u 0 FPL Energy Seabrook Station FPL Energy P.O. Box 300 Seabrook, NH 03874 Seabrook Station (603) 773-7000 OCT 2 9 2004 Docket No. 50-443 SBK-L-04090 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 Seabrook Station Confirmation of Implementation of Orders EA-03-039 and EA-03-086 The NRC issued Orders dated April 29, 2003: EA-03-038, Order for Compensatory Measures Related to Fitness-For-Duty Enhancements Applicable to Nuclear Facility Security Force Personnel; EA-03-039, Order for Compensatory Measures Related to Training Enhancements on Tactical and Firearms Proficiency and Physical Fitness Applicable to Armed Nuclear Power Plant Security Force Personnel; and EA-03-086, Order Requiring Compliance with Revised Design Basis Threat (collectively referred to as "Orders") for Seabrook Station. In addition to other requirements, the Orders required nuclear power plant licensees to revise their physical security plans, safeguards contingency plans, and security force training and qualification plans; submit those plans to the NRC for approval by April 29, 2004; and complete implementation of those plans by October 29, 2004, unless a request for a schedule extension for one or more elements of those plans was approved by the NRC.
On April 28, 2004, FPL Energy Seabrook, LLC filed a Supplemental Response to Order EA 086 that contained the Physical Security Plan, the Contingency Plan, and the Training and Qualification Plan as required by Order EA-03-086 for Seabrook Station.Section III.C. of Order EA-03-086 required FPL Energy Seabrook, LLC to advise the NRC when implementation of the NRC approved physical security plans, safeguards contingency plans, and general training and qualification plans has been accomplished. Section Ill.C.2. of Order EA-03-39 required FPL Energy Seabrook LLC to advise the NRC when full compliance with the requirements in to that Order has been achieved.
FPL Energy Seabrook, LLC hereby certifies that conditions of Order EA-03-086 as amended through October 29, 2004, have been met contingent on NRC review and approval of the Physical Security Plan, the Contingency Plan, and the Training and Qualification Plan.
an FPL Group company
U.S. Nuclear Regulatory Commission SBK-L-04090 / Page 2 FPL Energy Seabrook, LLC hereby certifies that conditions of Order EA-03-039 have been met.
Should you have any questions regarding this report, please contact James M. Peschel, Regulatory Programs Manager, at (603) 773-7194.
Very truly yours, FPL Energy Seabrook, LLC Mark E. Warner Site Vice President cc:
S. J. Collins, NRC Region I Administrator S. P. Wall, NRC Project Manager, Project Directorate I-2 G.T. Dentel, NRC Senior Resident Inspector
U.S. Nuclear Regulatory Commission SBK-L-04090 / Page 3 OATH AND AFFIRMATION In accordance with 10 CFR § 2.202(b), the following affirmation is provided:
I, Gene F. St. Pierre, Station Director of Seabrook Station, am authorized to execute this oath on behalf of FPL Energy Seabrook, LLC and, to the best of my knowledge and belief, the facts set forth in this letter are true.
Sworn and Subscribed before me this O) dayof 2004 Notary Public
-~
~
~
co
-~
FEI AC Gene F. St.Pierre Station Director
r "
i SBK-L-04090 CONFIRMATION OF IMPLEMENTATION OF ORDER EA-03-086 Dryden, M. S.
e-mail Mashhadi, M.
e-mail Giarrusso Jr., J.
e-mail Ross, M. S.
e-mail Weaver, R. C.
e-mail Guldemond, W.G.
e-mail Letter Distribution e-mail File 0018 01-48 RMD 02-06