Letter Sequence Supplement |
|---|
TAC:ME0219, Control Room Habitability, Revise Control Room Habitability Actions to Address Lessons Learned from TSTF-448 Implementation (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEARML0835703382008-12-0808 December 2008 Transmittal of ARCON96 and Radtrad Cds Supporting Alternative Source Term License Amendment Request 241 Project stage: Request NRC 2008-0085, Transmittal of ARCON96 and Radtrad Cds Supporting Alternative Source Term License Amendment Request 2412008-12-0808 December 2008 Transmittal of ARCON96 and Radtrad Cds Supporting Alternative Source Term License Amendment Request 241 Project stage: Request NRC 2008-0081, Submittal of License Amendment Request 241, Alternative Source Term2008-12-0808 December 2008 Submittal of License Amendment Request 241, Alternative Source Term Project stage: Request NRC 2009-0002, Supplement to License Amendment Request 241, Summary of Pbnp Sump Ph Calculation Inputs, Assumptions, Methodology and Results2009-01-16016 January 2009 Supplement to License Amendment Request 241, Summary of Pbnp Sump Ph Calculation Inputs, Assumptions, Methodology and Results Project stage: Supplement NRC 2009-0006, Supplement to License Amendment Request 241 Transmittal of Proposed License Conditions2009-01-27027 January 2009 Supplement to License Amendment Request 241 Transmittal of Proposed License Conditions Project stage: Supplement ML0903707702009-01-28028 January 2009 Email Regarding Need Supplemental Information for AST Acceptance Review from Containment and Ventilation Branch Project stage: Acceptance Review NRC 2009-0023, Supplement to License Amendment Request 241 Alternative Source Term2009-02-20020 February 2009 Supplement to License Amendment Request 241 Alternative Source Term Project stage: Supplement NRC 2009-0001, Calculation Project Schedule Update2009-02-20020 February 2009 Calculation Project Schedule Update Project stage: Request ML0905501512009-02-27027 February 2009 Acceptance Review for License Amendment Request 241 Alternate Source Term Project stage: Acceptance Review ML0907110612009-03-20020 March 2009 Request for Additional Information from Csgb Branch Related to License Amendment Request No. 241 Alternate Source Term Project stage: RAI ML0835309302009-03-25025 March 2009 FPL Energy Point Beach, LLC - Request for Withholding of Proprietary Information from Public Disclosure for Point Beach Nuclear Plant, Units 1 and 2 Project stage: Withholding Request Acceptance NRC 2009-0039, Response to Request for Additional Information License Amendment Request 241, Alternative Source Term2009-04-17017 April 2009 Response to Request for Additional Information License Amendment Request 241, Alternative Source Term Project stage: Response to RAI NRC 2009-0045, Supplement to License Amendment Request 241, Proposed Technical Specifications for Primary Auxiliary Building Ventilation (Vnpab)2009-04-17017 April 2009 Supplement to License Amendment Request 241, Proposed Technical Specifications for Primary Auxiliary Building Ventilation (Vnpab) Project stage: Supplement NRC 2009-0032, License Amendment Request 250, Corporation Name Change2009-04-17017 April 2009 License Amendment Request 250, Corporation Name Change Project stage: Request ML0909007222009-04-22022 April 2009 Request for Additional Information from Emcb Regarding License Amendment Request No. 241 Alternate Source Term Project stage: RAI NRC 2009-0026, Transmittal of Supplement to License Amendment Request 241 Regulatory Guide 1.183 Compliance Matrix2009-05-0808 May 2009 Transmittal of Supplement to License Amendment Request 241 Regulatory Guide 1.183 Compliance Matrix Project stage: Supplement ML0911105842009-05-13013 May 2009 Request for Additional Information from Reactor Systems Branch Regarding License Amendment Request No. 241 Alternate Source Term Project stage: RAI NRC 2009-0054, Response to Request for Additional Information License Amendment Request 241 Alternative Source Term2009-05-15015 May 2009 Response to Request for Additional Information License Amendment Request 241 Alternative Source Term Project stage: Response to RAI ML0916205602009-06-25025 June 2009 Request for Additional Information from the Human Performance Branch Regarding License Amendment Request 241 Alternate Source Term Project stage: RAI L-2009-134, Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 42009-06-29029 June 2009 Submittal of Quality Assurance Topical Report (QATR FPL-1) Revision 4 Project stage: Request NRC 2009-0075, License Amendment Request 241 Alternative Source Term Response to Request for Additional Information2009-07-24024 July 2009 License Amendment Request 241 Alternative Source Term Response to Request for Additional Information Project stage: Response to RAI ML0919700422009-07-24024 July 2009 Notice of Meeting with FPL Energy Point Beach, LLC, to Discuss Epu/Setpoint Submittal and Relationship Between