RC-17-0161, Submittal of Change of the Commitment Date of DRIB/105A&B Door

From kanterella
Jump to navigation Jump to search
Submittal of Change of the Commitment Date of DRIB/105A&B Door
ML17333A966
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/28/2017
From: Lippard G
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
IR 2016007, RC-17-0161
Download: ML17333A966 (3)


Text

SCE&G George A. Lippard Vice President, Nuclear Operations 803.345.4810 A SCANA COMPANY November 28, 2017 RC-17-0161 Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001

Dear Sir / Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS) UNIT 1 DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 CHANGE OF THE COMMITMENT DATE OF DRIB/105A&B DOOR SUBMITTAL

References:

1. George A. Lippard (SCE&G) to NRC Document Control Desk, "Reply to a Notice of Violation" dated December 20, 2016, (RC-16-0173)

[ML16355A277]

2. George A. Lippard (SCE&G) to NRC Document Control Desk, "Change of the Commitment Date of DRIB/105A&B Door Submittal" dated April 13, 2017, (RC-17-0049) [ML17103A535]
3. Bradley J. Davis, Acting Chief, NRC, to George Lippard, SCE&G, "NRC Problem Identification and Resolution Inspection Report 05000395/2016007 and Notice of Violation" dated November 22, 2016,

[ML16327A378]

South Carolina Electric & Gas Company (SCE&G), acting for itself and as an agent for South Carolina Public Service Authority (Santee Cooper), is providing notification of an intended change to a commitment date. Specifically, SCE&G identified in Reference 1 that a License Amendment Request (LAR) identifying DRIB/105A&B as doors that have been evaluated for variances from NFPA 80 requirements would be submitted. In Reference 2, SCE&G identified that the submittal would be made by November 30, 2017.

Since the original commitment was made and updated in References 1 and 2, SCE&G has identified the need for further efforts to provide additional information in the LAR submittal. The LAR will: (1) update the Fire Probabilistic Risk Assessment (Table W')

to correct modeling errors; (2) address de-scoped plant modifications; (3) identify DRIB/105A&B as doors that have been evaluated for variances from NFPA 80 requirements; and (4) revise documentation impacted by the changes. SCE&G will submit the LAR by June 30, 2018. An updated commitment is attached.

SCE&G l V.C. Summer Nuclear Station

  • P.O. Box 88

Document Control Desk CR-16-05919 RC-17-0161 Page 2 of 2 If there are any questions or if additional information is needed, please contact Mr. Bruce L. Thompson at (803) 931-5042.

Executed on JRB/GAL/nrk

Attachment:

Updated Commitment c:

K. B. Marsh J. E. Addison S. A. Byrne W. K. Kissam J. B. Archie W. M. Cherry L. W. Harris P. Ledbetter C. Haney G. J. Lindamood RTS (CR-16-05919)

File (815.01)

K. M. Sutton NRC Resident Inspector NSRC J. H. Hamilton S. A. Williams PRSF (RC-17-0161)

Document Control Desk Attachment CR-16-05919 RC-17-0161 Page 1 of 1 VIRGIL C. SUMMER NUCLEAR STATION (VCSNS)

DOCKET NO. 50-395 OPERATING LICENSE NO. NPF-12 ATTACHMENT UPDATED COMMITMENT Commitment Due Date/Event VCSNS will submit a LAR to: (1) update the Fire Probabilistic Risk Assessment (Table W') to correct modeling errors; (2) address de-scoped plant modifications; (3) identify DRIB/105A&B as doors that have been evaluated for variances from NFPA 80 requirements; and (4) revise documentation impacted by the changes.

June 30, 2018