system walkdown sample s as defined in IP 71111.04-05. | These activities constituted two partial system walkdown sample s as defined in IP | ||
==71111.04 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 193: | Line 200: | ||
, in accordance with the licensee's fire plan. The inspectors selected fire areas based on the overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional risk insights, or the potential to impact equipment which could initiate or mitigate a plant transient. The inspectors verified that: fire hoses and extinguishers were in the designated locations and available for immediate use; fire detectors and sprinklers were unobstructed; transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issue s identified during the inspection were entered into the licensee's CAP. Documents reviewed are listed in the Attachment to this report. | , in accordance with the licensee's fire plan. The inspectors selected fire areas based on the overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional risk insights, or the potential to impact equipment which could initiate or mitigate a plant transient. The inspectors verified that: fire hoses and extinguishers were in the designated locations and available for immediate use; fire detectors and sprinklers were unobstructed; transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issue s identified during the inspection were entered into the licensee's CAP. Documents reviewed are listed in the Attachment to this report. | ||
These activities constituted four quarterly fire protection inspection samples as defined in IP 71111.05-05. | These activities constituted four quarterly fire protection inspection samples as defined in IP | ||
==71111.05 - 05.== | |||
8 Enclosure b. No findings were identified. | 8 Enclosure b. No findings were identified. | ||
| Line 208: | Line 217: | ||
. Documents reviewed are listed in the Attachment to this report. Inspection Scope turbine building basement; and auxiliary building basement. | . Documents reviewed are listed in the Attachment to this report. Inspection Scope turbine building basement; and auxiliary building basement. | ||
These inspection s constituted two internal flooding sample s as defined in IP 71111.06-05. | These inspection s constituted two internal flooding sample s as defined in IP | ||
==71111.06 - 05.== | |||
b. A concern related to a potential internal flood scenario in the auxiliary building from a ruptured fire protection system in the TSC was identified by inspectors during the completion of NRC Temporary Instruction (TI) 2515/183 , "Follow-Up to the Fukushima Daiichi Nuclear Station Fuel Damage Event | b. A concern related to a potential internal flood scenario in the auxiliary building from a ruptured fire protection system in the TSC was identified by inspectors during the completion of NRC Temporary Instruction (TI) 2515/183 , "Follow-Up to the Fukushima Daiichi Nuclear Station Fuel Damage Event | ||
| Line 240: | Line 251: | ||
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the CAP with the appropriate significance characterization. Documents reviewed are listed in the to this report | The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the CAP with the appropriate significance characterization. Documents reviewed are listed in the to this report | ||
. This inspection constituted one quarterly maintenance effectiveness sample as defined in IP 71111.12-05. | . This inspection constituted one quarterly maintenance effectiveness sample as defined in IP | ||
==71111.12 - 05.== | |||
====b. Findings==== | ====b. Findings==== | ||
| Line 311: | Line 324: | ||
Documents reviewed are listed in the Attachment to this report. | Documents reviewed are listed in the Attachment to this report. | ||
These maintenance risk assessments and emergent work control activities constituted five samp le s as defined in IP 71111.13-05. | These maintenance risk assessments and emergent work control activities constituted five samp le s as defined in IP | ||
==71111.13 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 324: | Line 339: | ||
. | . | ||
Inspection Scope This operability inspection constituted one sample as defined in IP 71111.15-05. | Inspection Scope This operability inspection constituted one sample as defined in IP | ||
==71111.15 - 05.== | |||
====b. Findings==== | ====b. Findings==== | ||
| Line 359: | Line 376: | ||
. | . | ||
This operability inspection constituted one sample as defined in IP 71111.15-05. | This operability inspection constituted one sample as defined in IP | ||
==71111.15 - 05.== | |||
b. (1) Findings Failed Standoffs Result in an Inoperable Train of Shield Building Ventilatio n | b. | ||
: (1) Findings Failed Standoffs Result in an Inoperable Train of Shield Building Ventilatio n | |||
=====Introduction:===== | =====Introduction:===== | ||
| Line 405: | Line 425: | ||
The licensee's initial short | The licensee's initial short | ||
-term CAs removed the installed standoffs from both trains. The licensee performed an exten t-of-condition looking at previously completed item equivalency evaluations (IEEs) to determine if an SCE was needed or missing for newly installed components. The licensee at the conclusion of the inspection period was re-performing the ACE. | -term CAs removed the installed standoffs from both trains. The licensee performed an exten t-of-condition looking at previously completed item equivalency evaluations (IEEs) to determine if an SCE was needed or missing for newly installed components. The licensee at the conclusion of the inspection period was re-performing the ACE. | ||
: (2) Failure to Submit Licensee Event Report per 10 CFR 50.73 Introduction | |||
: A Severity Level (SL) IV NCV of 10 CFR 50.73(a)(2)(i)(B) and 50.73(a)(2)(v)(C) was identified by the inspectors for the failure of the licensee to report an event or condition that was prohibited by TSs , and an event or condition that could have prevented the fulfillment of a safety function that is relied upon to control the 18 Enclosure release of radioactive material. Specifically, the licensee failed to report th at SBV train A was inoperable from Decembe r 3, 2010 , through January 26, 20 11. Technical Specification 3.6.c.1 allow s a single train outage time of seven days. Additionally, SBV train B was inoperable on multiple occasions during the same time period, requiring the licensee to also report an event or condition that could have prevented the fulfillment of a safety function, which is relied upon to control the release of radioactive material. | : A Severity Level (SL) IV NCV of 10 CFR 50.73(a)(2)(i)(B) and 50.73(a)(2)(v)(C) was identified by the inspectors for the failure of the licensee to report an event or condition that was prohibited by TSs , and an event or condition that could have prevented the fulfillment of a safety function that is relied upon to control the 18 Enclosure release of radioactive material. Specifically, the licensee failed to report th at SBV train A was inoperable from Decembe r 3, 2010 , through January 26, 20 11. Technical Specification 3.6.c.1 allow s a single train outage time of seven days. Additionally, SBV train B was inoperable on multiple occasions during the same time period, requiring the licensee to also report an event or condition that could have prevented the fulfillment of a safety function, which is relied upon to control the release of radioactive material. | ||
| Line 445: | Line 464: | ||
==4OA7 of this report.== | ==4OA7 of this report.== | ||
These operability inspections constituted five samples as defined in IP 71111.15-05. | These operability inspections constituted five samples as defined in IP | ||
==71111.15 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 461: | Line 482: | ||
Documents reviewed are listed in the Attachment to this report. | Documents reviewed are listed in the Attachment to this report. | ||
This inspection constituted one permanent plant modification sample as defined in IP 71111.18-05. | This inspection constituted one permanent plant modification sample as defined in IP | ||
==71111.18 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 482: | Line 505: | ||
. | . | ||
These inspection s constituted four post-maintenance testing sample s as defined in IP 71111.19-05. | These inspection s constituted four post-maintenance testing sample s as defined in IP | ||
==71111.19 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 517: | Line 542: | ||
Documents reviewed are listed in the Attachment to this report. | Documents reviewed are listed in the Attachment to this report. | ||
Inspection Scope This inspection constituted one emergency preparedness drill sample as defined in IP 71114.06-05. | Inspection Scope This inspection constituted one emergency preparedness drill sample as defined in IP | ||
==71114.06 - 05.== | |||
b. No findings were identified. | b. No findings were identified. | ||
| Line 675: | Line 702: | ||
==2RS6 Radioactive Gaseous and Liquid Effluent TreatmentThis inspection constituted one complete sample as defined in== | ==2RS6 Radioactive Gaseous and Liquid Effluent TreatmentThis inspection constituted one complete sample as defined in== | ||
IP 71124.06-0 5. | IP | ||
==71124.06 - 0 5.== | |||
(71124.06) | (71124.06) | ||
| Line 1,022: | Line 1,051: | ||
The inspectors assessed the activities and actions taken by the licensee to assess its readiness to respond to an event similar to the Fukushima Daiichi nuclear plant fuel damage event. | The inspectors assessed the activities and actions taken by the licensee to assess its readiness to respond to an event similar to the Fukushima Daiichi nuclear plant fuel damage event. | ||
This included the following: | This included the following: | ||
: (1) an assessment of the licensee's capability to mitigate conditions that may result from beyond design basis events, with a particular emphasis on strategies related to the SFP, as required by NRC Security Order (Closed) NRC Temporary Instruction 2515/183: "Follow-Up to the Fukushima Daiichi Nuclear Station Fuel Damage Event" | |||
43 Enclosure Section B.5.b, issued February 25, 2002, as committed to in SAMGs, and as required by 10 CFR 50.54(hh); (2) an assessment of the licensee's capability to mitigate SBO conditions, as required by 10 CFR 50.63 and station design bases; (3) an assessment of the licensee's capability to mitigate internal and external flooding events, as required by station design bases; and (4) an assessment of the thoroughness of the walkdowns and inspections of important equipment needed to mitigate fire and flood events, which were performed by the licensee to identify any potential loss of function of this equipment during seismic events possible for the site. | 43 Enclosure Section B.5.b, issued February 25, 2002, as committed to in SAMGs, and as required by 10 CFR 50.54(hh); | ||
: (2) an assessment of the licensee's capability to mitigate SBO conditions, as required by 10 CFR 50.63 and station design bases; | |||
: (3) an assessment of the licensee's capability to mitigate internal and external flooding events, as required by station design bases; and | |||
: (4) an assessment of the thoroughness of the walkdowns and inspections of important equipment needed to mitigate fire and flood events, which were performed by the licensee to identify any potential loss of function of this equipment during seismic events possible for the site. | |||
IR 05000305/2011009 (ML111320380) documented detailed results of this inspection activity. | IR 05000305/2011009 (ML111320380) documented detailed results of this inspection activity. | ||
| Line 1,035: | Line 1,067: | ||
===.2 On May 27, 2011, the inspectors completed a review of the licensee's SAMGs, implemented as a voluntary industry initiative in the 1990's, to determine:=== | ===.2 On May 27, 2011, the inspectors completed a review of the licensee's SAMGs, implemented as a voluntary industry initiative in the 1990's, to determine:=== | ||
: (1) whether the SAMGs were available and updated | |||
; (2) whether the licensee had procedures and processes in place to control and update its SAMGs | ; | ||
; (3) the nature and extent of the licensee's training of personnel on the use of SAMGs | : (2) whether the licensee had procedures and processes in place to control and update its SAMGs | ||
; and (4) licensee personnel's familiarity with SAMG implementation. | ; | ||
: (3) the nature and extent of the licensee's training of personnel on the use of SAMGs | |||
; and | |||
: (4) licensee personnel's familiarity with SAMG implementation. | |||
(Closed) NRC Temporary Instruction 2515/184: "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)" | (Closed) NRC Temporary Instruction 2515/184: "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)" | ||
Revision as of 14:26, 18 September 2018
| ML11209B476 | |
| Person / Time | |
|---|---|
| Site: | Kewaunee |
| Issue date: | 07/28/2011 |
| From: | Kunowski M A NRC/RGN-III/DRP/B5 |
| To: | Heacock D A Dominion Energy Kewaunee |
| References | |
| IR-11-003 | |
| Download: ML11209B476 (67) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532
-4352 July 28, 2011 Mr. David President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.
Innsbrook Technical Center 5000 Dominion Boulevard
Glen Allen, VA 23060
-6711
SUBJECT: KEWAUNEE POWER STATION INTEGRATED INSPECTION REPORT 05000 305/2 0 11003
Dear Mr. Heacock:
On June 30, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed an integrated inspection at your Kewaunee Power Station. The enclosed report documents the results of this inspection, which were discussed on June 30, 2011, with Mr. Stephen Scace and other members of your staff.
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.
Based on the results of this inspection, one NRC-identified Severity Level IV violation, three NRC-identified findings , and one self-revealed finding of very low safety significance were identified. The Severity Level IV violation and one finding involve d violation s of NRC requirements
, and because of the very low safety significance and because they are entered into your corrective action program, the NRC is treating these findings as n on-cited violations (NCVs), in accordance with Section 2.3.2 of the NRC Enforcement Policy.
Additionally, two licensee
-identified violations are listed in Section 4OA7 of this report.
If you contest the subject or severity of these NCV s, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission
- Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532
-4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555
-0001; and the Resident Inspector Office at the Kewaunee Power Station. In addition, if you disagree with the cross
-cutting aspect assigned to any finding in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region III, and the NRC Resident Inspector at the Kewaunee Power Station. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely,/RA/ Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket No. 50
-305 License No. DPR
-43
Enclosure:
Inspection Report 050003 05/20 1100 3
w/Attachment:
Supplemental Information cc w/encl:
Distribution via ListServ
Enclosure U.S. NUCLEAR REGULATORY COMMISSION REGION III Docket No:
50-305 License N o: DPR-43 Report No:
050003 05/20 1100 3 Licensee: Dominion Energy Kewaunee, In c. Facility: Kewaunee Power Station Location: Kewaunee, WI Dates: April 1, 2011, through June 30, 2011 Inspectors:
R. Krsek, Senior Resident Inspector K. Barclay, Resident Inspector R. Winter, Reactor Inspector K. Carrington, Reactor Engineer J. Cassidy, Senior Health Physicist Approved by:
Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Enclosure
SUMMARY OF FINDINGS
IR 050003 05/20 1100 3 , 4/01/2011 - 6/30/2011; Kewaunee Power Station
- Maintenance Effectiveness, Operability Evaluations
, and Identification and Resolution of Problems
. This report covers a three-month period of inspection by resident inspectors and announced baseline inspections by regional inspectors. The inspectors identified one Severity Level (SL) IV violation, three Green finding s , and one Green finding was self-revealed. The SL IV violation and one finding were considered n on-cited violation s (NCV s) of NRC regulations. The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, "Significance Determination Process" (SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG
-1649, "React or Oversight Process," Revision 4, dated December 2006. A.
Cornerstone: Mitigating Systems
N RC-Identified and Self-Revealed Findings GreenThe finding was determined to be more than minor because the finding was associated with the Mitigating Systems Cornerstone attribute of equipment performance and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences.
Specifically, the failure of the output breaker to close and energize bus 1-46 caused the TSC DG to overheat and automatically shut down during a partial loss of offsite power
. The inspectors concluded the finding could be evaluated in accordance with I MC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1 - Initial Screening and Characterization of Findings," Table 4a, for the Mitigating Systems Cornerstone. The inspectors answered "Yes" to questions and 4 of the Mitigating Systems Cornerstone column and determined that the finding required a Phase analysis.
T he Region III senior reactor analyst completed a Phase 2 analysis and determined the risk significance of the issue to be very low (Green).
The finding has a cross-cutting aspect in the area of human performance, resources, because a licensee effort to review various plant components for possible inclusion in a preventive maintenance optimization project had assigned a low priority to this relay (H.2(a)). (Section 1R12.1) . A finding of very low safety significance was self-revealed for the failure to perform adequate preventive maintenance on latching relay VR1/B46, a relay required for closure of the Technical Support Center (TSC) diesel generator's (DG's) output breaker and automatic restoration of bus 1
-46, which powers the TSC DG's cooling system. Specifically, on March 20, 2011, during a partial loss of offsite power event, the TSC DG started but failed to load onto bus 1-46. After approximately 43 minutes of operation, the DG automatically shut down from an over-temperature condition, as designed. The licensee initiated condition report 417289 and performed apparent cause evaluation 018573. The licensee's short-term corrective actions included troubleshooting the initial failure, repairing relay VR1/B46, and restoring the TSC DG to functional status. The licensee's long-term corrective actions were in-progress at the completion of this inspection period.
GreenThe finding was determined to be more than minor because the finding, if left uncorrected, had the potential to become a more significant safety concern. Specifically, the failure to perform operability evaluations on degraded safety-related systems could lead to situations where systems needed to mitigate design basis accidents were not capable of performing their required safety functions. The inspectors determined the finding could be evaluated using IMC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1 - Initial Screening and Characterization of Findings," Table 4a , for the Mitigating Systems Cornerstone. The inspectors answered "No" to the Mitigating Systems questions and screened the finding as having very low safety significance (Green). The finding has a cross-cutting aspect in the area of human performance, work practices, because the licensee failed to communicate decisions and the bases for decisions to personnel who had a need to know the information in order to perform work safely. Specifically, the licensee failed to effectively communicate the expectation to assess operability of the service water system in the pre-job brief and peer review (H.1(c)). (Section 1R15.1
) . A finding of very low safety significance was identified by the inspectors for the failure to adequately assess operability of the service water system in operability determination 413, "EDG A Jacket Water Expansion Tank Overflow," in accordance with site Procedure OP-AA-102-1001, "Development of Technical Basis to Support Operability Determinations."
At the end of the inspection period, the licensee was completing an apparent cause evaluation to determine the cause and develop corrective actions. GreenThe finding was determined to be more than minor because
, if left uncorrected
, the finding had the potential to lead to a more significant safety concern. Specifically, the failure to review and update the SAMGs would have hampered the licensee's response in the unlikely event of a severe accident, because the SAMGs were not current. The inspectors, in consultation with the Region III senior reactor analyst, determined that the finding could be evaluated using the Significance Determination Process in accordance with IMC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1
- Initial Screening and Characterization of Findings," Table 4a , for the Mitigating Systems Cornerstone. The inspectors answered " No" to t he Mitigating Systems questions and screened the finding as having very low safety significance (Green). The finding has a cross-cutting aspect in the area of problem identification and resolution, corrective action program, because the licensee failed to take appropriate corrective actions to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity. . A finding of very low safety significance was identified by the inspectors for the licensee's failure to perform reviews and update the Severe Accident Management Guidelines (SAMGs) in accordance with the licensee's nuclear administrative directives (NAD s). Specifically, Procedure NAD-14.06 required that the engineering group review industry correspondence related to SAMGs and implement appropriate changes, and that the emergency preparedness group conduct biennial reviews of the SAMGs. The inspectors identified that neither group had performed the reviews. As a result
, the SAMGs were not adequately updated. The licensee entered this issue into their corrective action program as condition reports (CR s) 424681, 424855, 424865, 424866, 425092, 426999, and 427092, and was still evaluating the cause for this condition at the end of this inspection period.
The licensee scheduled the revision of the SAMGs for completion by December 2011.
