ML25006A002
| ML25006A002 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 01/30/2025 |
| From: | Michael Mahoney NRC/NRR/DORL/LPL4 |
| To: | Meister R Entergy Operations |
| Wengert, Thomas | |
| References | |
| EPID L-2024-LLA-0158 | |
| Download: ML25006A002 (1) | |
Text
From:
Michael Mahoney To:
Meister, Richard Cc:
Tony Nakanishi; pcoutur@entergy.com
Subject:
Acceptance Review - Grand Gulf - License Amendment Request to Revise Technical Specifications Related to Spent Fuel Storage Racks (L-2024-LLA-0158)
Date:
Monday, December 30, 2024 12:58:00 PM Attachments:
image001.png Hi Rich, By letter GNRO2024-00033 dated November 25, 2024 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML24330A233), as supplemented by letter dated December 16, 2024 (ML24351A148), Entergy Operations, Inc. (Entergy, the licensee) submitted a license amendment request (LAR) to revise the Technical Specifications (TS) for Grand Gulf Nuclear Station, Unit 1 (Grand Gulf). The proposed amendment includes, 1) a revision to the criticality safety analysis for the spent fuel storage racks, 2) addition of requirements for the analysis for the fuel pool storage racks as contained in TS 4.3, Fuel Storage, Subpart 4.3.1, Criticality, and 3) the addition of requirements for monitoring of the neutron absorber material in the storage racks in TS 5.5, Programs and Manuals, new Subpart 5.5.15, Spent Fuel Storage Rack Neutron Absorber Monitoring Program.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the TS) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 565 hours0.00654 days <br />0.157 hours <br />9.341931e-4 weeks <br />2.149825e-4 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is December 30, 2025. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application, and they could change due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please let me know.
Thanks Mike Mahoney Senior Project Manager, LPL4 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Desk: (301)-415-3867 Mobile: (301)-250-0450 Email: Michael.Mahoney@nrc.gov