W3F1-2002-0017, January 2002 Monthly Operating Report for Waterford 3 Ses
| ML020640375 | |
| Person / Time | |
|---|---|
| Site: | Waterford |
| Issue date: | 02/14/2002 |
| From: | Brandon M Entergy Operations |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| W3F1-2002-0017 | |
| Download: ML020640375 (5) | |
Text
Entergy Operations, Inc.
17265 River Road Killona, LA 70066 tergyTel 504 739 6650 W3F 1-2002-0017 A4.05 PR February 14, 2002 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555
Subject:
Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:
Attached is the subject report which covers the operating statistics for the month of January, 2002. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.
Due to minor errors in the spreadsheets used in 2001 for calculating Gross Thermal Energy Generated (MWHt), the values reported in the December 2001 Monthly Operating Report were slightly higher than the actuals. This error resulted in the Gross Thermal Energy Generated values reported in the December 2001 Monthly Operating Report being approximately 0.01 % higher than the actuals. The corrected Year To Date value (actual) is 29,441,069 MWHt vice the reported 29,444,278 MWHt, and the corrected Cummulative value (actual) is 402,097,036 MWHt vice the reported 402,100,245 MWHt. Data reported prior to 2001 are not impacted.
Monthly Operating Report W3F 1 -2002-0017 Page 2 February 14, 2002 There are no commitments associated with this submittal. Should you have any questions regarding the above, please contact T.M. Manzella at (504) 739-6882.
Very truly yours, M.K. Brandon Manager, Licensing MKB/TMM/cbh Attachment cc:
E.W. Merschoff (NRC Region IV),
N. Kalyanam (NRC-NRR),
J. Smith, N.S. Reynolds, B. Lewis (Utility Data Institute, Inc.),
lerevents@inpo.org - INPO Records Center, NRC Resident Inspectors Office
NRC MONTHLY OPERATING REPORT
SUMMARY
OF OPERATIONS WATERFORD 3 for January, 2002 The unit operated at an average reactor power level of 99.8% and experienced no shutdowns or significant power reductions during the period.
Page : 1 of 6 2/5/02
PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES WATERFORD 3 for January, 2002 There were no pressurizer safety valve failures or challenges experienced during the month.
2/5/02 Page : 2 of 6
OPERATING DATA REPORT DOCKET NUMBER:
UNIT NAME:
DATE OF REPORT:
COMPLETED BY:
TELEPHONE:
50-382 WATERFORD 3 February 5, 2002 Jim Pollock (504) 739-6561 OPERATING STATUS
- 1. Reporting Period Gross Hours in Reporting Period
- 2. Currently Authorized Power Level (MWt)
Maximum Dependable Capacity (Net MWe)
Design Electrical Rating (Net MWe)
- 3. Power Level to which Restricted (if any) (Net
- 4. Reason for Restriction (if any)
January, 2002 744 3,390 1,075 1,104 MWe)
N/A Number of Hours Reactor was Critical Reactor Reserve Shutdown Hours Hours Generator was On-line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)
Gross Electrical Energy Generated (MWH)
Net Electrical Energy Generated (MWH)
Reactor Service Factor Reactor Availability Factor Unit Service Factor Unit Availability Factor Unit Capacity Factor (using MDC)
Unit Capacity Factor (using DER)
Unit Forced Outage Rate THIS MONTH 744.0 0.0 744.0 0.0 2,518,017 855,135 821,080 100.0 100.0 100.0 100.0 102.7 100.0 0.0 YEAR TO DATE 744.0 0.0 744.0 0.0 2,518,017 855,135 821,080 100.0 100.0 100.0 100.0 102.7 100.0 0.0 CUMULATIVE 122,827.4 0.0 121,568.7 0.0 404,615,053 135,650,952 129,553,386 85.7 85.7 84.8 84.8 84.1 81.8 3.9 Page: 3 of 6 N/A