ES-2.1 Facility:
Date of Examination:
Developed:
Written: Facility:
NRC:
//
Operating:
Facility:
NRC:
Days from Exam Target Date*
Chief Examiner's Initials
-240 06/18/22 JCN/RDB
-210 07/18/22 JCN/RDB
-210 07/18/22 JCN/RDB
-210 07/18/22 JCN/RDB
-210 07/18/22 JCN/RDB
-195 09/02/22 JCN/RDB
-150 09/16/22 JCN/RDB
-136 09/30/22 N/A
-100 11/18/22 JCN/RDB
-75 11/28/22 JCN/RDB
-60 12/15/22 JCN/RDB
-50 12/25/22 JCN/RDB
-50 12/25/22 JCN/RDB
-35 01/16/23 JCN
-30 01/14/23 JCN
-14 01/30/23 JCN
-7 02/06/23 JCN
-7 02/06/23 JCN
-7 02/06/23 JCN
-7 02/06/23 JCN
-7 02/06/23 JCN Exam Date:
02/13/2023
- 2. NRC examiners and facility contact assigned (B.1 and C.1-3).
- 3. Facility licensee contact briefed on examination security and other requirements (D.4). As applicable, the facility licensee contact submits to the NRC any prescreened K/As for elimination from the written examination outline, with a description of the facility licensees prescreening process (ES-4.1 A.1.a and ES-4.1 B.2).
- 4. Reference material due for NRC-prepared exams (F).
- 5. Examination kick-off call held (C.4) The NRC sends the corporate notification letter (A.5).
- 6. Written examination outline developed by the NRC and sent to the facility licensee contact (must be on the examination security agreement) (B.2, ES-4.1 A.1.b and ES-4.1 A.2.a).
Task Description (Reference)
- 1. Examination administration date confirmed (A.1-5). For NRC prepared examinations, arrangements are made for the facility licensee to submit reference materials (B.4, C.4.g, & F).
Form ES-2.1-1 February 13, 2023 Point Beach Examination Preparation Checklist
- 7. Operating test outlines and checklists due. Forms 1.3-1, 2.3-1, 3.2-1, 3.2-2, 3.3-1, and 3.4-1, as applicable (B.6). Facility licensee provides a draft operating test administration schedule to the NRC (B.18).
- 8. Operating test outlines reviewed by the NRC and feedback provided to facility licensee (ES-2.3).
- 9. NRC-prepared examinations are approved by the NRC supervisor and forwarded for facility licensee review (ES-2.3).
- 11. Preliminary waiver/excusal requests due (ES-2.2 E.1).
- 10. Proposed examinations (written, JPMs, and scenarios, as applicable) and outline forms; quality checklists and supporting documentation (including Forms 2.3-2 and 2.3-4 and any Form 2.3-1, 1.3-1, and 3.4-1 updates); and reference materials due.
- 12. Written examination and operating test reviews completed (ES-2.3). The NRC supervisor's authorization to proceed with the facility review granted (ES-2.3 D).
- 14. Examination preparatory week conducted by the NRC and the facility licensee (l).
- 15. Preliminary license applications, including any waiver/excusal requests, due (ES-2.2 C.1).
- 16. Final license applications, including any waiver/excusal requests, due and Form 2.2-1 prepared (ES-2.2 C and E).
- 17. Written examinations and operating tests approved by the NRC supervisor (C.9).
- 13. Examination review results discussed between the NRC and facility licensee (B.14).
- 18. Facility licensee management feedback on the examination requested by the NRC supervisor (C.10).
- 19. Final applications reviewed; 10% of applications audited to confirm qualifications/eligibility (ES-2.2 G); and examination approval letter (Letter 2.3-1) and waiver/excusal letters sent.
- 20. Written examination administration guidelines reviewed with the facility licensee (D.14).
- 21. Approved scenarios and job performance measures distributed to NRC examiners (D.12).
- Target dates are based on facility licensee-prepared examinations and the examination date identified in the corporate notification letter.
These dates are for planning purposes and may be adjusted in coordination with the facility licensee.