EPU and AST Project stage: Meeting ML0919500722009-07-24024 July 2009 Request for Additional Information (RAI) from the Containment and Ventilation Branch Regarding License Amendment Request No. 241 Alternate Source Term Project stage: RAI ML0921905632009-08-0606 August 2009 Extended Power Uprate and Alternate Source Term Review Planning Meeting Presentation Project stage: Request ML0922402982009-08-0606 August 2009 Extended Power Uprate and Alternate Source Term Review Planning Meeting Presentation (Handout 2) Project stage: Request ML0921500922009-08-0707 August 2009 Request for Additional Information (RAI) from Electrical Engineering Branch Alternate Source Term Project stage: RAI ML0921511232009-08-13013 August 2009 Request for Additional Information from Accident Dose Branch Alternate Source Term Project stage: RAI ML0922507682009-08-13013 August 2009 Draft - Request for Additional Information from Containment and Ventilation Branch on Alternate Source Term Project stage: Draft RAI NRC 2009-0080, License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information2009-08-20020 August 2009 License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information Project stage: Response to RAI ML0923605352009-08-26026 August 2009 Request for Additional Information, Round 2, from Containment and Ventilation Branch, on the Proposed Amendment Re. Alternative Source Term Project stage: RAI NRC 2009-0085, License Amendment Request 241 Alternative Source Term Response to Request for Additional Information2009-09-0404 September 2009 License Amendment Request 241 Alternative Source Term Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0086, License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information2009-09-0404 September 2009 License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0090, License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information2009-09-10010 September 2009 License Amendment Request 241, Alternative Source Term, Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0076, Units I & 2, License Amendment Request 241, Alternative Source Term Commitment for Seismic Evaluation2009-09-10010 September 2009 Units I & 2, License Amendment Request 241, Alternative Source Term Commitment for Seismic Evaluation Project stage: Request ML0923211842009-09-14014 September 2009 Meeting Summary, Meeting with FPL Energy Point Beach, LLC, on the Extended Power Uprate and Alternate Source Term Amendments Project stage: Meeting NRC 2009-0105, License Amendment Request 241, Alternative Source Term, Response Clarification Request2009-10-0202 October 2009 License Amendment Request 241, Alternative Source Term, Response Clarification Request Project stage: Request ML0931307642009-11-16016 November 2009 Individual Notice of Consideration of Issuance of Amendments to Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing Project stage: Other ML0917006072009-11-16016 November 2009 FRN: Point Beach, Units 1 & 2 - Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing for AST Additional TS Project stage: Other NRC 2009-0109, License Amendment Request 241 Re Alternative Source Term, Response to Request for Additional Information2009-11-25025 November 2009 License Amendment Request 241 Re Alternative Source Term, Response to Request for Additional Information Project stage: Response to RAI ML0936302462010-01-0505 January 2010 Request for Additional Information Regarding Alternative Source Term Project stage: RAI ML1008905132010-05-20020 May 2010 Summary of Meeting with FPL Energy Point Beach, LLC, on Outstanding Issues and Schedule Changes to the Alternate Source Term, Extended Power Uprate, and Auxiliary Feedwater Amendment Reviews Project stage: Meeting NRC-2010-0089, Supplement to License Amendment Requests 241 Alternative Source Term, Revised Proposed Technical Specifications for Control Room Envelope Habitability Program2010-07-0808 July 2010 Supplement to License Amendment Requests 241 Alternative Source Term, Revised Proposed Technical Specifications for Control Room Envelope Habitability Program Project stage: Supplement ML1022302882010-07-27027 July 2010 E-mail: Point Beach Nuclear Plant, Units 1 and 2 - Draft RAIs AST License Amendment Request Project stage: Draft RAI ML1022302952010-07-27027 July 2010 E-mail Attachment: RAI - Point Beach Nuclear Plant, Units 1 and 2 Alternate Source Term (AST) License Amendment Request (LAR) Project stage: RAI ML1021800302010-08-11011 August 2010 Meeting Summary Point Beach Nuclear Power Plant, Units 1 and 2 - Discussion of AST, AFW, Non-Conservative Setpoint Methodology, and EPU License Amendment Requests Project stage: Meeting ML1023712882010-08-19019 August 2010 Followup to August 16, 2010, Phone Call Wgdt Release Project stage: Other ML1102400542011-04-14014 April 2011 Issuance of License Amendments Regarding Use of Alternative Source Term Project stage: Approval ML1112200782011-05-0404 May 2011 Correction Letter for License Amendment Nos. 240 and 244 for Renewed Facility Operating Licenses DPR-24 and DPR-27, Alternate Source Term (AST) Project stage: Other NRC 2016-0029, Response to Request for Additional Information Regarding License Amendment Request 280 - Removal of Completed License Conditions and Change to the Ventilation Filter Testing Program2016-07-11011 July 2016 Response to Request for Additional Information Regarding License Amendment Request 280 - Removal of Completed License Conditions and Change to the Ventilation Filter Testing Program Project stage: Response to RAI 2009-06-29
