IR 05000244/2018001: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 63: Line 63:
The unit began the inspection period at 100 percent power and operated at full power until March 8 , 2018, when the unit was shut down to replace a faulty current transformer on the main generator's output line. The unit was returned to rated power on March 13, following replacement of the current transformer, and it remained at or near 100 percent power for the remainder of the inspection period.
The unit began the inspection period at 100 percent power and operated at full power until March 8 , 2018, when the unit was shut down to replace a faulty current transformer on the main generator's output line. The unit was returned to rated power on March 13, following replacement of the current transformer, and it remained at or near 100 percent power for the remainder of the inspection period.


INSPECTION SCOPE S  Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading
==INSPECTION SCOPE==
S  Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading
-rm/doc-collections/insp
-rm/doc-collections/insp
-manual/inspection
-manual/inspection
Line 74: Line 75:


==REACTOR SAFETY==
==REACTOR SAFETY==
71111.01 - Adverse Weather Protection Impending Severe Weather (1 Sample)  The inspectors evaluated readiness for impending adverse weather conditions for predicted heavy snow accumulation on March 1, 2018
 
. 71111.04 - Equipment Alignment Partial Walkdown (3 Sample s)  The inspectors evaluated system configuration s during partial walkdowns of the following systems/trains
==71111.01 - Adverse Weather Protection==
: (1) 'C' standby auxiliary feedwater on January 26, 2018 (2) Turbine-driven auxiliary feedwater on March 9, 2018 (3) 'B' safety injection on March 22, 2018 71111.05Q  
 
- Fire Protection Quarterly Quarterly Inspection (5 Samples)  The inspectors evaluated fire protection program implementation in the following selected areas:  
===Impending Severe Weather===
(1) Co mpensatory measures during replacement of fire water piping in 'A' emergency diesel generator room on January 17, 2018 (2) 'B' b attery room on February 16, 2018 (3) Intermediate building controlled side basement on March 22, 2018 (4) Intermediate building controlled side top floor on March 30, 2018 (5) Hemyc wrap on March 30, 2 018 71111.06 - Flood Protection Measures Cables (1 Sample)  The inspectors evaluated cable submergence protection in:
{{IP sample|IP=IP 71111.01|count=1}}
  (1) Manholes MH1A-01, MH1B-01, MH3-03 West, MH5A
The inspectors evaluated readiness for impending adverse weather conditions for predicted heavy snow accumulation on March 1, 2018
.
 
==71111.04 - Equipment Alignment==
 
Partial Walkdown (3 Sample s)  The inspectors evaluated system configuration s during partial walkdowns of the following systems/trains
:
: (1) 'C' standby auxiliary feedwater on January 26, 2018
: (2) Turbine-driven auxiliary feedwater on March 9, 2018
: (3) 'B' safety injection on March 22, 2018 71111.05Q  
- Fire Protection Quarterly Quarterly Inspection (5 Samples)  The inspectors evaluated fire protection program implementation in the following selected areas:
: (1) Co mpensatory measures during replacement of fire water piping in 'A' emergency diesel generator room on January 17, 2018
: (2) 'B' b attery room on February 16, 2018
: (3) Intermediate building controlled side basement on March 22, 2018
: (4) Intermediate building controlled side top floor on March 30, 2018
: (5) Hemyc wrap on March 30, 2 018
 
==71111.06 - Flood Protection Measures==
 
===Cables===
{{IP sample|IP=IP 71111.06|count=1}}
The inspectors evaluated cable submergence protection in:
: (1) Manholes MH1A-01, MH1B-01, MH3-03 West, MH5A
-01, 02 , and 03 on February 19 and 20, 2018.
-01, 02 , and 03 on February 19 and 20, 2018.


71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance Operator Requalification (1 Sample)  The inspectors observed and evaluated a crew of licensed operators in the plant's simulator during licensed operator requalification training, involving a failed steam flow transmitter, trip of a running component cooling water pump, a main steam line leak and a steam generator tube rupture, on February 13, 2018.
==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
 
===Operator Requalification===
{{IP sample|IP=IP 71111.11|count=1}}
The inspectors observed and evaluated a crew of licensed operators in the plant's simulator during licensed operator requalification training, involving a failed steam flow transmitter, trip of a running component cooling water pump, a main steam line leak and a steam generator tube rupture, on February 13, 2018.


Operator Performance (1 Sample)  The inspectors observed Control Room operator performance during a lowering water level in the screen house intake on February 13, 2018, power decrease for the turbine-driven auxiliary feedwater run on March 7, 2018
Operator Performance (1 Sample)  The inspectors observed Control Room operator performance during a lowering water level in the screen house intake on February 13, 2018, power decrease for the turbine-driven auxiliary feedwater run on March 7, 2018
, and start up activities on March 10 to March 13, 2018. 71111.12 - Maintenance Effectiveness Routine Maintenance Effectiveness (2 Samples)  The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions
, and start up activities on March 10 to March 13, 2018.
. (1) House heating boiler maintenance rule (a)(1) evaluation on March 1, 20 18 (2) Chemical and volume control system (charging) on March 6, 2018 71111.13 - Maintenance Risk Assessments and Emergent Work Control (5 Samples)  The inspectors evaluated the risk assessments for the following planned and emergent work activities
 
: (1) Elevated risk for planned under
==71111.12 - Maintenance Effectiveness==
-voltage testing on electrical bus s es 16 and 17 on February 1, 2018 (2) Atmospheric relief valve 3411 hand-wheel planned replacement on February 27, 2018 (3) 'A' residual heat removal planned maintenance on March 15, 2018 (4) 'C' safety injection pump planned maintenance on March 21 and March 22, 2018 (5) 'A' component cooling water planned maintenance on March 26, 2018 71111.15 - Operability Determinations and Functionality Assessments (4 Samples)
 
===Routine Maintenance Effectiveness===
{{IP sample|IP=IP 71111.12|count=2}}
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions
.
: (1) House heating boiler maintenance rule (a)(1) evaluation on March 1, 20 18
: (2) Chemical and volume control system (charging) on March 6, 2018
 
