Entergy Entergy Nuclear Northeast Indian Point Energy Center 295 Broadway, Suite 1 RO. Box 249 Buchanan, NY 10511-0249 Tel 914 734 5340 Fax 914 734 5718 Fred Dacimo Vice President, Operations June 12, 2003 NL-03-101 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station O-P1-17 Washington, DC 20555-0001
Subject:
Indian Point Unit No. 2 Docket No. 50-247 License No. DPR-26 Monthly Operating Report for May 2003
Dear Sir:
Enclosed is the Monthly Operating Report for Indian Point 2 for the month of May 2003 that is being submitted in accordance with Technical Specification 6.9.1.7. Please be advised that by NRC letter dated May 22, 2003, a 1.4% power uprate was issued by the NRC as Amendment 237 to the Indian Point 2 Facility Operating License and Technical Specifications. The 1.4% power uprate amendment was implemented in the May reporting period.
Entergy is making no commitments in this letter. Should you have any questions regarding this submittal, please contact Mr. John McCann, Manager, Licensing, Indian Point Energy Center at (914) 734-5074.
Sincerely yours, Fred R. Dacimo Vice President, Operations Indian Point Energy Center cc: see next page
Docket No. 50-247 NL-03-101 Page 2 of 2 Attachment cc:
Mr. Hubert J. Miller Regional Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1498 Resident Inspector U.S. Nuclear Regulatory Commission Indian Point 2 P.O. Box 38 Buchanan, NY 10511 INPO Records Center 700 Galleria Parkway Atlanta, Georgia 30339-5957 Mr. Paul Eddy State of New York Department of Public Service 3 Empire Plaza Albany, NY 12223
NL-03-1 01 Attachment Page 1 of 4 OPERATING DATA REPORT DOCKET NO.
DATE COMPLETED BY TELEPHONE 50-247 June 6, 2003 S. Smith (914)714-8304 OPERATING STAT[JS
- 1. Unit Name:
INDIAN POINT UNIT No. 2 Notes
- 2. Reporting Period:
May-2003
- 3. Licensed Thermal Power ( MWt):
- 3114.4
- 4. Nameplate Rating ( Gross Mwe):
1008
- 5. Design Electrical Rating (Net Mwe):
- 993
- 6. Maximum Dependable Capacity ( Gross Mwe):
- 988
- 7. Maximum Dependable Capacity ( Net Mwe ):
- 956
- 8. If Changes Occur in Capacity Ratings ( Items Number 3 Through 7 ) Since Last Report, Give Reasons:
- New thermal power value effected with commencement of 1.4% power uprate on May 23, 2003. Ratings based on new thermal output.
- 9. Power Level To Which Restricted, If Any (Net Mwe):
- 10. Reasons For Restrictions, If Any:
This Month I.
Hours In Reporting Period 744
- 12. Number Of Hours Reactor Was Critical 744
- 13. Reactor Reserve Shutdown Hours 0
- 14. Hours Generator On-Line 744
- 15. Unit Reserve Shutdown Hours 0
- 16. Gross Thermal Energy Generated ( MWH )
2,285,897
- 17. Gross Electrical Energy Generated ( MWH) 752,603
- 18. Net Electrical Energy Generated ( MWH) 726,901
- 19. Unit Service Factor 100.0
- 20. Unit Availability Factor 100.0
- 21. Unit Capacity Factor ( Using MDC Net) 104.2
- 22. Unit Capacity Factor ( Using DER Net) 98.9
- 23. Unit Forced Outage Rate 0
Yr.-to-Date 3,623 3,589.68 0
3,577.78 0
10,944,296 3,607,175 3,488,390 98.8 98.8 101.9 97.6 1.2 Cumulative 253,488 178,091.30 4,566.64 174,150.08 0
491,387,415 153,685,531 147,267,862 68.7 68.7 65.0 62.8 13.6
- 24. Shutdowns Scheduled Over Next 6 Months ( Type,Date, and Duration Of Each):
- 25. If Shut Down At End Of Report Period, Estimated Date Of Startup:
- 26. Units In Test Status ( Prior to Commercial Operation ):
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast Achieved N/A N/A N/A N/A N/A N/A (9/77)
NL-03-1 01 Attachment Page 2 of 4 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-247 UNIT I.P. Unit #2 DATE June 6,2003 COMPLETED BY S. Smith TELEPHONE (914)714-8304 May-2003 MONTH DAY AVERAGE DAILY POWER LEVEL (MWC-Net) 1 875 2
978 3
979 4
980 5
979 6
979 7
980 8
971 9
969 10 978 11 979 12 974 13 972 14 975 15 976 16 979 DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 980 979 978 978 978 978 982 988 990 990 995 989 989 983 988 INSTRUCTIONS On this fornat, list the average daily unit power level in Mwe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
NL-03-101 Attachment Page 3 of 4 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH DOCKET NO.
UNIT DATE COMPLETED BY TELEPHONE May-2003 50-247 I.P. Unit #2 June 6, 2003 S. Smith (914)714-8304 2
F : Forced S: Scheduled Reason:
A - Equipment Failure ( Explain )
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error ( Explain )
H - Other ( Explain) 3 Method:
I - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Other ( Explain )
4 Exibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Repott ( LER ) File ( NUREG-0161 )
5 Exibit I - Same Source (9/77)
Licensee No.
Date c
Event Cause & Corective Action to Prevent Recurrence 0~~~~~E-Report#
NONE f-f tf I
f-I 1"
\\
I
Docket No. 50-247 NL-03-1 01 Attachment Page 4 of 4 Summary Of Operating Exnerience May 2003 Indian Point Unit No. 2 was synchronized to the bus for a total of 744 hours0.00861 days <br />0.207 hours <br />0.00123 weeks <br />2.83092e-4 months <br />, producing a gross electrical generation of 752,603 MWH.
On May 22, 2003, Indian Point 2 received Amendment 237 to revise the Facility Operating License (DPR-26) and Technical Specifications to increase the licensed core thermal power level by 1.4%. The power uprate increased the licensed core thermal power level to 3114.4 MWt which is a 1.4% increase above the previously authorized power level of 3071.4. The power uprate commenced on May 23, 2003, at 0902 hours0.0104 days <br />0.251 hours <br />0.00149 weeks <br />3.43211e-4 months <br />, and was completed on May 24, 2003, at 1231 hours0.0142 days <br />0.342 hours <br />0.00204 weeks <br />4.683955e-4 months <br />. The unit remained on line at full power for the remainder of the reporting period.