ML20134F787
| ML20134F787 | |
| Person / Time | |
|---|---|
| Site: | Clinton |
| Issue date: | 08/06/1985 |
| From: | Chan T, Georgiev G, Heishman R, Mclellan T, Nemoto J, Peranich M, Smeenge R, Stein S NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III), NRC OFFICE OF INSPECTION & ENFORCEMENT (IE) |
| To: | |
| Shared Package | |
| ML20134F777 | List: |
| References | |
| 50-461-85-30, NUDOCS 8508210250 | |
| Download: ML20134F787 (125) | |
See also: IR 05000461/1985030
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION
OFFICE OF INSPECTION AND ENFORCEMENT
DIVISION OF INSPECTION PROGRAffS
REACTOR CONSTRUCTION PROGRAMS BRANCH
Report No.:
50-461/85-30
Docket No.:
50-461
Licensee:
Illinois Power Company
Facility Name:
Clinton Power Station
Inspection At:
Clinton, Illinois
Inspection Conducted:
flay 20-31 and June 10-21, 1985
Inspectors:
/ [ //Mor/Ed
/I
~ h, Chief, Construction Programs /
Date Signed
li. W. Per
c
CAT S
ion Team Le
$6/85
ons uction Engineer
Date Signed
T.(L.#LhaT, Reactor
P A ,e
M'
S h5
G. B. g giev,L5r. Rdactor Co
uction Engineer
Date'51gned
VO b.J
bbW
T. K. McLellan, Reactor Construction Engineer
Date Signed
0
(/f
8/fo/85
I. Nemoto, Reactor Construction Engineer
Da'te signed
//b Aff97fc^
R///SV
[R.J.5meenge,ReactorInspector(RegionIII)
Date Signed
2 st A u n?'
warc
[4
5. R. Stein, Reactor Construction Engineer
Date Signed
~
Consultants:
A. V. DuBouchet, D. C. Ford, J. B. McCormack,
0. P. Mallon, W. S. Marini, E. Y. ifartindale,
R. E. Serb and W. J. Sperko, Jr.
Approved By:
c
M
Robert F. Heishman, Chief
Date Signed
Reactor Construction Programs Branch
8508210250 850015
DR
ADOCK 050
1
_ - _ _ - _ - - _ -
-
.
.
,
1
l
TABLE OF CONTENTS
,
1
1
TOPIC
SECTION
INSPECTION SCOPE AND OBJECTIVES..................................
I
ELECTRICAL AND INSTRUMENTATION CONSTRUCTION......................
II
MECHANICAL CONSTRUCTION..........................................
III
WELDING AND NONDESTRUCTIVE EXAMINATION...........................
IV
CIVIL AND STRUCTURAL CONSTRUCTION................................
V
MATERIAL TRACEABILITY AND CONTR0L................................
VI
DESIGN CHANGE CONTR0L............................................
VII
CORRECTIVE ACTION SYSTEMS........................................
VIII
ATTACHMENT A - PERSONS CONTACTED AND DOCUMENTS REVIEWED
ATTACHMENT B - GLOSSARY OF ABBREVIATIONS
l
l
l
l
I
l
_____s
_
I.
INSPECTION SCOPE AND OBJECTIVES
The objective of this inspection was to evaluate the adequacy of
construction at the Clinton Power Station site.
This objective was accom-
plished through review of the construction program, evaluation of project
construction controls, and review of selected portions of the Quality
Assurance Program, with emphasis on the installed hardware in the field.
The scope and significance of identified problems were also determined.
In
addition, a sample of the results of the licensee's Overinspection Program
were compared with the NRC CAT inspection findings in applicable areas
inspected.
Within the areas examined, the inspection consisted of a detailed examina-
tion of selected hardware subsequent to quality control inspections, a
selective examination of procedures and representative records, and limited
observation of in process work.
For each of the areas inspected, the following was determined:
Were project construction controls adequate to assure quality
'
construction?
Was the hardware or product fabricated or installed as designed?
Were quality verifications performed during the work process with
applicable hold points?
i
Was there adequate documentation to determine the acceptability of
installed hardware or product?