==71111.13 - Maintenance Risk Assessments and Emergent Work Control==
 
======
{{IP sample|IP=IP 71111.13|count=5}}
The inspectors evaluated the risk assessments for the following planned and emergent work activities
:
: (1) Elevated risk for planned under
-voltage testing on electrical bus s es 16 and 17 on February 1, 2018
: (2) Atmospheric relief valve 3411 hand-wheel planned replacement on February 27, 2018
: (3) 'A' residual heat removal planned maintenance on March 15, 2018
: (4) 'C' safety injection pump planned maintenance on March 21 and March 22, 2018
: (5) 'A' component cooling water planned maintenance on March 26, 2018
 
==71111.15 - Operability Determinations and Functionality Assessments==
 
======
{{IP sample|IP=IP 71111.15|count=4}}
 
The inspectors evaluated the following operability determinations and functionality assessments:
The inspectors evaluated the following operability determinations and functionality assessments:
  (1) 'A' emergency diesel generator due to a ground on a lube oil heater on January 12, 2018 (2) 'B' battery room vault water intrusion on January 31, 2018 (3) Fire suppression system S
: (1) 'A' emergency diesel generator due to a ground on a lube oil heater on January 12, 2018
-15 alarm inputs on February 13, 2018 (4) Main steam safety valve 351 2 seat leakage on February 28, 2018 71111.19 - Post Maintenance Testing (7 Samples)  The inspectors evaluated post maintenance testing for the following maintenance/repair activities
: (2) 'B' battery room vault water intrusion on January 31, 2018
: (1) Excess letdown divert valve AOV
: (3) Fire suppression system S
-312 gag installation on February 12, 2018 (2) 'A' spent fuel pool pump check valve, CV-8655 maintenance, on February 13, 2018 (3) 'A' spent fuel pool pump maintenance and diode replacement on February 16, 2018 (4) 'A' flex diesel air compressor preventive maintenance on February 22, 2018 (5) 'D' service water pump/motor replacement and maintenance on March 3, 2018 (6) 'A' residual heat removal pump/motor alignment on March 15, 2018 (7) Technical support center ventilation fan maintenance on  March 22, 2018 71111.20 - Refueling and Other Outage Activities (1 Sample)  The inspectors evaluated forced outage activities from March 7 t o March 10, 2018
-15 alarm inputs on February 13, 2018
. 71111.22 - Surveillance Testing The inspectors evaluated the following surveillance tests:
: (4) Main steam safety valve 351 2 seat leakage on February 28, 2018
Routine (3 Samples) (1) STP-O-16QA , 'A' motor driven auxiliary feedwater pump surveillance test on January 10, 2018 (2) STP-O-40.5 , national fire protection association emergency diesel generator surveillance test on February 9, 2018 (3) STP-O-12.1 , 'A' emergency diesel generator surveillance test on February 12, 2018 Inservice (1 Sample)
 
  (1) STP-O-3QB, containment spray pump 'B' quarterly test on March 20, 2018 RADIATION SAFET Y 71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls Radiological Work Planning (1 Sample)
==71111.19 - Post Maintenance Testing==
 
======
{{IP sample|IP=IP 71111.19|count=7}}
The inspectors evaluated post maintenance testing for the following maintenance/repair activities
:
: (1) Excess letdown divert valve AOV
-312 gag installation on February 12, 2018
: (2) 'A' spent fuel pool pump check valve, CV-8655 maintenance, on February 13, 2018
: (3) 'A' spent fuel pool pump maintenance and diode replacement on February 16, 2018
: (4) 'A' flex diesel air compressor preventive maintenance on February 22, 2018
: (5) 'D' service water pump/motor replacement and maintenance on March 3, 2018
: (6) 'A' residual heat removal pump/motor alignment on March 15, 2018
: (7) Technical support center ventilation fan maintenance on  March 22, 2018
 
==71111.20 - Refueling and Other Outage Activities==
 
======
{{IP sample|IP=IP 71111.20|count=1}}
The inspectors evaluated forced outage activities from March 7 t o March 10, 2018
.
 
==71111.22 - Surveillance Testing==
 
The inspectors evaluated the following surveillance tests:
Routine (3 Samples)
: (1) STP-O-16QA , 'A' motor driven auxiliary feedwater pump surveillance test on January 10, 2018
: (2) STP-O-40.5 , national fire protection association emergency diesel generator surveillance test on February 9, 2018
: (3) STP-O-12.1 , 'A' emergency diesel generator surveillance test on February 12, 2018 Inservice (1 Sample)
: (1) STP-O-3QB, containment spray pump 'B' quarterly test on March 20, 2018 RADIATION SAFET Y
 
==71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls==
 
===Radiological Work Planning===
{{IP sample|IP=IP 71124.02|count=1}}
 
The inspectors evaluated Exelon's radiological work planning by reviewing the following activities
The inspectors evaluated Exelon's radiological work planning by reviewing the following activities
: (1) ALARA Plan 2017
:
-1009 (2) ALARA Plan 2017
: (1) ALARA Plan 2017
-1018 (3) ALARA Plan 2017
-1009
: (2) ALARA Plan 2017
-1018
: (3) ALARA Plan 2017
-1036  Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)
-1036  Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)
The inspectors evaluated dose estimates and exposure tracking
The inspectors evaluated dose estimates and exposure tracking
. Implementation of ALARA and Radiological Work Controls (1 Sample)
. Implementation of ALARA and Radiological Work Controls (1 Sample)
The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:
The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:
  (1) ALARA Plan 2017
: (1) ALARA Plan 2017
-1009 (2) ALARA Plan 2017
-1009
-1018 (3) ALARA Plan 2017
: (2) ALARA Plan 2017
-1018
: (3) ALARA Plan 2017
-1036
-1036


