Notification of NRC Baseline Inspection and Request for Information, Inspection Report 05000265/2026001
ML25335A167
Person / Time
Site: Quad Cities Constellation icon.png
Issue date: 12/03/2025
From: Magnuson D
NRC/RGN-III/DORS/ERPB
To: Mudrick C
Constellation Energy Generation
References
IR 2026001
Download: ML25335A167 (0)


See also: IR 05000265/2026001

Text

Christopher H. Mudrick

Senior Vice President

Constellation Energy Generation, LLC

President and Chief Nuclear Office (CNO)

Constellation Nuclear

200 Energy Way, KSA-3N

Kennett Square, PA 19348

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION, UNIT 2 - NOTIFICATION OF

NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION:

INSPECTION REPORT 05000265/2026001

Christopher H. Mudrick:

On March 23, 2026, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline

Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed

March 23, 2026, through April 3, 2026.

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. In order to minimize the impact to your onsite resources, and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

These documents have been divided into two groups.

The first group identifies information necessary to ensure that the inspector is adequately

prepared. The second group identifies the information the inspector will need upon arrival at the

site. It is important that all of these documents are up-to-date, and complete, in order to

minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

We have discussed the schedule for inspection activities with your staff and understand that our

regulatory contact for this inspection will be Richard Swart of your organization. If there are any

questions about this inspection or the material requested, please contact the lead inspector

Eric Magnuson at 630-829-9798, or via email at eric.magnuson@nrc.gov.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required

to respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

December 2, 2025

C. Mudrick

2

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Eric Magnuson

Engineering and Reactor Projects Branch

Division of Operating Reactor Safety

Docket No. 50-265

License No. DPR-30

Enclosure:

Document Request for Inservice Inspection

cc: Distribution via LISTSERV

Signed by Magnuson, Eric

on 12/02/25

C. Mudrick

3

Letter to Christopher H. Mudrick from Eric Magnuson dated December 2, 2025.

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION, UNIT 2 - NOTIFICATION OF

NRC BASELINE INSPECTION AND REQUEST FOR INFORMATION:

INSPECTION REPORT 05000265/2026001

DISTRIBUTION:

Rodney Clagg

RidsNrrDorlLpl3

RidsNrrPMQuadCities Resource

RidsNrrDroIrib Resource

Jack Giessner

Mohammed Shuaibi

Diana Betancourt-Roldan

John Pelchat

Jared Heck

Jennifer Dalzell

R3-DORS

ADAMS Accession Number: ML25335A167

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

OFFICE

RIII

NAME

EMagnuson:sw

DATE

12/02/2025

OFFICIAL RECORD COPY

Enclosure

Inspection Report: 05000265/2026001

Inspection Dates:

March 23, 2026-April 3, 2026

Inspection Procedures:

Inspection Procedure 71111.08, Inservice Inspection

Lead Inspector:

Eric Magnuson, DORS/ERPB

630-829-9798

A.

Information for the In-Office Preparation Week

The following information (electronic copy) is requested by February 23, 2026, to

facilitate the selection of specific items that will be reviewed during the onsite inspection

week. The inspector will select specific items from the information requested below and

request a list of additional documents needed onsite to your staff. We request that the

specific items selected from the lists be available and ready for review on the first day of

inspection. The following information is applicable to the outage Unit unless otherwise

indicated. If you have any questions regarding this information, please call the inspector

as soon as possible.

For the upcoming outage, a detailed schedule (including dates, is possible) and

description of:

a.

List of all Non-Destructive Examinations (NDEs) planned to be performed as part

of your American Society of Mechanical Engineers (ASME) Code Inservice

Inspection (ISI) Program (include edition and addenda of Code committed to),

and NDEs planned for other systems performed as part of a Risk-Informed

ISI Program, or other augmented inspection programs (e.g., ASME Code

Case N-770 examination of dissimilar metal welds and examinations to meet an

industry initiative). Description shall include component ASME Code Class,

component IDs, categorization (Section XI, Risk Informed, or Augmented, etc.),

and dates/times the NDEs are scheduled to be performed.

b.

List of Welding on Code Class 1, 2, or 3 components to be performed during the

outage.

c.

List identifying NDE reports (Volumetric, Surface, and Visual), which have

identified relevant indications on ASME Code Class 1 and 2 Systems since the

beginning of the last refueling outage. For indications that were accepted as-is for

continued service, provide schedule of successive exams required by Code.

d.

List of repair/replacement welds in ASME Code Class 1, 2, and 3 Systems, which

have been fabricated since the beginning of the last refueling outage.

2

e.

List of Title 10 CFR Part 21 reports applicable to your structures, systems, or

components within the scope of ASME Code Section XI that have been identified

since the beginning of the last refueling outage.

f.

List of corrective action documents related to ISI issues such as piping

degradation or damage, or errors identified during piping examinations since the

beginning of the last refueling outage.

g.

Copy of latest revision to the Inservice Inspection Program Plan.

h.

Point of contact information (names and site numbers) for ISI/Welding.

B.

Onsite Information to be provided to the inspector on the first onsite date.

The following information is requested for only specific items that are

selected by the inspector from list A above:

a) A copy of ASME Section XI, Code Relief Requests applicable to the selected

items.

b) Copies of applicable NDE procedures, weld procedure specifications (WPS),

NDE procedure qualification records, WPS qualification records, NDE personnel

performance qualification records, welder performance qualification records, and

ISI related corrective action documents.

c)

Copy of the ASME Section XI, Code of record for the selected items.

d) Copy of the applicable Code of Construction for repair/replacement activities on

selected items.