ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)
ML21321A326
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 11/17/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 2.7.04.03, ND-21-0713
Download: ML21321A326 (7)


Text

Southern Nuclear NOV 1 7 2021 Docket No.: 52-025 U.S. Nuclear Regulatory Commission Document Control Desk Wastiington, DC 20555-0001 Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 ND-21-0713 10 CFR 52.99(c)(1)

Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 [Index Number 7161 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP)

Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.7.04.03 [Index Number 716]. This ITAAC confirms controls exist in the Main Control Room (MCR) to cause the components identified in Combined License (COL) Table 2.7.4-1 to perform the listed functions and confirms the display of the parameters can be retrieved in the MCR. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) request NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli A. Roberts at 706-848-6991.

Respectfully sdbmHttec; Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

MJY/DCH/sfr Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.7.04.03 [Index Number 716]

U.S. Nuclear Regulatory Commission ND-21-0713 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Reoulatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. McCurry Mr. j. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-21-0713 Page 3 of 3 Oalethorpe Power CorDoration Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani Mr. D. 0. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Pubiic Service Commission Mr. R. L. Trokey, Georgia Pubiic Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-21-0713 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-21-0713 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.7.04.03 [Index Number 716]

U.S. Nuclear Regulatory Commission ND-21-0713 Enclosure Page 2 of 4 ITAAC Statement Desion Commitment

3. Controls exist In the MCR to cause the components Identified In Table 2.7.4-1 to perform the listed function.
4. Displays of the parameters Identified In Table 2.7.4-1 can be retrieved In the MCR.

Inspections. Tests. Analvses Testing will be performed on the components In Table 2.7.4-1 using controls In the MCR.

Inspection will be performed for retrlevablllty of the parameters In the MCR.

Acceptance Criteria Controls In the MCR operate to cause the components listed In Table 2.7.4-1 to perform the listed functions.

The displays Identified In Table 2.7.4-1 can be retrieved In the MCR.

ITAAC Determination Basis Tests and Inspections were performed to ensure controls exist In the Main Control Room (MCR) to cause the components Identified In Combined License (COL) Table 2.7.4-1 (Attachment A) to perform the listed functions and to verify the displays of the parameters listed In Attachment A can be retrieved In the MCR.

Controls In the MCR operate to cause the components listed In Table 2.7.4-1 to perform the listed functions.

Testing was performed In accordance with the Unit 3 component test procedure listed In Reference 1 to verify controls In the MCR operate to cause the Diesel Generator Building Ventilation System (VZS) components (fans and heaters) listed In COL appendix C Table 2.7.4-1 (Attachment A) to perform the listed functions. At a MCR operator workstation, the fans listed In Attachment A were started using Plant Control System (PLS) controls from the MCR. For the heaters listed In Attachment A, the applicable heater controller was locally adjusted to above ambient temperature and the heaters were enabled using PLS controls from the MCR.

Inspections verified the fans started and heaters energized on the PLS monitor In the MCR and was documented In the test. Local verification of fan and heater status was performed during the component testing.

Unit 3 test results (Reference 1) confirmed that controls In the MCR operate to cause the components listed In Table 2.7.4-1 to perform the listed functions.

The displavs Identified In Table 2.7.4-1 can be retrieved In the MCR.

An Inspection was performed In accordance with the Unit 3 component test procedure listed In Reference 1 for VZS component Indication verifications, and visually confirmed that when each of the displays of parameters Identified In Attachment A was summoned at a MCR workstation, the summoned plant parameter appeared on a display monitor at that MCR workstation.

U.S. Nuclear Regulatory Commission ND-21-0713 Enclosure Page 3 of 4 The Unit 3 test results (Reference 1) confirmed that the VEGP Unit 3 plant parameter displays Identified In Attachment A can be retrieved In the MGR.

Reference 1 Is available for NRG Inspection as well as the Unit 3 ITAAG 2.7.04.03 Completion Package (Reference 2).

ITAAC Finding Review In accordance with plant procedures for ITAAG completion, Southern Nuclear Operating Company (SNG) performed a review of all ITAAG findings pertaining to the subject ITAAG and associated corrective actions. This review found there were no relevant findings associated with this ITAAG. The review Is documented In the ITAAG Completion Package (Reference 2) and Is available for NRG review.

ITAAC Completion Statement Based on the above Information, SNG hereby notifies the NRG that ITAAG 2.7.04.03 was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAG are being maintained In their as-designed, ITAAG compliant condition In accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. 3-VZS-ITR-800716, Rev 0, "Unit 3 VZS Diesel Generator Building Heating and Ventilation System Controls and Indications Test Resuitd'
2. 2.7.04.03-U3-GP-Rev0, ITAAG Completion Package

U.S. Nuclear Regulatory Commission ND-21-0713 Enclosure Page 4 of 4 Attachment A

'Excerpt of COL Appendix C Table 2.7.4-1 Table 2.7.4-1*

Equipment Name*

Tag No.

  • Display*

Control Function*

Diesel Generator Room A Standby Exhaust Fans VZS-MY-V01A VZS-MY-V02A Yes (Run Status)

Start Diesel Generator Room B Standby Exhaust Fans VZS-MY-V01B VZS-MY-V02B Yes (Run Status)

Start Service Module A Air Handling Units (AHU) Supply Fan VZS-MA-01A Yes (Run Status)

Start Service Module B AHU Supply Fan VZS-MA-01B Yes (Run Status)

Start Diesel Oil Transfer Module Enclosure A Exhaust Fan VZS-MY-V03A Yes (Run Status)

Start Diesel Oil Transfer Module Enclosure A Electric Unit Heater VZS-MY-U03A Yes (Run Status)

Energize Diesel Oil Transfer Module Enclosure B Exhaust Fan VZS-MY-V03B Yes (Run Status)

Start Diesel Oil Transfer Module Enclosure B Electric Unit Heater VZS-MY-U03B Yes (Run Status)

Energize