Specifically, the licensee identified in an apparent cause evaluation initiated in April 2010 that the emergency preparedness organization had not performed the required reviews and updates of emergency preparedness procedures, and the SAMGs were identified in the licensee's extent-of-condition. However, the inspectors identified that the corrective action s issued for th is extent-of-condition did not address the SAMGs and , therefore , no corrective actions were taken (P.1(d)). (Section 4OA2.3)
Cornerstone: Barrier Integrity
GreenThe finding was determined to be more than minor because the finding was associated with the Barrier Integrity Cornerstone attribute of procedure quality, and adversely affected the cornerstone objective of providing reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, the licensee failed to have and follow adequate procedures which led to the failure of SBV train A. The inspectors determined that this was a type B containment finding since it was related to a degraded condition that had potential important implications for the integrity of the containment, without affecting the likelihood of core damage. The inspector evaluated the finding using the SDP in accordance with I MC 0609, Appendix H, "Containment Integrity SDP," Table 4.1, and determined that the finding did not relate to a containment structure, system, and component, nor containment status that had an impact on large early release frequency. Because of this, the issue screened as Green, using the flowchart in Figure 4.1. The finding has a cross-cutting aspect in the area of problem identification and resolution, corrective action program, because the licensee failed to thoroughly evaluate problems such that the resolutions address causes and extent-of-conditions, as necessary.
This includes properly classifying, prioritizing, and evaluating for operability and reportability conditions adverse to quality.
This also includes, for significant problems, conducting effectiveness reviews of corrective actions to ensure that the problems are resolved. Specifically, the licensee failed to properly evaluate and identify the cause of the SBV train A failure and produce a resolution that addressed the cause (P.1(c)). (Section 1R15.2(1)) . A finding of very low safety significance and associated non-cited violation of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," was identified by inspectors for the failure to have and follow adequate procedures for the evaluation and installation of component s in shield building ventilation (SBV) train A. Specifically, the licensee failed to have adequate procedures to direct the completion of a subcomponent classification evaluation (SCE) and prevent nonsafety-related parts from being installed in safety-related applications; have torque specifications for the standoffs (spacers for circuit cards) in the work instructions; and properly accomplish the SCE procedure when evaluating the standoffs.
The licensee's initial short-term corrective actions removed the installed standoffs from both trains. The licensee also performed an extent-of-condition looking at previously completed item equivalency evaluations to determine if an SCE was needed or missing for newly installed components.
===Cornerstone:
Other Findings
=
SL IV. A Severity Level IV non-cited violation of 10 CFR 50.73(a)(2)(i)(B)and 50.73(a)(2)(v)(C) was identified by the inspectors for the failure of the licensee to report an event or condition that was prohibited by Technical Specifications
, and an event or condition that could have prevented the fulfillment of a safety function that is relied upon to control the release of radioactive material. Specifically, the licensee failed to report that shield building ventilation train A was inoperable from December 3, 2010 , through January 26, 2011. Technical Specification 3.6.c.1 allow s a single train outage time of seven days. Additionally, shield building ventilation train B was inoperable on multiple occasions during the same time period, requiring the licensee to also report an event or condition that could have prevented the fulfillment of a safety function, which is relied upon to control the release of radioactive material.
At the end of the inspection period, the licensee was completing an apparent cause evaluation to determine the cause and develop corrective actions.
Because violations of 10 CFR 50.73 are considered to be violations that potentially impact the regulatory process, they are dispositioned using the traditional enforcement process instead of the Reactor Oversight Process Significance Determination Process. A cross-cutting aspect was not assigned to this violation. Per the NRC Enforcement Policy, Section 6.0, "Violation Examples," a failure to submit a required licensee event report is categorized as a Severity Level IV violation.
(Section 1R15.2(2)) B. Violations of very low safety significance that were identified by the licensee have been reviewed by inspectors. Corrective actions planned or taken by the licensee have been entered into the licensee's corrective action program. These violations and corrective action tracking numbers are listed in Section 4OA7 of this report.
=
Licensee-Identified Violations===
REPORT DETAILS
Kewaunee Power Station (KPS) operated at full power
, for the entire inspection period, except for brief downpowers to conduct planned maintenance and surveillance activitie s, Summary of Plant Status
REACTOR SAFETY
Cornerstone s: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness
1R01 Adverse Weather Protection
.1
a. Readiness of Offsite and Alternate AC Power System s The inspectors verified that plant features and procedures for operation and continued availability of offsite and alternate alternating current (AC) power systems during adverse weather were appropriate. The inspectors reviewed the licensee's procedures affecting these areas
, and the communications protocols between the transmission system operator (TSO) and the plant to verify that the appropriate information was exchanged when issues arose that could impact the offsite power system. Examples of aspects considered in the inspectors' review included:
Inspection Scope the coordination between the TSO and the plant during off
-normal or emergency events; the explanations for the events; the estimates of when the offsite power system would be returned to a normal state; and the notifications from the TSO to the plant when the offsite power system was returned to normal.
The inspectors also verified that plant procedures addressed measures to monitor and maintain availability and reliability of both the offsite AC power system and the onsite alternate AC power system prior to or during adverse weather conditions. Specifically, the inspectors verified that the procedures addressed the following:
the actions to be taken when notified by the TSO that the post
-trip voltage of the offsite power system at the plant would not be acceptable to assure the continued operation of the safety
-related (SR) loads without transferring to the onsite power supply; the compensatory actions identified to be performed if it would not be possible to predict the post
-trip voltage at the plant for the current grid conditions
- a re-assessment of plant risk based on maintenance activities which could affect grid reliability, or the ability of the transmission system to provide offsite power
- and the communications between the plant and the TSO when changes at the plant could impact the transmission system, or when the capability of the transmissio n system to provide adequate offsite power was challenged
.
6 Enclosure Documents reviewed are listed in the Attachment to this report.
The inspectors also reviewed corrective action program (CAP) items to verify that the licensee was identifying adverse weather issues at an appropriate threshold and entering them into the CAP in accordance with station corrective action (CA) procedures.
This inspection constituted one readiness of offsite and alternate AC power systems sample as defined in Inspection Procedure (IP)
71111.01 - 05.
b. No findings were identified.
Findings
.2 a. External Flooding
The inspectors evaluated the design, material condition, and procedures for coping with the design basis maximum probable flood. The evaluation included a review to check for deviations from the descriptions in the Updated Safety Analysis Report (USAR) for features intended to mitigate the potential for flooding from external factors. As part of this evaluation, the inspectors checked for obstructions that could prevent draining and determined that barriers required to mitigate the flood were in place and operable.
The inspectors also reviewed the abnormal operating procedure for mitigating the design basis flood to ensure it could be implemented as written.
Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one external flooding sample as defined in IP
71111.01 - 05.
b. No findings were identified.
Findings 1R04 Equipment Alignment
.1
a. Quarterly Partial System Walkdow ns The inspectors performed partial system walkdowns of the following risk
-significant systems: Inspection Scope turbine-driven auxiliary feedwater (TDAFW) following the quarterly test; and bus 1-43 following troubleshooting on breaker 14305 for pressurizer heater D. The inspectors selected these systems based on their risk significance relative to the Reactor Safety (RS) Cornerstones at the time they were inspected. The inspectors attempted to identify any discrepancies that could impact the function of the system, and, therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, the USAR, Technical Specification (TS) requirements, outstanding work orders (WOs), condition reports (CRs), and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors 7 Enclosure also walked down accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers
, and entered them into the CAP with the appropriate significance characterization. Documents reviewed are listed in the Attachment to this report
.
These activities constituted two partial system walkdown sample s as defined in IP
71111.04 - 05.
b. No findings were identified.
Findings 1R05 Fire Protection
.1
Routine Resident Inspector Tours a. (71111.05Q)
The inspectors conducted fire protection (FP) walkdowns which were focused on availability, accessibility, and the condition of firefighting equipment in the following risk-significant plant areas: Inspection Scope AX-33, condensate and makeup water tank room; AX-37, control rod drive equipment room; AX-39, bottled gas storage; and TU-96, oil storage room B.
The inspectors reviewed areas to assess if the licensee had implemented a n FP program that: adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive FP features in good material condition; and implemented adequate compensatory measures for out-of-service, degraded, or inoperable FP equipment, systems, or features
, in accordance with the licensee's fire plan. The inspectors selected fire areas based on the overall contribution to internal fire risk as documented in the plant's Individual Plant Examination of External Events with later additional risk insights, or the potential to impact equipment which could initiate or mitigate a plant transient. The inspectors verified that: fire hoses and extinguishers were in the designated locations and available for immediate use; fire detectors and sprinklers were unobstructed; transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition. The inspectors also verified that minor issue s identified during the inspection were entered into the licensee's CAP. Documents reviewed are listed in the Attachment to this report.
These activities constituted four quarterly fire protection inspection samples as defined in IP
71111.05 - 05.
8 Enclosure b. No findings were identified.
Findings
1R06 Flooding.1
a. Internal Flooding The inspectors reviewed selected risk important plant design features and licensee procedures intended to protect the plant and SR equipment from internal flooding events. The inspectors reviewed flood analyses and design documents, includin g
the USAR, engineering calculations, and abnormal operating procedures. In addition, the inspectors reviewed licensee drawings to identify areas and equipment that may be affected by internal flooding caused by the failure or misalignment of nearby sources of water, such as the fire suppression or circulating water systems.
The inspectors also reviewed the licensee's corrective action documents with respect to past flood
-related items identified in the CAP to verify the adequacy of the CAs. The inspectors performed a walkdown of the following plant areas to assess the adequacy of watertight doors and verify that drains and sumps were clear of debris and operable
. Documents reviewed are listed in the Attachment to this report. Inspection Scope turbine building basement; and auxiliary building basement.
These inspection s constituted two internal flooding sample s as defined in IP
71111.06 - 05.
b. A concern related to a potential internal flood scenario in the auxiliary building from a ruptured fire protection system in the TSC was identified by inspectors during the completion of NRC Temporary Instruction (TI) 2515/183 , "Follow-Up to the Fukushima Daiichi Nuclear Station Fuel Damage Event
." The issue is being tracked by unresolved item (URI) 05000305/2011003
-07 and is discussed in Section 4OA5.4
.
Findings 1R11 Licensed Operator Requalification Program
.1
Resident Inspector Quarterly Review a. (71111.11Q)
On June 6, 2011, the inspectors observed a crew of licensed operators in the plant's simulator during licensed operator training activities to verify that training was being conducted in accordance with licensee procedures, and adequately addressed plant modifications. The inspectors evaluated the following areas during training
- Inspection Scope adequacy of revised operating procedures
- prioritization, interpretation, and verification of new annunciator alarms; correct use and implementation of revised abnormal and emergency operating procedures; control board equipment manipulations; and oversight and direction from supervisors.
Documents reviewed are listed in the Attachment to this report.
This inspection constituted one quarterly licensed operator requalification program sample as defined in IP 71111.11.
b. No findings were identified.
Findings 1R12 Maintenance Effectiveness
.1
Routine Quarterly EvaluationsThe inspectors evaluated degraded performance issues associated with the TSC diesel generator (DG) output breaker failing to close during an actual event and the subsequent over-temperature trip of the TSC DG. (71111.12Q)
The inspectors reviewed the event and independently verified the licensee's actions to address system performance or condition problems in terms of the following:
implementing appropriate work practices; identifying and addressing common cause failures; scoping of systems in accordance with 10 CFR 50.65(b) of the maintenance rule; characterizing system reliability issues for performance; charging unavailability for performance; trending key parameters for condition monitoring; ensuring 10 CFR 50.65(a)(1) or (a)(2) classification or re
-classification; and verifying appropriate performance criteria for structures, systems, and components (SSCs)/functions classified as (a)(2) or appropriate and adequate goals and CAs for systems classified as (a)(1).
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the CAP with the appropriate significance characterization. Documents reviewed are listed in the to this report
. This inspection constituted one quarterly maintenance effectiveness sample as defined in IP
71111.12 - 05.
b. Findings
Technical Support Center Diesel Generator Output Breaker Fails to Close Introduction
- A finding of very low safety significance was self
-revealed for the failure to perform adequate preventive maintenance (PM) on latching relay VR1/B46, a relay required for closure of the TSC DG's output breaker and automatic restoration of bus 1-46, which powers the TSC DG's cooling system. Specifically, on March 20, 2011, during a partial loss of offsite power (LOOP) event, the TSC DG started but failed to load 10 Enclosure onto bus 1
-46. After approximately 43 minutes of operation, the DG automatically shut down from an over
-temperature condition, as designed
.
DescriptionThe licensee's troubleshooting and investigation determined that relay VR1/B46 did not remain latched and was the cause of the output breaker failing to close. The licensee also found that the relay was obsolete, no longer manufactured, and had been installed for almost 30 years with no history of maintenance other than a visual inspection. The licensee was able to ma ke adjustments to the relay, verified and tested its proper operation, and reinstalled it. The licensee's Apparent Cause Evaluation (A CE) determined that the PM established for the latching relay (a visual check) was inadequate for maintaining and verifying the ability of the relay to remain latched during automatic bus 1-46 voltage restoration. The last time the relay was verified t o function properly was October 30, 2006, during an automatic restoration of bus 1-46.
- On March 10, 2011, Dominion technicians performed relay testing on newly installed breaker RST
-199 in the switchyard control house. During the testing, the technicians inappropriately selected an in
-service breaker which provided power to bus 6 (a safety-related 4160
-volt bus) through the main auxiliary transformer (MAT). When the relay for the in
-service breaker was tested, the breaker opened, as designed, causing a partial LOOP. In response, emergency diesel generator (EDG)
B automatically started as designed and restored power to bus 6. The TSC DG also automatically started as designed, but the output breaker did not close and restore power to bus 1
-46 as expected. With the bus not energized, the cooling system for the TSC DG was not functioning and the TSC DG eventually shut down automatically on an over
-temperature condition, as designed. At the time of the event, the reactor was defueled with all fuel offloaded into the spent fuel pool (SFP). The SFP cooling requirement, at the time of the event, was one train of cooling, which was maintained throughout the event. The licensee's planned CAs for the ACE were to establish a PM task to periodically test and clean relay VR1/B46
, and to revise the TSC DG test procedures to visually chec k and verify that the latching mechanism was properly engaged after the output breaker was opened at the completion of testing. Additionally, the licensee opened a separate CA item to find a replacement relay that is not obsolete and schedule a relay replacement.
AnalysisThe finding was determined to be more than minor in accordance with IMC 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," dated December 24, 2009, because the finding was associated with the Mitigating Systems Cornerstone attribute of equipment performance and adversely affected the cornerstone objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure of the output breaker to close and energize bus 1-46 caused the TSC DG to overheat and stop running during a partial LOOP, which left bus 1-46 de-energized for the event.
- The inspectors determined that the failure to perform an adequate PM on latching relay VR1/B46 was contrary to the licensee's PM program, and was a performance deficiency warranting a significance evaluation
.
The inspectors determined the finding, although identified when the reactor was shutdown, existed for longer time periods when the reactor was operating and, thus, could be evaluated in accordance with IMC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1 - Initial Screening and Characterization of Findings,"
11 Enclosure Table 4a, for the Mitigating Systems Cornerst one, dated January 10, 2008. The inspectors answered "Yes" to questions 2 and 4 of the Mitigating Systems Cornerstone column and determined that the finding required a Phase 2 analysis.
The inspectors reviewed the Kewaunee Risk-Informed Inspection Notebook (Notebook) and the pre
-solved Phase 2 spreadsheets. The Notebook included a statement in Table 2 that the TSC DG can be manually aligned in a station blackout (SBO) scenario in about an hour, but the significance of failure of the TSC DG is not evaluated. Alignment of the TSC DG takes longer than 13 minutes and thus is not effective in influencing the reactor coolant pump seal loss
-of-coolant accident. As with the Notebook, the spreadsheets do not evaluate the significance of the TSC DG.
The Region III senior reactor analyst (SRA) contacted the KPS probabilistic risk analysis staff to discuss the risk significance of this failure. The PRA staff stated that the TSC DG is modeled as being manually loaded onto its bus and the actual failure that occurred on March 10 would not have prevented plant operators from manually loading the DG onto its bus. The inspectors and SRA verified this to be the case and determined that manually loading the DG is addressed in the site emergency operating procedure for loss of all AC power. Considering this, the SRA determined the risk significance of the issue to be very low (Green).
The finding has a cross
-cutting aspect in the area of human performance, resources, because a licensee project to optimize its preventive maintenance activities assigned a low priority to this relay (H.2(a)).
EnforcementThe licensee initiated CR417289 and performed ACE018573. The licensee's short
-term CAs included troubleshooting the initial failure, repairing relay VR1/B46, and restoring the TSC DG to functional status. The licensee's long
-term CAs were in-progress at the completion of this inspection period.
- No violation of regulatory requirements occurred but the inspectors did identify a finding (FIN 05000305/2011003-01; Technical Support Center Diesel Generator Output Breaker Fails to Close)
.
.2 Routine Quarterly EvaluationsThe inspectors evaluated degraded performance issues for the
rod control and rod position indication system.
The inspectors reviewed events
, such as where ineffective equipment maintenance had resulted in valid or invalid automatic actuations of engineered safeguards systems , and independently verified the licensee's actions to address system performance or condition problems in terms of the following: implementing appropriate work practices; identifying and addressing common cause failures; scoping of systems in accordance with 10 CFR 50.65(b) of the maintenance rule; characterizing system reliability issues for performance; charging unavailability for performance; trending key parameters for condition monitoring; ensuring 10 CFR 50.65(a)(1) or (a)(2) classification or re
-classification; and verifying appropriate performance criteria for SSCs/functions classified as (a)(2) or appropriate and adequate goals and corrective actions for systems classified as (a)(1).
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were entered into the CAP with the appropriate significance characterization. Documents reviewed are listed in the to this report
.
This inspection constituted one quarterly maintenance effectiveness sample as defined in IP 7 1111.12-05.
b. No findings were identified.