==OTHER ACTIVITIES==
==OTHER ACTIVITIES==
- BASELINE  71151 - Performance Indicator Verification The inspectors verified Exelon's performance indicator submittals listed below. (3 Sample s) (1) Unplanned Scrams on March 16, 2018 (2) Unplanned Scrams with Complications on March 16, 2018 (3) Unplanned Power Changes Per 7000 Critical Hours on March 16, 2018 71152 - Problem Identification and Resolution Annual Follow
- BASELINE  71151 - Performance Indicator Verification The inspectors verified Exelon's performance indicator submittals listed below. (3 Sample s)
: (1) Unplanned Scrams on March 16, 2018
: (2) Unplanned Scrams with Complications on March 16, 2018
: (3) Unplanned Power Changes Per 7000 Critical Hours on March 16, 2018
 
==71152 - Problem Identification and Resolution==
 
Annual Follow
-up of Selected Issue s (1 Sample)  The inspectors reviewed the Exelon's implementation of its corrective action program related to the following issues:
-up of Selected Issue s (1 Sample)  The inspectors reviewed the Exelon's implementation of its corrective action program related to the following issues:
  (1) Maintenance Rule availability performance criteria and reliability performance criteria selection in accordance with Exelon procedure ER
: (1) Maintenance Rule availability performance criteria and reliability performance criteria selection in accordance with Exelon procedure ER
-AA-310-1003 Revision 5, on  March 30, 2018. Action Request (AR)04126470 and 02658070
-AA-310-1003 Revision 5, on  March 30, 2018. Action Request (AR)04126470 and 02658070
.
.
71153 - Follow-up of Events and Notices of Enforcement Discretion Events (2 Sample s)  T h e inspectors evaluated response to the following events
71153 - Follow-up of Events and Notices of Enforcement Discretion Events (2 Sample s)  T h e inspectors evaluated response to the following events
. (1) Reactor coolant system leak January 23 through January 27, 2018 (2) Forced outage March 7 to March 10, 2018  Licensee Event Reports (1 Sample)  The inspectors evaluated the following licensee event report which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx
.
: (1) Licensee Event Report (LER) 05000244/2017-001-01, During surveillance testing, lift pressure s et points on three main stream safety valves found outside Technical Specifications limits on March 23, 2018. Revision 0 of this LER was previously closed in Inspection Report 05000244/2017004. Revision 1 updates the LER with the results of the cause evaluation.
: (1) Reactor coolant system leak January 23 through January 27, 2018
: (2) Forced outage March 7 to March 10, 2018  Licensee Event Reports (1 Sample)  The inspectors evaluated the following licensee event report which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx
:
: (1) Licensee Event Report (LER) 05000244/2017-001-01, During surveillance testing, lift pressure s et points on three main stream safety valves found outside Technical Specifications limits on March 23, 2018. Revision 0 of this LER was previously closed in Inspection Report 05000244/2017004. Revision 1 updates the LER with the results of the cause evaluation.


No additional findings were identified. This LER is close d. Personnel Performance (1 Sample)
No additional findings were identified. This LER is close d. Personnel Performance (1 Sample)
  (1) Unplanned plant shutdown March 8 to 9, 2018, due to a current transformer failure on the main generator outgoing power line
: (1) Unplanned plant shutdown March 8 to 9, 2018, due to a current transformer failure on the main generator outgoing power line
. INSPECTION RESULTS Minor Violation 71152 Follow
 
==INSPECTION RESULTS==
Minor Violation 71152 Follow
-up of Selected Issues Minor Violation:  Title 10 of the Code of Federal Regulations (10 CFR) 50.65 (a)(2) allows safety system structure and components to not be monitored under 10 CFR 50 (a)(1), if an adequate demonstration that system performance is being maintained through effective maintenance is provided. In order to demonstrate this, Maintenance Rule availability performance criteria and reliability performance criteria are established and select ed in accordance with Exelon procedure ER
-up of Selected Issues Minor Violation:  Title 10 of the Code of Federal Regulations (10 CFR) 50.65 (a)(2) allows safety system structure and components to not be monitored under 10 CFR 50 (a)(1), if an adequate demonstration that system performance is being maintained through effective maintenance is provided. In order to demonstrate this, Maintenance Rule availability performance criteria and reliability performance criteria are established and select ed in accordance with Exelon procedure ER
-AA-310-1003 , "Maintenance Rule  
-AA-310-1003 , "Maintenance Rule  
Line 139: Line 243:
-AA-310-1003 , Revision 5, constitutes a minor violation that is not subject to enforcement action in accordance with the NRC's Enforcement Policy.
-AA-310-1003 , Revision 5, constitutes a minor violation that is not subject to enforcement action in accordance with the NRC's Enforcement Policy.


EXIT MEETING S AND DEBRIEFS The inspectors verified no proprietary information was retained or documented in this report.
==EXIT MEETING S AND DEBRIEFS==
The inspectors verified no proprietary information was retained or documented in this report.


On March 22, 2018, the inspectors presented the inspection results related to IP 71124.02 to Mr. William Carsky, Site Vice President, and other members of the Ginna staff.
On March 22, 2018, the inspectors presented the inspection results related to IP 71124.02 to Mr. William Carsky, Site Vice President, and other members of the Ginna staff.

Revision as of 01:28, 9 September 2018

R.E. Ginna Nuclear Power Plant, LLC - Integrated Inspection Report 05000244/2018001
ML18122A332
Person / Time
Site: Ginna Constellation icon.png
Issue date: 05/01/2018
From: Michelle Catts
NRC Region 1
To: Bryan Hanson
Exelon Generation Co
References
IR 2018001
Download: ML18122A332 (12)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., Suite 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 May 1, 2018 Mr. Bryan C. Hanson Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT: R.E. GINNA NUCLEAR POWER PLANT, LLC

- INTEGRATED INSPECTION REPORT 05000 244/2018001

Dear Mr. Hanso n:

On March 31, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant, LLC (Ginna)

. On April 16, 2018, the NRC inspectors discussed the results of this inspection with Mr. William Carsky, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading

-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely,/RA/ Michelle Catts , Acting Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Number: 50-244 License Number: D PR-18

Enclosure:

Inspection Report 05000 244/20 18 00 1 cc w/encl:

Distribution via ListServ

ML18 122A322 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME NPerry/AR per tele conv ARosebrook MCatts DATE 0 5/1/18 0 5/1/18 0 5/1/18 1 Enclosure U.S. NUCLEAR REGULATORY COMMISSION Inspection Report Docket Number: 50-244 License Number: DPR-18 Report Number: 05000 244/20 18 00 1 Enterprise Identifier:

I-20 18-001-0045 Licensee: Exelon Generation Company, LLC (Exelon)

Facility: R.E. Ginna Nuclear Power Plant, LLC (Ginna)

Location: Ontario, New York Inspection Dates: January 1, 2018 to March 31, 2018 Inspectors:

N. Perry, Senior Resident Inspector J. Schussler, Resident Inspector A. Rosebrook, Senior Project Engineer H. Anagnostopoulos, Senior Health Physicist S. Obadina, Project Engineer Observer: K. Warner, Health Physicist Approved By:

M. Catts, Acting Chief Reactor Projects Branch 1 Division of Reactor Projects

2

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring

Exelon's performance at Ginna by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

No findings or more-than-minor violations were identified.

