NL-08-0510, Technical Specification Amendment Request Containment Leakage Rate Testing Program

From kanterella
Jump to navigation Jump to search

Technical Specification Amendment Request Containment Leakage Rate Testing Program
ML080990386
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 04/07/2008
From: Stinson L
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-08-0510
Download: ML080990386 (2)


Text

L M. Stinson (Mikel Vice President Fleet Operations Support Southern Nuclear Operating Company. Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham, Alabama 35201 April 7, 2008 Tel 205.992.5181 Fax 205.992.0341 SOUTHERN A.

COMPANY Energy to Serve }OurWorM""

Docket Nos.: 50 50 348 364 NL-08-0510 U. S. Nuclear ATTN: Docum Washington, D. C.

ent Reg Control Desk 20555-0001 ulatory Commission Joseph M. Farley Nuclear Plant Unit 1 and 2 Technical Specification Amendment Request Containment Leakage Rate Testing Program Ladies and Gentlemen:

By letter dated November 5, 2007 Southern Nuclear Operating Company (SNC) proposed a change to the Joseph M. Farley Nuclear Plant (FNP) Unit 1 and Unit 2 Technical Specifications (TS). This proposed change will revise TS section 5.5.17, "Containment Leakage Rate Testing Program," to resolve a timing conflict between the FNP Unit 2 R20 refueling outage schedule and the FNP Unit 2 Type A Containment Integrated Leak Rate Test (ILRT) required completion date of March 2010. Although Unit 1 does not have a current timing conflict, a similar Unit 1 change is proposed for consistency.

SNC proposed to modify Technical Specification 5.5.17 to state "Section 9.2.3:

The next Type A test, after the March 1994 test for Unit 1 and the March 1995 test for Unit 2, shall be performed during refueling outage R22 (Spring 2009) for Unit 1 and during refueling outage R20 (Spring 2010) for Unit 2. This is a one time exception."

Based on discussions between SNC and the Nuclear Regulatory Commission on March 19, 2008, SNC is providing dates for the Unit 1 Spring 2009 and Unit 2 Spring 2010 refueling outages. These outages will start no later than April 18.

2009 for the Unit 1 Spring 2009 refueling outage and April 24, 2010 for the Unit 2 Spring 2010 refueling outage.

(Affirmation and signature are provided on the following page.)

U. S. Nuclear Regulatory Commission NL-08-0510 Page 2 Mr. L. M. Stinson states he is a Vice President of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and to the best of his knowledge and belief, the facts set forth in this letter are true.

This letter contains no NRC commitments. If you have any questions, please advise.

Respectfully submitted, SOUTHERN NUCLEAR OPERATING COMPANY L. M. Stinson Q.."

r*

Vice President Fleet Operations Support SW0'j to and. subscribed before me this 1tft day of tJ;;1-/

,2008.

.>&J{l~

Notary Public My commission expires: J:./I/ S ;10/0

/

7 LMS/BDM/daj cc:

Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. J. R. Johnson, Vice President - Farley Mr. D. H. Jones, Vice President - Engineering RTYPE: CFA04.054; LC#14741 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Acting Regional Administrator Mr. R. A. Jervey, NRR Project Manager - Farley Mr. E. L. Crowe, Senior Resident Inspector - Farley Alabama Department of Public Health Dr. D. E. Williamson, State Health Officer