MEMORANDUM TO:
William T. Jessup, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM:
Mallecia A. Sutton, Senior Project Manager Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF THE JANUARY 24, 2023, CLOSED PRE-APPLICATION MEETING WITH TERRAPOWER, LLC TO DISCUSS THE FUEL HANDLING PROCESS AND EQUIPMENT OVERVIEW FOR THE NATRIUM DESIGN (EPID NO.
Meeting Information:
Applicant: TerraPower, LLC (TerraPower)
Docket/Project No.: 99902100 Public Meeting Notice: Agencywide Documents Access and Management System (ADAMS)
Accession No.: ML22325A094 Applicant Presentation Slides: ML23019A322 August 4, 2023 Signed by Sutton, Mallecia on 08/04/23
W. Jessup Meeting Summary:
The U.S. Nuclear Regulatory Commission (NRC) staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271). The main points of discussion during the meeting included:
On January 24, 2023, the NRC staff held a closed meeting with TerraPower. The purpose of the meeting was for TerraPower to provide the NRC staff with an overview of the fuel handling process and equipment overview for the Natrium design. Participants included representatives from TerraPower, the U.S. Department of Energy, General Electric Hitachi, Bechtel, and Duke Energy. The list of meeting attendees is provided in the enclosure to this summary.
The NRC staff began the meeting with introductions and explained that the meeting would be closed due to the discussion of proprietary information. During the meeting, TerraPower provided the NRC staff with an overview of the Natrium reactor, the fuel handling process and equipment overview for the Natrium design. TerraPower representatives and the NRC staff discussed the next steps for future interactions regarding the Natrium Reactor design.
CONTACT: Mallecia Sutton, NRR/DANU (301) 415-0673
Enclosure:
List of Meeting Attendees
W. Jessup
SUBJECT:
SUMMARY
OF JANUARY 24, 2023, CLOSED PRE-APPLICATION MEETING WITH TERRAPOWER, LLC TO DISCUSS THE FUEL HANDLING PROCESS AND EQUIPMENT OVERVIEW FOR THE NATRIUM DESIGN (EPID NO.
L-2021-LRM-0071) DATED: AUGUST 4, 2023 DISTRIBUTION:
PUBLIC RidsNrrDanuUal1 Resource RidsNrrDanu Resource MSutton, NRR CBanks, NRR DGreene, NRR WJessup, NRR ADAMS Accession Number: ML23055A037 NRR-052 OFFICE NRR/DANU/UAL1/PM NRR/DANU/UAL1/PM NRR/DANU/UAL1/BC NRR/DANU/UAL1/PM NAME CBanks MSutton WJessup MSutton DATE 7/27/2023 7/27/2023 8/3/2023 8/4/2023 OFFICIAL RECORD COPY
Enclosure List of Meeting Attendees Closed Pre-Application Meeting with TerraPower, LLC to Discuss Fuel Handling Process and Equipment Overview for the Natrium Design January 24, 2023 Name Organization Mallecia Sutton U.S. Nuclear Regulatory Commission (NRC)
Courtney Banks NRC Reed Anzalone NRC Steve Jones NRC Joseph Ashcraft NRC Calvin Cheung NRC Ryan Sprengel TerraPower, LLC (TerraPower)
Brian Johnson TerraPower Bryan Eyers TerraPower Dan Althouse TerraPower James Vollmer TerraPower Joseph LaPrad TerraPower Kyle Stanton TerraPower Lauren Neuburger TerraPower Matt Mareka TerraPower Mike Montecalvo TerraPower Nathan Smith TerraPower Nick Kellenberger TerraPower Owen Nelson TerraPower Pamela Fergen TerraPower Trevor McWilliams TerraPower Victoria Graham TerraPower Lisa Schichlein General Electric Hitachi Steve Kline Bechtel Daniel Patton Bechtel Lee Grzeck Duke Energy James Breuninger U.S. Department of Energy