Findings 1R13 Maintenance Risk Assessments and Emergent Work Control
.1
a. Maintenance Risk Assessments and Emergent Work Control The inspectors reviewed the licensee's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk
-significant and SR equipment to verify that the appropriate risk assessments were performed prior to removing equipment for work during the following weeks
- Inspection Scope May 9; May 16; May 23; May 30; and June 13. These activities were selected based on their potential risk significance relative to the R S Cornerstones. As applicable for each activity, the inspectors verified that risk assessments were performed as required by 10 CFR 50.65(a)(4) and were accurate and complete. When emergent work was performed, the inspectors verified that the plant risk was promptly reassessed and managed. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed TS requirements and walked down portions of redundant safety systems, when applicable, to verify that risk analysis assumptions were valid and applicable requirements were met.
Documents reviewed are listed in the Attachment to this report.
These maintenance risk assessments and emergent work control activities constituted five samp le s as defined in IP
71111.13 - 05.
b. No findings were identified.
Findings 13 Enclosure 1R15 Operability Evaluations
.1
a. Operability Evaluations The inspectors reviewed CR 421752 , "Jacket Water Dripping From Reservoir Overflow Line on EDG A ," based on the risk significance of the EDG. The inspectors evaluated the technical adequacy of the evaluation to ensure that TS operability was properly justified , and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TSs and USAR to the licensee's evaluation to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations.
Additionally, the inspectors reviewed a sampling of CA documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Documents reviewed are listed in the to this report
.
Inspection Scope This operability inspection constituted one sample as defined in IP
71111.15 - 05.
b. Findings
Inadequate Operability Determination of a Heat Exchanger Leak on Emergency Diesel Generator A
Introduction:
A finding of very low safety significance was identified by the inspectors for the failure to adequately assess operability of the service water (SW) system in operability determination (OD) 413, "EDG 'A' Jacket Water Expansion Tank Overflow,"
in accordance with site Procedure OP-AA-102-1001, "Development of Technical Basis to Support Operability Determinations."
Description:
On April 11, 2011, the licensee identified water dripping from the jacket water reservoir overflow line of EDG A. The reservoir site glass indicated the tank was completely full. The licensee determined, based on chemistry sampling and the absence of oil in the jacket water, that a n SW leak had developed in the jacket water heat exchanger. The licensee performed OD
-413, which was completed and approved on April 15. On April 21, the inspectors reviewed OD
-413 and found it assessed the effects of the degraded condition on the EDG, but did not assess how the degraded condition affected the SW system, the high pressure side of the leak, as well as an American Society of Mechanical Engineers (ASME) Code Class III pressure boundary. The inspectors shared their concern with the licensee, who initially believed that the leak was not an AMSE Code Class III pressure boundary leak and consequently not operational leakage. The inspectors reviewed the licensee's basis document for code class boundaries and found that it specifically referred to the tube side of the EDG cooling water heat exchanger as "Class 3." The resident inspectors consulted with regional inspectors and Office of Nuclear Reactor Regulation staff who concluded that the leak was pressure boundary leakage and needed to be evaluated. The licensee revised OD 413 to include an assessment of how the ASME Code Class III pressure 14 Enclosure boundary leakage affected SW system operability, and concluded that the system remained operable and that EDG A was operable but degraded. The licensee preliminarily determined that the licensee staff who performed the OD did not understand the need to address SW from an operability standpoint, and did not capture the direction to include it, which was discussed in a peer review that occurred prior to performing the OD. This licensee entered the issue into the CAP as CR423665 and performed an ACE, which was not complete at the conclusion of this inspection period.
AnalysisThe finding was determined to be more than minor in accordance with IMC 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," dated December 24, 2009, because the finding, if left uncorrected, had the potential to become a more significant safety concern. Specifically, the failure to perform operability evaluations on degraded SR systems could lead to situations where systems needed to mitigate design basis accidents were not capable of performing their required safety functions. The inspectors determined the finding could be evaluated using IMC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1 Initial Screening and Characterization of Findings," Table 4a for the Mitigating Systems Cornerstone , dated January 10, 2008. The inspectors answered "No" to the Mitigating Systems questions and screened the finding as having very low significance (Green).
- The inspectors determined that the failure to assess operability of the SW system in OD 413 was contrary to Procedure OP-AA-102-1001, and was a performance deficiency warranting a significance evaluation.
The finding has a cross
-cutting aspect in the area of human performance, work practices, because the licensee failed to communicate decisions and the bas e s for decisions to personnel who had a need to know the information in order to perform work safely. Specifically, the licensee failed to effectively communicate the expectation to assess operability of the SW system in the pre
-job brief and peer review (H.1 (c)).
EnforcementThis licensee entered this issue into the CAP as CR423665 and performed an ACE , which was not complete at the conclusion of th is inspection period.
- No violation of regulatory requirements occurred but the inspectors did identify a finding (FIN 05000305/2011003
-02, Inadequate Operability Determination of a Heat Exchanger Leak on Emergency Diesel Generator A).
.2 a. Operability Evaluations
The inspectors reviewed the operability determination of CR 411681 , "Shield Building Ventilation
[SBV] Standoffs for Servo Board Broken," because of the potential for a common mode failure that could affect both trains. The inspectors evaluated the technical adequacy of the evaluation to ensure that TS operability was properly justified
, and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TSs and USAR to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the Inspection Scope
15 Enclosure evaluation. Additionally, the inspectors reviewed a sampling of CA documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Documents reviewed are listed in the to this report
.
This operability inspection constituted one sample as defined in IP
71111.15 - 05.
b.
- (1) Findings Failed Standoffs Result in an Inoperable Train of Shield Building Ventilatio n
Introduction:
A finding of very low safety significance and associated non
-cited violation (NCV) of 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," was identified by the inspectors for the failure to have and follow adequate procedures for the evaluation and installation of component s in SBV train A. Specifically, the licensee failed to: have adequate procedures to direct the completion of a subcomponent classification evaluation (SCE) and prevent nonsafety-related (NS) parts from being installed in SR applications; have torque specifications for the standoffs (spacers for circuit cards) in the work instructions; and properly accomplish the SCE procedure when evaluating the standoffs.
DescriptionDuring their review of this issue, the inspectors identified the following concerns:
- On January 26, 2011, plant personnel were inspecting train A of the SBV control cabinets and discovered a circuit card had broken free from three of the four standoffs. The licensee declared SBV train A inoperable and visually confirmed that the same condition did not exist on train B. The standoffs had previously been installed in both trains as a defense
-in-depth action to provide additional clearance behind the installed circuit cards to prevent screws on the back of the cards from contacting insulating paper. Based on available information, t he licensee determined train B remained operable because separate personnel had installed standoffs on the two different trains and those on train A were installed with either inadequate installation techniques or excessive torque whereas those on train B were not. On January 27, during the initial investigation, the licensee determined that plant personnel had previously failed to perform an SCE to determine if the standoffs in the SBV system would have an SR quality classification or an NS quality classification. The standoffs that failed were NS and purchased from a vendor that did not have a 10 CFR Appendix B quality assurance program. Upon discovery, the licensee performed an SCE on the standoffs, which concluded that NS standoffs could be used in this application. The licensee conservatively decided to remove the standoffs from both trains and return to the original configuration. Train A was repaired and declared operable on January 27 and the standoffs on train B were removed on February 3. The licensee performed an ACE, which concluded that the standoffs failed because the quality and design of the standoff material was insufficient, which resulted in improper adhesion between the metal stud and the neoprene body that constitute the standoff.
the licensee installed a NS part in an SR host component without performing the correct evaluation to determine if it was appropriate; the licensee failed to have torque specifications in the work instruction that installed the standoffs; the licensee improperly applied the SCE procedure and came to the incorrect determination about the required quality of the standoffs; and the licensee's ACE came to the incorrect conclusion about the cause of the failure. The inspectors found that the licensee had performed an item equivalency evaluation for any design and configuration concerns with regards to adding the standoffs. However, under these specific circumstances, nothing directed the licensee to perform Procedure MS-AA-SCE-301, "Subcomponent Evaluation," which determined if the standoffs perform ed an SR or NS function, and the quality of part that could be purchased for installation.
The inspectors found that no torque requirements were specified in the work instructions that installed the standoffs on December 2, 2010. The licensee's investigation following the failure found that the standoffs fail at low torque values, which could easily be exceeded with a standard screwdriver.
The inspectors' in
-depth review of the SCE, completed on January 27, 2011, found that it did not document the licensee's response to questions in steps 3.2.16, 3.2.17 and 3.2.18 of Procedure MS-AA-SCE-301. Step 3.2.16 stated, "If host component would not be able to perform all safety functions if the item were nonfunctional, then consider the item safety
-related." The inspectors determined that the standoffs function ed to structurally support the circuit card. If the manufacturing process and quality controls of the NS vendor were inadequate, then the standoffs may fatigue and fail over time from gravity, operational vibrations, or a seismic event, thus preventing the SBV system from performing its safety function. Step 3.2.17 stated, "Determine if the item is required to ensure qualification of the component." Step 3.2.18 stated, "If item is required to ensure qualification, then use the safety classification of the host component." The inspectors determined that the standoffs were the only structural support or anchors for the SR circuit card and were needed to ensure the seismic qualification of the card.
The licensee agreed with the inspectors' observations that the standoffs should have been SR and procured as SR or commercially
-dedicated; the work instructions for the circuit card installation were inadequate; and that the conclusions of the ACE were incorrect. At the end of this inspection period, the licensee was re
-performing the ACE and sent the failed standoffs to a laboratory for failure analysis.
AnalysisThe finding was determined to be more than minor in accordance with IMC 0612, "Power Reactor Inspection Reports,: Appendix B, "Issue Screening," dated December 24, 2009, because the finding was associated with the Barrier Integrity Cornerstone attribute of procedure quality, and adversely affected the cornerstone objective of providing reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, because : The inspectors determined that the failure to have and follow adequat e procedures was a performance deficiency warranting a significance evaluation.
17 Enclosure of the procedure problems, one train of the ventilation system for the shield building, surrounding containment, failed.
The inspectors determined that this was a type B containment finding since it was related to a degraded condition that had potential important implications for the integrity of the containment, without affecting the likelihood of core damage. The inspector evaluated the finding using the SDP in accordance with IMC 0609, Appendix H, "Containment Integrity SDP," Table 4.1, dated May 6, 2004, and determined that the finding did not relate to a containment SSC, nor containment status that had an impact on large early release frequency. Because of this, the issue screened as Green, using the flowchart in Figure 4.1.
The finding has a cross
-cutting aspect in the area of problem identification and resolution, c orrective action program, because the licensee failed to thoroughly evaluate problems such that the resolutions would address causes and extent-of-conditions, as necessary.
This includes properly classifying, prioritizing, and evaluating for operability and reportability conditions adverse to quality.
This also includes, for significant problems, conducting effectiveness reviews of corrective actions to ensure that the problems are resolved. Specifically, the licensee failed to properly evaluate and iden tify the cause of the SBV train A failure and produce a resolution that addressed the cause (P.1(c)).
EnforcementContrary to th is, from October 23, 2009 , through January 27, 2011, the licensee failed to prescribe documented instructions, procedures, or drawings of a type appropriate to the circumstances, and failed to accomplish activities affecting quality in accordance with instructions, procedures, or drawings. Specifically, the licensee failed to have adequate procedures to direct the completion of an SCE and prevent NS parts from being installed in SR applications; have torque specifications in the work instructions that installed the standoffs; and properly accomplish SCE Procedure MS-AA-SCE-301 when evaluating the standoffs. Because this violation was of very low safety significance and was entered into the licensee's CAP
, as CR 429386 and CR432053
, this violation is being treated as an NCV, consistent with Section 2.3.2 of the NRC Enforcement Policy (NCV 05000305/2011003
-03; Failed Standoffs Result in an Inoperable Train of Shield Building Ventilation).
- 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures, and Drawings," requires, in part, that activities affecting quality be prescribed by documented instructions, procedures, or drawings, of a type appropriate to the circumstances and be accomplished in accordance with these instructions, procedures, or drawings.
The licensee's initial short
-term CAs removed the installed standoffs from both trains. The licensee performed an exten t-of-condition looking at previously completed item equivalency evaluations (IEEs) to determine if an SCE was needed or missing for newly installed components. The licensee at the conclusion of the inspection period was re-performing the ACE.
- (2) Failure to Submit Licensee Event Report per 10 CFR 50.73 Introduction
- A Severity Level (SL) IV NCV of 10 CFR 50.73(a)(2)(i)(B) and 50.73(a)(2)(v)(C) was identified by the inspectors for the failure of the licensee to report an event or condition that was prohibited by TSs , and an event or condition that could have prevented the fulfillment of a safety function that is relied upon to control the 18 Enclosure release of radioactive material. Specifically, the licensee failed to report th at SBV train A was inoperable from Decembe r 3, 2010 , through January 26, 20 11. Technical Specification 3.6.c.1 allow s a single train outage time of seven days. Additionally, SBV train B was inoperable on multiple occasions during the same time period, requiring the licensee to also report an event or condition that could have prevented the fulfillment of a safety function, which is relied upon to control the release of radioactive material.
DescriptionAt the end of this inspection period, the licensee was re
-performing the ACE, after the inspectors indentified concerns with its conclusions. Additional details related to the failure of the standoffs are discussed in Section 1R15.2(1).
- As part of its review of SBV train A circuit card standoff issues discussed earlier, the licensee performed an ACE, which received its first management review on February 25, 2011, and concluded that the standoffs failed because the quality and design of the standoff material was insufficient, which resulted in improper adhesion between the metal stud and the neoprene. The ACE also discussed the possibility that excessive torque may have been applied to the standoffs during installation. During their review of this issue, the inspectors identified a concern that the licensee should have reviewed past operability and reported the extended inoperability of SBV train A to the NRC. The inspectors also identified that SBV train B was inoperable on multiple occasions during the same time period in which SBV train A was inoperable. The licensee reviewed the inspectors
' concerns and concluded that the failure of the SBV train A should have been reported, in accordance with 10 CFR 50.73(a)(2)(i)(B) and 50.73(a)(2)(v)(C).
Analysis:
The inspectors determined that the failure to report the condition in accordance with 10 CFR 50.73 was a performance deficiency. Because violations of 10 CFR 50.73 are considered to be violations that potentially impact the regulatory process, they are dispositioned using the traditional enforcement process instead of the Reactor Oversight Process (ROP) SDP.
A cross-cutting aspect was not assigned to this violation. Per the NRC Enforcement Policy, Section 6.0, "Violation Examples," a failure to submit a required licensee event report (LER) is categorized as a n SL IV violation.
Enforceme nt: Title 10 CFR 50.73(a)(2)(i)(B) requires, in part, that licensees report any event or condition that is prohibited by TSs. Title 10 CFR 50.73(a)(2)(v)(C) requires, in part, that licensees report any event or condition that could have prevented the fulfillment of the safety function of structures or systems that are needed to control the release of radioactive material
. Contrary to these requirements, on March 28, 2011, the licensee failed to report th at SBV train A was inoperable from December 3, 2010 , through January 26, 2011, a condition prohibited by TS 3.6.c.1, and failed to report the associated event or condition which could have prevented the fulfillment of a safety function that is relied upon to control the release of radioactive material.
Because this violation was not repetitive or willful, and was entered into the licensee's CAP
, as CR429469, this violation is being treated as an SL IV NCV, consistent with Section 2.3.2 of the NRC Enforcement Policy (NCV 05000305/2011003
-0 4; Failure to Submit LER per 10 CFR 50.73).
19 Enclosure
.3 a. Operability Evaluations
The inspectors reviewed the following issues:
Inspection Scope CR428470, runout on EDG B generator collector ring is out of tolerance; ODM000135, increased leakage into safety injection (SI) accumulator B; both residual heat removal (RHR) pit covers removed while critical
-7A controlling erratically.
The inspectors selected these potential operability issues based on the risk significance of the associated components and systems. The inspectors evaluated the technical adequacy of the evaluations to ensure that TS operability was properly justified and the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the TSs and USAR to the licensee's evaluations to determine whether the components or systems were operable. Where compensatory measures
were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. The inspectors determined, where appropriate, compliance with bounding limitations associated with the evaluations. Additionally, the inspectors reviewed a sampling of CA documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Documents reviewed are listed in the to this repo rt.
A licensee
-identified violation was identified by the inspectors during the review of CR416884 and is documented in Section
4OA7 of this report.
These operability inspections constituted five samples as defined in IP
71111.15 - 05.
b. No findings were identified.
Findings 1R18 Plant Modifications
.1
a. Plant Modifications The inspectors reviewed the following modification(s):
Inspection Scope DCR KW-10-01011, Replace Core Exit Thermocouple (CET) and Associated Connectors and Cables
. The inspectors reviewed the configuration changes and associated 10 CFR 50.59 safety evaluation screening s against the design basis, the USAR, and the TS s, as applicable, to verify that the modification s did not affect the operability or availability of the affecte d systems. The inspectors, as applicable, observed ongoing and completed work activities to ensure that the modifications were installed as directed and consistent with the design control documents; the modifications operated as expected; post
-modificatio n
20 Enclosure testing adequately demonstrated continued system operability, availability, and reliability; and that operation of the modifications did not impact the operability of any interfacing systems. As applicable, the inspectors verified that relevant procedure, design, and licensing documents were properly updated.
Documents reviewed are listed in the Attachment to this report.
This inspection constituted one permanent plant modification sample as defined in IP
71111.18 - 05.
b. No findings were identified.
Findings 1R19 Post-Maintenance Testing
.1
a. Post-Maintenance Testing
The inspectors reviewed the following post
-maintenance testing (PMT) activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:
Inspection Scope EDG A following 18
-month maintenance; replacement of auxiliary feedwater (AFW) pump A control switch; EDG B following 18
-month maintenance; and SW pump 1B1.
These activities were selected based upon the SSC s' ability to impact risk. The inspectors evaluated these activities for the following (as applicable):
the effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed; acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate; tests were performed as written in accordance with properly reviewed and approved procedures; equipment was returned to its operational status following testing (temporary modifications or jumpers required for test performance were properly removed after test completion);
and test documentation was properly evaluated. The inspectors evaluated the activities against TS s, the USAR , 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed CA documents associated with PMTs to determine whether the licensee was identifying problems and entering them in to the CAP , and that the problems were being corrected commensurate with their importance to safety. Documents reviewed are listed in the Attachment to this report
.
These inspection s constituted four post-maintenance testing sample s as defined in IP
71111.19 - 05.
b. No findings were identified.
