July 6, 2020 Mr. Don Moul Executive Vice President, Nuclear Division, and Chief Nuclear Officer NextEra Energy Seabrook, LLC Mail Stop: NT3/JW 15430 Endeavor Drive Jupiter, FL 33478
SUBJECT:
SEABROOK STATION, UNIT NO. 1 - WITHDRAWAL OF RELIEF REQUEST (EPID L-2020-0041)
Dear Mr. Moul:
By letter dated March 20, 2020 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML20080J159), NextEra Energy Seabrook, LLC (NextEra) submitted a request for relief for Seabrook Station, Unit No. 1. The proposed relief would have allowed the use of American Society of Mechanical Engineers approved Code Case OMN-13, Performance-Based Requirements for Extending Snubber Inservice Visual Examination Interval at LWR Power Plants, Revision 2. Subsequently, by letter dated June 18, 2020 (ADAMS Accession No. ML20170A523), NextEra withdrew the request.
The purpose of this letter is to advise that the above-cited request for relief is being treated as withdrawn.
Sincerely,
/RA/
Justin C. Poole, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-443 cc: Listserv