Letter Sequence Draft Approval |
|---|
EPID:L-2022-LLA-0140, Review of Limerick Generating Station Defense in Depth and Diversity Common Cause Failure Coping Analysis, WNA-AR-01074-GLIM-P, Rev 1. Without Attachment 3 Enclosure (Open) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
Results
Other: ML22353A632, ML23032A244, ML23187A096, ML23241A945, ML24093A091, ML24208A159, ML24243A048, ML24263A003, ML24310A260, ML24361A129, ML25094A145, ML25223A077
|
MONTHYEARML22046A0742022-02-14014 February 2022 Review of Limerick Generating Station Defense in Depth and Diversity Common Cause Failure Coping Analysis, WNA-AR-01074-GLIM-P, Rev 1. Without Attachment 3 Enclosure Project stage: Request PMNS20220709, Meeting Between NRC Staff and Constellation Energy Generation, LLC on the Review of the Defense-in-Depth and Diversity Coping Analysis Supporting the Digital Upgrade of Instrumentation and Controls at Limerick Generating Station, Units2022-07-22022 July 2022 Meeting Between NRC Staff and Constellation Energy Generation, LLC on the Review of the Defense-in-Depth and Diversity Coping Analysis Supporting the Digital Upgrade of Instrumentation and Controls at Limerick Generating Station, Units 1 an Project stage: Request ML22224A1492022-08-15015 August 2022 Review of Limerick Generating Station Defense in Depth and Diversity Common Cause Failure Coping Analysis, WNA-AR-01074-GLIM-P, Revision 2, July 2022, and the Licensing Technical Report for the Limerick Generating Station Units 1&2 Digital Project stage: Request PMNS20221157, Meeting Between NRC and Constellation Energy Generation, LLC Regarding Ongoing Acceptance Review of Limerick Generating Station, Units 1 and 2 Digital Instrumentation and Controls License Amendment Request2022-11-0707 November 2022 Meeting Between NRC and Constellation Energy Generation, LLC Regarding Ongoing Acceptance Review of Limerick Generating Station, Units 1 and 2 Digital Instrumentation and Controls License Amendment Request Project stage: Acceptance Review ML23009A5622022-11-0707 November 2022, 14 November 2022, 11 January 2023 Summary of December 15, 2022 Public Meeting on Limeric Digital I&C LAR Acceptance Project stage: Request ML22312A4402022-11-10010 November 2022 Public Meeting with Constellation About Acceptance Review: Status of NRC Staffs Acceptance Review of the Limerick Digital Instrumentation and Controls License Amendment Request Project stage: Acceptance Review ML22340A2172022-11-10010 November 2022, 21 November 2022, 6 December 2022 Summary of November 10, 2022, Meeting with Constellation Energy Generation, Lic on Acceptance Review of Limerick Digital Instrumentation and Controls License Amendment Requests Project stage: Request ML22319A0012022-11-14014 November 2022 Constellation Energy Generation, LLCs Presentation for November 10, 2022 Public Meeting with NRC Project stage: Request ML22320A1132022-11-21021 November 2022 Generation Station, Units 1 and 2 - Supplemental Information Needed for Acceptance of Digital Instrumentation and Controls License Amendment Requests Project stage: Acceptance Review ML22333A8172022-11-29029 November 2022 Response to Supplemental Information Needed for Acceptance of Digital Instrumentation and Controls License Amendment Requests for the Limerick Generating Station Project stage: Supplement ML22327A0192022-12-0606 December 2022 Summary of November 10, 2022, Meeting with Constellation Energy Generation, Lic on Acceptance Review of Limerick Digital Instrumentation and Controls License Amendment Requests Project stage: Acceptance Review ML22339A0642022-12-0909 December 2022 Generation Station, Unit Nos. 1 and 2 – Acceptance of Requested Licensing Action Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System Project stage: Acceptance Review ML22347A1532022-12-13013 December 2022 Public Meeting Presentation, December 15, 2022 Di&C License Amendment Request Project stage: Meeting ML23003A1702022-12-15015 December 2022 Official Transcript of the 12/15/22 Meeting with Constellation Energy to Discuss the Exceptions Described for the Independence and Operating Bypass with IEEE 603 of the Proposed Plant Protection System in the Limerick Station, Units 1 and 2 Project stage: Meeting ML23009A5872023-01-11011 January 2023 Summary of December 15, 2022, Meeting with Constellation Energy Generation, LLC on Potential Compliance with Certain Clauses of IEEE Standard 603-1991 in Limerick Digital Instrumentation and Controls License Amendment Requests