General Atomics Triga Reactor Facility Final Status Survey Report -Cover Letter
ML21012A273
Person / Time
Site: General Atomics
Issue date: 12/14/2020
From: Grogan M
General Atomics
To: Marlayna Vaaler Doell
Reactor Decommissioning Branch
Doell M
Shared Package
ML21012A268 List:
References
38/67-5040
Download: ML21012A273 (1)


Text

.

/

December 14,2020 38/67-5040 VIAOVERNIGHT DELIVERY SERVICE Document Control Desk ATTN:Ms.Marlayna Doell,Project Manager Reactor Decommissioning Branch Division ofDecommissioning, UraniumRecovery

&WastePrograms Office ofNuclear Material Safety andSafeguards U.S.Nuclear RegulatoryCommission TwoWhiteFlint

North, Mailstop 8F8 11545Rockville Pike Rockville, Maryland 20852-2738

Subject:

Docket No.50-89, Facility License R-38, and Docket No.50-163, Facility License R-67; Submittal ofGeneral Atomics TRIGAA Reactor Facility (TRF)

Final Status SurveyReport

References:

1 "General Atomics TRIGAReactorFacility Decommissioning Plan",

GAReport PC-000482, Rev.3,July1999 2."TRIGAReactor Facility Final Status Survey Plan, Rev.2,General

Atomics, February 2020

DearMs.Doell:

Thepurpose ofthis letter istorequest termination ofGeneral Atomics' Mark I(License R-38)andMarkF (License R-67)

TRIGAS research reactor licenses following completion of decontamination, decommissioning andfinal survey activities inaccordance with GA'sNRC-approved TRIGAReactor Facility Decommissioning Plan(Ref.

1)andsupplemental NRC-approved Final Status Survey Plan(Ref.

2).

Herein GAprovides information demonstrating that alllandareascomprising GA'sTRFandallfacilities thereon (authorized locationsunder the jurisdiction ofR-38andR-67) havebeendecontaminated, asneeded,inaccordance with criteria setforth in10CFR20Subpart E.

Should youneedadditional information concerning theabove,please contact meat(858) 455-2809 orbyemailmichael.grogan@ga.com, orMr.PaulPater at(858) 455-2758 orat paul.pater@ga.com.

Verytrul rs,

/

/

i/#

A o

MhaelGrogan, S

Licensing, Safety andNuclear Compliance

Enclosures:

1)Final Status Survey Report fortheGeneral Atomics TRIGA*

Reactor

Facility, datedDecember 2020(2Copies) 3550GENERALATOMICS COURT,SANDIEGO,CA92121-1122 POBOX85608,SANDIEGO,CA92186-5608 (858) 455-3000