Are systems turned over to the startup organization in operable
condition and are they being properly maintained?
I-l
_
_-
.
_ _ -
_
. _ _ _ . . _ _
__
.-
_
.
II.
ELECTRICAL AND INSTRUMENTATION CONSTRUCTION
A.
Objective
The primary objective of the appraisal of electrical and instrumentation
construction was to determine whether safety-related components and
,
systems were installed in accordance with regulatory requirements,
Safety Analysis Report commitments, and approved vendor and construction
specifications and drawings.
Additional objectives were to determine
whether procedures, instructions and drawings used to accomplish
construction activities were adequate and whether quality related
records accurately reflected the completed work.
B.
Discussion
Within the broad categories of electrical and instrumentation
construction, attention was given to several specific areas.
These
included electrical cable, raceways and raceway supports, electrical
equipment, and instrumentation piping and components. Additionally,
a review was made of a selected number of documents associated with
design change control and nonconformance reporting.
A number of inspection samples in several areas coincided with either
Baldwin Associates' Field Verification (BAFV) Program or Illinois
Power Company's Overinspection (IPOI) Program.
These are identified
in the following sections along with an assessment of the programs'
findings compared to the observations of this inspection.
Refer to
Section VII, Design Change Control, of this report for further
discussion of the IPOI Program.
1.
Electrical Raceway Installation
a.
Inspection Scope
Seventy segments of installed Class 1E cable tray, representing a
total length of about 1,200 feet, were selected from various plant
areas for detailed examination by the NRC Construction Appraisal
Team (CAT).
These segments were inspected for compliance to
requirements relative to routing, location, separation, identifica-
tion, protection, physical loading, support spacing and support
configuration.
Additionally, 31 runs of installed conduit, with an
aggregate length of about 1,000 feet, were inspected for compliance
to specified requirements such as routing, location, separation,
bend radii, support spacing and associated fittings.
The BAFV
records for a number of the conduit runs inspected were also
reviewed.
Thirteen raceway supports were examined in detail for such items
as location, material, anchor spacing, weld quality, bolt torque
and installed configuration.
See Table II-1 for a listing of the cable tray, conduit and raceway
support samples.
II-1
--
-
- -
-
-
The following documents provided the basic acceptance for the
inspection:
Sargent & Lundy Clinton Power Station Unit 1 Specification
K-2999, " Electrical Installation," Amd. 10
Baldwin Associates Project Procedure BAP 3.3.1, " Exposed
Conduit Installation and Traveler Processing," Rev. 18
BAP 3.3.6, " Electrical Raceway Support Installation,"
Rev. 9
OAP 3.3.10, " Cable Tray Installation and Traveler Pro-
c?ssing," Rev. 6
BA) 2.3.11, " Cable Tray Attachment Installation," Rev. 6
BAP 3.3.14, " Conduit Support Installation," Rev. 1 Change B
Baldwin Associates Quality Assurance Instruction BQAI-190-8,
" Electrical Raceway Hanger / Supports Field Verification,"
Rev. 4
BQAI-190-9, " Electrical Raceway Field Verification,"
Rev. 4.
b.
Inspection Findings
The NRC CAT inspectors observed that, in general, Class 1E raceway
installations were in accordance with applicable design criteria.
Important quality attributes such as material type, location,
identification and installed configuration were found to be as shown
on approved construction drawings.
However, several construction
deficiencies were identified and are discussed in the following
sections.
(1) Raceway Separation
The requirement to establish physically independent and
redundant cable raceway systems is specified in the Clinton
Power Station (CPS) Final Safety Analysis Report (FSAR).
Section 8.3.1.4, entitled " Independence of Redundant Systems,"
describes requirements for physical arrangement of raceways in
order to comply with the requirements of Regulatory Guide (RG)
1.75.
The CPS raceway design includes four safety-related divisions
to serve the Engineered Safety Features systems and two
nonsafety-related divisions which serve the balance of plant
systems.
Minimum spatial separation between raceways
comprising each of these divisions has been established in
accordance with the guidelines specified in the Institute of
Electrical and Electronic Engineers (IEEE) Standard 384-1974.