Findings 21 Enclosure 1R22 Surveillance Testing
.1
a. Surveillance Testing The inspectors reviewed the test results for the following activities to determine whether risk-significant systems and equipment were capable of performing their intended safety function and to verify that testing was conducted in accordance with applicable procedural and TS requirements:
Inspection Scope OP-KW-NOP-SI-001: filling, pressurizing, and venting SI accumulator B (routine testing); spare battery charger (routine testing);
TDAFW pump quarterly test (inservice testing (IST)); and motor-driven AFW pump B quarterly test (IST).
The inspectors observed in-plant activities and reviewed procedures and associated records to determine the following:
did preconditioning occur
- were the effects of the testing adequately addressed by control room personnel or engineers prior to the commencement of the testing; were acceptance criteria clearly stated, demonstrated operational readiness, and consistent with the system design basis; plant equipment calibration was correct, accurate, and properly documented; as-left setpoints were within required ranges; and the calibration frequency was in accordance with TSs, the USAR, procedures, and applicable commitments; measuring and test equipment calibration was current; test equipment was used within the required range and accuracy; applicable prerequisites described in the test procedures were satisfied; test frequencies met TS requirements to demonstrate operability and reliability; tests were performed in accordance with the test procedures and other applicable procedures; jumpers and lifted leads were controlled and restored where used; test data and results were accurate, complete, within limits, and valid; test equipment was removed after testing; where applicable for IST activities, testing was performed in accordance with the applicable version of Section XI, ASME code, and reference values were consistent with the system design basis; where applicable, test results not meeting acceptance criteria were addressed with an adequate operability evaluation or the system or component was declared inoperable; where applicable for SR instrument control surveillance tests, reference setting data were accurately incorporated in the test procedure; where applicable, actual conditions encountering high resistance electrical contacts were such that the intended safety function could still be accomplished; prior procedure changes had not provided an opportunity to identify problems encountered during the performance of the surveillance or calibration test; equipment was returned to a position or status required to support the performance of its safety functions; and all problems identified during the testing were appropriately documented and dispositioned in the CAP.
Documents reviewed are listed in the Attachment to this report.
This inspection constituted two routine surveillance testing samples and two inservice testing samples as defined in IP 71111.22, Sections
-02 and -05.
b. No findings were identified.
Findings 1EP6 Drill Evaluation
.1
a. Emergency Preparedness Drill Observation The inspectors evaluated the conduct of a routine licensee emergency drill on May 10 to identify any weaknesses and deficiencies in classification, notification, and protective action recommendation development activities.
The inspectors observed emergency response operations in the Emergency Operations Facility to determine whether the event classification and notifications were performed in accordance with procedures.
The inspectors also attended the licensee drill critique to compare any inspector-observed weaknesses with those identified by the licensee to evaluate the critique and to verify whether the licensee staff properly identified weaknesses and entered them into the CAP.
Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one emergency preparedness drill sample as defined in IP
71114.06 - 05.
b. No findings were identified.
Findings
RADIATION SAFETY
Cornerstones: Occupational and Public Radiation Safety
2RS5 Radiation Monitoring InstrumentationThis inspection constituted one complete sample as defined in
IP 71124.0 5-0 5.
(71124.05)
.1 Inspection Planning
a. (02.01) The inspectors reviewed the plant USAR to identify radiation instruments associated with monitoring area radiological conditions including airborne radioactivity, process streams, Inspection Scope
23 Enclosure effluents, materials/articles, and workers. Additionally, the inspectors reviewed the instrumentation and the associated TS requirements for post
-accident monitoring instrumentation including instruments used for remote emergency assessment.
The inspectors reviewed a listing of in-service survey instrumentation including air samplers and small article monitors, along with instruments used to detect and analyze workers' external contamination. Additionally, the inspectors reviewed personnel contamination monitors and portal monitors including whole
-body counters to detect workers' internal contamination. The inspectors reviewed this list to assess whether an adequate number and type of instruments were available to support operations.
The inspectors reviewed licensee and thi rd-party evaluation reports of the radiation monitoring program since the last inspection. These reports were reviewed for insights into the licensee's program and to aid in selecting areas for review ("smart sampling").
The inspectors reviewed procedures that govern ed instrument source checks and calibrations, focusing on instruments used for monitoring transient high radiological conditions, including instruments used for underwater surveys. The inspectors reviewed the calibration and source check procedures for adequacy and as an aid to smart sampling.
The inspectors reviewed the area radiation monitor alarm setpoint values and setpoint bases as provided in the TSs and the USAR.
The inspectors reviewed effluent monitor alarm setpoint bases and the calculational methods provided in the Offsite Dose Calculation Manual (ODCM).
b. No findings were identified.
Findings
.2 Walkdowns and Observations
a. (02.02) The inspectors walked down effluent radiation monitoring systems, including at least one liquid and one airborne system. Focus was placed on flow measurement devices and all accessible point
-of-discharge liquid and gaseous effluent monitors of the selected systems. The inspectors assessed whether the effluent/process monitor configurations align ed with ODCM descriptions and observed monitors for degradation and out-of-service tags.
Inspection Scope The inspectors selected portable survey instruments in use or available for issuance and assessed calibration and source check stickers to ensure the instruments were in calibration, as well as instrument material condition and operability.
The inspectors observed licensee staff performance as the staff demonstrated source checks for various types of portable survey instruments. The inspectors assessed whether high
-range instruments were source checked on all appropriate scales.
The inspectors walked down area radiation monitors and continuous air monitors to determine whether the monitors were appropriately positioned relative to the radiation 24 Enclosure sources or areas they were intended to monitor. Selectively, the inspectors compared monitor response (via local or remote control room indications) with actual area conditions for consistency.
The inspectors selected personnel contamination monitors, portal monitors, and small article monitors and evaluated whether the periodic source checks were performed in accordance with the manufacturer's recommendations and licensee procedures.
b. No findings were identified.
Findings
.3 Calibration and Testing Program
(02.0 3) a. Process and Effluent Monitors The inspectors selected effluent monitor instruments (such as gaseous and liquid) and evaluated whether channel calibration and functional tests were performed consistent with radiological effluent TS/ODCM. The inspectors assessed whether
- the licensee calibrated its monitors with National Institute of Standards and Technology traceable sources; the primary calibrations adequately represented the plant nuclide mix; when secondary calibration sources were used, the sources were verified by the primary calibration; and the licensee's channel calibrations encompassed the instrument's alarm set-points.
Inspection Scope The inspectors assessed whether the effluent monitor alarm setpoints are established as provided in the ODCM and station procedures.
For changes to effluent monitor setpoints, the inspectors evaluated the basis for changes to ensure that an adequate justification exists.
b. No findings were identified.
Findings
.4 a. Laboratory Instrumentation The inspectors assessed laboratory analytical instruments used for radiological analyses to determine whether daily performance checks and calibration data indicate
d that the frequency of the calibrations was adequate and there were no indications of degraded instrument performance.
Inspection Scope The inspectors assessed whether appropriate CAs were implemented in response to indications of degraded instrument performance.
b. No findings were identified.
Findings 25 Enclosure
.5 a. Whole Body Counter
The inspectors reviewed the methods and sources used to perform whole body count functional checks before daily use of the instrument and assessed whether check sources were appropriate and aligned with the plant's isotopic mix.
Inspection Scope The inspectors reviewed whole body count calibration records since the last inspection and evaluated whether calibration sources were representative of the plant source term and that appropriate calibration phantoms were used. The inspectors looked for anomalous results or other indications of instrument performance problems.
b. No findings were identified.
Findings
.6 a. Post-Accident Monitoring Instrumentation
Inspectors selected containment high
-range monitors and reviewed the calibration documentation since the last inspection.
Inspection Scope The inspectors assessed whether an electronic calibration was completed for all range decades above 10 rem/hour and whether at least one decade at or below 10 rem/hour w as calibrated using an appropriate radiation source.
The inspectors assessed whether the calibration acceptance criteria was reasonable, accounting for the large measuring range and the intended purpose of the instruments.
The inspectors selected two effluent/process monitors that were relied on by the licensee in its emergency operating procedure s as a basis for triggering emergency action levels and subsequent emergency classifications, or to make protective action recommendations during an accident. The inspectors evaluated the calibration and availability of these instruments.
The inspectors reviewed the licensee's capability to collect high
-range, post
-accident iodine effluent samples.
As available, the inspectors observed electronic and radiation calibration of these instruments to verify conformity with the licensee's calibration and test protocols.
b. No findings were identified.
Findings 26 Enclosure
.7 a. Portal Monitors, Personnel Contamination Monitors , and Small Article Monitors
For each type of these instruments used on site, the inspectors assessed whether the alarm setpoint values were reasonable under the circumstances to ensure that licensed material was not released from the site.
Inspection Scope The inspectors reviewed the calibration documentation for each instrument selected and discussed the calibration methods with the licensee to determine consistency with the manufacturer's recommendations.
b. No findings were identified.
Findings
.8 a. Portable Survey Instruments, Area Radiation Monitors, Electronic Dosimetry, and Air Samplers/Continuous
Air Monitors The inspectors reviewed calibration documentation for at least one of each type of instrument. For portable survey instruments and area radiation monitors (ARM s), the inspectors reviewed detector measurement geometry and calibration methods and had the licensee demonstrate use of its instrument calibrator as applicable. The inspectors conducted comparison of instrument readings versus an NRC survey instrument if problems were suspected.
Inspection Scope As available, the inspectors selected portable survey instruments that did not meet acceptance criteria during calibration or source checks to assess whether the licensee had taken appropriate corrective action for instruments found significantly out of calibration (greater than 50 percent). The inspectors evaluated whether the licensee had evaluated the possible consequences of instrument use since the last successful calibration or source check.
b. No findings were identified.
Findings
.9 a. Instrument Calibrator
The inspectors reviewed the current output values for the licensee's portable survey and area radiation monitor instrument calibrator units. The inspectors assessed whether the licensee periodically measured calibrator output over the range of the instruments used through measurements by ion chamber/electrometer.
Inspection Scope The inspectors assessed whether the measuring devices were calibrated by a facility using National Institute of Standards and Technology traceable sources and whether corrective factors for these measuring devices were properly applied by the licensee in its output verification.
27 Enclosure b. No findings were identified.
Findings
.10 a. Calibration and Check Sources
The inspectors reviewed the licensee's 10 CFR Part 61, "Licensing Requirements for Land Disposal of Radioactive Waste,"
source term to assess whether calibration sources used were representative of the types and energies of radiation encountered in the plant.
Inspection Scope b. No findings were identified.
Findings
.11 Problem Identification and Resolution
a. (02.04) The inspectors evaluated whether problems associated with radiation monitoring instrumentation were identified by the licensee at an appropriate threshold and were properly addressed for resolution in the licensee corrective action program. The inspectors assessed the appropriateness of the CA s for a selected sample of problems documented by the licensee that involve d radiation monitoring instrumentation.
Inspection Scope b. No findings were identified.
Findings
2RS6 Radioactive Gaseous and Liquid Effluent TreatmentThis inspection constituted one complete sample as defined in
IP
71124.06 - 0 5.
(71124.06)
Inspection Planning
and Program Reviews (02.01) a. Event Report and Effluent Report Reviews The inspectors reviewed the radiological effluent release reports issued since the last inspection to determine if the reports were submitted as required by the ODCM/TS.
The inspectors reviewed anomalous results, unexpected trends, or abnormal releases identified by the licensee for further inspection to determine if they were evaluated, were entered into the CAP, and were adequately resolved.
Inspection Scope The inspectors identified radioactive effluent monitor operability issues reported by the licensee as provided in effluent release reports, to review these issues during the onsite inspection, as warranted, given their relative significance and determined whether the issues were entered into the CAP and adequately resolved.
28 Enclosure b. No findings were identified.
Findings a. Offsite Dose Calculation Manual and Updated Safety Analysis Report Review The inspectors reviewed USAR descriptions of the radioactive effluent monitoring systems, treatment systems, and effluent flow paths so they can be evaluated during inspection walkdowns.
Inspection Scope The inspectors reviewed changes to the ODCM made by the licensee since the last inspection against the guidance in NUREG
-1301, NUREG-0133, and Regulatory Guides 1.109, 1.21
, and 4.1. When differences were identified, the inspectors reviewed the technical bases or evaluations of the change during the onsite inspection to determine whether they were technically justified and maintained effluent releases as-low-as-is-reasonably
-achievable (ALARA).
The inspectors reviewed licensee documentation to determine if the licensee had identified any non
-radioactive systems that have become contaminated as disclosed either through an event report or the ODCM since the last inspection. This review provided an intelligent sample list for the onsite inspection of any 10 CFR 50.59 evaluations and allowed a determination if any newly contaminated systems had an unmonitored effluent discharge path to the environment
, whether any required ODCM revisions were made to incorporate these new pathways
, and whether the associated effluents were reported in accordance with Regulatory Guide 1.21.
b. No findings were identified.
Findings a. Groundwater Protection Initiative Program The inspectors reviewed reported groundwater monitoring results and changes to the licensee's written program for identifying and controlling contaminated spills/leaks to groundwater.
Inspection Scope b. No findings were identified.
Findings a. Procedures, Special Reports, and Other Documents The inspectors reviewed LERs, event reports and/or special reports related to the effluent program issued since the previous inspection to identify any additional focus areas for the inspection based on the scope/breadth of problems described in these reports.
Inspection Scope
29 Enclosure The inspectors reviewed effluent program implementing procedures, particularly those associated with effluent sampling, effluent monitor setpoint determinations, and dose calculations.
The inspectors reviewed copies of licensee and third party (independent) evaluation reports of the effluent monitoring program since the last inspection to gather insights into the licensee's program and aid in selecting areas for inspection review (smart sampling).
b. No findings were identified.
Findings Walkdowns and Observations a. (02.02) The inspectors walked down selected components of the gaseous and liquid discharge systems to assess whether the equipment configuration and flow paths align ed with the documents reviewed in 02.01 above and to assess equipment material condition. Special attention was made to identify potential unmonitored release points (such as temporary structures butted against turbine, auxiliary or containment buildings), building alterations which could impact airborne, or liquid, effluent controls, and ventilation system leakage that communicated directly with the environment.
Inspection Scope For equipment or areas associated with the systems selected for review that were not readily accessible due to radiological conditions, the inspectors reviewed the licensee's material condition surveillance records, as applicable.
The inspectors walked down filtered ventilation systems to evaluate conditions, such as degraded high-efficiency particulate air/charcoal banks, improper alignment, or system installation issues that would impact the performance, or the effluent monitoring capability, of the effluent system.
As available, the inspectors observed selected portions of the routine processing and discharge of radioactive gaseous effluent (including sample collection and analysis) to evaluate whether appropriate treatment equipment was used and the processing activities aligned with discharge permits.
The inspectors determined if the licensee had made significant changes to the effluent release points, e.g., changes subject to a 10 CFR 50.59 review or required NRC approval of alternate discharge points.
As available, the inspectors observed selected portions of the routine processing and discharge liquid waste (including sample collection and analysis) to assess whether appropriate effluent treatment equipment was being used and that radioactive liquid waste was processed and discharged in accordance with procedure requirements and aligned with discharge permits.
b. No findings were identified.
Findings 30 Enclosure Sampling and Analyses a. (02.03) The inspectors selected effluent sampling activities, consistent with smart sampling, and assessed whether adequate controls were implemented to ensure representative samples were obtained (e.g.
, provisions for sample line flushing, vessel recirculation, composite samplers, etc.).
Inspection Scope The inspectors selected effluent discharges made with inoperable (declared out-of-service) effluent radiation monitors to determine that controls were in place to ensure compensatory sampling was performed consistent with the radiological effluent TS/ODCM and that those controls were adequate to prevent the release of unmonitored liquid and gaseous effluents.
The inspectors assessed whether the facility routinely relied on the use of compensatory sampling in lieu of adequate system maintenance, based on the frequency of compensatory sampling since the last inspection.
The inspectors reviewed the results of the inter
-laboratory comparison program to evaluate the quality of the radioactive effluent sample analyses and assessed whether the inter-laboratory comparison program included difficult
-to-detect isotopes as appropriate.
b. No findings were identified.
Findings Instrumentation and Equipment (02.04) a. Effluent Flow Measuring Instruments The inspectors reviewed the methodology the licensee used to determine the effluent stack and vent flow rates to assess whether the flow rates were consistent with radiological effluent TS/ODCM or USAR values, and differences between assumed and actual stack and vent flow rates did not affect the results of the projected public doses.
Inspection Scope b. No findings were identified.
Findings a. Air Cleaning Systems The inspectors assessed whether surveillance test results since the previous inspection for TS required ventilation effluent discharge systems (high-efficiency particulate air and charcoal filtration), such as the Containment/Auxiliary Building Ventilation System, met TS acceptance criteria.
Inspection Scope
31 Enclosure b. No findings were identified.
Findings Dose Calculations a. (02.05) The inspectors reviewed all significant changes in reported dose values compared to the previous radiological effluent release report (e.g., a factor of 5, or increases that approached Appendix I criteria) to evaluate the factors which may have resulted in the change.
Inspection Scope The inspectors reviewed radioactive liquid and gaseous waste discharge permits to evaluate whether the projected doses to members of the public were accurate and based on representative samples of the discharge path.
The inspectors evaluated the methods used to determine the isotopes that are included in the source term to ensure all applicable radionuclides were included, within detectability standards. The review included the current Part 61 analyses to ensure difficult-to-detect radionuclides were included in the source term.
The inspectors reviewed changes in the licensee's offsite dose calculations since the last inspection to assess whether the changes were consistent with the ODCM and Regulatory Guide 1.109. The inspectors reviewed meteorological dispersion and deposition factors used in the ODCM and effluent dose calculations to ensure appropriate factors were used for public dose calculations.
The inspectors reviewed the latest Land Use Census to evaluate whether the changes (e.g., significant increases or decreases to population in the plant environs, changes in critical exposure pathways, the location of nearest member of the public, or critical receptor, etc.) were factored into the dose calculations.
For the releases reviewed above, the inspectors evaluated whether the calculated doses (monthly, quarterly, and annual dose) were within the 10 CFR Par t 50, Appendix I and TS dose criteria.
