The U.S. Nuclear Regulatory Commission Staff’S Revised Schedule for Review and Approval of Framatomes Topical Report, ANP-10358P, Revision 0, Increased Burnup for Pressurized Water Reactors
ML25199A116
Person / Time
Site: 99902041
Issue date: 07/23/2025
From: Ngola Otto
Licensing Processes Branch
To: Elliott G
Framatome
Otto N, NRR/DORL/LLPB
References
EPID L-2024-TOP-0033
Download: ML25199A116 (1)


Text

July 23, 2025 Gayle Elliott, Director Licensing and Regulatory Affairs Framatome Inc.

3315 Old Forest Road Lynchburg, VA 24501

SUBJECT:

THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVISED SCHEDULE FOR REVIEW AND APPROVAL OF FRAMATOMES TOPICAL REPORT, ANP-10358P, REVISION 0, INCREASED BURNUP FOR PRESSURIZED WATER REACTORS (EPID L-2024-TOP-0033)

Dear Gayle Elliott:

By letter dated November 26, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24331A085), Framatome, Inc. (Framatome) submitted Topical Report (TR) ANP-10358P, Revision 0, Increased Burnup for Pressurized Water Reactors, for U.S. Nuclear Regulatory Commission (NRC) staffs review and approval. In the November 26, 2024, letter Framatome requested approval of the TR by March 2026 to support license amendment requests for potential customers. The NRC staff accepted the TR for review on January 29, 2025 (ML25023A196) and provided an initial review schedule. Since the acceptance, the NRC staff conducted an audit on March 25-27, 2025 (ML25106A159), issued requests for additional information (RAIs) on April 29, 2025 (ML25120A115), and conducted a follow-up audit on June 17, 2025 (ML25168A258). Framatome provided a response to the NRC staffs RAIs in letter dated June 20, 2025 (ML25171A043).

Based on the current review progress, the NRC staff will reduce the current review schedule by 5 months and plan to issue the Draft Safety Evaluation (SE) by November 21, 2025. The revised schedule milestones and assumptions are provided in the enclosed Revised Schedule.

This schedule information takes into consideration the NRCs current review priorities and available technical resources and may be subject to change. If modifications to these dates are deemed necessary, we will provide appropriate updates to this information. The revised schedule milestones were discussed between the Framatome and the NRC Project Manager on July 18, 2025. Please note that a potential reduction in the hours planned for this review due to the reduced schedule has not been evaluated.

The Advisory Committee on Reactor Safeguards (ACRS) will decide on whether it is interested in reviewing this TR, and as such, ACRS subcommittee and full committee meetings would occur after issuance of the draft SE but before the final SE is completed.

If you have any questions regarding this revised schedule and letter, please contact me at 301-415-6695 or via email at Ngola.Otto@nrc.gov.

Sincerely,

/RA/

Ngola A. Otto, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902041

Enclosure:

Revised Schedule

Enclosure Revised Schedule Milestone Initial Planned Date Revised Date Initial Submittal November 26, 2024 Acceptance January 30, 2025 January 29, 2025 Conduct Audit #1 March 2025 March 25-27, 2025 Issue Requests for Additional Information (RAI) Set #1 April 30, 2025 April 29, 2025 Response to RAI Set #1 June 30, 2025 June 20, 2025 Conduct Audit #2 August 2025 June 17, 2025 Issue RAI Set #2 September 2025 N/A Response to RAI Set #2 November 2025 N/A Issue Draft Safety Evaluation (SE)

April 30, 2026 November 21, 2025 Advisory Committee on Reactor Safeguards (ACRS) Sub-Committee Meeting June 2026 TBD ACRS Full Committee Meeting July 2026 TBD Issue Final SE August 31, 2026 TBD

ML25199A116

  • via eConcurrence NRR-106 OFFICE NRR/DORL/LLPB/PM*

NRR/DORL/LLPB/LA*

NRR/DSS/SFNB/BC*

NAME NOtto DHarrison SKrepel DATE 7/18/2025 7/22/2025 7/22/2025 OFFICE NRR/DORL/LLPB/BC*

NRR/DORL/LLPB/PM*

NAME JRankin NOtto DATE 7/23/2025 7/23/2025