Extension of Date to Issue Amendments - Sequoyah and Watts Bar Nuclear Plants LAR to Add One RHR Pump Flow Path to LCO 3.5.2
ML25338A016
Person / Time
Site: Sequoyah, Watts Bar  Tennessee Valley Authority icon.png
Issue date: 12/03/2025
From: Kimberly Green
NRC/NRR/DORL/LPL2-2
To: Baron J, Hughes S
Tennessee Valley Authority
Green K, NRR/DORL/LPL2-2
References
EPID L-2024-LLA-0152
Download: ML25338A016 (0)


Text

From:

Kimberly Green To:

Hughes, Shawna; Baron, Jesse Shawn Cc:

Aboulfaida, Amber Vendel; David Wrona; NRR_DORL_LPMB Resource

Subject:

Extension of Date to Issue Amendments - Sequoyah and Watts Bar Nuclear Plants LAR to Add One RHR Pump Flow Path to LCO 3.5.2 (EPID L-2024-LLA-0152)

Date:

Wednesday, December 3, 2025 3:38:00 PM

Dear Ms. Hughes and Mr. Baron:

By email dated December 3, 2024 (ML24339B831), I notified you of the NRC staffs acceptance review results for the subject LAR. In that email, I indicated that we could complete our review by December 3, 2025. However, due to the government shutdown, we are extending the expected completion date to January 16, 2026. Our estimated level of effort remains unchanged.

If you have any questions regarding the revised date, please feel free to contact me.

Regards, Kimberly Green Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission 301-415-1627