Project stage: Meeting ML22353A6322023-01-17017 January 2023 Supplement to Regulatory Audit Plan in Support of Review of Digital I&C Upgrade to Protection Systems (EPID L-2022-LLA-0140) - Non-Proprietary Project stage: Other PMNS20230026, Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-01-20020 January 2023 Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23076A1062023-01-20020 January 2023, 12 May 2023 Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request ML23032A2442023-02-0606 February 2023 Regulatory Audit Plan for Review of Human Factors Engineering Portion of Limerick Digital Instrumentation and Controls License Amendment Request Project stage: Other ML23039A1412023-02-0808 February 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)-Human Factors Engineering Project stage: Supplement ML23046A2662023-02-15015 February 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System Project stage: Supplement PMNS20230032, Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-02-23023 February 2023 Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting PMNS20230033, Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-03-0606 March 2023 Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23121A0042023-03-0606 March 2023, 12 May 2023 Summary of March 29, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request PMNS20230254, Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-03-17017 March 2023 Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23118A3792023-03-17017 March 2023, 9 June 2023 April 12, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request ML23089A3242023-03-30030 March 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System Human Factors Engine Project stage: Supplement ML23095A2232023-04-0505 April 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System (PPS)- Human Factors Project stage: Supplement PMNS20230423, Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-04-17017 April 2023 Meeting with Constellation Energy Generation, LLC Regarding Planned Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23132A3092023-04-17017 April 2023, 18 May 2023 Summary of May 3, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request ML23121A0022023-05-12012 May 2023 Summary of March 29, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23076A1042023-05-12012 May 2023 Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23076A0132023-05-12012 May 2023 March 15, 2023, Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting PMNS20230627, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-05-15015 May 2023 Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23145A0672023-05-15015 May 2023, 31 May 2023 May 17, 2023, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request PMNS20230606, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-05-16016 May 2023 Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23156A4172023-05-16016 May 2023, 9 June 2023 Summary of May 24, 2023, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Request ML23132A3082023-05-18018 May 2023 Summary of May 3, 2023, Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23143A3422023-05-23023 May 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System Project stage: Supplement ML23145A0352023-05-31031 May 2023 Summary of May 17, 2023, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23156A2472023-06-0909 June 2023 Summary of Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23118A3752023-06-0909 June 2023 Summary of Audit Meeting with Constellation Energy Generation Concerning a Digital Instrumentation and Control Upgrade License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23177A2242023-06-26026 June 2023 Supplement to License Amendment Request to Revise the Licensing and Design Basis to Incorporate the Replacement of Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection . Project stage: Supplement PMNS20230846, Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 22023-07-18018 July 2023 Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2 Project stage: Meeting ML23187A0962023-07-19019 July 2023 Generation Station, Unit Nos. 1 and 2 - Revised Estimated Review Completion Date Concerning License Amendment Request to Replace Existing Safety-Related Analog Control Systems with a Single Digital Plant Protection System Project stage: Other 2023-02-23
[Table View] |
Text
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION December 11, 2025 Mr. Christopher H. Mudrick, Sr.
Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
DRAFT SAFETY EVALUATION FOR LIMERICK GENERATING STATION, UNITS 1 AND 2, DIGITAL INSTRUMENTATION AND CONTROLS LICENSE AMENDMENT REQUEST (EPID L-2022-LLA-0140)
Dear Mr. Mudrick:
By letter dated September 26, 2022 (Agencywide Documents Access and Management System Accession No. (ADAMS) ML22269A569; non-public), as supplemented by letters dated August 12, 2022 (ML22224A149), November 29, 2022 (ML22333A817), February 8, 2023 (ML23039A141), February 15, 2023 (ML23046A266), March 30, 2023 (ML23089A324), April 5, 2023 (ML23095A223), June 26, 2023 (ML23177A224), July 31, 2023 (ML23212B236),
September 12, 2023 (ML23255A095), October 30, 2023 (ML23303A223), November 21, 2023 (ML23325A206), January 26, 2024 (ML24026A296), February 26, 2024 (ML24057A427),
March 7, 2024 (ML24067A294), March 18, 2024 (ML24057A427), April 23, 2024 (ML24114A322), May 3, 2024 (ML24124A043), June 13, 2024 (ML24165A264), June 14, 2024 (ML24166A114), June 28, 2024 (ML24180A157), February 5, 2025 (ML25037A286),
February 21, 2025 (ML25055A156), April 4, 2025 (ML25094A145), June 3, 2025 (ML25154A616), July 2, 2025 (ML25183A133), July 10, 2025 (ML25191A223), July 30, 2025 (ML25211A294), September 8, 2025 (ML25251A214), September 26, 2025 (ML25269A191),
and October 1, 2025 (ML25274A140),Constellation Energy Generation, LLC (Constellation, the licensee) submitted license amendment requests (LAR) for Limerick Generating Station, Units 1 and 2, to the U.S. Nuclear Regulatory Commission (NRC) staff for review. Enclosed for Constellation review and comment is a copy of the NRC staffs draft safety evaluation (SE) for the LAR.
The supplement dated September 12, 2023, replaces in its entirety the original LAR dated September 26, 2022. The licensee replaced the original submittal, because the licensee had mistakenly included proprietary information in the non-proprietary parts of the request. The NRC staff made all the original submittal non-public. With the exceptions noted by the licensee in the letter dated September 12, 2023, the content of the replacement and the original are the same.
NOTICE: The enclosure to this letter contains proprietary information. Upon separation from the enclosure, this letter is DECONTROLLED.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION Pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations, we have determined that the enclosed draft SE contains proprietary information. If Constellation believes that any information in the enclosure is proprietary and has not been identified with appropriate portion markings (i.e., double bold brackets), please identify such information line-by-line. Also, we have determined that the draft SE does not contain any export control information. If Constellation believes that any export control information is in the draft SE, please identify such information line-by-line. While reviewing the draft SE to confirm proprietary information has been properly marked and export control information has been excluded, if Constellation believes it has identified any factual errors or has clarity concerns, please identify such errors or concerns line-by-line.
To facilitate the NRC staffs review of Constellations comments, if any, please provide a marked-up copy of the draft SE showing proposed changes and provide a summary table of the proposed changes. The NRC staffs disposition of Constellations comments on the draft SE may be discussed in the final SE. The final SE will be issued after making any necessary changes.
Note that at this stage of the review process, the NRC staff has completed our review of the submitted information and will not entertain additional technical arguments. The NRC staff conclusions and conditions will not change unless new information is provided on the docket that was not available during our review. The review of additional information will delay the issuance of the NRCs decision on the LAR.
Please provide Constellations comments, if any, within 10 working days of the date of this letter. If you have any questions, please contact Michael Marshall via phone at 301-415-2871 or via email at michael.marshall@nrc.gov.
Sincerely,
/RA/
Undine Shoop, Chief Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353
Enclosure:
Proprietary Draft Safety Evaluation cc: Listserv (without Enclosure)
ML25321A429 Letter w/Enclosure (Proprietary)
ML25349B290 Letter w/o-Enclosure OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NRR/DORL/LPL1/PM NAME MMarshall KEntz UShoop MMarshall DATE 11/17/2025 12/1/2025 12/10/2025 12/11/2025