- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARND-21-0973, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361)2021-10-29029 October 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361) Project stage: Request ML21342A2922021-11-0202 November 2021, 9 December 2021 Update to Targeted Inspections, Tests, Analyses, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 3 and 4 Project stage: Request ND-21-0982, ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462)2021-11-0303 November 2021 ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462) Project stage: Request ND-21-0992, ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815)2021-11-0404 November 2021 ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815) Project stage: Request ND-21-0377, ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116)2021-11-0505 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116) Project stage: Request ND-20-0801, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2021-11-0808 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ND-21-0995, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2021-11-10010 November 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) Project stage: Request ND-21-0167, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816)2021-11-11011 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816) Project stage: Request ND-21-0038, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2021-11-12012 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-21-0713, ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)2021-11-17017 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716) Project stage: Request ND-21-1010, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670)2021-11-18018 November 2021 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670) Project stage: Request ND-21-1025, Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565)2021-11-24024 November 2021 Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565) Project stage: Request ND-21-0757, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2021-12-0202 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) Project stage: Request ND-21-0769, ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120)2021-12-0707 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120) Project stage: Request ND-20-1378, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2021-12-0808 December 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-21-1084, ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322) Project stage: Request ND-21-1036, ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214) Project stage: Request ND-21-0779, ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459) Project stage: Request ND-21-1030, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-21-1022, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291)2021-12-16016 December 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291) Project stage: Request ND-21-0993, ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67)2021-12-16016 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67) Project stage: Request ND-21-0270, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644)2021-12-17017 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644) Project stage: Request ND-21-0802, ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91) Project stage: Request ND-21-1095, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75)2021-12-21021 December 2021 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75) Project stage: Request ND-21-0956, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) Project stage: Request ND-21-0990, ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572)2021-12-27027 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572) Project stage: Request ND-21-0744, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2022-01-21021 January 2022 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) Project stage: Request ND-20-0582, ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491) Project stage: Request ND-22-0049, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654) Project stage: Request ND-22-0052, ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655)2022-01-27027 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655) Project stage: Request ND-22-0080, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422)2022-02-0404 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422) Project stage: Request ND-21-1026, ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579)2022-02-14014 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579) Project stage: Request ND-22-0051, (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652)2022-02-16016 February 2022 (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652) Project stage: Request ND-21-0796, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) Project stage: Request ND-22-0070, ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821) Project stage: Request ND-22-0103, ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501) Project stage: Request ND-22-1157, ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703)2022-02-17017 February 2022 ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703) Project stage: Request ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647) Project stage: Request ND-21-0271, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) Project stage: Request ND-21-0654, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) Project stage: Request ND-22-0131, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593) Project stage: Request ND-21-0795, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) Project stage: Request ND-21-0092, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454)2022-02-22022 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454) Project stage: Request ND-21-0723, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2022-02-22022 February 2022 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) Project stage: Request ND-22-0046, ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878) Project stage: Request ND-22-0092, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-22-0085, ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399) Project stage: Request ND-20-0880, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455) Project stage: Request ND-22-0088, ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582) Project stage: Request ND-22-0148, ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616)2022-02-25025 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616) Project stage: Request 2021-12-21
[Table View] |
Text
Southern Nuclear Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 tel Docket No.:
52-025 FEB 2 8 2022 ND-22-0079 IOCFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of 2.3.04.04.11 [Index Number 3311 Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria ITAAC item 2.3.04.04.ii [Index Number 331]
for flow rate from the two highest fire-hose stations when aligned to the Passive Containment Cooling Water Storage Tank (PCCWST) is not less than 75 gallons per minute (gpm). The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted.
MichaelJ. Yox (/ \\y Regulatory Affairs Dir^tor Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.3.04.04.ii [Index Number 331]
MJY/DLW/sfr
U.S. Nuclear Regulatory Commission ND-22-0079 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Belike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Reoulatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. McCurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-22-0079 Page 3 of 3 Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Daiton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani Mr. D. 0. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NU8, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GD8 Associates, Inc.
Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-22-0079 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-22-0079 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.3.04.04.ii [index Number 331]
U.S. Nuclear Regulatory Commission ND-22-0079 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment
- 4. The FPS provides for manual fire fighting capability in plant areas containing safety-related equipment.
inspections/Tests/Anaivses ii) Testing will be performed by measuring the water flow rate as it is simultaneously discharged from the two highest fire-hose stations and when the water for the fire is supplied from the PCS storage tank.
Acceptance Criteria ii) Water is simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gpm.
ITAAC Determination Basis Multiple ITAAC are performed to demonstrate the Fire Protection System (FPS) provides for manual fire fighting capability in plant areas containing safety-related equipment. This ITAAC performed testing by measuring the water flow rate as it was simultaneously discharged from the two highest fire-hose stations when the water for the fire system was supplied from the Passive Containment Cooling System (PCS) storage tank.
Testing was performed as documented in Reference 1 using instruction in the Unit 3 preoperational test to confirm that when the water for the FPS was supplied from the PCS storage tank, water was simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gallons per minute (gpm). The 2 highest fire-hose stations in plant areas containing safety-related equipment was determined to be F151A (room 12506) and F151B (room 12504). The flow measurement was performed at a level above the Primary Containment Cooling Water Storage Tank (PCCWST) technical specification minimum since the level in the tank will have negligible impact on gravity flow. There is a 1.1 foot elevation difference between the maximum PCCWST level and the technical specification minimum and a 187 foot elevation difference between the maximum PCCWST level and the highest fire-hose stations. The fire protection system was aligned to isolate the normal fire protection from the tested fire hose stations and the PCS storage tank was aligned to provide water to the fire-hose stations being tested. Ultrasonic flow instruments were installed upstream of the fire-hose stations and the fire hose was run and secured to a suitable drain. The fire-hose station isolation valves were opened, flow was monitored at each flow instrument and recorded approximately every 10 seconds and 30 readings were taken. The flow readings were corrected for measurement uncertainty and compared to the acceptance criteria. The flow for Unit 3 F151A was 82 gpm and 95 gpm for Unit 3 F151B. The completed test results, contained in Reference 1, confirm that water was simultaneously discharged from each of the two highest fire-hose stations in plant areas containing safety-related equipment at not less than 75 gpm.
U.S. Nuclear Regulatory Commission ND-22-0079 Enclosure Page 3 of 3 Reference 1 is available for NRG Inspection as part of the ITAAC 2.3.04.04.11 Completion Package (Reference 2).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.3.04.04.11 (Reference 2) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.3.04.04.11 was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC Inspection)
- 1. SV3-FPS-ITR-800331, Rev 0, "Unit 3 Recorded Results of PCS Storage Tank Discharge to Two Highest Fire-hose Stations: ITAAC 2.3.04.04.11"
- 2. 2.3.04.04.ii-U3-CP-Rev0, ITAAC Completion Package