Additional Tracking Item s Type Issue number Title Report Section Status LER 05000244/201800 1-00 Leakage in Reactor Coolant System Pressure Boundary N/A Open LER 05000244/2017001

-01 During Surveillance Testing, Lift Pressure Setpoints on Three Main Steam Safety Valves F ound Outside Technical Specification Limits 71153 Open/Closed

3

PLANT STATUS

The unit began the inspection period at 100 percent power and operated at full power until March 8 , 2018, when the unit was shut down to replace a faulty current transformer on the main generator's output line. The unit was returned to rated power on March 13, following replacement of the current transformer, and it remained at or near 100 percent power for the remainder of the inspection period.

INSPECTION SCOPE

S Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading

-rm/doc-collections/insp

-manual/inspection

-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, "Light

-Water Reactor Inspection Program - Operations Phase."

The inspectors performed plant status activities described in IMC 2515 Appendix D, "Plant Status" and conducted routine reviews using IP 71152, "Problem Identification and Resolution."

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon's performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards."

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather

The inspectors evaluated readiness for impending adverse weather conditions for predicted heavy snow accumulation on March 1, 2018

.

71111.04 - Equipment Alignment

Partial Walkdown (3 Sample s) The inspectors evaluated system configuration s during partial walkdowns of the following systems/trains

(1) 'C' standby auxiliary feedwater on January 26, 2018
(2) Turbine-driven auxiliary feedwater on March 9, 2018
(3) 'B' safety injection on March 22, 2018 71111.05Q

- Fire Protection Quarterly Quarterly Inspection (5 Samples) The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Co mpensatory measures during replacement of fire water piping in 'A' emergency diesel generator room on January 17, 2018
(2) 'B' b attery room on February 16, 2018
(3) Intermediate building controlled side basement on March 22, 2018
(4) Intermediate building controlled side top floor on March 30, 2018
(5) Hemyc wrap on March 30, 2 018

71111.06 - Flood Protection Measures

Cables

The inspectors evaluated cable submergence protection in:

(1) Manholes MH1A-01, MH1B-01, MH3-03 West, MH5A

-01, 02 , and 03 on February 19 and 20, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification

The inspectors observed and evaluated a crew of licensed operators in the plant's simulator during licensed operator requalification training, involving a failed steam flow transmitter, trip of a running component cooling water pump, a main steam line leak and a steam generator tube rupture, on February 13, 2018.

Operator Performance (1 Sample) The inspectors observed Control Room operator performance during a lowering water level in the screen house intake on February 13, 2018, power decrease for the turbine-driven auxiliary feedwater run on March 7, 2018

, and start up activities on March 10 to March 13, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions

.

(1) House heating boiler maintenance rule (a)(1) evaluation on March 1, 20 18
(2) Chemical and volume control system (charging) on March 6, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control

==

The inspectors evaluated the risk assessments for the following planned and emergent work activities

(1) Elevated risk for planned under

-voltage testing on electrical bus s es 16 and 17 on February 1, 2018

(2) Atmospheric relief valve 3411 hand-wheel planned replacement on February 27, 2018
(3) 'A' residual heat removal planned maintenance on March 15, 2018
(4) 'C' safety injection pump planned maintenance on March 21 and March 22, 2018
(5) 'A' component cooling water planned maintenance on March 26, 2018

71111.15 - Operability Determinations and Functionality Assessments

==

The inspectors evaluated the following operability determinations and functionality assessments:

(1) 'A' emergency diesel generator due to a ground on a lube oil heater on January 12, 2018
(2) 'B' battery room vault water intrusion on January 31, 2018
(3) Fire suppression system S

-15 alarm inputs on February 13, 2018

(4) Main steam safety valve 351 2 seat leakage on February 28, 2018

71111.19 - Post Maintenance Testing

==

The inspectors evaluated post maintenance testing for the following maintenance/repair activities

(1) Excess letdown divert valve AOV

-312 gag installation on February 12, 2018

(2) 'A' spent fuel pool pump check valve, CV-8655 maintenance, on February 13, 2018
(3) 'A' spent fuel pool pump maintenance and diode replacement on February 16, 2018
(4) 'A' flex diesel air compressor preventive maintenance on February 22, 2018
(5) 'D' service water pump/motor replacement and maintenance on March 3, 2018
(6) 'A' residual heat removal pump/motor alignment on March 15, 2018
(7) Technical support center ventilation fan maintenance on March 22, 2018

71111.20 - Refueling and Other Outage Activities

==

The inspectors evaluated forced outage activities from March 7 t o March 10, 2018

.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine (3 Samples)

(1) STP-O-16QA , 'A' motor driven auxiliary feedwater pump surveillance test on January 10, 2018
(2) STP-O-40.5 , national fire protection association emergency diesel generator surveillance test on February 9, 2018
(3) STP-O-12.1 , 'A' emergency diesel generator surveillance test on February 12, 2018 Inservice (1 Sample)
(1) STP-O-3QB, containment spray pump 'B' quarterly test on March 20, 2018 RADIATION SAFET Y

71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls

Radiological Work Planning

The inspectors evaluated Exelon's radiological work planning by reviewing the following activities

