Informs That Action Plan for Insp of Unit 2 Pressurizer Instrument Nozzle Weld Flaw Will Be Prepared by 990226,as Committed to in 980806 Telcon W/Nrc.Based on Results,Util Will Develop & Implement Appropriate Corrective Actions
ML20237D915
Person / Time
Site: Calvert Cliffs Constellation icon.png
Issue date: 08/25/1998
From: Cruse C
BALTIMORE GAS & ELECTRIC CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9808280022
Download: ML20237D915 (1)


Text

Cu anu.s 11. Curss:

11alunmre Gas and Electric Company

%ce PreOdent Cahen Chffs Nuclear Pow er Plant Nuclear Energy 1650 Cah en Chffs Parkway Lusb). Mary land 20657 410 495-4455 l

August 25,1998 J

U. S. Nuclear Regulatory Commission Washington,DC 20555 ATTENTION:

Document Control Desk

SUBJECT:

Calvert Cliffs Nuclear Power Plant l

Unit No. 2; Docket No. 50-318 l

Pressurizer Instrument Nonle Weld Flaw

REFERENCE:

(a)

Telephone Conference, Beween Mr. J. M. Osbome, et al (BGE) and Mr. B. J. Elliot (NRC), August 6,1998, Calvert Cliffs' Unit 2 Pressurizer Instrument Nozzle Leak L

t During Reference (a), the Baltimore Gas and Electric Company committed to provide a date for preparation of an action plan to inspect the Unit 2 pressurizer instrument nozzle weld Daw.

I l

The action plan for inspection of the Unit 2 pressurizer instrument nozzle weld Daw will be prepared by J

February 26,1999.

l Baltimore Gas ~and Electric Company will make the results of the inspection available to the NRC as they are obtained. Based on the results, we will develop and implement appropriate corrective actions.

,l.,,q.,,

Should you have questions regarding this matter, we will be pleased to discuss them with you.

Very truly yours, f

kf

t. -

CHC/JKK/dlm cc:

R. S. Fleishman, Esquire H. J. Miller, NRC J. E. Silberg, Esquire Resident inspector, NRC S. S. Bajwa, NRC R.1. McLean, DNR A. W. Dromerick, NRC J. H. Walter, PSC 9808280022 980825 PDR ADDCK 05000318

..