II-2
NRC CAT inspectors reviewed documents which explained the CPS
electrical separation design philosophy.
In summary, Sargent
& Lundy Engineers (S&L) as the Architect Engineer controls
electrical separation through their design process.
Location
dimensions on electrical raceway installation drawings are used
for maintaining proper separation.
Consequently, specific
separation criteria is purposely not included in the specifica-
tions and instructions issued to the electrical contractor for
installation and inspection.
This has resulted in an inspec-
tion program which verifies the correct location of raceway
components but does not include attributes for inspection of
electrical separation.
To verify the adequacy of controls established through the
design process, NRC CAT inspectors selected a sample of com-
pleted raceway installations for review.
During the examina-
tion the inspectors identified numerous installations which did
not maintain spatial separation as described in the FSAR.
Several deficiencies existed between components of redundant
safety divisions, but deficiencies primarily occurred between
safety and nonsafety-related components.
Specific cable tray
deficiencies were then compared to design drawings to determine
if required fire barriers (i.e., tray covers) had been detailed
for installations which exhibited less than the required
spatial separation.
It was noted that in many cases barriers
had not been specified on the applicable drawing.
Reference
Table II-2 for a listing of raceway separation deficiencies
identified by the NRC CAT inspectors.
Discussions with the licensee indicate that they had become
aware of the need to perform specific walkdowns for electrical
separation because field installation tolerances could not be
controlled by design drawings.
As such, field walkdowns of
raceway for seismic interaction were incorporated into S&L's
Clinton Project Instruction PI-CP-034, Interaction Analysis
Procedure, early in 1983.
However, incorporation of specific
electrical raceway separation criteria was not accomplished
until mid 1985.
In order to evaluate this program, NRC CAT inspectors reviewed
the walkdown procedure, examined the plant area previously
inspected by the separation walkdown team, and interviewed the
engineers responsible for performing the walkdown.
The
following concerns were identified as a result of this
evaluation:
Separation criteria detailed in the walkdown procedure is
not complete in that spatial separation between raceway
and exposed electrical cable has not been addressed.
Personnel performing separation walkdowns have not
received training adequate to assure that they are
knowledgeable of all accept / reject criteria.
II-3
_
_
-.
The program represents the final inspection and acceptance
of raceway for the attribute of electrical separation.
As
such, it lacks appropriate involvement from the quality
assurance (QA) organization.
In connection with this issue, review of Sargent & Lundy
Electrical Department Standard ESI-180 indicates that analysis
has been used to justify many of the installations which
exhibit less than the required spatial separation.
NRC CAT
inspectors noted that this does not satisfy the requirement of
section 8.1.6.14 position C.6 of the CPS FSAR which states,
"The analysis 'out' given in paragraphs 4.5(3), 4.6.2 and
5.1.1.2 has not been used."
An S&L calculation, No. 19-BD-13, was cited as justification
for the examples of lessor separation identified by the NRC CAT
between non-Class 1E raceway run above Class 1E cable tray.
A
review of the analysis indicates that it does not meet the
requirements of IEEE-384 paragraph 5.1.1.2 in that it is not
based on tests of proposed installations and does not consider
actual raceway arrangements.
The analysis only addresses non-
Class 1E raceway which crosses over Class IE cable tray and
states that covers are not required for the Class 1E tray as
the heat from a fire or fault in the upper raceway will rise.
Discussions with the licensee revealed that an amendment to
the CPS FSAR has been prepared which would allow the use of
analysis to establish adequate electrical separation.
As a
result, further evaluation of this issue will be required by
NRC personnel.
In summary, the review of design, construction, and inspection
activities indicates that existing design and quality verifica-
tion programs have not been adequate to assure that commitments
relative to electrical separation have been met.
As a result
of this observation, the licensee has indicated that a program
evaluation will be performed.
Additionally, based upon
results of the evaluation and concerns addressed in this
report, program requirements may be revised.
(2) Raceway Supporting Scaffolding
BAP 3.3.10 permits the use of installed cable tray to support
temporary scaffolding with notification of BA quality control
(QC) by the area electrical supervisor, and the procedure
provides inspection criteria following removal of the scaf-
folding.