(1) ALARA Plan 2017

-1009

(2) ALARA Plan 2017

-1018

(3) ALARA Plan 2017

-1036 Verification of Dose Estimates and Exposure Tracking Systems (1 Sample)

The inspectors evaluated dose estimates and exposure tracking

. Implementation of ALARA and Radiological Work Controls (1 Sample)

The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:

(1) ALARA Plan 2017

-1009

(2) ALARA Plan 2017

-1018

(3) ALARA Plan 2017

-1036

OTHER ACTIVITIES

- BASELINE 71151 - Performance Indicator Verification The inspectors verified Exelon's performance indicator submittals listed below. (3 Sample s)

(1) Unplanned Scrams on March 16, 2018
(2) Unplanned Scrams with Complications on March 16, 2018
(3) Unplanned Power Changes Per 7000 Critical Hours on March 16, 2018

71152 - Problem Identification and Resolution

Annual Follow

-up of Selected Issue s (1 Sample) The inspectors reviewed the Exelon's implementation of its corrective action program related to the following issues:

(1) Maintenance Rule availability performance criteria and reliability performance criteria selection in accordance with Exelon procedure ER

-AA-310-1003 Revision 5, on March 30, 2018. Action Request (AR)04126470 and 02658070

.

71153 - Follow-up of Events and Notices of Enforcement Discretion Events (2 Sample s) T h e inspectors evaluated response to the following events

.

(1) Reactor coolant system leak January 23 through January 27, 2018
(2) Forced outage March 7 to March 10, 2018 Licensee Event Reports (1 Sample) The inspectors evaluated the following licensee event report which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx
(1) Licensee Event Report (LER) 05000244/2017-001-01, During surveillance testing, lift pressure s et points on three main stream safety valves found outside Technical Specifications limits on March 23, 2018. Revision 0 of this LER was previously closed in Inspection Report 05000244/2017004. Revision 1 updates the LER with the results of the cause evaluation.

No additional findings were identified. This LER is close d. Personnel Performance (1 Sample)

(1) Unplanned plant shutdown March 8 to 9, 2018, due to a current transformer failure on the main generator outgoing power line

INSPECTION RESULTS

Minor Violation 71152 Follow

-up of Selected Issues Minor Violation: Title 10 of the Code of Federal Regulations (10 CFR) 50.65 (a)(2) allows safety system structure and components to not be monitored under 10 CFR 50 (a)(1), if an adequate demonstration that system performance is being maintained through effective maintenance is provided. In order to demonstrate this, Maintenance Rule availability performance criteria and reliability performance criteria are established and select ed in accordance with Exelon procedure ER

-AA-310-1003 , "Maintenance Rule

- Performance Criteria Selection." Section 4.4, "Selecting Reliability Performance Criteria,"

3, "Process for Selecting Reliability Performance Criteria," contains a process to be used in which a criteria greater than or equal to two is acceptable with documentation of past performance. Contrary to the above , two maintenance rule systems contained criteria greater than or equal to two without documentation of past performance in the "Basis and Justification for Criteria Values" section of the maintenance rule basis document.

Thus, an adequate technical basis was not documented for a required 10 CFR 50.65 (a)(2) performance criteria in accordance with Exelon's procedures.

Screening:

The inspectors independently evaluated the deficiency for significance in accordance with the guidance in IMC 0612, Appendix B, "Is sue Screening," issued December 31, 2017, and Appendix E, "Examples of Minor Issues," issued August 11, 2009. The inspectors determined that not documenting the past performance , which was used to determine the reliability criteria

, was a deficiency of minor significance since the criteria selected did not require a maintenance rule a(1) evaluation. As a result it is not subject to enforcement action in accordance with the NRC's enforcement policy. This issue was captured in Exelon's Corrective Action Program as A R 04126470 and 02658070

.

Enforcement:

This failure to comply with procedure ER

-AA-310-1003 , Revision 5, constitutes a minor violation that is not subject to enforcement action in accordance with the NRC's Enforcement Policy.

EXIT MEETING S AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On March 22, 2018, the inspectors presented the inspection results related to IP 71124.02 to Mr. William Carsky, Site Vice President, and other members of the Ginna staff.

On April 16, 2018, the inspector s presented the integrated quarterly resident inspector report inspection results to Mr. William Carsky, Site Vice President and other members of the Ginna staff.

DOCUMENTS REVIEWED

71111.01 - Adverse Weather Protection

Procedures

ER-SC.1, Adverse Weather Plan, Revision 024

71111.05 - Fire Protection

Procedures

A-54.7, Fire Protection Tour, Revision

A-601.13, Fire Protection Compensatory Actions, Revision

FPS-3, Fire Barrier

Inspection Program, Revision

71111.06 - Flood Protection Measures

Condition Reports

04106112 04106114 04106123 Drawings 33013-0014, 34.5KV Duct & Control Duct Plan & Profile, Revision L

Maintenance Orders/Work Orders

WO C 93597827 71111.11 - Licensed Operator Requalification Program

Procedures

HU-AA-1211, Pre-Job Briefings, Revision

OP-AA-101-113-1006, 4.0 Crew Critique Guidelines, Revision

TQ-GI-150-F31 (LORT), Ginna Site Specific License Operator Requalification Training Program, Revision 4 71111.12 - Maintenance Effectiveness

Procedures

ER-AA-310, Implementation of the Maintenance Rule, Revision

1 ER-AA-310-1001, Maintenance Rule

- Scoping, Revision

ER-AA-310-1002, Maintenance Rule Functions

- Safety Significance Classification, Revision

ER-AA-310-1003, Maintenance Rule

- Performance Criteria Selection, Revision 5 ER-AA-310-1004, Maintenance Rule - Performance Monitoring, Revision

