NL-03-045, February 2003 Monthly Operating Report for Indian Point Unit 2
| ML030770562 | |
| Person / Time | |
|---|---|
| Site: | Indian Point |
| Issue date: | 03/13/2003 |
| From: | Dacimo F Entergy Nuclear Northeast |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NL-03-045 | |
| Download: ML030770562 (6) | |
Text
-'Entergy Entergy Nuclear Northeast Indian Point Energy Center 295 Broadway, Suite 1 PO Box 249 Buchanan, NY 10511-0249 Tel 9147345340 Fax 914 734 5718 Fred Dacimo Vice President, Operations March 13, 2003 NL-03-045 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station O-P1-17 Washington, DC 20555-0001
Subject:
Indian Point Unit No. 2 Docket No. 50-247 License No. DPR-26 Monthly Operating Report for February 2003
Dear Sir:
Enclosed is the Monthly Operating Report for Indian Point 2 for the month of February 2003 that is being submitted in accordance with Technical Specification 6.9.1.7.
Entergy is making no commitments in this letter. Should you have any questions regarding this submittal, please contact Mr. John McCann, Manager, Licensing, Indian Point Energy Center at (914) 734-5074.
Fred R. Dacimo Vice President, Operations Indian Point Energy Center cc: see next page ový
Docket No. 50-247 NL-03-045 Page 2 of 2 Attachment cc:
Mr. Hubert J. Miller Regional Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1498 Resident Inspector U.S. Nuclear Regulatory Commission Indian Point 2 P.O. Box 38 Buchanan, NY 10511 INPO Records Center 700 Galleria Parkway Atlanta, Georgia 30339-5957 Mr. Paul Eddy State of New York Department of Public Service 3 Empire Plaza Albany, NY 12223
NL-03-045 Attachment Page 1 of 4 OPERATING DATA REPORT DOCKET NO.
50-247 DATE March 6, 2003 COMPLETED BY M. Walther TELEPHONE (914)734-5728 OPERATING STATUS
- 1.
- 2.
- 3.
- 4.
- 5.
- 6.
- 7.
8.
Unit Name:
INDIAN POINT UNIT No. 2 Notes Reporting Penod:
February-2003 Licensed Thermal Power ( MWt):
3071.4 Nameplate Rating ( Gross Mwe )
1008 Design Electrical Rating ( Net Mwe) :
986 Maximum Dependable Capacity (Gross Mwe):
985 Maximum Dependable Capacity (Net Mwe ):
951 If Changes Occur in Capacity Ratings ( Items Number 3 Through 7 ) Since Last Report, Give Reasons:
- 9. Power Level To Which Restricted, If Any (Net Mwe) :
- 10. Reasons For Restrictions, If Any This Month Yr.-to-Date Cumulative
- 11. Hours In Reporting Period 672 1,416 251,281 12 Number Of Hours Reactor Was Critical 672 1,416 175,917.62 13 Reactor Reserve Shutdown Hours 0
0 4,566 64 14 Hours Generator On-Line 672 1,416 171,988 30 15 Unit Reserve Shutdown Hours 0
0 0
16 Gross Thermal Energy Generated ( MWH) 2,063,465 4,340,036 484,783,155
- 17. Gross Electncal Energy Generated ( MWH) 681,966 1,431,509 151,509,865 18 Net Electrcal Energy Generated (MWH) 660,312 1,385,871 145,165,343 19 Unit Service Factor 1000 1000 68 4 20 Unit Availability Factor 1000 1000 68 4
- 21. Unit Capacity Factor (Using MDC Net) 103 3 1029 64 6
- 22. Unit Capacity Factor ( Using DER Net) 99 7 99 3 62.5
- 23. Unit Forced Outage Rate 0
0 13.7 24 Shutdowns Scheduled Over Next 6 Months (Type, Date, and Duration Of Each ) :
25 If Shut Down At End Of Report Period, Estimated Date Of Startup:
26 Units In Test Status (Prior to Commercial Operation):
INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION Forecast N/A N/A N/A Achieved N/A N/A N/A (9177)
NL-03-045 Attachment Page 2 of 4 AVERAGE DAILY UNIT POWER LEVEL DOCKET NO.
50-247 UNIT I.P. Unit #2 DATE March 6,2003 COMPLETED BY M. Walther TELEPHONE (914)734-5728 February-2003 MONTH DAY AVERAGE DAILY POWER LEVEL (MWe-Net) 1 983 2
982 3
983 4
988 5
977 6
983 7
983 8
982 9
984 10 982 11 982 12 983 13 983 14 984 15 982 16 983 DAY AVERAGE DAILY POWER LEVEL
( MWc-Net) 17 982 18 982 19 983 20 982 21 982 22 980 23 982 24 983 25 983 26 983 27 982 28 984 29 30 31 INSTRUCTIONS On this format, list the average daily unit power level in Mwe-Net for each day in the reporting month. Compute to the nearest whole megawatt.
(9/77)
NL-03-045 Attachemtn Page 3 of 4 UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH February-2003 DOCKET NO.
50-247 UNIT I.P. Unit #2 DATE March 6, 2003 COMPLETED BY M. Walther TELEPHONE (914)734-5728 1
F : Forced S : Scheduled 2
Reason :
A - Equipment Failure ( Explain)
B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training & License Examination F - Administrative G - Operational Error ( Explain)
H - Other ( Explain )
3 Method:
1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Other (Explain) 4 Exibit G - Instructions for Preparation of Data Entry Sheets for Licensee Event Report ( LER) File ( NUREG-0161 )
5 Exibit I - Same Source (9/77) 0 o
Licensee 0
No t Event E
o Cause & Corrective Action to Prevent Recurrence S:
Report #
0 0
)
NONE
Docket No. 50-247 NL-03-045 Attachment Page 4 of 4 Summary Of Operating Experience February 2003 Indian Point Unit No. 2 began the month of February at full power and ran until February 20, 2003 when at 2312 hours0.0268 days <br />0.642 hours <br />0.00382 weeks <br />8.79716e-4 months <br />, power was decreased to conduct a scheduled Turbine Stop Valve test. Reactor power was reduced to 96.2 percent during this evolution. Testing was completed on February 21, 2003 with power escalation starting at 0136 hours0.00157 days <br />0.0378 hours <br />2.248677e-4 weeks <br />5.1748e-5 months <br />. Full power was achieved at 0302 hours0.0035 days <br />0.0839 hours <br />4.993386e-4 weeks <br />1.14911e-4 months <br /> on February 21, 2003. The unit continued to run at full power for the remainder of the reporting period.