R. Franseen
February 03, 2022
EA-21-096
Mr. Robert Franssen, Site Vice President
Entergy Operations, Inc.
Grand Gulf Nuclear Station
P.O. Box 756
Port Gibson, MS 39150
SUBJECT: GRAND GULF NUCLEAR STATION - ACKNOWLEDGMENT OF RESPONSE TO
NOTICE OF VIOLATION AND NRC INSPECTION REPORT 05000416/2021091
AND 05000416/2021092 AND INVESTIGATION REPORTS 4-2019-021, 4-2020-
025, AND 4-2020-029
Dear Mr. Franssen:
This letter acknowledges your letter to the U.S. Nuclear Regulatory Commission dated January
25, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No.
ML22031A156), which provided a response to the Notice of Violation that was issued in NRC
Inspection Reports 05000416/2021091 and 05000416/2021092, and Investigation Reports 4-
2019-021, 4-2020-025, and 4-2020-029, dated December 15, 2021 (ADAMS Accession No.
ML21349B337). This Notice of Violation included violations involving: (A) an exam proctor
willfully providing inappropriate assistance to engineering students during engineering support
qualification examinations, (B) inaccurate information deliberately entered into a condition report
(CR), and (C) a senior security supervisor deliberately performed maintenance on a personal
security access control device without initiating a CR.
We have reviewed your response regarding violations B and C and find that it meets the
requirements of 10 CFR 2.201. As previously stated in Inspection Report 05000416/2021092
the NRC has concluded that information regarding: (1) the reason for Violation A (EA-20-125);
(2) the corrective actions that have been taken and the results achieved; and (3) the date when
full compliance was achieved is already adequately addressed on the docket in your March 25,
2021 (ADAMS Accession No. ML21085A565), written response. We will review implementation
of your corrective actions for all three violations in a future inspection to determine whether full
compliance has been achieved and maintained.
The Regional Administrator has previously authorized follow-up inspection to be performed
using Inspection Procedure 92702, Follow-Up on Traditional Enforcement Actions Including
Violations, Deviations, Confirmatory Action Letters, and Orders, to review your actions to
address all three violations. This inspection will be scheduled when you notify the NRC of your
readiness.
R. Franssen
2
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice and Procedure, a copy of
this letter will be available electronically for public inspection in the NRCs Public Document
Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide
Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
Jeffrey Josey, Chief
Reactor Project Branch C
Division of Reactor Projects
Docket No. 05000416
License No. NPF-47
cc w/ encl: Distribution via LISTSERV
Signed by Josey, Jeffrey
on 02/03/22
SUNSI Review By:
PJV
ADAMS:
Yes No
Sensitive
Non-Sensitive
Non-Publicly Available
Publicly Available
Keyword
OFFICE
PE:DRP/C
SPE:DRP/C
TL:ACES
BC:DRS/EB2
BC:DRP/C
NAME
DNani
PVossmar
JGroom
ASiwy
JJosey
SIGNATURE
/RA/
/RA/
/RA/
/RA/
/RA/
DATE
2/2/2022
2/1/2022
2/2/2022
2/1/2022
2/3/2022