ER-AA-310-1005, Maintenance Rule

- Dispositioning Between (A)(1) and (A)(2), Revision 7

Condition Reports

04068393 04083945

0 71111.13 - Maintenance Risk Assessments and Emergent Work Control

Procedures

OP-AA-102-102, General Area Checks and Operator Field Rounds, Revision 15

OP-A A-108-117, Protected

Equipment Program, Revision 5

OPG-PROTECTED-EQUIPMENT, Operations Protected

Equipment Program, Revision

WC-AA-101, On-Line Work Control Process, Revision 27

WC-AA-101-1006, On-Line Risk Management and Assessment, Revision 2

WC-AA-104, Integrated Risk Management, Revision

Condition Reports

04099860 71111.15 - Operability Determinations and Functionality Assessments

Procedures

A-3.3, Containment Integrity Program, Revision 27

OP-AA-108-115, Operability Determinations, Revision 19

Condition Reports

2534565 04091493 04096584 04099235 04101267 04108798* Miscellaneous

ECP-17-000051, Technical Evaluation of Lube Oil Heaters, Revision 0

OPEVAL-15-008, 64 - 125 VDC Electrical System SR, 65

- Diesel Generator Emergency Power System, Revision 1

OPEVAL-18-001, S/G 'B' Main Steam Safety Valve 3512, Revision 1

71152 - Problem Identification and Resolution

Procedures

ER-AA-310, Implementation of the Maintenance Rule, Revision 11

ER-AA-310-1003, Maintenance Rule

- Performance Criteria Selection, Revision 5

ER-AA-310-1004, Maintenance Rule

- Performance Monitoring, Revision 14

ER-AA-310-1005, Maintenance Rule

- Dispositioning Between (a)(1) and (a)(2), Revision 7

PI-AA-120, Issue Identification and Screening Process, Revision 7

PI-AA-125, Corrective Action Program (CAP) Procedure, Revision

Condition Reports (*initiated in response to inspection)

AR 02658070

AR 04126470

Procedures

A-80, Startup Readiness Control, Revision019

AP-TURB.5, Rapid Load Reduction, Revision 018

Condition Reports

04096294 04097619 Maintenance Orders/Work Orders

WO C93654311

UNITED STATES NUCLEAR REGULATORY COMMISSION

REGION I 2100 RENAISSANCE BLVD., Suite 100

KING OF PRUSSIA, PENNSYLVANIA

19406-2713 May 1, 2018 Mr. Bryan C. Hanson

Senior Vice President, Exelon Generation Company, LLC

President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

R.E. GINNA NUCLEAR POWER PLANT, LLC

- INTEGRATED INSPECTION REPORT 05000 244/2018001 Dear Mr. Hanso n: On March 31, 2018, the

U.S. Nuclear Regulatory Commission (NRC) completed an inspection at R.E. Ginna Nuclear Power Plant, LLC (Ginna)

. On April 16, 2018, the NRC inspectors discussed the results of this inspection with Mr. William Carsky, Site Vice President and other

members of your staff. The results of this inspection are documented in the enclosed report.

The NRC inspectors did not identify any finding or violation of more than minor significance.

This letter, its enclosure, and your response (if any) will be made

available for public inspection and copying at http://www.nrc.gov/reading

-rm/adams.html

and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations

(10 CFR), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."

Sincerely, /RA/ Michelle Catts , Acting Chief Reactor Projects Branch

Division of Reactor Projects

Docket Number: 50-244 License Number: D PR-18 Enclosure:

Inspection Report

05000 244/20 18 00 1 cc w/encl:

Distribution via ListServ

ML18 122A322 SUNSI Review

Non-Sensitive Sensitive Publicly Available

Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME NPerry/AR per tele conv ARosebrook

MCatts DATE 0 5/1/18 0 5/1/18 0 5/1/18

Enclosure U.S. NUCLEAR REGULATORY COMMISSION

Inspection Report

Docket Number: 50-244 License Number: DPR-18 Report Number: 05000 244/20 18 00 1 Enterprise Identifier:

I-20 18-001-0045 Licensee: Exelon Generation Company, LLC (Exelon)

Facility:

R.E. Ginna Nuclear Power Plant, LLC (Ginna)

Location: Ontario, New York

Inspection Dates: January 1, 2018

to March 31, 2018

Inspectors:

N. Perry, Senior Resident Inspector
J. Schussler, Resident Inspector
A. Rosebrook, Senior Project

Engineer

H. Anagnostopoulos, Senior Health Physicist
S. Obadina, Project Engineer

Observer:

K. Warner, Health Physicist

Approved By:

M. Catts, Acting Chief Reactor Projects Branch

Division of Reactor Projects

SUMMARY The U.S. Nuclear Regulatory Commission (NRC) continued monitoring

Exelon's performance at Ginna by conducting the baseline inspections described in this report

in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for

overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html

for more information.

No findings

or more-than-minor violations

were identified.

Additional Tracking Item s Type Issue number

Title Report Section Status LER 05000244/201800

1-00 Leakage in

Reactor Coolant System Pressure Boundary N/A Open LER 05000244/2017001

-01 During Surveillance

Testing, Lift Pressure Setpoints on

Three Main Steam Safety Valves F ound Outside Technical Specification

Limits 71153 Open/Closed

PLANT STATUS

The unit began the inspection period at 100 percent power and operated at full power until March 8 , 2018, when the unit was shut down to replace a faulty current transformer on the main generator's output line. The unit was returned to rated power on March 13, following replacement of the current transformer, and it remained at or near 100 percent power for the remainder of the inspection period.

INSPECTION SCOPE

S Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading

-rm/doc-collections/insp

-manual/inspection

-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, "Light

-Water Reactor Inspection Program - Operations Phase."

The inspectors performed plant status activities described in IMC 2515 Appendix

DProperty "Inspection Manual Chapter" (as page type) with input value "NRC Inspection Manual 2515 Appendix</br></br>D" contains invalid characters or is incomplete and therefore can cause unexpected results during a query or annotation process., "Plant Status" and conducted routine reviews using IP 71152, "Problem Identification and Resolution."

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon's performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards."