[Table View] |
Text
FPL Energy Point Beach Nuclear Plant February 20,2009 FPL Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241 NRC 2009-0023 10 CFR 50.90 U.S Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Point Beach Nuclear Plant, Units 1 and 2 Dockets 50-266 and 50-301 Renewed License Nos. DPR-24 and DPR-27 Su~~lement to License Amendment Request 241 Alternative Source Term
Reference:
(1) FPL Energy Point Beach LLC, License Amendment Request 241 dated December 8,2008, "Alternative Source Termn (ML083450683)
A teleconference was held between representatives from FPL Energy Point Beach and the NRC Staff on February 6, 2009. The purpose of the teleconference was to discuss supplemental information needed by the staff to support the review of License Amendment Request 241, "Alternative Source Term." provides the NRC staffs questions, the FPL Energy Point Beach, LLC responses, and contains two new regulatory commitments.
This supplement does not affect the no significant hazards conclusion, as defined in 10 CFR 50.92, provided in Reference (1).
An FPL Group Company
Document Control Desk Page 2 Summarv of Reaulatory Commitments The following two new Regulatory Commitments for the primary auxiliary building ventilation (VNPAB) system are proposed:
The VNPAB system will be added to the scope of the Maintenance Rule (10 CFR 50.65) and the scope of the License Renewal Program (10 CFR 54.37(b)). These actions will be completed during the Unit 1 (Spring 2010) refueling outage that implements the LAR.
FPLE Energy Point Beach, LLC will submit proposed TS for the VNPAB system by April 21, 2009.
In accordance with 10 CFR 50.91, a copy of this letter is being provided to the designated Wisconsin Official.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on February 20,2009.
Very truly yours, FPL Energy Point Beach, LLC Enclosure cc:
Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW
ENCLOSURE I FPL ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT, UNITS I AND 2 SUPPLEMENT TO LICENSE AMENDMENT REQUEST 241 ALTERNATIVE SOURCE TERM The following information is provided as a follow-up from the teleconference between the NRC staff and representatives from FPL Energy Point Beach, LLC, dated February 6, 2009. The information supports review of License Amendment Request 241, "Alternative Source Term" by the staff.
Questions 1 and 2:
- 1.
The licensee is crediting the Control Room Ventilation System (VNCR) and the Primary Auxiliary Building Ventilation (VNPAB) System for implementing the AST. However, the licensee submittal did not make any mention of adding these systems to the scope of the Maintenance Rule program in accordance with 10 CFR 50.65, and to the scope of the license renewal in accordance with 10 CFR 54.37(b).
- 2.
The above equipment should also be added to the Technical Specifications (TS) with appropriate Limiting Condition for Operation (LCO) and Sun/eillance Requirements (SR) because the equipment is required for safe operation of the facility as required by 10 CFR 50.36(d)(2)(io(C), Criteria 3, "A structure, system, or component that is part of the primary success path and which functions or actuates to mitigate a design-basis accident or transient that either assumes the failure of or presents a challenge to the integrity of a fission product barrier. "
FPL Enersrv Point Beach Response:
The Control Room Emergency Filtration System (CREFS) is the portion of the Control Room Ventilation System that supports the radiological habitability of the Control Room. CREFS is currently in the Point Beach Nuclear Plant Technical Specifications (TS). CREFS is also within the scope of the Maintenance Rule Program (1 0 CFR 50.65) and the License Renewal Program (10 CFR 54.37(b)). The new alignment currently proposed in LAR 241 does not require Technical Specification changes other than those previously submitted.
Two new regulatory commitments for the VNPAB system are proposed:
The VNPAB system will be added to the scope of the Maintenance Rule (10 CFR 50.65) and the scope of the License Renewal Program (10 CFR 54.37(b)). These actions will be completed during the Unit 1 (Spring 2010) refueling outage that implements the MR.
FPLE Energy Point Beach, LLC will submit proposed TS for the VNPAB system by April 21, 2009.
Page 1 of 1