The inspectors reviewed, as available, records of any abnormal gaseous or liquid tank discharges (e.g., discharges resulting from misaligned valves, valve lea k-by, etc.) to ensure the abnormal discharge was monitored by the discharge point effluent monitor. Discharges made with inoperable effluent radiation monitors, or unmonitored leakages were reviewed to ensure that an evaluation was made of the discharge to satisfy 10 CFR 20.1501 , so as to account for the source term and projected doses to the public.
b. No findings were identified.
Findings 32 Enclosure Groundwater Protection Initiative Implementation a. (02.06) The inspectors reviewed monitoring results of the Groundwater Protection Initiative to assess whether the licensee implemented the program as intended, and to identify any anomalous results. For anomalous results or missed samples, the inspectors assessed whether the licensee identified and addressed deficiencies through its corrective action program.
Inspection Scope The inspectors reviewed identified leakage or spill events and entries made into 10 CFR 50.75(g) records. The inspectors reviewed evaluations of leaks or spills, and reviewed any remediation actions taken for effectiveness. The inspectors reviewed onsite contamination events involving groundwater and assessed whether the source of the leak or spill was identified and mitigated.
For unmonitored spills, leaks, or unexpected liquid or gaseous discharges, the inspectors assessed whether an evaluation was performed to determine the type and amount of radioactive material that was discharged by:
Assessing whether sufficient radiological surveys were performed to evaluate the extent of the contamination and the radiological source term and assessing whether a survey/evaluation was performed to include consideration of hard-to-detect radionuclides.
Determining whether the licensee completed offsite notifications, as provided in its Groundwater Protection Initiative implementing procedures.
The inspectors reviewed the evaluation of discharges from onsite surface water bodies that contained or potentially contained radioactivity, and the potential for gr oundwater leakage from these onsite surface water bodies. The inspectors assessed whether the licensee properly accounted for discharges from these surface water bodies as part of the effluent release reports.
The inspectors assessed whether onsite groundwater sample results and a description of any significant onsite leaks/spills into groundwater for each calendar year was documented in the Annual Radiological Environmental Operating Report for the radiological environmental monitoring program or the Annual Radiological Effluent Release Report for the radiological effluent TS.
For significant, new effluent discharge points (such as significant or continuing leakage to groundwater that continues to impact the environment if not remediated), the inspectors evaluated whether the ODCM was updated to include the new release point.
b. No findings were identified.
Findings 33 Enclosure Problem Identification and Resolution a. (02.07) The inspectors assessed whether problems associated with the effluent monitoring and control program were identified by the licensee at an appropriate threshold and were properly addressed for resolution in the licensee CAP. In addition, they evaluated the appropriateness of the CAs for a selected sample of problems documented by the licensee involving radiation monitoring and exposure controls.
Inspection Scope b. No findings were identified.
Findings
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, and Emergency Preparedness
4OA1 Performance Indicator Verification
.1
a. Mitigating Systems Performance Index (MSPI) - Emergency Alternating Current (AC) Power System s The inspectors sampled licensee submittals for the mitigating systems performance index (MSPI) - Emergency AC Power Systems performance indicator (PI) for the first quart er 2010 through the first quarter 201 1. To determine the accuracy of the PI data, definitions and guidance contained in the Nuclear Energy Institute (NEI) Document 99-02, "Regulatory Assessment Performance Indicator Guideline,"
Revision 6, were used. The inspectors reviewed the licensee's operator narrative logs, MSPI derivation reports, CRs, event reports, and NRC integrated inspection reports (IRs) to validate the accuracy of the submittals. The inspectors reviewed the MSPI component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's CR database to determine if any problems were identified with the PI data collected or transmitted for this indicator. Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one MSPI emergency AC power system s sample as defined in IP 7 1151-05.
b. No findings were identified.
Findings 34 Enclosure
.2 a. Mitigating Systems Performance Index
- High Pressure Injection Systems The inspectors sampled licensee submittals for the MSPI
- High Pressure Injection Systems PI for the first quarter 2010 through the first quarter 2011. To determine the accuracy of the PI data, definitions and guidance contained in the NEI Document 99-02, "Regulatory Assessment PI Guideline," Revision 6, were used. The inspectors reviewed the licensee's operator narrative logs, CRs, MSPI derivation reports, event reports, and NRC integrated IR s to validate the accuracy of the submittals. The inspectors reviewed the MSPI component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's CR database to determine if any problems were identified with the PI data collected or transmitted for this indicator. Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one MSPI high pressure injection system s sample as defined in IP 7 1151-05.
b. No findings were identified.
Findings
.3 a. Mitigating Systems Performance Index
- Heat Removal System s The inspectors sampled licensee submittals for the MSPI
- Heat Removal System s PI for the second quarter 2010 through the first quarter 2011. To determine the accuracy of the PI data reported, PI definitions and guidance contained in the NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, dated October 2009, were used. The inspectors reviewed the licensee's operator narrative logs, issue reports, event reports, MSPI derivation reports, and NRC inspection reports to validate the accuracy of the submittals. The inspectors reviewed the MSPI component risk coefficient to determine if it had changed by more than 25 percent since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's issue report database to determine if any problems were identified with the PI data collected or transmitted for this indicator and none were identified. Documents reviewed are listed in the to this report.
Inspection Scope This inspection constituted one MSPI heat removal system s sample as defined in IP 7 1151-05.
b. No findings were identified.
Findings 35 Enclosure
.4 a. Mitigating Systems Performance Index
- Residual Heat Removal System s The inspectors sampled licensee submittals for the MSPI
- Residual Heat Removal (RHR) System s PI for the first quarter 2010 through the first quarter 2011. To determine the accuracy of the PI data, definitions and guidance contained in the NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, were used. The inspectors reviewed the licensee's operator narrative logs, CRs, MSPI derivation reports, event reports
, and NRC integrated IRs to validate the accuracy of the submittals. The inspectors reviewed the MSPI component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's CR database to determine if any problems were identified with the PI data collected or transmitted for this indicator. Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one MSPI residual heat removal system s sample as defined in IP 7 1151-05.
b. No findings were identified.
Findings
.5 a. Mitigating Systems Performance Index
- Cooling Water Systems The inspectors sampled licensee submittals for the MSPI
- Cooling Water Systems PI for the second quarter 2010 through the first quarter 2011.
To determine the accuracy of the PI data, definitions and guidance contained in the NEI Document 99-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, were used. The inspectors reviewed the licensee's operator narrative logs, issue reports, MSPI derivation reports, event reports, and NRC IRs to validate the accuracy of the submittals. The inspectors reviewed the MSPI component risk coefficient to determine if it had changed by more than 25 percent since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensee's issue report database to determine if any problems were identified with the PI data collected or transmitted for this indicator and none were identified.
Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one MSPI cooling water system s sample as defined in IP 7 1151-05.
b. No findings were identified.
Findings 36 Enclosure
.6 a. Radiological Effluent Technical Specification/Offsite Dose Calculation Manual Radiological Effluent Occurrences
The inspectors sampled licensee submittals for the radiological effluent TS/ODCM radiological effluent occurrences PI for the fourth quarter 2010 through the second quarter 2011. The inspectors used PI definitions and guidance contained in the NEI Document 99
-02, "Regulatory Assessment Performance Indicator Guideline," Revision 6, dated October 2009, to determine the accuracy of the PI data reported. The inspectors reviewed the licensee's issue report database and selected individual reports generated since this indicator was last reviewed to identify any potential occurrences such as unmonitored, uncontrolled, or improperly calculated effluent releases that may have impacted offsite dose. The inspectors reviewed gaseous effluent summary data and the results of associated offsite dose calculations for selected dates between the fourth quarter 2010 through the second quarter 201 1 to determine if indicator results were accurately reported. The inspectors also reviewed the licensee's methods for quantifying gaseous and liquid effluents and determining effluent dose. Documents reviewed are listed in the Attachment to this report.
Inspection Scope This inspection constituted one Radiological Effluent Technical Specification/Offsite Dose Calculation Manual radiological effluent occurrences sample as defined in IP 71151 05.
b. No findings were identified.
Findings
4OA2 Identification and Resolution of ProblemsCornerstones:
Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical Protection (71152)
.1 a. Routine Review of Items Entered into the Corrective Action Program
As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensee's CAP at an appropriate threshold, that adequate attention was being given to timely CAs, and that adverse trends were identified and addressed. Attributes reviewed included: the complete and accurate identification of the problem; that timeliness was commensurate with the safety significance; that evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent
-of-condition reviews, and previous oc currences reviews were proper and adequate; and that the classification, prioritization, focus, and timeliness of CA s were commensurate with safety and sufficient to prevent recurrence of the issue. Minor issues entered into the licensee's CAP as a result of the inspectors' observations are listed in the Attachment to this report.
Inspection Scope 37 Enclosure These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure
, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.
b. No findings were identified.
Findings
.2 a. Daily Corrective Action Program Reviews
To assist with the identification of repetitive equipment failures and specific human performance issues for follow
-up, the inspectors performed a daily screening of items entered into the licensee's CAP. This review was accomplished through inspection of the station's daily CR packages.
Inspection Scope These daily reviews were performed by procedure as part of the inspectors' daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.
b. No findings were identified.
Findings
.3 a. Selected Issue Follow
-Up Inspection:
Apparent Cause Evaluation (ACE) 018119, Revision And Review Process for Emergency Plan Implementing Procedures (EPIPs) Has Not Been Effective The inspectors reviewed the CAs from ACE018119, "Revision And Review Process for Emergency Plan Implementing Procedures (EPIPs) Has Not Been Effective." Specifically, the inspectors reviewed the CAs for the apparent cause and the extent-o f-condition associated with the issues identified in the condition report.
Inspection Scope This review constituted one in-depth problem identification and resolution sample as defined in IP 7 1152-05.
b. Findings
Failure to Review and Update Severe Accident Management Guidelines in Accordance with an Established Program
Introduction:
A finding of very low safety significance was identified by the inspectors for the licensee's failure to review and update the Severe Accident Management Guidelines (SAMGs) in accordance with the licensee's nuclear administrative directives (NAD s). Specifically, Procedure NAD-14.06 required that the engineering group review industry correspondence related to SAMGs and implement changes, and that the emergency preparedness group conduct biennial reviews of the SAMGs. The inspectors identified 38 Enclosure that neither group performed the respective reviews, and as a result
, the SAMGs were not adequately updated.
DescriptionThe inspectors determined through interviews with emergency preparedness and engineering personnel that neither section 5.1 nor 5.2 of NAD
-14.06 were currently implemented by site personnel. In addition, the inspectors determined that the last partial biennial review of the SAMGs occurred in 2005. The inspectors subsequently performed a review of the SAMGs and identified the following additional issues:
- In correspondence to the NRC, dated January 30, 1995, the licensee committed to implement the formal industry position on SAMGs in Section 5 of NEI document 91-04, "Severe Accident Issue Closure Guidelines," Revision 1. Procedure NAD-14.06, "Severe Accident Management Program Maintenance and Control," translated the licensee's commitments into a procedure for implementation by engineering and emergency preparedness personnel. Section 5.1 of the procedure required, in part, that the engineering group perform the following: review new correspondence from industry and regulatory agencies to determine the potential impact on SAMGs and basis documents; facilitate and conduct engineering analyses to identify changes to the SAMGs and bas es documents that were appropriate for implementation at KPS; forward the results to the emergency preparedness organization; and implement revisions to the SAMGs based on the analyses performed. Section 5.2 required, in part, that the emergency preparedness group perform the following: initiate changes to the emergency plan and procedures to implement the SAMG program; and conduct biennial reviews of the SAMGs and computational aids in support of the emergency plan.
60 percent of the SAMGs were last revised in October 2000; SAG-3, "Inject Into The RCS," Revision C, October 3, 2000, Attachment A
, did not include guidelines for the long
-term concerns of inadequate injection flow and conservation of refueling water storage tank water inventory as outlined in Revision 0 of the Westinghouse Owners Group (WOG) SAMGs; SAG-6, "Contro l Containment Conditions," Revision C, October 3, 2000, Attachment A , did not include guidelines for the long
-term concern of iodine retention and stress corrosion cracking of stainless steel piping as outlined in Revision 0 of the WOG SAMGs; the SAMGs prescribed the use of hydrogen recombiners no longer maintained onsite by the licensee; however, the SAMGs did not prescribe actions to ensure the offsite hydrogen recombiners were ordered to ensure timely onsite arrival when needed; the licensee did not currently implement background documents for all the SAMGs in the procedures program; the licensee's SAMG s lacked details on component descriptions and did not identify equipment locations for ease of implementation
- the licensee ha d not evaluated or incorporated Revision 1 to the WOG SAMGs dated October 2001 into the KPS SAMGs. The inspectors determined the changes were appropriate for implementation at KPS (Revision 1 affected 17 of the 25 guidelines); and the licensee had not incorporated applicable 10 CFR 50.54(hh) strategies into the SAMG procedures in accordance with a different licensee commitment. T he inspectors identified that both CR038990 and CR039498
, written in November 2006 , had CAs to integrate the applicable 10 CFR 50.54(hh)39 Enclosure strategies into the SAMG procedures; yet those CAs were closed without completion of these action s.
Therefore, based on these issues, the inspectors concluded that the licensee was not implementing Procedure NAD-14.06 to ensure that the original NRC commitments were met. The inspectors also reviewed ACE018119, "Revision And Review Process For EPIPs Has Not Been Effective," which was initiated in April 2010
, to evaluate why the emergency preparedness group procedure reviews were not effective. The inspectors noted that the extent of cause evaluation identified that the vulnerability for ineffective reviews also existed in the SAMGs. However, the CA created to correct the SAMGs, CA168865, only incorporated the EPIPs and inadvertently excluded the SAMGs. Therefore, no CA s were taken for the SAMGs as a result of the ACE extent-of-condition. AnalysisThe finding was determined to be more than minor in accordance with IMC 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," dated December 24, 2009, because , if left uncorrected
, the finding had the potential to lead to a more significant safety concern. Specifically, the failure to update and review the SAMGs would have hampered the licensee's response in the unlikely event of a severe accident, because the SAMGs were not current and up
-to-date. The inspectors, in consultation with the Region III senior reactor analyst, determined that the finding could be evaluated using the SDP in accordance with IMC 0609, "Significance Determination Process," Attachment 0609.04, "Phase 1
- Initial Screening and Characterization of Findings," Table 4a , for the Mitigating Systems Cornerstone, dated January 10, 2008.
The inspectors answered " No" to the Mitigating Systems questions and screened the finding as having very low safety significance (Green).
- The inspectors determined that the licensee's failure to review and update the SAMGs and background documents was contrary to the licensee's Procedure NAD-14.06 requirements and commitments made to the NRC; therefore, this was a performance deficiency warranting a significance evaluation.
The finding has a cross
-cutting aspect in the area of problem identification and resolution, corrective action program, because the licensee failed to take appropriate CAs to address safety issues and adverse trends in a timely manner, commensurate with their safety significance and complexity (P.1(d)). Specifically, the licensee identified in an ACE initiated in April 2010 that the emergency preparedness organization had not performed the required reviews and updates of emergency preparedness procedures, and the SAMGs were identified in the licensee's extent-of-condition. However, the inspectors identified that the CA s issued for th is extent-of-condition did not address the SAMGs and , therefore , no CAs were taken.
EnforcementThe licensee entered this issue into its CAP as CR s 424681, 424855, 424865, 424866, 425092, 426999, and 427092, and was still evaluating the cause for this condition at the end of th is inspection period. The licensee has planned CAs to remediate the issues identified by the inspectors to correct the SAMGs. At the end of th is inspection period
, the licensee scheduled revision of the SAMGs for completion by December 2011.
- No violation of regulatory requirements occurred but the inspectors did identify a finding (FIN 05000305/2011003
-05, Failure to Review and Update Severe Accident Management Guidelines in Accordance with an Established Program).
40 Enclosure
.4 a. Semi-Annual Trend Review
The inspectors performed a review of the licensee's CAP and associated documents to identify trends that could indicate the existence of a more significant safety issue. The inspectors' review was focused on repetitive equipment issues, but also considered the results of daily inspector CAP item screening discussed in Section 4OA2.2 above, licensee trending efforts, and licensee human performance results. The inspectors' review nominally considered the period of December 2010 through May 2011, although some examples expanded beyond those dates where the scope of the trend warranted.
Inspection Scope The review also included issues documented outside the normal CAP in major equipment problem lists, repetitive and/or rework maintenance lists, system health reports, quality assurance audit/surveillance reports, and self
-assessment reports. The inspectors compared their results with the results contained in the licensee's CAP trending reports. CAs associated with a sample of the issues identified in the licensee's trending reports were reviewed for adequacy. Documents reviewed are listed in the Attachment to this report.
This review constituted one semi-annual trend inspection sample as defined in IP 7 1152-05.
b. No findings were identified.
Findings
4OA3 Follow-Up of Events and Notices of Enforcement Discretion
.1
On January 21, 2011, during normal plant walkdowns, the inspectors identified that the lower cane bolt for door 3, a steam exclusion door, was not engaged. With the can e bolt not engaged, door 3 was non
-functional
. In accordance with Technical Requirement s Manual (TRM) 3.0.9 , all equipment supported by the steam exclusion barrier was declared inoperable. The door was properly secured within 6 minutes and the licensee initiated a n ACE to determine the cause.
The licensee's investigation determined that the most likely cause was an inadvertent disengagement by a licensee employee or contractor traversing through door 3. A subsequent engineering evaluation by the licensee determined that the lower cane bolt was not required for door 3 to fulfill its function as a steam exclusion barrier; therefore, the door remained functional. The licensee subsequently retracted Event Notification (EN) EN46562 on March 22, 2011. Retraction of Event Notification EN46562, "Non
-Functional Steam Exclusion Door" The inspectors reviewed the licensee's evaluation and concurred with the license e's technical justification and event retraction. The inspectors determined that the performance deficiency was minor and no findings were identified.
Therefore, this EN is closed. This event follow
-up review constituted one sample as defined in IP 7 1153-05.
41 Enclosure
.2 On December 13, 2010, with the plant at 100 percent power, charcoal laboratory radioiodine test results were found to be below the acceptance criteria of 97.5 percent for auxiliary building special ventilation (ABSV) train A charcoal adsorber efficiency.
This caused train A to be inoperable in excess of the TS 3.6, "Containment System Integrity," allowed outage time of 7 days.
