| | Start date | Site | Title |
|---|
| IR 05000254/2025002 | 14 August 2025 | Quad Cities | Reissue Quad Cities Nuclear Power Station Integrated Inspection Report 05000254/2025002 and 05000265/2025002 |
| ML25224A046 | 12 August 2025 | Quad Cities | Integrated Inspection Report 05000254/2025002 and 05000265/2025002 |
| ML24046A124 | 29 February 2024 | Oyster Creek | – NRC Inspection Report 05000219/2023003 |
| ML23277A108 | 15 February 2024 | | Enclosure 3 - Regulatory Analysis of Advance Tribal Notification |
| ML25035A097 | 9 January 2024 | | Headquarters Operations Officer (HOO) Training Procedure T.1 |
| ML23200A223 | 19 July 2023 | | Hps Am 2023 - a Day in the Life of a HOO - H. Crouch |
| ML23061A071 | 4 May 2023 | | NSIR Fisma System (NFS) - Privacy Impact Assessment (Pia) |
| ML23048A096 | 16 March 2023 | | OMB 3150-0219, Draft Clearance Renewal Suspicious Activity Reporting Using the Protected Web Server (PWS) PWS Screenshots |
| IR 05000219/2022002 | 9 February 2023 | Oyster Creek | NRC Inspection Report No. 05000219/2022002 |
| IR 07200001/2021401 | 27 September 2021 | 07200001 | GE-Hitachi Morris (Gehmo) Independent Spent Fuel Storage Installation - NRC Security Inspection Report 07200001/2021401 |