NRC ACCEPTS INSPECTOR GENERAL FINDINGS REGARDING HEMYC FIRE BARRIER TESTING The Nuclear Regulatory Commission staff is working to address the findings of a special inquiry from the agencys Inspector General into the agencys actions to confirm the acceptability of the fire barrier material Hemyc. A few U.S. nuclear power plants use this material to protect electrical cables that enable a plant to shut down safely.
We agree with the IG - the staff could have acted more promptly in investigating what turned out to be Hemycs limited ability to protect important electrical systems, said Jim Dyer, Director of the NRCs Office of Nuclear Reactor Regulation. We remain convinced, however, that every U.S. plants overall fire protection program ensures it can shut down safely. The staff is reviewing the IG findings to determine how we can improve our performance in the future.
The NRC requires U.S. nuclear power plants to protect their safety-related systems against fires. The agency updated these requirements in 1981 following a fire at the Browns Ferry nuclear power plant in 1975. The first use of Hemyc as an electrical cable fire barrier to meet NRC requirements was in 1983, based on the manufacturers test data. Today, there are 16 reactors (out of 104) using the material.
Under the NRCs direction, the National Institute of Standards and Technology conducted a small-scale test in 1993 that called into question Hemycs fire endurance. NRC staff efforts did not produce a follow-up test until April 2005, with the results failing to confirm the manufacturers assertion that Hemyc could act as a one-hour fire barrier. The staff then issued a Generic Letter in 2006 (http://www.nrc.gov/reading-rm/doc-collections/gen-comm/gen-letters/2006/gl200603.pdf) requiring all U.S. nuclear power plants to document how the plants will resolve the Hemyc issue.
The IG found the staff has yet to budget or schedule any inspections specifically reviewing plants Hemyc resolution efforts. The staff points out, however, that it has found all the Generic Letter responses acceptable, and that two ongoing programs will continue to ensure the Hemyc issue does not affect fire protection safety:
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415-8200 Washington, D.C. 20555-0001 E-mail: opa@nrc.gov Site: http://www.nrc.gov No. 08-12 January 25, 2008
- continuing staff oversight of the Shearon Harris plants first-of-its-kind transition to a risk-informed fire protection program, where all aspects of existing protection, including Hemyc, are reviewed;
- routine reviews of plant fire protection by NRC inspectors.
The IG also found no evidence of additional Hemyc tests between April 2005 and December 2007, but the staff notes that Progress Energy conducted such tests in 2005 and 2006.
The staff will continue to monitor the Hemyc issue to ensure nuclear power plants properly protect their safety-related systems against fires.
The IG Special Inquiry is available on the NRCs Web site at:
http://www.nrc.gov/reading-rm/doc-collections/insp-gen/2008/. A staff memo listing all plant responses to the generic letter, including whether a plant is using Hemyc, is available by entering ML073470708 on this Web page: http://adamswebsearch.nrc.gov/dologin.htm.
News releases are available through a free listserv subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.