(Closed) LER 5000305/20 11-001-00: Auxiliary Building Special Ventilation Inoperability Results in Prohibited Technical Specification Condition Specifically, at the time filter bank A was removed for analysis on December 1, 2010, there was no indication that the ABSV train A was inoperable. The sample analysis failure identified on December 13, 2010, constituted discovery that the ABSV train A exceeded the TS surveillance requirement for a charcoal adsorber efficiency of greater than 97.5 percent. With the charcoal adsorber filter replacement completed on December 16, 2010, there was a 15
-day period where the ABSV train A did not satisfy the surveillance requirement, even though the filters were replaced within the time allowed by TS s (from the time of discovery). Consequently, the allowed outage was exceeded because the elapsed time, from removal of the sample to the time the vendor analysis was obtained, plus the time required for corrective actions to be completed to address the condition, exceeded the 7-day TS allowance for one train being inoperable by 8 days. The event was reported in accordance with 10 CFR 50.73(a)(2)(i)(B) for any operation or condition which was prohibited by TS s. The accident analysis for KPS assumes a charcoal adsorber efficiency of 95 percent; however, the acceptance criteria of 97.5 percent is used to ensure a safety factor of two is utilized. The actual charcoal adsorber test results for ABSV train A were at a 96.59 percent efficiency, therefore train A still maintained its safety function since the measured value for efficiency was greater than the accident analysis assumption of 95 percent efficiency. The inspectors reviewed the licensee's evaluation of the TS violation and subsequent actions taken. The inspectors concluded the licensee's resolution of this issue was adequate and that the performance deficiency was not greater than minor. Documents reviewed are listed in the Attachment to this report.
Therefore, this LER is closed. This event follow
-up review constituted one sample as defined in IP 7 1153-05.
.3 On March 11, 2011, with the plant shut
down and the reactor defueled, power was lost to safeguards 4160
-Volt bus 6. EDG B started and re
-energized bus 6. At the time of the event, bus 6 was energized from the main auxiliary transformer on backfeed. The event was caused by the opening of an incorrect breaker by technicians working in a substation (switchyard) relay building
. (Closed) LER 5000305/20 11-002-00: Loss of Station Backfeed Results in Loss of One Train of Offsite Power During Refueling Outage All equipment operated as expected for the voltage restoration to bus 6 via EDG B. Safeguards bus 5 remained energized from offsite power during the event. SFP cooling train A remained in operation during the event and train B was restarted following restoration of power to bus 6. The event also caused a loss of non
-safeguards 4160-Volt bus 4. In response to the loss of power to bus 4, the TSC/SBO DG started but failed to load on 480
-Volt bus 1-46 , resulting in continued loss of power to t he TSC.
42 Enclosure T he licensee reported the event in accordance with 10 CFR 50.73(a)(2)(iv)(A) for any event or condition that resulted in the automatic actuation of emergency electrical power systems (EDG B).
The performance deficiency associated with the initiating error by the substation technicians was previously documented in NRC IR 05000305/2011002, Section 4OA3.1. The performance deficiency associated with the failure of the TSC/SBO DG failure to automatically load on bus 1-46 is documented in Section
1R12 .1.
The inspectors reviewed the licensee's evaluation of the event and subsequent actions taken, and concluded no additional performance deficiencies existed. Documents reviewed are listed in the Attachment to this report.
Therefore, this LER is closed. This event follow
-up review constituted one sample as defined in IP 7 1153-05.
.4 On March 24, 2011, with the plant shut
down and in Mode 3, a shift technical advisor performed a protected equipment walkdown and identified that the electrical breaker for motor operated valve SI
-11A, safety injection to loop A cold leg, was in the "O n" position with the valve open. The required breaker position for Mode 3 was "O ff" and locked, as required by TS Surveillance Requirement 3.5.2.1. The valve was in the required open position and was thereby providing the required SI flow path; however, the breaker was not off and locked.
(Closed) LER 5000305/20 11-003-00: Valve SI
-11A, Safety Injection to Loop A Cold Leg, Breaker Found On with Plant in Mode 3 The licensee identified that the requirements of TS Limiting Condition of Operation (LCO) 3.0.4, for entering a mode of applicability when an LCO is not met, were not completed prior to entering Mode 3. The licensee determined that the breaker was in the incorrect position from 2:58 a.m. to 11:30 a.m. on March 24, 2011, for a total of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and 32 minutes.
The licensee reported the event in accordance with 10 CFR 50.73(a)(2)(i)(B) for any operation or condition which was prohibited by TS s.
The licensee's causal evaluation determined the event was caused by inadequate guidance in the procedure associated with safety injection to loop A cold leg check valve leakage measurement, which was performed just prior to the transition from Mode 4 to Mode 3. This licensee
-identified performance deficiency is discussed in Section 4OA7.1 of this report.
Therefore, this LER is closed. This event follow
-up review constituted one sample as defined in IP 7 1153-05.
4OA5
.1 Other Activities
The inspectors assessed the activities and actions taken by the licensee to assess its readiness to respond to an event similar to the Fukushima Daiichi nuclear plant fuel damage event.
This included the following:
- (1) an assessment of the licensee's capability to mitigate conditions that may result from beyond design basis events, with a particular emphasis on strategies related to the SFP, as required by NRC Security Order (Closed) NRC Temporary Instruction 2515/183: "Follow-Up to the Fukushima Daiichi Nuclear Station Fuel Damage Event"
43 Enclosure Section B.5.b, issued February 25, 2002, as committed to in SAMGs, and as required by 10 CFR 50.54(hh);
- (2) an assessment of the licensee's capability to mitigate SBO conditions, as required by 10 CFR 50.63 and station design bases;
- (3) an assessment of the licensee's capability to mitigate internal and external flooding events, as required by station design bases; and
- (4) an assessment of the thoroughness of the walkdowns and inspections of important equipment needed to mitigate fire and flood events, which were performed by the licensee to identify any potential loss of function of this equipment during seismic events possible for the site.
IR 05000305/2011009 (ML111320380) documented detailed results of this inspection activity.
Following issuance of the report, the inspectors conducted detailed follow
-up on selected issues.
The observations documented in IR 05000305/2011009 that were determined to be performance deficiencies were assessed as being minor by the inspectors, unless otherwise documented in Sections 4OA2.3, 4OA5.3 , or 4OA5.4 of this report.
.2 On May 27, 2011, the inspectors completed a review of the licensee's SAMGs, implemented as a voluntary industry initiative in the 1990's, to determine:
- (1) whether the SAMGs were available and updated
- (2) whether the licensee had procedures and processes in place to control and update its SAMGs
- (3) the nature and extent of the licensee's training of personnel on the use of SAMGs
- and
- (4) licensee personnel's familiarity with SAMG implementation.
(Closed) NRC Temporary Instruction 2515/184: "Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)"
The results of this review were provided to the NRC task force chartered by the Executive Director for Operations to conduct a near
-term evaluation of the need for agency actions following the Fukushima Daiichi fuel damage event in Japan.
Plant-specific results for the KPS were provided as an Enclosure to a Memorandum to the Chief, Reactor Inspection Branch, Division of Inspection a nd Regional Support, dated June 1, 2011 , (ML111520396).
Following issuance of the memorandum, the inspectors conducted detailed follow
-up on selected issues.
The observations documented in the enclosure for KPS that were determined to be performance deficiencies were assessed as being minor by the inspectors, unless otherwise documented in Section 4OA2.3 of this report.
.3 Improved TS Surveillance Requirement
3.7.6.1, requires, in part, that the usable volume in the condensate storage tank s (CSTs) is greater than or equal to 41,500 gallons. The inspectors reviewed calculation CN-SEE-02-47, "Kewaunee Condensate Storage Tank Minimum Volume Analysis for 7.4 Percent Power Uprate Program," Revision 0, dated October 9, 2002, and determined that the calculation established a minimum CST volume based on restoring and maintaining no
-load level in the steam generators, which equated to the steam generator narrow range level of 0 percent. The inspectors noted that Procedure ECA 0.0, "Loss Of All AC Power," implemented by plant operators during an SBO, required operators to feed the steam generators at greater than 210 gallons per minute , and to maintain a minimum steam generator level of 5 percent narrow range (Open) URI 05000305/2011003
-06: "Kewaunee Condensate Storage Tank Minimum Volume Analysis
"
44 Enclosure level. Therefore, the inspectors questioned why the operating procedures for an SBO, which established maintenance of a minimum 5 percent steam generator narrow range level, did not comport with the calculation, which was based on maintaining a no
-load level in the steam generators of 0 percent, a smaller volume level. In addition, the inspectors noted that the 41,500
-gallon minimum volume also did not consider the following additional items: CST volumes wasted to the condenser during the first 10 minutes of a SBO; and CST volumes wasted to a drain trench from the TDAFW pump lube oil cooler. The licensee initiated CR425837 to capture the inspectors' observations.
The inspectors are opening this URI since more information is required to determine if there is a performance deficiency.
.4 During independent walkdowns, the inspectors identified that the basement of the TSC was connected to the basement of the auxiliary building through two air lock doors.
The inspectors identified that no credited flooding barriers existed to preclude flood waters from a ruptured fire protection system in the TSC from entering the auxiliary building. The licensee determined that both doors were special ventilation doors, and one door had seals that would limit leakage into the auxiliary building because it was also a steam exclusion boundary. The doors also closed into their frames during a TSC flooding event and were not expected to fail. The licensee initiated CR424708 to further evaluate this observation.
(Open) URI 05000305/2011003
-07: "Potential Internal Flood Scenario Due to Postulated Loss of the Technical Support Center
" The inspectors are opening this URI since more information is required to determine if there is a performance deficiency.
.5 The inspectors confirmed that the licensee has reported the initial inventories of sealed sources pursuant to
10 CFR 20.2207 and verified that the National Source Tracking System database correctly reflects the Categories 1 and 2 sealed sources in custody of the licensee. Inspectors interviewed personnel and performed the following:
(Closed) Temporary Instruction 2515/179, "Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in the National Source Tracking System Pursuant to Title 10, Code of Federal Regulations, Part 20.2207 (10 CFR 20.2207)" reviewed the licensee's source inventory; verified the presence of any Categories 1 or 2 sources; reviewed procedures for and evaluated the effectiveness of storage and handling of sources; reviewed documents involving transactions of sources; and reviewed adequacy of licensee maintenance, posting, and labeling of nationally tracked sources.
No findings were identified.
.6 On March 10, 2011, the licensee inadvertently opened a switchyard breaker that was
providing power to various non
-safeguards busses, as well as bus 6, a 4160-Volt (Closed) URI 05000 30 5/2011002-05: "Technical Support Center Diesel Fails To Load
"
45 Enclosure safeguards bus. The TSC DG automatically started as expected. However, the output breaker failed to close and power bus 1-46, as designed. The self
-revealed performance deficiency associated with this URI is documented in Section
1R12
.1 of this report. Therefore, this URI is considered closed.
.7 The inspectors identified that the licensee entered TS action requirement 3.0.c, standard shutdown sequence, for a leak inside containment on a containment fan cooler unit SW
line on September 13, 2009. The inspectors reviewed a similar leak that occurred on August 15, 2008, and found that the licensee did not enter the same TS action requirement for that leak. The inspectors reviewed the licensee
's final analysis and evaluation of the two events provided in June 201 1 , and determined that no performance deficiency existed; therefore , this URI is considered closed.
(Closed) URI 05000 30 5/2009004-01: "Technical Specification Action Requirements During a Leak in a Containment Fan Coil Unit Service Water Line
"
4OA6
.1 Management Meetings
On June 30 , 2 011 , the inspector s presented the inspection results to Mr. S. Scace and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.
Exit Meeting Summary
.2 Interim exits were conducted for:
Interim Exit Meetings the results of the radiation monitoring instrumentation and Temporary Instruction 2515/179 inspection with the Safety and Assessment Director, Mr. M. Wilson, on April 15, 2011; and the results of the radioactive gaseous and liquid effluent treatment and verification of the public radiation safety PI with the Site Vice-President , Mr. S. Scace, on June 10, 2011
.
The inspectors confirmed that none of the potential report input discussed was considered proprietary.
Proprietary material received during the inspection was returned to the licensee.
4OA7 The following violations of very low significance (Green) or
SL IV were identified by the licensee and are violations of NRC requirements which meet the criteria of the NRC Enforcement Policy for being dispositioned as a n NCV.
Licensee-Identified Violations
.1 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures
, and Drawings," states, in part, that activities affecting quality shall be prescribed and accomplished by documented instructions or procedures of a type appropriate to the circumstances.
Inadequate Procedure Instructions Led to Incorrect Breaker Position for Valve SI
-11A 46 Enclosure Contrary to this, on March 24, 2011, licensee personnel performed Procedure SP-33-297A, "Safety Injection To Loop A Cold Leg Check Valve Leakage," which left the breaker for valve SI
-11A, SI valve to loop A cold leg, in the incorrect position. The valve was required by TS Surveillance Requirement 3.5.2.1 to be open with the breaker in the off position and locked. Procedure SP 297A correctly established an open position for the valve, thereby providing the required SI system flow path, but failed to place the breaker in the off and locked position.
The Shift Technical Advisor identified the incorrect breaker position during protected equipment rounds in the plant and also identified that the requirements of TS LCO 3.0.4, for entering a mode of applicability when an LCO is not met were not completed prior to entering Mode 3. The licensee later determined the breaker was in the incorrect position from 2:58 a.m. to 11:30 a.m. on March 24, 2011, for a total of 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> and 32 minutes, which was also reported to the NRC in accordance with 10 CFR 50.73(a)(2)(i)(B) for any operation or condition which was prohibited by TS s (Section 4OA3.
4 of this report).
The inspectors answered "
No" to the Mitigating Systems Cornerstone questions and screened the finding as having very low safety significance (Green) in accordance with IMC 0609, "Significance Determination Process," Attachm ent 0609.04, "Phase 1
- Initial Screening and Characterization of Findings," Table 4a, dated January 10, 2008.
The licensee documented this violation in CR 419235. The licensee performed a n ACE which determined Procedure SP-33-297A did not provide direction on the required breaker manipulations and implemented CA s that included revision of the procedure, and an extent-of-condition evaluation to correct other deficient procedures
.
.2 10 CFR Part 50, Appendix B, Criterion V, "Instructions, Procedures
, and Drawings," states, in part, that activities affecting quality shall be prescribed and accomplished by documented instructions or procedures of a type appropriate to the circumstances.
Incorrect Diesel Generator A Governor Setting Contrary to this, in 1990, the licensee replaced the governor on the EDG A without any specific setting in the WOs or Procedure CMP 05, Revision A , for the compensation needle valve in the governor
. On March 9, 2011, during the first hot fast start test performed on EDG A since the 1990 governor replacement, the governor began hunting and caused perturbations in the EDG speed, frequency
, and voltage. Operators immediately shut down the EDG and commenced troubleshooting with a vendor representative that identified the compensation needle valve in the governor was not set. Bench testing accurately reproduced oscillation of a magnitude and frequency similar to those observed during the test. The hot fast start testing was previously not required by KPS TS s and the test was being performed for the first time since implementation of improved TSs. All the acceptance criteria for the speed of response and stability of EDG A were met under the required conditions.
The inspectors answered "
No" to the Mitigating Systems Cornerstone questions and screened the finding as having very low safety significance (Green) in accordance with IMC 0609, "Significance Determination Process," Attachm ent 0609.04, "Phase 1
- Initial Screening and Characterization of Findings," Table 4a, dated January 10, 2008.
The licensee documented this violation in CR416884. The licensee performed a n ACE which determined Procedure CMP-10-05, Revision A , did not provide direction on the 47 Enclosure required compensation needle valve on the governor and implemented CA s that included revision of the current maintenance procedure, and an extent
- of condition evaluation for EDG B
. EDG B was determined to not have been subject to the inadequate guidance in Procedure CMP-10-05 and also met the acceptance criteria of the first hot fast start test performed in March 2011
, and did not exhibit the same governor hunting as was experienced on EDG A. ATTACHMENT:
SUPPLEMENTAL INFORMATION
==KEY POINTS OF
CONTACT==
- S. Scace, Site Vice
-President Licensee
- M. Wilson, Director, Safety and Licensing
- R. Simmons, Plant Manager
- S. Yuen, Director, Engineering
- D. Asbel, Engineering Programs Manager
- D. Lawrence, Operations Manager
- J. Gadzala, Licensing Engineer
- M. Aulik, Engineering Design Manager
- T. Breene, Licensing Manager
- J. Hale, Radiation Protection and Chemistry Manager
- M. Hovis, Radiation Protection Supervisor
- A. Maly, Health Physicist
- M. Kunowski, Chief, Division of Reactor Projects, Branch 5
Nuclear Regulatory Commission
- D. Passehl, Senior Reactor Analyst
- N. Valos, Senior Reactor Analyst
LIST OF ITEMS
OPENED, CLOSED AND DISCUSS
ED 05000 305/201 1 00 3-0 1 Opened FIN Technical Support Center Diesel Generator Output Breaker Fails to Close
(Section 1R12.1)
05000 305/20 1 1 00 3-0 2 FIN Inadequate
Operability Determination of a Heat Exchanger Leak on Emergency Diesel Generator
A (Section 1R15.1)
05000 305/201 1 00 3-0 3 NCV Failed Standoffs Result in an Inoperable Train of Shield Building Ventilation (Section 1R15.2(1)) 05000 30 5/201 1 00 3-0 4 NCV Failure to Submit LER per
CFR 50.73 (Section 1R15.2(2)) 05000 305/201 1 00 3-0 5 FIN Failure to Review and Update Severe Accident Management Guidelines in Accordance with
an Established Program
(Section 4OA2.3)
05000 305/201 1 00 3-0 6 URI Kewaunee Condensate Storage Tank Minimum Volume Analysis (Section 4OA5.3)
05000 305/201 1 00 3-0 7 URI Potential Internal Flood Scenario Due to Postulated Loss of the Technical Support Center (Section 4OA5.4)
05000 305/201 1 00 3-0 1 Closed FIN Technical Support Center Diesel Generator
Output Breaker Fails to Close
(Section 1R12.1)
05000 30 5/2011003-02 FIN Inadequate
Operability Determination of a Heat Exchanger Leak on Emergency Diesel Generator
A (Section 1R15.1)
Attachment
05000 30 5/2011003-03 NCV Failed Standoffs Result in an Inoperable Train of Shield Building Ventilation (Section 1R15.2(1))) 05000 30 5/2011003-04 NCV Failure to Submit LER per
CFR 50.73 (Section 1R15.2(2)) 05000 305/201 1 00 3-0 5 FIN Failure to Review and Update Severe Accident Management
Guidelines in Accordance with
an Established Program
(Section 4OA2.3)
5000305/20
11-001-00 LER Auxiliary Building Special Ventilation Inoperability Results in Prohibited Technical Specification Condition (Section 4OA3.2) 5000305/20
11-002-00 LER Loss of Station Backfeed Results in Loss of One Train of Offsite Power During Refueling Outage (Section 4OA3.3)
5000305/20
11-003-00 LER Valve SI-11A, Safety Injection to Loop A Cold Leg, Breaker Found On with Plant in Mode 3 (Section 4OA3.4)
Follow-up to the Fukushima Daiichi Nuclear Station Fuel Damage Event
(Section 4OA5.1)
Availability and Readiness Inspection of Severe Accident Management Guidelines (SAMGs)
(Section 4OA5.2)
Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in the National Source Tracking System Pursuant to Title 10, Code of Federal Regulations, Part 20.2207 (10 CFR 20.2207) (Section 4OA5.5) 05000 30 5/2011002-05 URI Technical Support Center Diesel Fails To Load (Section 4OA5.6)
-01 URI Technical Specification Action Requirements During a Leak in a Containment Fan Coil Unit Service Water Line
(Section 4OA5.7)
Discussed
None
Attachment
LIST OF DOCUMENTS REVIEWED
The following is a partial list of documents reviewed during the inspection.