The NRC CAT inspectors questioned the procedure
controls that would alert BA QC whenever Class 1E cable trays
were used to support scaffolding and assure inspection of the
trays after removal of the scaffolding.
Since the controls were not well documented, BA's Deputy
Project Manager subsequently issued letter EPR-160-85 June 4,
1985.
The letter only permits placing scaffolds on Class 1E
cable tray on an exception basis requiring Superintendent
II-4
. = -
-.
-
approval.
The letter also requires documentation in a depart-
mental log and written notification to BA QC.
Section III, Mechanical Construction, of this report, also
discusses support of temporary scaffolding.
(3) Electrical Conduit
In general, the installation of conduit conforms to design
requirements. A number of separation violations were noted
between conduits, and between conduits and cable tray and are
included in the discussion in Section II.B.1.b(1), above.
In what the NRC CAT inspectors considcr an isolated case, con-
duits C9822, C9823, and C9824 are not attached to support E29-
1000-02C-122 as required by drawing E29-1000-02C-EIH.
The
licensee subsequently issued Nanconformance Report (NCR) 31717
to document the condition.
(4) Raceway Supports
The examination of seismic raceway supports was accomplished
for both cable tray and conduit installations.
In general,
attributes such as location, material type and size, anchor
spacing, welds (location, size and general quality) and
installed configuration were found to be in accordance with
design requirements.
c.
Conclusions
The use of engineering analysis to establish adequate electrical
separation is not consistent with current FSAR commitments, and an
analysis to justify separation between Class IE and non-Class IE
raceway was found to be technically inadequate.
The licensee's existing programs of design and quality verification
activities have not been adequate to assure that raceway
installations conform to FSAR commitments for electrical separation.
With the exception of compliance with electrical separation
criteria, conduit and support installations appear to be in
conformance with requirements.
2.
Electrical Cable Installation
a.
Inspection Scope
The NRC CAT inspectors selected a sample of installed Class IE
cable runs that had been previously accepted by BA QC inspectors.
The sample included medium and low voltage power, control, and
instrumentation cables.
For each of the cable runs, physical
inspection was made to ascertain compliance with applicable design
criteria relative to size, type, location, routing, bend radii,
protection, separation, identification and support.
In addition,
II-5
..
. _ .
-
,
IPOI records for installation and termination of those cables marked
with an *, below, were reviewed.
The NRC CAT inspectors selected approximately 270 cable ends for
examination.
These were inspected to applicable design and
installation documents for items such as lug size and type, proper
terminal point configuration, correct identification of cable and
conductors, proper crimping of lugs or connectors, and absence of
insulation or jacket damage.
See Table II-3 for a listing of cable
terminations examined.
The following medium and low voltage power cables, totaling about
1,650 feet, were selected from different systems, electrical trains
and locations:
Cable
Type
3 Conductor 750 MCM
- 1HP08A-P3E
3 Conductor 500 MCM
3 Conductor 1/0 AWG
- 1RH27A-P1E
3 Conductor 19/22 AWG
- 1CC08A-P2E
3 Conductor 19/22 AWG
3 Conductor 4/0 AWG
- 1LP01A-PIE
3 Conductor 500 MCM
ILP03A-P1E
3 Conductor 19/22 AWG
The following control cables totaling approximately 1,020 feet were
selected from different systems, electrical trains and locations:
Cable
Type
2 Conductor 19/22 AWG
15 Conductor 19/25 AWG
4 Conductor 19/25 AWG
- 1IA028-CIE
12 Conductor 19/25 AWG
The following instrument cables totaling approximately 560 feet
were selected from different systems, electrical trains and
locations:
Cable
Type
1 Pair 16 AWG Twisted Wire Shielded
ISC76A-K1E
1 Pair 16 AWG Twisted Wire Shielded
IDC06G-K4E
1 Pair 16 AWG Twisted Wire Shielded
- 1NR758-KIN
1 Pair 16 AWG Twisted Wire Shielded
The following documents provided the basic acceptance criteria for
the inspection:
S&L Clinton Power Station Specification K-2999, " Electrical
Installation," Amd. 10
BAP 3.3.2, " Cable Installation," Rev. 14
II-6
,
BAP 3.3.3, " Cable Terminations," Rev. 6
BAP 3.3.9, " Cable Protection," Rev. 6
BQAI-190-12, " Electrical Cable Installation Field
Verification"
BQAI-190-7, " Electrical Cable Termination Field
Ve ri fication. "
b.
