Informs That Licensee Identified Addl Problems W/Analysis Documentation Associated W/Updated Seismic Hazard Analysis Performed by Risk Engineering,Inc,Submitted on 971201 & Revised 980306
ML20249B921
Person / Time
Site: Paducah Gaseous Diffusion Plant
Issue date: 06/18/1998
From: Toelle S
UNITED STATES ENRICHMENT CORP. (USEC)
To: Knapp M
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
References
GDP-98-0125, GDP-98-125, TAC-L32054, NUDOCS 9806250050
Download: ML20249B921 (3)


Text

_

l l-Q-

~

USEC A cla6ai Eaerry compaar u

June 18,1998 GDP 98-0125 i

Dr. Malcolm R. Knapp Acting Director, Office of Nuclear Material Safety and Safeguards Attention: Documen' Control Desk f

U.S. Nuclear Regulawry Commission Washington, D.C. 20555-0001 Paducah Gaseous Diffusion Plant (PGDP)

Docket No. 70-7001 Compliance Plan Issue 36 - Updated Seismic Hazard Analysis (TAC No. L32054) l

Dear Dr. Knapp:

{

In a letter dated May 13,1998 (Reference 1), the NRC requested additional information to complete its review of the updated seismic hazard analysis performed by Risk Engineering, Inc.

(REI) that was originally submitted to the NRC on December 1,1997 and revised on March 6,1998.

On May 18-19,1998, a meeting was held in REI's offices in Boulder, Colorado to discuss the NRC's information request. As part of that meeting, the NRC reviewed the supporting documents prepared by REI and its subcontractors and identified several problems with the analysis documentation.

These problems were discussed at the meeting and are further described in the NRC's June 2,1998 i

meeting summary (Reference 2). Related deficiencies were also identified by PGDP Engineering f

personnel, l

In response to these documentation issues, during the week of June 8,1998, an evaluation

)

i of REI's implementation of the USEC Quality Assurance Program and implementing procedures and l

l a comprehensive review of the quality documentation associated with this project was conducted by l

l members of the PGDP Engineering and Safety, Safeguards, and Quality organizations in REI's l

offices. Based on this review, additional problems with the analysis documentation have been j

identified.

PGDP personnel are currently working with REI to resolve all identified deficiencies and to make the necessary corrections to the analysis documentation. This effort will be completed by August 28,1998. Based on resolving all identified deficiencies in the analysis documentation, USEC's responses to the NRC's May 13,1998 questions will be submitted by August 28,1998.

In addition to the above actions, by August 28,1998, a review ofcurrent policies, practices, I

H and procedures related to the control of subcontractors will be pe' formed and any necessary charges I

h) P "y

. identified.

9806250050 900619

~~

PDR ADOCK 07007001 C

PDR

c Drive, Bethesda, MD 20817-1818 m

2'avo{3{

Telephone 301-564-3200 Fax 301-564-3201 http://www.usec.com DON 2 2 g r

[

Offices in Livermore, CA Paducah, KY Portsmouth. OH Washington, DC 1

T T :..

c.,.-

]

Dr. Malcolm R. Knapp

j June 18,1998

]

GDP 98-0125, Page 2 1

1{

Should you have any questions related to this subject, please contact Steve Routh at (301) h 564-3251. Commitments contained in this submittal are identified in the enclosure.

e' I!

Sincerely,

$.C. kdk-(0/'

Steven A.Toelle Nuclear Regulatory Assurance and Policy Manager 3

i

References:

1.

Letter from Mr. Robert C. Pierson (NRC) to Steven A. Toelle (USEC),,

"Paducah Gaseous Diffusion Plant Seismic Hazard Analysis," U.S. Nuclear a

Regulatory Commission, Docket No. 70-7001, May 13,1998.

2.

NRC Memorandum from Drew Persinko to Robert C. Pierson, " Meeting Summary - Paducah Seismic Hazard Study with U.S. Enrichment Corporation," June 2,1998.

1'

Enclosure:

Commitments Contained in this Submittal u

cc:

Mr. Robert C. Pierson, NRC NRC RegionIII Office l

NRC Residentinspector-PGDP j

NRC Resident Inspector-PORTS

(!

a l

b 1

i.

l1 l

I!

D

?

O L

lu---------------

7 __.. _ _ - _ _ _ - _ _ _ _ _ _ - _

[

1

~

Enclosure GDP 98-0125 f

Page1ofI s

r Commitments Contained in this Submittal 1.

PGDP personnel are currently working with REI to resolve all identified deficiencies and to make the necessary corrections to the analysis documentation. This effort will be completed

.i by August 28, 1998. Based on resolving all identified deficiencies in the analysis documentation, USEC's responses to the NRC's May 13,1998 questions will be submitted by August 28,1998.

2.

By August 28,1998, a review of current policies, practices, and procedures related to the control of subcontractors will be performed and any necessary changes identified.

i 4

a O

g.

s