Forwards Insp Rept 50-285/86-23 on 860801-0930 & Notice of Violation.Response to Violation a Unnecessary Since Corrective Action Already Taken.Notice of Violation Withheld (Ref 10CFR73.21)
ML20213E947
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 11/07/1986
From: Gagliardo J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Andrews R
OMAHA PUBLIC POWER DISTRICT
Shared Package
ML20213E949 List:
References
NUDOCS 8611130386
Download: ML20213E947 (3)


See also: IR 05000285/1986023

Text

NOV

T 126

-

o

-In Reply Refer To:

Docket: 50-285/86-23

Omaha Public Power District

ATTN:

R. L. Andrews, Division Manager-

Nuclear Production

1623 Harney Street

Omaha, Nebraska 68102

Gentlemen:

This refers to the inspection conducted by Messrs. P. H. Harrell and M. E. Murphy

of this office during the period August 1 through September 30, 1986, of

activities authorized by NRC Operating License DPR-40 for the Fort Calhoun

Station, and to the discussion of our findings with you and other members of

your staff at the conclusion of the inspection.

Areas examined during the inspection included operational safety verification,

maintenance, surveillance, plant tours, safety-related system walkdowns,

security observations, review of the tests and experiments program, followup on

previously identified items, followup on a licensee event report, and

management organizational changes. Within these areas, the inspection

consisted of selective examination of procedures and representative records,

i

interviews with personnel, and observations by the inspector. The inspection

findings are documented in the enclosed inspection report.

During this inspection, it was found that certain of your activities were in

violation of NRC requirements.

Consequently, you are required to respond to

these violations, in writing, in accordance with the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2. Title 10, Code of Federal Regulations.

Your response should be based on the specifics contained in the Notice

of Violation enclosed with this letter.' Since it was also found during this

inspection that you had taken corrective action, including action to prevent

recurrence, for Violation A, no response to that violation need be submitted.

The material enclosed in Appendix A and Safeguards Attachment to Appendix B

contains Safeguards Information as defined by 10 CFR Part 73.21 and its

disclosure to unauthorized individuals is prohibited by Section 147 of the

Atomic Energy Act of 1954, as amended. Therefore, the material contained in

Appendix A and Attachment will not be placed in the Public Document Room.

We have also examined actions you have taken with regard to previously

identified inspection findings. The status of these items is identified in

paragraph 2 of the enclosed report.

8611130386 861107

PDR

ADOCK 05000285

G

PDR

-

_-

---

.-

RIV:

RIV.gl

EP&Q

C:EP& P

C:RPB/

C:RPB d

PHarrell:nc MMur hy RCaN

11 LYande

Dfiunte

JGagliardo

Ib/Sp/86

P/9 /86 9 / /86 6/61/86

W/h /86 l' / /86

REMOVAL OF THE PAGES MARKED " SAFEGUARDS INFORMATION"

t

_ DECONTROLS THE REMAINDER OF THIS DOCUMENT.

I

I

,

_

__

_

_ _

__

_

.-_

_ _ . . _ _ _ . _ _ . _ . - _ . _ _ _

,

.

,

.

!

Y

~

,

Omana Public Power District

-2-

l

One unresolved item is identified in paragraph 11 of the enclosed inspection

report.

i

The response directed by this letter and the accompanying Notice is not subject

to the clearance procedures of the Office of lianagement and Budget as required

j

by the Paperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this inspection, we will be pleased to

.

discuss them with you.

j

l

Sincerely,

,

>

ORIGINAL SIGNED BY:

l

J. E. Gagliardo, Chief

Reactor Projects Branch

$

Enclosures:

1

1.

Appendix A - Notice of Violation

which is Safeguards Information

.

l

2.

Appendix B - NRC Inspection Report

50-285/86-23

,

3.

Safeguards Attachment to Appendix B

U

i

cc report w/o Appendix A which is safeguards information and Safeguards

l

Attachment to Appendix B:

l

W. G. Gates, Manager

l

Fort Calhoun Station

i

P. O. Box 399

!

Fort Calhoun, Nebraska 68023

i

l

Harry H. Voigt, Esq.

LeBoeuf, Lamb, Leiby & MacRae

'

i

1333 New Hampshire Avenue, NW

i

Washington, DC 20036

)

Kansas Radiation Control Program Director

i

Nebraska Radiation Control Program Director

i

bcc: Copy of entire report maintained in RIV Security Files and sent to:

G. McCorkle, NMSS

J. Gibson, SSPD/NRR

j

IE File

Resident Inspector

j

R. D. Martin, RA

Security Inspector

Chief. EPSPS

D. Powers, E0

i

R. L. Bangart

REMOVAL OF THE PAGES MARKED " SAFEGUARDS INFORMATION_"_

l

l

DECONTROLS THE REMAINDER OF THIS DOCUMENT,

'

_ . . . _ _ _ _ . _ _ - . . . _ _ _ _ . . . . _ . , _ _ _ _

.

.

,

._ ,. _. _ ,. _ _ ,,.., _ _ _

-

w

.

Omaha Public Power District

-3-

bcc: RIV - Copy of report w/o Appendix A which is Safeguards Information and

Safeguards Attachment to Appendix B and w/766:

RPB

D. Weiss, LFMB (AR-2015)

Section Chief (RPSB)

RIV File

MIS

RSTS Operator

R&SPB

bec: RIV - Copy of report w/o Appendix A which is Safeguards Information and

Safeguards Attachment to Appendix B w/o 766:

MB-IE04

E.H. Johnson, DRS&P

R_EMOVAL OF THE PAGES MARKED " SAFEGUARDS

DECONTROLS THE REMAINDER OF THIS DOCUMENT.