Inspection Findings
(1) Ro ut.i_ng
n
In ceneral, the routing of Class 1E cables through design
designated raceway systems was found to be in accordance with
specified criteria.
Each of the Class IE cables examined by
NRC CAT inspectors had been installed in accordance with the
roul.ing detailed on the applicable computer generated Cable
Pu'l Ticket.
One instance of improper routing was identified in the Power
Generation Control Complex (PGCC).
NRC CAT inspectors noted
that nonsafety-related cable C11A-XX-030 had been looped into
a Division 2 safety-related floor section near panel H13-P652.
Investigation indicated that this condition was the result of
improper distribution of excessive slack in the cable.
A
review of the applicable design document, Panel Module
Wirelist 287A5660, Rev. 11 showed a correct routing of this
cable through nonsafety-related floor sections.
As a result of this observation, the licensee has issued
Nonconforming Material Report (NCMR) 2-0304 and Construction
'
Work Request (CWR) 6271 to document and correct this condition.
(2) Separation
During the inspection of Class IE cables NRC CAT inspectors
identified a number of cable and wiring installations which
did not conform to specified requirements for electrical
separation.
Examples identified include wiring deficiencies
which were located inside of control room operator panels.
In
this area, examination revealed that vendor installed wiring
had been routed through flexible metalic conduit.
In several
areas conduits which contained redundant Class 1E wiring had
been installed in physical contact with one another.
Examples
of this condition were observed in the following panels:
P800-62, 63, 64, 65
P870-55, 57, 58, 59, 61
P601-19, 22
Additionally, inadequate spatial separation was observed be-
tween exposed Class IE wiring in several of the control panel
sections.
II-7
_
_
__
NRC CAT inspectors examined the documents whic.h control the
design and installation of equipment in the cortrol room area.
The General Electric Company (GE) Topical Repor?. NEDO-10466-A
provides design criteria and safety evaluation 1or components
comprising the PGCC.
In accordance with the definition pro-
vided by this document, the PGCC consists of 1) a set of steel
floor sections, 2) a set of termination cabinets, and 3) a set
of interpanel cables.
Other control room panels, such as operator and signal
conditioning panels, are not considered part of the PGCC
and were designed by Sargent & Lundy Engineers.
However,
internal separation for all control room panels was to be
in accordance with the requirements of GE document 22A7472
" Electrical Equipment, Independence For Nuclear Safety-
Related Systems."
In reviewing these documents NRC CAT inspectors raised
questions concerning the use of flexible conduit as a fire
rated barrier within control room panels.
Discussions with
licensee personnel indicate that the use of flexible conduit
in the PGCC panels and ficor sections has been justified by
test and analysis as stated in Section 8.3.1.4.5.5 of the
FSAR and that this analysis provides justification for use
of flexible conduit in other control room panels as well.
However, based upon subsequent discussions with the NRR staff,
NRC CAT inspectors concluded that analysis of components
outside the scope of the PGCC has not been provided.
As such,
the wiring configurations described above do not comply with
FSAR requirements.
Additionally, the use of flexible conduit as a fire rated
barrier and the fire protection adequacy of control room panels
outside the scope of the PGCC installation are issues requiring
further evaluation by the NRC.
In connection with this issue a program weakness was identified
concerning the review of vendor issued specifications.
specification 22A7472 was issued in April of 1981 and, as pre-
viously indicated, provides requirements for separation within
electrical equipment.
However, the S&L review of this spec-
ification did not occur until January of 1985.
The S&L approval
of this specification stipulates that " contractor may proceed
in accordance with specification based on making the revisions
noted and resubmit." NRC CAT inspectors expressed concerns re-
garding the timeliness of this review in light of the fact that
S&L revisions and comments to the specification were extensive
and that much of the equipment affected by the requirements of
the specification had previously been installed and, in some
cases, turned over to operations.