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Impending Severe Weather

(1 Sample) The inspectors evaluated readiness for impending adverse weather conditions for predicted heavy snow accumulation

on March 1, 2018

. 71111.04 - Equipment Alignment

Partial Walkdown

(3 Sample s) The inspectors evaluated system configuration

s during partial walkdowns of the following systems/trains

(1) 'C' standby auxiliary feedwater

on January 26, 2018

(2) Turbine-driven auxiliary feedwater on March 9, 2018

(3) 'B' safety injection on March 22, 2018

71111.05Q

- Fire Protection Quarterly

Quarterly Inspection

(5 Samples) The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Co mpensatory measures during replacement of fire water piping in 'A' emergency diesel generator room on January

17, 2018 (2) 'B' b attery room on February 16, 2018

(3) Intermediate building controlled side basement on March 22, 2018

(4) Intermediate building controlled side top floor

on March 30, 2018

(5) Hemyc wrap on March 30, 2

018 71111.06 - Flood Protection Measures

Cables (1 Sample) The inspectors evaluated cable submergence protection in:

(1) Manholes MH1A-01, MH1B-01, MH3-03 West, MH5A

-01, 02 , and 03 on February 19 and 20, 2018.

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification

(1 Sample) The inspectors observed and evaluated a crew of licensed operators in the plant's simulator during licensed operator requalification training, involving a failed steam flow transmitter, trip of a running component cooling water pump, a main steam line leak

and a steam generator tube rupture, on February 13, 2018.

Operator Performance

(1 Sample) The inspectors

observed Control Room

operator performance during a lowering water level in the screen house intake on February 13, 2018, power decrease for the turbine-driven auxiliary feedwater run

on March 7, 2018

, and start up activities on March 10

to March 13, 2018. 71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness

(2 Samples) The inspectors evaluated

the effectiveness of routine

maintenance activities associated with the following equipment and/or safety significant functions

. (1) House heating boiler

maintenance rule (a)(1) evaluation on March 1, 20

(2) Chemical and volume control system (charging) on March 6, 2018

71111.13 - Maintenance Risk Assessments and Emergent Work Control

(5 Samples) The inspectors evaluated the risk assessments for the following planned and emergent work activities

(1) Elevated risk for planned under

-voltage testing on electrical bus

s es 16 and 17 on

February 1, 2018

(2) Atmospheric relief valve

3411 hand-wheel planned replacement on February 27, 2018

(3) 'A' residual heat removal

planned maintenance on March 15, 2018

(4) 'C' safety injection pump planned maintenance on March 21 and

March 22, 2018

(5) 'A' component cooling water

planned maintenance on March 26, 2018

71111.15 - Operability Determinations and Functionality Assessments

(4 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) 'A' emergency diesel generator due to a ground on

a lube oil heater on January 12, 2018

(2) 'B' battery room vault water

intrusion on January 31, 2018

(3) Fire suppression system S

-15 alarm inputs on February 13, 2018

(4) Main steam safety valve

351 2 seat leakage on February 28, 2018

71111.19 - Post Maintenance Testing

(7 Samples) The inspectors evaluated

post maintenance testing for the following maintenance/repair activities

(1) Excess letdown divert valve AOV

-312 gag installation on February 12, 2018

(2) 'A' spent fuel pool

pump check valve, CV-8655 maintenance, on February 13, 2018

(3) 'A' spent fuel pool

pump maintenance and diode replacement on February 16, 2018

(4) 'A' flex diesel air compressor preventive maintenance on February 22, 2018

(5) 'D' service water pump/motor replacement and maintenance on March 3, 2018

(6) 'A' residual heat removal

pump/motor

alignment on March 15, 2018

(7) Technical support center

ventilation fan

maintenance

on March 22, 2018

71111.20 - Refueling and Other Outage Activities

(1 Sample) The inspectors evaluated forced outage activities

from March 7 t o March 10, 2018

. 71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine (3 Samples) (1) STP-O-16QA , 'A' motor driven auxiliary feedwater

pump surveillance test

on January 10, 2018 (2) STP-O-40.5 , national fire protection association

emergency diesel generator

surveillance test on February 9, 2018

(3) STP-O-12.1 , 'A' emergency diesel generator

surveillance test on February 12, 2018

Inservice (1 Sample)

(1) STP-O-3QB, containment spray pump 'B' quarterly test on March 20, 2018

RADIATION SAFET

Y 71124.02 - Occupational As Low As Reasonably Achievable (ALARA) Planning and Controls

Radiological Work Planning

(1 Sample)

The inspectors evaluated Exelon's radiological work planning by reviewing the following activities

(1) ALARA Plan 2017

-1009 (2) ALARA Plan 2017

-1018 (3) ALARA Plan 2017

-1036 Verification of Dose Estimates and Exposure Tracking

Systems (1 Sample)

The inspectors

evaluated dose estimates and

exposure tracking

. Implementation of ALARA and Radiological Work Controls

(1 Sample)

The inspectors reviewed ALARA practices and radiological work controls by reviewing the following activities:

(1) ALARA Plan 2017

-1009 (2) ALARA Plan 2017

-1018 (3) ALARA Plan 2017

-1036 OTHER ACTIVITIES

- BASELINE 71151 - Performance Indicator Verification

The inspectors verified Exelon's performance

indicator submittals

listed below. (3 Sample s) (1) Unplanned Scrams on March 16, 2018

(2) Unplanned Scrams with Complications

on March 16, 2018

(3) Unplanned

Power Changes Per 7000 Critical Hours

on March 16, 2018 71152 - Problem Identification and Resolution

Annual Follow

-up of Selected Issue s (1 Sample) The inspectors reviewed the Exelon's

implementation of its corrective action program related

to the following issues:

(1) Maintenance Rule availability performance criteria and reliability performance criteria selection in accordance with Exelon procedure ER

-AA-310-1003 Revision 5, on March 30, 2018. Action Request (AR)

04126470 and 02658070

.

71153 - Follow-up of Events

and Notices of Enforcement Discretion

Events (2 Sample s) T h e inspectors evaluated response to the following events

. (1) Reactor coolant system

leak January 23

through January 27, 2018 (2) Forced outage March 7 to

March 10, 2018 Licensee Event Reports (1 Sample) The inspectors evaluated the following licensee event report which can be accessed at https://lersearch.inl.gov/LERSearchCriteria.aspx

(1) Licensee Event Report (LER) 05000244/2017-001-01, During surveillance testing, lift

pressure s et points on three main stream

safety valves found outside Technical Specifications

limits on March 23, 2018. Revision 0 of this LER was previously closed in Inspection Report 05000244/2017004. Revision 1 updates the LER with the results of the cause evaluation.