- Inclusion on this list does not imply that the NRC inspector reviewed the documents in their entirety, but rather that selected sections or portions of the documents were evaluated as part of the overall inspection effort.
- Inclusion of a document on this list does not imply NRC acceptance of the document or any part of it, unless this is stated in the body of the inspection report.
-
- CR027067; Minor Oil Leak At EDG Oil Cooler Connection
- 1R0 1 Adverse Weather Protection
-
- CR113742; Temperature Indicator 12265 Is Reading High
-
- CR113767; TI
- 55115 Was Found Out Of Spec
-
- CR348081; Possible Insufficient Seal On Seiche Door #182
-
- CR348085; Door 164 Cannot Open Far Enough For Door Inspection Resulting In UNSAT Condition'
-
- CR348087; Possible Inadequate Door Seal On Seiche Door 165 (Inactive)
-
- CR364486; Upper Angle Guide Is Not Located In The Upper Position For 1
-610BKR -
- CR420528; RST And TST Secondary Voltage Causing Operational Problems
-
- CR423130; NRC Questions On RAS000105 Assumptions Following Walkdown
-
- CR424517; NRC
-Inspector Identified:
- 47033 P Possible Improvement
-
- CR427327; Hard Drive Failed In PPC
-A Causing The Server To Lockup
-
-
- CR430269; Secondary Alarm Station Door Is Bindi ng -
- CR430511; Evaluate Operational Decision Making For Safeguards Bus Voltage
-
- CR430800; Oil Buildup On Casing Near Overspeed Trip Mechanism For EDG "A"
- EOP
- ES-0.1; Reactor Trip Response; Revision 31
- NERC Standard NUC
-001; Nuclear Plant Interface Coordination Agreement Between Dominion Energy Kewaunee, Inc. And American Transmission Company LLC;
- Effective April 1, 2010 -
- OP-KW-AOP-GEN-002; Rapid Power Reduction; Revision 10
-
- OP-KW-NOP-SUB-003; RST And TST Load Tap Changer Operation, System 59; Revision
-
- RAS 105; Possible Insufficient Seal On Door 182, 164, And 165; March 21, 2011
-
- CR433023; Breaker 14305 Would Not Close From The Control Room
- 1R04 Equipment Alignment
- High Risk Contingency Plan Actions Dated June 30, 2011, For Breaker 14305 Troubleshooting
-
-
- OP-KW-NCL-AFW-001; Auxiliary Feedwater System Prestartup Checklist
-
- SP-05B-284; Turbine Driven AFW Pump Full Flow Test
- IST; Revision 39
- Troubleshooting Plan For Breaker 14305, CR43278
- WO KW100570163; Investigate and Repair Heated Load Connections On Breaker MCC43B-D2 - Fire Zone Summary For AX
-33 and AX39, Condensate And Makeup Water Tank Room and Adjacent Areas; Revision 8
- 1R05 Fire Protection
- Fire Zone Summary for AX
-37, Control Rod Drive, Reactor Trip Cabinet, Instrument Lab and Emergency Air Lock Areas; Revision 8
- Attachment
- Fire Zone Summary For TU
-96 Oil Storage Room "B"; Revision 8
-
- TU-22, 96, Turbine Building Basement; Revision G
-
- AX-33 and
- AX-39, Condensate And Makeup Water Tank Room And Adjacent Areas; Revision D
-
- AX-37, Control Rod Drive, Reactor Trip Cabinet, Instrument Lab and Emergency Air Lock Areas; Revision E
-
- CR424708; Identification Of Previously Unanalyzed Flooding Source
- 1R0 6 Flooding -
- CR424896; Trench Barrier Not Inspected
- Drawing A-528-1; Flood Boundary; Revision F
- Drawing A-528-2; Flood Boundary Revision C
- Drawing S-508; Administration Building Foundation Plan & Floor Drains; Revision
- R -
- ICP-04-22; Turbine Building Level Switches To Circulating Water Pump Trip Functional Test; March 11, 2011 -
- MA-KW-MPM-MDS-001; Inspection Of Flood Protection Floor Drain Check Valves; March 6, 2011 -
- OP-KW-AOP-GEN-004; Response To Natural Events; Revision
-
- OP-KW-AOP-MDS-001; Abnormal Operation Of Miscellaneous Drains And Sumps, System
- MDS-30; Revision
-
-30; Revision
-
-30; Revision
-
-30; Revision
-
- OP-KW-ARP-47033-R; Aux Bldg Flood Level High, System MDS
-30; Revision
-
-04; Revision
-
- OP-KW-ARP-47051-Q; Turbine Building Service Water Isolation, System SW
-02; Revision
-
- OP-KW-ARP-47052-N; Turbine Bldg Flood Level Alert, System CW
-04; Revision
-
- OP-KW-ARP-47053-N; Cond Trench Water Level High, System CW
-04; Revision
-
- OP-KW-ARP-47054-N; SFGRD Alley Flood Level High, System MDS
-30; Revision
- Report No. SW
-02-19(App.C); Dynamic Seismic Analysis; March 30, 1990 - WO KW100276096; PM30
-547:
- Inspect Valve Internals; June
- 11, 2010 - WO KW100280620; PM30
-548:
- Inspect Valve Internals; June
- 11, 2010 - WO KW100474718; PM89A055:
- Inspect Flood Barriers; November
- 17, 2009 - WO KW100576053; PM08
-805:
- Inspection Of Doors On Elevation 569 And 586; August 10, 2010 - WO KW100593929; PM30
-543:
- Inspect Valve Internals; October
- 2, 2010 - WO KW100593989; PM30
-542:
- Inspect Valve Internals; October
- 2, 2010 - WO KW100596190; PM30
-552:
- Inspect Valve Internals; March
- 11, 2011 - WO KW100596331; PM30-544:
- Inspect Valve Internals; October
- 2, 2010 - WO KW100598634; PM04
-582:
- Turbine Bldg CW Pump Functional Test; March
- 15, 2011 - WO KW100599448; PM30
-553:
- Inspect Valve Internals; October
- 2, 2010 - WO KW100768370; PM89A067:
- Inspect/Functional Check (Monthly) SPV Doors; March 9, 2011 -
- LRC-11-DY201; 11-02 Cycle Dynamic; Revision A
- 1R11 Licensed Operator Requalification Program
- Attachment
- AC Source
- Operating; B 3.8.1
-21; Amendment No. 207
- 1R12 Maintenance Effectiveness
- ACE018573; CR417289:
- Inspect TSC D/G Output Breaker
-
- CR342455; Experienced A Temporary Loss Of All Plant Process Computer Functions
-
- CR379304; Received TLA
-1 During For Rod K07 During Power Escalation
-
- CR411774; Maximo Did Not Create ENGPR Restraints For NS Parts On 3 SR Work Orders
-
- CR417078; Loss Of Station Backfeed
-
- CR417099; TSC Diesel Generator Tripped On High Water Temperature
-
- ECA-0.0; Loss Of All AC Power; Revision 44
- Emergency Diesel Generator; Maintenance Rule Scoping Questions; Attachment
- A; Revision 3 - Emergency Diesel Generator; Maintenance Rule System Basis; Revision
- 14; July 11, 2011 - Emergency Diesel Generator; SSC Performance Criteria Sheet; Attachment B; Revision
-
- ER-AA-BKR-1001; Circuit Breaker Program; Revision
-
- ER-AA-PRS-1010; Preventive Maintenance Task Basis And Maintenance Strategy; Revision
- Log Entries Report; March 11 To March 14, 2011
- Maintenance Rule Performance Criteria; Rod Control And Rod Position Indication System
- Attachment B, Revision 3
- Maintenance Rule Scoping Questions; Rod Control And Rod Position Indication System; Attachment A, Revision 2
- Maintenance Rule System Basis
- Rod Control And Rod Position Indication System; Revision 7
-
- MRE 010898; Experienced A Temporary Loss Of All Plant Process Computer Functions
- MRE 012060;
- Received TLA
-1 During For Rod K07 During Power Escalation
- MRE013358; CR417289:
- Inspect TSC D/G Output Breaker
-
- OP-KW-ARP-47086-H; Bus 46 Voltage Low; Revision 0
-
- OP-KW-ARP-47086-I; TSC Diesel Gen Abnormal; Revision 1
-
- OP-KW-NOP-DGM-001C; TSC Diesel Generator Operation; Revision 4
- Rod Control And Rod Position Indication System Balancing; October 2009
- March 2011
- System 40; 480 Volt Electrical Supply And Distribution; Maintenance Rule System Basis; Revision 7; July 11, 2011 - System 40; 480 Volt Electrical Supply And Distribution; Maintenance Rule Scoping Questions; Attachment
- A; Revision
- System 40; 480 Volt Electrical Supply And Distribution; SSC Performance Criteria Sheet;
- B; Revision
- Technical Support Center Diesel Maintenance Rule Data Sheets; December 2009 Through June 2011 - Planning and Scheduling, Work Week Risk and Work Schedule Documentation for the Weeks of May 9, May 16, May 23, May 30 and June 13, 2011;
- 1R13 Maintenance Risk - ACE018531; Failed Standoffs Used To Mount SBV Servo Boards
- 1R15 Operability Evaluations
- ACE018531; SBV Standoffs For Servo Boards Broken
- ACE018578; CR416884:
- Diesel Generator 'A' Hunting During Hot Fast Start Test
-
- CR411681; Shield Building Vent Standoffs For Servo Boards Found Broken, Board Hanging
-
- CR411774; Maximo Did Not Create ENGPR Restraints For NS Parts On 3 SR Work Orders
-
- CR421752; Jacket Water Dripping From Reservoir Overflow Line On Diesel Generator A
- Attachment
-
- CR423665; NRC Identified Issue With OD
-413 (EDG "A" Jacket Water Expansion Tank Overflow) -
- CR423969; Operational Through
-Wall Leakage Flowchart Does Not Address HX Tube Leakage -
- CR427292; FW
-7A Controlling Erratically
-
- CR428470; Runout On Outboard Generator Collector Ring Is Out Of Acceptance Range
-
- CR429224; Heat Exchanger Tube Leakage Requirements
-
- CR429386; NRC Questions Use Of Non
-Safety-related Part In Shield Building Ventilation System -
- CR429469; NRC Resident Question On Reportability Of 1/2011 SBV Servo Board Issue
-
- CR432053; Questions Concerning The Conclusions In ACE018531, Failed Standoffs In SBV System - Design Review Of Post
-Accident Plant Shielding And Equipment Radiation Qualification; Project:
- 23
-7127-053; February 13, 1981
- Drawing ISIM
-202-1; ISI Flow Diagram Service Water System; Revision Y
- EOP
- IEE No. 10000008907; Version 00
- Kewaunee Power Station Fourth 10
-Year Interval Inservice Inspection Program, Revision 4, Appendix I, Basis Document for ISI Code Class Boundaries, Page I
-31 - Log Entries Report; January 25 To February 4, 2011
-
- MA-KW-GMP-BLD-003; RHR Pump Pit Cover Removal And Installation With Flood Barrier Installed; Revision
- MRE013146; Shield Building Vent Standoffs For Servo Boards Found Broken
- MRE013340; Stopped DG A And Placed To Pullout Per Step 5.9.17 Of OSP
-DGE-004A -
- MS-AA-IEE-301; Item Equivalency Evaluation; Revision 2
-
- MS-AA-SC E-301; Subcomponent Classification Evaluation; Revision 1
-
- NRC-03-057; Letter From Kewaunee Nuclear Power Plant To NRC, Re:
- License Amendment Request 195, Application For Stretch Power Uprate For Kewaunee Nuclear Power Plant;
- May 22, 2003 -
- ODM-201; Operational Decision Making Checklist; May 25, 2011
-
- OP-AA-101 - Attachment 2; Operational Decision Making Checklist For
- CR362131; December 22, 2009 -
- OP-AA-102; Operability Determination; Revision 6
-
- OP-AA-102-1001; Development Of Technical Basis To Support Operability Determinations; Revision 4 -
- OP-KW-OSP-DGE-001A; Diesel Generator A Monthly Availability Test; Revision 10
- Prompt Operability Determination Documentation For
- CR421752, Revision
- 0; April 15, 2011 - Prompt Operability Determination Documentation For
- CR421752, Revision 1; April 23, 2011 - Q-List Package:
- QL
-24; System 24
- Shield Building Ventilation (SBV); May 12, 2010
-
- SCE 10000015810; SBV Servo Boards NS Parts; Revision 00
- Station Log; May 24, 2011 Time:
- 08:37
- 17:56 - WO KW100471263; Inspect Circuit Board For Damage - WO KW100755550; Contingency.
- Remove Standoffs On Servo Board 35108/35109
- WO KW100755927; Remove The Circuit Board Standoffs From Train B Shield Building Vent
- 50.59/72.48 Screen, Replace The Connectors On The CETs And CET Cables Between Reactor Head And Junction Boxes
- 1R18 Plant Modifications
- DCR
- KW-10-01011, Replace Core Exit Thermocouple (CET) And Associated Connectors And Cables Attachment
- Regulatory Guide 1.187; Guidance For Implementation Of
- CFR 50.59, Changes, Tests, And Experiments; November 2000
-
- CR414237; CRPAR PMT Lessons Learned
- 1R1 9 Post-Maintenance Testing
-
- High Risk Contingency Plan Actions dated June 3, 2011, For Replacement Motor Driven Auxiliary Feedwater A
-
- MA-KW-ESP-DGE-003B; Diesel Generator B Semi
-Annual Fast Start Test; System
- 2; Revision 16 -
- MA-KW-ESP-DGE-004B; Inspection Of Diesel Generator B (Component Retest); System
- 2; Revision 7 -
- OP-KW-OSP-AFW-005; Auxiliary Feedwater Pump A Low Suction Pressure Trip Test And SW
- Valve IST; System 05B; Revision 1
- Pre-Job Briefing No. 1159; Maintenance
-Mechanical; May 9, 2011
-
- SP-02-292B; SW Train B Pumps Reference Value And Testing; Revision
- Tracking And Processing Record For: SP
-02-292B; SW Train B Pumps Reference Value And Testi ng - WO KW100799844; Replace The 1B D/G Engine Driven Fuel Oil Pump
- WO KW100801677; Replace 'A' AFW Pump C/S With New From Stock
-
- OP-KW-NOP-SI-001; Filling, Pressurizing, And Venting SI Accumulators; System 33; Revision 8 1R22 Surveillance Testing
-
- SP-05B-283A; Motor Driven AFW Pump A Full Flow Test
- IST; Performed June
- 17, 2011 -
- SP-05B-283B; Motor Driven AFW Pump B Full Flow Test
- IST; June 2, 2011 -
- SP-05B-284; Turbine Driven AFW Pump Full Flow Test
- IST; Performed June
- Drill Scenario Package dated May 10, 2011,
- CR426783; Steam Flow 464A
- 1EP6 Drill Evaluation
- 2009 Annual Effluent Release Report; Kewaunee Power Station; April 26, 2010
- 2RS1 Radiological Hazard Assessment and Exposure Controls
- 2010 Annual Effluent Release Report; Kewaunee Power Station; April 13, 2011 - ACE18489; Charcoal Filter Efficiency Test Failures; April 1, 2011
- Audit 08-06; Radiological Protection And Process Control Program; September
- 4, 2008 - Audit 09-08; Radiation Protection/Process Control Program/Chemistry; July
- 29, 2009 - Audit 09-15; Offsite Dose Calculation Manual/Radiological Environmental Monitoring Program/Environmental Protection Program 7 Surry Refueling Activities; January
- 28, 2010 - Audit 10-07; Radiological Protection And Process Control Program; September
- 23, 2010 - Calculation C11988; Estimation Of Carbon
-14 At Kewaunee Power Station Gaseous Effluents; Revision 0 - Calculation No. C10690; ODCM Setpoint Calculations; Revision A
- Calculation No. C11620; Evaluation Of Radiological Effluent Monitor Response Action Levels; Revision 0
- Attachment
- Calculation No. C11805; EAL Calculation For Abnormal Radiological Releases; Revision
- 0; Addendum A -
- CR103668; 2007 Annual Effluent Release Report Contains An Inaccurate Stateme nt -
- CR117760; NRC Question Of Self Eval Review For RG 1.97 Vulnerabilities In Rad Monitoring
- CR117759; NRC Question of the PM Program for Rad Monitoring System
-
- CR430015; 2010 Annual Effluent Release Report Contains An Inaccurate Statement
-
- CR430267; Ineffective Review Of Radiological Crosscheck Results
-
- CR430361; SP
-33-113 Data Sheets Misfiled
-
- CR430443; Minor Discrepancy Between CY
-AA-LQC-400-1000 And Actual Vendor Practice
-
- CY-AA-LQC-400-1000; Confirmatory Measurements Using Blind Samples; Revision
-
- CY-KW-000-003; Attachment B; Chemistry Interlab Quality Control Sample Data Sheet; March 26, 2010 -
- CY-KW-000-003; Attachment B; Chemistry Interlab Quality Control Sample Data Sheet; March 19, 2010 -
- CY-KW-000-003; Attachment B; Chemistry Interlab Quality Control Sample Data Sheet; September 23, 2010 -
- CY-KW-000-003; Attachment B; Chemistry Interlab Quality Control Sample Data Sheet; December 1, 2010 -
- CY-KW-000-003; Attachment B; Chemistry Interlab Quality Control Sample Data Sheet; April 20, 2011 -
- CY-KW-000-003; Interlab Quality Control; Revision 3
-
- CY-KW-042-001; Makeup Water Sample Specifications; Revision 11
-
- CY-KW-049-013; Sludge Sampling; Revision 2
-
- HP-05.015; Miscellaneous Gaseous Radwaste Releases; Revision 12
-
- HP-07.018; Instrument Calibration Procedure
- Ion Chambers;
- Revision 9 -
- HP-07.040; Instrument Calibration Procedure
- JL Shepherd Model 89
-400 Calibrator Source Characterization Verification; Revision
-
- HP-07.072; Instrument Calibration Procedure
-
- PCM-1C Contamination Monitor; Revision
- KPS Radiac Calibration Worksheet; AM
-2 (3096-3); Serial No. 9817
-132; November 3, 2010
- KPS Radiac Calibration Worksheet; AMP
-200 (0-10,000 R/hr); Serial No. 7705
-009; April, 15, 2010 - KPS Radiac Calibration Worksheet; AMS
-4; Instrument S/N 1394; November
-4; Serial No. 110; September 29, 2010
- KPS Radiac Calibration Worksheet; Ludlum 12S; Serial No. 67666; August
- 5, 2010 - KPS Radiac Calibration Worksheet; Ludlum 9
-3; Serial No.