The licensee should deter-
mine whether S&L's specification changes are being incorporated
into the installed equipment.
II-8
Separation deficiencies were also identified in 4160V switch-
'
gear E22-5004.
However, this deficiency and the adequacy of
the installation are addressed in Potential Deficiency Report
81-05.
Construction activity in connection with resolution of
l
this report has not been completed.
Separation Leficiencies also exist between exposed electrical
cable and raceway components.
As discussed in Section
II.B.1.b(1) above, these deficiencies had not been identified
by the licensee due to inadequate incorporation of accept /
reject criteria into separation walkdown procedures.
(3) Power Cable Spacing and Derating
CPS power cable installations have been designed in accordance
with Insulated Power Cable Engineers Association (IPCEA) publi-
cations P-46-426 " Power Cable Ampacities - Volume I - Copper
Conductors" and P-54-440 "Ampacities - Cables in Open Top Cable
Trays." The power cables have been derated in accordance with
the IPCEA standards such that cables sharing raceways may be in
contact.
Additionally, ampacities for power cables are based
on a 2-inch average depth of fill in cable tray.
As a result,
cables in solid metal trays could be installed without
maintained spacing.
The project's power cable ampacities calculation, S&L No.
19-G-1, was reviewed and compared to the FSAR commitments.
The calculation takes the appropriate values from tables in
IPCEA P-54-440, adjusts the values for actual cable
diameters and applys a five percent general derating factor
for tray covers.
The ampacities are derated an additional
10 percent as required by IPCEA P-54-440 for a 50 C ambient
temperature and it is these values that are listed in the
FSAR Section 8.3.
No deficiencies were identified in this area.
(4) Cable Damage
With the exception of the Class 1E cables damaged as a result
of the watt transducer fire in 4160V switchgear 1E22-5004
discussed in Section II.B.3, below, no deficiencies were
identified in this area.
(5) Cable Identification
In general, the identification of Class 1E cable installations
was found to be in accordance with applicable design
criteria.
No construction deficiencies were identified.
(6) Terminations
In general, cable termination activities performed by
construction personnel conformed to requirements.
However,
two types of deficiencies were observed and are discussed
below,
i
II-9
}
(a) The NRC CAT examined four 5kV terminations in switchgear
and found three which were not insulated as required by
specification.
These were the "from" ends of cables
1LP01A-PIE, 1HP08A-P3E and 1HP030-P3E.
Section 1004.1C2
of S&L Specification K-2999 and paragraph 4.12.la of BAP
3.3.3 require all SkV terminations in switchgear to be
insulated with termination kits or insulating boots.
The
BA QC Inspection Checklists for the three terminations and
IPOI's checklist for ILP01A accepted the installations
indicating that insulation was not required.
The terminations for 1HP08A and 1HP03D in switchgear
1E22-S004 were subsequently documented on NCR 32232 and
Field Change Request (FCR) 38981 and dispositioned use-
as-is.
This was based on S&L's determination that the
busses for this particular switchgear were not required
to be insulated and, therefore, the cable terminations
need not be.
IP startup had identified uninsulated bus
to breaker connections in the switchgear containing cable
ILP01A, but had not identified the uninsulated cable
terminations.
Although discussions with the licensee indicate there may
be technical justifications for certain uninsulated SkV
terminations, the installations identified by the NRC CAT
inspectors do not conform to current specification require-
ments.
(b) A field-installed jumper wire in the remote shutdown panel
was found by the NRC CAT to be a type which is not qualified
for Class 1E service.
This jumper wire is located on ter-
minal strip GG, between terminal points 18 and 26, and is
depicted on drawing E03-1C61-P001, sheet 6, Rev. K.
Further
investigation of this finding revealed the following:
Startup discovered, during system checkout, that the
required jumper between these points was missing and
initiated Maintenance Work Request (MWR) B02288 in
order to have plant operating staff personnel install
the missing jumper wire.
The MWR form was improperly reviewed, thus the K R
was processed as a nonsafety-related work order.