No additional findings were identified. This LER is close d. Personnel Performance

(1 Sample)

(1) Unplanned plant shutdown March 8

to 9, 2018, due to a current transformer failure

on the main generator outgoing power line

. INSPECTION RESULTS

Minor Violation

71152 Follow

-up of Selected Issues Minor Violation: Title 10 of the Code of Federal Regulations

(10 CFR) 50.65 (a)(2) allows safety system structure and components to not be monitored under 10 CFR 50 (a)(1), if an adequate demonstration that system performance is being maintained through effective maintenance is provided. In order to demonstrate this, Maintenance Rule availability performance criteria and reliability performance criteria are established and select ed in accordance with Exelon procedure ER

-AA-310-1003 , "Maintenance Rule

- Performance Criteria Selection." Section 4.4, "Selecting Reliability Performance Criteria,"

3, "Process for Selecting Reliability Performance Criteria," contains a process to be used in which a criteria greater than or equal to two is acceptable with documentation of past performance. Contrary to the above , two maintenance rule systems contained criteria greater than or equal to two without documentation of past performance in the "Basis and Justification for Criteria Values" section of the maintenance rule basis document.

Thus, an adequate technical basis was not documented

for a required 10 CFR 50.65 (a)(2) performance criteria in accordance with Exelon's procedures.

Screening:

The inspectors independently evaluated the deficiency for significance in accordance with the guidance in IMC 0612, Appendix B, "Is

sue Screening," issued December 31, 2017, and Appendix E, "Examples of Minor Issues," issued August 11, 2009. The inspectors determined that not documenting the past performance , which was used to determine the reliability criteria

, was a deficiency of minor significance since the criteria

selected did not require a maintenance rule a(1) evaluation. As a result it is not subject to enforcement action in accordance with the NRC's enforcement

policy. This issue was captured in Exelon's Corrective Action Program

as A R 04126470 and 02658070

. Enforcement: This failure to comply with procedure ER

-AA-310-1003 , Revision 5, constitutes a minor violation that is not subject to enforcement action in accordance with the NRC's Enforcement Policy.

EXIT MEETING S AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On March 22, 2018, the inspectors presented the inspection results related to IP 71124.02 to Mr. William Carsky, Site Vice President, and other members of the Ginna staff.

On April 16, 2018, the inspector

s presented the integrated quarterly resident inspector report inspection results to Mr. William Carsky, Site Vice President

and other members of the Ginna staff.

DOCUMENTS REVIEWED

71111.01 - Adverse Weather Protection

Procedures

ER-SC.1, Adverse Weather Plan, Revision 024

71111.05 - Fire Protection

Procedures

A-54.7, Fire Protection Tour, Revision

A-601.13, Fire Protection Compensatory Actions, Revision

FPS-3, Fire Barrier

Inspection Program, Revision

71111.06 - Flood Protection Measures

Condition Reports

04106112 04106114 04106123 Drawings 33013-0014, 34.5KV Duct & Control Duct Plan & Profile, Revision L

Maintenance Orders/Work Orders

WO C 93597827 71111.11 - Licensed Operator Requalification Program

Procedures

HU-AA-1211, Pre-Job Briefings, Revision

OP-AA-101-113-1006, 4.0 Crew Critique Guidelines, Revision

TQ-GI-150-F31 (LORT), Ginna Site Specific License Operator Requalification Training Program, Revision 4 71111.12 - Maintenance Effectiveness

Procedures

ER-AA-310, Implementation of the Maintenance Rule, Revision

1 ER-AA-310-1001, Maintenance Rule

- Scoping, Revision

ER-AA-310-1002, Maintenance Rule Functions

- Safety Significance Classification, Revision

ER-AA-310-1003, Maintenance Rule

- Performance Criteria Selection, Revision 5 ER-AA-310-1004, Maintenance Rule - Performance Monitoring, Revision

ER-AA-310-1005, Maintenance Rule

- Dispositioning Between (A)(1) and (A)(2), Revision 7

Condition Reports

04068393 04083945

0 71111.13 - Maintenance Risk Assessments and Emergent Work Control

Procedures

OP-AA-102-102, General Area Checks and Operator Field Rounds, Revision 15

OP-A A-108-117, Protected

Equipment Program, Revision 5

OPG-PROTECTED-EQUIPMENT, Operations Protected

Equipment Program, Revision

WC-AA-101, On-Line Work Control Process, Revision 27

WC-AA-101-1006, On-Line Risk Management and Assessment, Revision 2

WC-AA-104, Integrated Risk Management, Revision

Condition Reports

04099860 71111.15 - Operability Determinations and Functionality Assessments

Procedures

A-3.3, Containment Integrity Program, Revision 27

OP-AA-108-115, Operability Determinations, Revision 19

Condition Reports

2534565 04091493 04096584 04099235 04101267 04108798* Miscellaneous

ECP-17-000051, Technical Evaluation of Lube Oil Heaters, Revision 0

OPEVAL-15-008, 64 - 125 VDC Electrical System SR, 65

- Diesel Generator Emergency Power System, Revision 1

OPEVAL-18-001, S/G 'B' Main Steam Safety Valve 3512, Revision 1

71152 - Problem Identification and Resolution

Procedures

ER-AA-310, Implementation of the Maintenance Rule, Revision 11

ER-AA-310-1003, Maintenance Rule

- Performance Criteria Selection, Revision 5

ER-AA-310-1004, Maintenance Rule

- Performance Monitoring, Revision 14

ER-AA-310-1005, Maintenance Rule

- Dispositioning Between (a)(1) and (a)(2), Revision 7

PI-AA-120, Issue Identification and Screening Process, Revision 7

PI-AA-125, Corrective Action Program (CAP) Procedure, Revision

Condition Reports (*initiated in response to inspection)

AR 02658070

AR 04126470

Procedures

A-80, Startup Readiness Control, Revision019

AP-TURB.5, Rapid Load Reduction, Revision 018

Condition Reports

04096294 04097619 Maintenance Orders/Work Orders

WO C93654311