ML25345A013
| ML25345A013 | |
| Person / Time | |
|---|---|
| Site: | Browns Ferry |
| Issue date: | 12/10/2025 |
| From: | Kimberly Green NRC/NRR/DORL/LPL2-2 |
| To: | Eckermann J Tennessee Valley Authority |
| Green K, NRR/DORL/LPL2-2 | |
| References | |
| EPID L-2025-LLA-0034 | |
| Download: ML25345A013 (0) | |
Text
From:
Kimberly Green To:
Eckermann, J Beau Cc:
Taylor, Andrew Charles; Aboulfaida, Amber Vendel; David Wrona; NRR_DORL_LPMB Resource
Subject:
Extension of Date to Issue Amendments for Browns Ferry Nuclear Plant, Units 1, 2, and 3 re Hydrologic Analysis (EPID L-2025-LLA-0034)
Date:
Wednesday, December 10, 2025 1:41:00 PM
Dear Mr. Eckermann:
By email dated March 19, 2025 (ML25078A178), I notified you of the NRC staffs acceptance review results for the subject request. In that email, I indicated that we could complete our review by March 19, 2026. However, due to the government shutdown and delayed completion of audit discussions, we are extending the expected completion date to May 19, 2026.
If you have any questions regarding the revised date, please feel free to contact me.
- Regards, Kimberly Green Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-1627