Mark J. Ajluni. P.E.
Southern Nuclear Nuclear Licensing Director Operating Company. Inc.
40 Inverness Center Parkway Post Office Box 1295 Birmingham. Alabama 35201 Tel 205.992.7673 Fax 205.992.7885 November 3,2011 SOUTHERN '\\
COMPANY Docket Nos: 50-348 50-321 50-424 50-364 50-366 50-425 NL-11-2163 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant Edwin I. Hatch Nuclear Power Plant Vogtle Electric Generating Plant Emergency Response Data System (ERDS)
Virtual Private Network (VPN) Transition Ladies and Gentlemen:
In accordance with the requirements of 10 CFR 50, Appendix E, Section VI, Item 3a, Southern Nuclear Operating Company is submitting a notification of changes to the Joseph M. Farley Nuclear Plant, Unit 1 and Unit 2; Edwin I. Hatch Nuclear Power Plant, Unit 1 and Unit 2; and the Vogtle Electric Generating Plant, Unit 1 and Unit 2, Emergency Response Data System (ERDS).
Changes involve a conversion from a dial-up modem-based system to a more reliable internet-based system using a plant information server and NRC supplied virtual private network (VPN) appliance. The planned changes to the ERDS systems were previously communicated on July 31,2011, when SNC verbally informed the NRC of SNC's intent to implement the ERDS VPN on November 16, 2011. Installation and testing of the ERDS VPN have been completed; however, the SNC implementation date has been revised to December 13, 2011. No changes were made to the data point libraries for any of the three sites.
If you have any questions regarding this submittal, please contact Mr. C. E.
Boone, Fleet Emergency Preparedness Manager at (205) 992-6635.
Respectfully submitted, M. J. Ajluni Nuclear Licensing Director MJAlCLNllac
U. S. Nuclear Regulatory Commission NL-11-2163 Page 2 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Bost, Chief Nuclear Officer Mr. T. A. Lynch, Vice President - Farley Mr. D. R. Madison, Vice President - Hatch Mr. T. E. Tynan, Vice President - Vogtle Ms. P. M. Marino, Vice President - Engineering RType: Farley=CFA04.054; Hatch=CHA02.004; Vogtle=CVC7000 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. V. Sreenivas, NRR Project Manager - Farley Mr. E. L. Crowe, Senior Resident Inspector - Farley Mr. E. D. Morris, Senior Resident Inspector - Hatch Mr. L. M. Cain, Senior Resident Inspector - Vogtle Mr. D. H. Jaffe, NRR Senior Project Manager-Vogtle, Fleet Mr. W. C. Gleaves, NRR Senior Project Manager-Hatch