- 265319; August
- 3, 2010 - KPS Radiac Calibration Worksheet; MGP Telepole; Serial No, 6606
-026; June 3, 2010 - KPS Radiac Calibration Worksheet; PNR
-4; Serial No. 2234; July 7, 2010
- KPS Radiac Calibration Worksheet; RAM
-GAM; Serial No. 1899
-035; October
-2; Serial No. 5907; January 6, 2011
- KPS Radiac Calibration Worksheet; RO
-7; Serial No. 125; December 14, 2010
- KPS Radiac Calibration Worksheet; SAM
-11; Serial No. 269; October 12, 2010
- KPS Radiac Calibration Worksheet; Xetex 330A Telescan; Serial No. 50025; July
- 7, 2010 -
- NAD-01.12; Radiological Gaseous Waste Discharge; Revision 8
- Offsite Dose Calculation Manual (ODCM); Revision 12
- Offsite Dose Calculation Manual (ODCM); Revision 13
-
- RP-KW-005-004; Effluent Monitoring And Sampling Requirements; Revision 11
-
- RP-KW-007-099; Eberline Personnel Monitor Model PM
-77, Calibration And Operation; Revision 1 -
- SP-29-069; Liquid Continuous Radioactive Releases
- Steam Generator, Turbine Building Sump; Revision 34
-
- SP-29-255; Liquid Continuous Radioactive Releases Surveillances; Revision 12
- Attachment
-
- SP-32-113; Gaseous Radioactive Effluents Reports For Continuous Releases; Revision
-
- SP-32-114; Liquid Batch Radioactive Release Surveillances; Revision 23
-
- SP-32-115; Doses From Liquid Effluents; Revision 14
-
- SP-32-299; Incineration Of Contaminated Oil Using Heating Boiler; Revision 11
-
- SP-32A-136; Radiological Liquid Discharges (Batch Mode); Revision 38
-
- SP-32A-266; Effluent Dose Limit Verifications; Revision 11
-
- SP-32B-116; Gaseous Radioactive Effluents
- Reports For Batch Releases; Revision
-
- SP-32B-268; Site Boundary Dose From Gaseous Effluents; Revision
-
- SP-45-290; Radioactive Gaseous Effluent Monitoring Instrumentation, Compensatory Actions For Channels Out Of Service; Revision 8
-
- SP-63-280; Annual Environmental Reports; Revision 13
- System Health Report; Radiation Monitoring; July
- 7, 2010 - September 30, 2010
- System Health Report; Radiation Monitoring; October 1, 2010
- December 31, 2010 - Control Room / Out
-Of-Service Logs, March 2010, May 2010, September 2010, November 2010, and February 2011
- 4OA1 Performance Indicator (PI) Verification
-
-
- CR407784; Standardized Log Entries For MSPI/WANO/Maintenance Rule
-
- CR429924; Venting From RHR
-501A On 5-5-2011 Not Logged And No Partial Procedure Found - Kewaunee Mitigating System Performance Index Basis Document; Revision G
- Kewaunee Mitigating System Performance Index Basis Document; Revision H
- Kewaunee Mitigating System Performance Index Basis Document; Revision 9
- List of Maintenance Rule Evaluations for MSPI systems, 2008
-2011 - Maintenance Rule Data Sets, Auxiliary Feedwater; April, 2010
- March, 2011
- Maintenance Rule Data Sets, Component Cooling Water; April, 2010
- March, 2011
- Maintenance Rule Data Sets, Diesel Generators; January, 2010
- March, 2011
- Maintenance Rule Data Sets, Residual Heat Removal; January, 2010
- March, 2011
- Maintenance Rule Data Sets, Safety Injection; January, 2010
- March, 2011
- Maintenance Rule Data Sets, Service Water; April, 2010
- March, 2011
- MRE012615; While Restoring Air On WO KW100674232
- SW-4A Opened - MSPI Derivation Reports, Auxiliary Feedwater; April, 2010
- March, 2011
- MSPI Derivation Reports, Component Cooling Water; April, 2010
- March, 2011
- MSPI Derivation Reports, Diesel Generator;
- January, 2010
- March, 2011
- MSPI Derivation Reports, Residual Heat Removal;
- January, 2010
- March, 2011
- MSPI Derivation Reports, Safety Injection; January, 2010
- March, 2011
- MSPI Derivation Reports, Service Water; April, 2010
- March, 2011
-
- SP-32A-266; Effluent Dose Limit Verifications; Data Sheet A;
- February 9, 20
-
- SP-32A-266; Effluent Dose Limit Verifications; Data Sheet A; May 19, 201
- ACE018119; Revision and Review Process For EPIPs Has Not Been Effective
- 4OA2 Identification and Resolution of Problems
-
- NAD-14.06; Severe Accident Management Program Maintenance And Control
- Attachment
- ACE18615; Door 3 Lower Bolt Was Found Not Engaged
- 4OA3
- Follow-Up of Events and Notices of Enforcement Discretion
- EN45562; Non
-Functional Steam Door
- Engineering Technical Evaluation; ETE
-KW-2011-0013; Transmittal Of Information To Support Analysis Of HELB Door 3 With Disengaged Lower Cane Bolt; March
- 15, 2011 - Engineering Technical Evaluation; ETE
-KW-2011-0016; HELB Capability Of Door 3 With Lower Cane Bold Disengaged; March
- 2, 2011 -
- KPS-70224866-S01; Door 3 Structural Analysis; March 17, 2011
- LER 5000305/20
- 11-001-00; Auxiliary Building Special Ventilation Inoperability Results in Prohibited Technical Specification Condition
- LER 5000305/20
- 11-002-00; Loss of Station Backfeed Results in Loss of One Train of Offsite Power During Refueling Outage - LER 5000305/20
- 11-003-00; Valve SI
-11A, Safety Injection to Loop A Cold Leg, Breaker Found On with Plant in Mode 3
-
- CA-01; RCS Injection To Recover Core
- Revision B; July 3, 2003
- 4OA 5
- Other Activities
-
- CA-02; Injection Rate For Long Term Decay Heat Removal; Revision B; July 3, 2003
-
- CA-03; Hydrogen Flammability In Containment
- Revision 3; April 21, 2009
-
- CA-04; Volumetric Release Rate From Vent
- Revision A; October 3, 2000
-
- CA-05; Containment Water Level And Volume
- Revision 4; April 23, 2009
-
- CA-06; RWST Gravity Drain
- Revision A; October 3, 2000
-
- CA-07; Hydrogen Impact When Depressurizing Containment
- Revision A; October 3, 2000 -
- CR106141; Service Water Leak Identified On Containment Fan Coil Unit B
-
- CR348133; Increased Containment Sump A In Leakage
-
- CR422219; Verifying Serial Numbers In Model 1000 Multi
-Source Gamma Calibrator
-
- CR422311; Serial Number Of National Source Tracking System Source Not Correct
- DFC; Diagnostic Flow Chart
- Revision D; August 29, 2006
-
- ETE-KW-2011-027; Containment Fan Coil Unit Service Water Leaks And Barrier Operability; Prepared June 23, 2011
- NRC Form 748; 50
-305; Eberline Model 1000; April 4, 2011
-
- SACRG-01; Severe Accident Control Room Guideline
- Initial Response
- Revision 8; March 17, 2011 -
- SACRG-02; Severe Accident Control Room Guideline - After TSC Is Functional
- Revision 4; March 17, 2011 -
- SAEG-01; TSC Long Term Monitoring
- Revision C; October 3, 2000
-
- SAG-01; Feed The Steam Generator
- Revision 11; March 17, 2011
-
- SAG-02; Depressurize The RCS
- Revision C; October 3, 2000
-
- SAG-03; Inject Into The RCS
- Revision C; October 3, 2000
-
- SAG-04; Inject Into Containment
- Revision C; October 3, 2000
-
- SAG-05; Reduce Fission Product Releases
- Revision 4; April 19, 2011
-
- SAG-06; Control Containment Conditions
- Revision C; October 3, 2000
-
- SAG-07; Reduce Containment Hydrogen
- Revision C; October 3, 2000
-
- SCG-01; Mitigate Fission Product Releases
- Revision C; October 3, 2000
-
- SCG-02; Depressurize Containment
- Revision C; October 3, 2000
-
- SCG-03; Control Hydrogen Flammability
- Revision B; October 3, 2000
-
- SCG-04; Control Containment Vacuum
- Revision B; October 3, 2000
- SCST; Severe Challenge Status Tree
- Revision D; August 29, 2006
-
- UG-01; SAMG Users Guide
- Revision B; October 3, 2000
- Attachment
- ACE18578; Diesel Generator A Hunting During Hot Fast Start
- 4OA 7
- Licensee-Identified Violations
- LER 5000305/20
- 11-003-00; Valve SI
-11A, Safety Injection to Loop A Cold Leg, Breaker Found On with Plant in Mode 3
-
- CR420698; BUS 1 And 2 FME Concern
- NRC-Identified Condition Reports
-
- CR420700; Blue Painters Tape On Spent Fuel Pool System Piping -
- CR421810; Control Of 10 Hour Limitation On AFW Pump Operation Under Min Flow Conditions
-
- CR422025; Control Room Notified Door 1 Found Ajar
-
- CR422215; Cross
-Cutting Aspects Identified At NRC Quarterly Exit Meeting
-
- CR422219; Verifying Serial Numbers Contained In Model 1000 Multi
-Source Gamma Calibrator
-
- CR422311; Serial Number Of National Source Tracking System Source Not Correct
-
- CR422471; NRC Concern With Ability To Meet Emergency Plan Iodine Sampling Requirements
-
- CR423104; Perform Needs Assessment For B.5.b For Selected Maintenance Training Programs -
- CR423130; NRC Questions On RAS000105 Assumptions Following Walkdown
-
- CR423525; NRC Identified:
- Door 1 (EDG B Room To Screenhouse Tunnel) Lower Cane Bolt Issue -
- CR423665; NRC Identified Issue With OD
-413 (EDG "A" Jacket Water Expansion Tank Overflow) -
- CR423711; RFT
- SAMG Training For Non
-Licensed Operators
-
- CR423733; Evaluate Addition Of SAMG Training To NAO Training Program
-
- CR423884; Incorrect Procedure Referenced In OP
-KW-ARP-47054-N -
- CR423964; NRC Identified:
- Door 5 Lower Cane Bolt Found Not In The Down (Latched)
- Position -
- CR424226; Failure Of KPS Process To Identify Door Cane Bolt Issues
-
- CR424445; NRC Identified TAV62
-B Is Leaking Rainwater Into EDG B Room
-
- CR424488; SBO/TSC Diesel
- Ability To Withstand Effects Of Likely Weather Related Events
-
- CR424508; NRC Identified Improvements To Procedure AOP
-AFW-001 -
- CR424517; NRC Inspector Identified:
- ARP 47033 P Possible Improvement
-
- CR424681; Ownership Of SACRG
-1 And SACRG
-2 -
- CR424708; Identification Of Previously Unanalyzed Flooding Source
-
- CR424852; NRC Prompted
- SW Isolation Valves Not On SACRG
-1 Attachment
- A -
- CR424855; NRC Prompt
- SAMG Procedures Lack Detail
-
- CR424858; NRC Prompt
- B.5.b Procedures Lack Detail
-
- CR424864; NRC Prompt
-
- SACRG-2 Additional Component Evaluati on -
- CR424865; NRC Prompt
- SAMG Procedure Step To Order Hydrogen Recombiner
-
- CR424866; NRC Prompt
- SAMG Procedures Lack B.5.b Strategies
-
- CR424870; NRC Prompt
- ERO Training Lacks Training On B.5.b Procedures
-
- CR424896; Trench Barrier Not Inspected
-
- CR425092; NRC Identified
- No Clear Direction To Obtain Hydrogen Recombiners
-
- CR425383; NRC Questions Absence Of SAMG Training In Maintenance Training Program-RFT -
- CR425608; NRC Prompt
- Deficiencies In
- Memorandums Of Understanding
-
- Attachment
-
- CR425881; HD
-370B Has A Stem Packing Leak
-
- CR425961; Procedure PRP
-02 Revision May Have Introduced Error Trap
-
- CR425962; Enhancement Recommended To Agreement With Point Beach Nuclear Plant
-
- CR426999; NRC Prompted
- SAMGs Documents Not Updated To Current WOG Revision
-
- CR427092; NAD
-14./06 Severe Accident Management Program Review Requirements Not Performed -
- CR427381; Aux Bldg Crane Annual Inspection Steps In 2010 Incorrectly Marked N/A
-
- CR427517; NRC Prompted
- Evaluate Increasing Scope Of SAMG Training In The TSC ERO
-
- CR427519; NRC Prompted
- No SAMG Drills/Tabletops Performed In The Past Several Years
-
- CR427575; BRC
-103 Breaker 27 Red Indicating Light Bulb Is Burnt Out
-
- CR427577; NRC Identified:
- Electrical Ground cart Placed Against Door 401 Flood Barrier
-
- CR427578; NRC Identified:
- Spare Electrical Conduit Found Behind Service Water Piping In AB -
- CR427900; NRC Prompted
- Evaluate Increasing The Amount Of SAMG Training To The ED
-
- CR427968;
- ODM 135 Trigger Reached
-
- CR428242; Residual Boric Acid Deposit Identified At Drain For 1A SI Pump Inboard Seal
-
- CR428275; NRC Bulletin 2011
-01, Mitigating Strategies, 30 And 60 Day Response Required
-
- CR428327; MCC
-62H Work In Progress Sign Is In Disrepair
-
- CR428489; Controls For Storage Of Combustibles Not Followed
-
- CR429386; NRC Questions Use Of Non
-Safety-related Part In Shield Building Ventilation System -
- CR429469; NRC Resident Question On Reportability Of 1/2011 SBV Servo Board Issue
-
- CR429498; NRC Questions The Operability Statement Concerning The SBV -
- CR430015; 2010 Annual Radiological Effluent Release Report Contains Inaccurate Statement
-
- CR430267; Ineffective Review Of Radiological Crosscheck Results
-
- CR430931; Additional TSC Flood Source
-
- CR431619; Copper Tubing Found On Control Room A/C Train A
- Ductwork -
- CR431621; Door 441 Found Ajar
-
- CR432053; Questions Concerning The Conclusions In
- ACE 018531 Failed Standoffs In SBV
- System -
- CR432099; Evaluate Staging A Hand Held Tachometer At TDAFW Pump
-
- CR432567; NRC Resident Inspector Maintenance Rule Question
-
- CR432756; NRC Identifies That ACE Did Not Document Operations Response To TSC D/G Breaker Attachment
LIST OF ACRONYMS
ALARA As-Low-As-Is-Reasonably
-Achievable
IMC Inspection Manual Chapter
I P Inspection Procedure
PI Performance Indicator
PM Preventive
Maintenance
RS Reactor Safety
SAMG Severe Accident Management Guideline
Attachment
TI Temporary Instruction
TRM Technical Requirement
s Manual
WO Work Order
WOG Westinghouse Owners Group
D. Heacock
-2- In accordance with
NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records
System (PARS) component of
NRC Website at http://www.nrc.gov/reading
-rm/adams.html
(the Public Electronic Reading Room).
Sincerely, /RA/ Michael A. Kunowski, Chief
Branch 5 Division of Reactor Projects
Docket No. 50
-305 License No
. DPR-43 Enclosure:
Inspection Report 050003
05/20 11003 w/Attachment: Supplemental Information
cc w/encl:
Distribution via ListServ
DISTRIBUTIONSee next page
DOCUMENT NAME: G:\DRPIII\1-Secy\1-Work In Progress
\KEW 2011 003.docx Publicly Available
Non-Publicly Available
Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl
"E" = Copy
with attach/encl "N" = No copy
- OFFICE [[]]
- RIII [[]]
- RIII [[]]
- RIII [[]]
- RIII [[]]
- RECORD [[]]
COPY
Letter to D. Heacock from M. Kunowski dated
July 28, 2011
- POWER [[]]
STATION INTEGRATED INSPECTION REPORT 05000305/20
11003
RidsNrrDorlLpl3
-1 Resource
RidsNrrPMKewaunee
RidsNrrDirsIrib Resource
Cynthia Pederson
- DRPIII [[]]
DRSIII Patricia Buckley