Due to the error in the processing of the MWR form,
non-Class 1E qualified jumper wire was obtained from
the operations warehouse and installed by plant
operating staff personnel, and QC inspection of this
installation was not performed.
Subsequently, the licensee has issued MWR-B11255 and
Condition Report 1-85-06-007 to document this NRC CAT
finding.
However, the condition report inaccurately
indicates that use of unqualified wire does not involve
^
nonconforming material and, therefore, does not indicate
II-10
~_.
_
___ _.
the appropriate safety classification for the condition
being reported.
It should be noted that, due to a similar finding by the
NRC CAT at another facility, the licensee had previously
instituted a program to assure that all field-installed
wiring was accomplished using Class 1E qualified wire.
This included the removal of all unqualified wire from
the construction warehouses to preclude its inadvertent
use.
However, this purge of unqualified wire did not
extend into IP's operations warehouse.
The NRC CAT inspectors then selected an additional 10
safety-related MWRs which involved termination activi-
ties requested by startup and performed by plant staff.
The MWRs selected are: 804831, B1000, B10039, A13589,
B10038, A16980, A14412, A17116, A17112, and 810159.
These
were reviewed for proper processing of the form and evi-
dence of the application of adequate QA program require-
ments to the work performed.
In addition, the NRC CAT
inspectors physically inspected the completed hardware
pertaining to each MWR.
The results of this review are as follows:
Two additional instances of unqualified jumper wire
were discovered.
These were related to MWRs A16980
and A17116 and involved internal wiring in
safety-related motor operated valves ISX004C and
1SX006C.
The form for MWR A14412 indicated that no QC inspection
was required.
The work associated with this MWR is the
splicing of internal motor leads to field cable in
safety-related motor operated valve ISX004C,
Sargent
& Lundy Standard EA-209 requires these splices to be
insulated, either with Class IE qualified insulating
and jacketing tapes, or with Class IE qualified heat-
shrinkable tubing.
The completed configurations of
either of these methods renders it impossible to
determine whether or not qualified materials were
used and were properly installed.
Therefore, in order
to assure the adequacy of these splices, an in process
witnessing inspection by QC was necessary.
MWR 81000 involves the swapping of two motor leads at
the Residual Heat Removal pump 1C motor in order to
achieve proper phase rotation of the motor.
Review of
the MWR form and associated QC inspection documentation
indicates that the work was properly accomplished and
inspected.
However, no documentation was generated
which would inform the designer of the change in motor
phasing.
Therefore, the currently approved design doc-
ument (wiring diagram E03-1RH00, SH.9, Rev. D) is in
II-11
---
_ _ _
___
._ .____.._._ __
_ _ _ - _ _ _ . _ - -
. -
_
conflict with the as-installed configuration of the in-
sta11ation.
The licensee stated that the disposition of
FCR 24896 allows motor terminations to be changed with-
out initiating a design change document and that the
4
designer need not be notified of such changes in motor
!
phasing.
A review of this FCR reveals that, although
it does state " connections may be modified as required
to obtain proper motor rotation", it does not indicate
'
that approved design drawings (wiring diagrams) do not
1
i
have to depict the as-installed wiring configurations.
j
In addition, on page 2 of 5 of the "Clinton Power
'
Station As-built Program" dated May 2, 1985, the
licensee has committed to maintain wiring diagrams
l
in an as-built condition.
In summary, of 11 maintenance work orders reviewed, 6
instances of either unqualified material, improperly
documented or missed inspections, and conflict between
as-built configuration and approved drawing were observed.
This indicates that the Maintenance Work Request Program
is ineffective in identifying safety-related work and
prescribing the appropriate QA requirements for the work.
c.
Conclusions
Wiring installations in a number of control panels are not in
I
accordance with applicable electrical separation requirements.
Additionally, the use of flexible conduit as a fire rated barrier
and the fire protection adequacy of certain control room panels are
issues requiring further evaluation by the NRC.
A number of Class
IE 4160V cable terminations have not been completed in accordance
with applicable design requirements.
The hardware and QA program deficiencies identified in the area of
l
'
"
the Maintenance Work Request program indicate a need for additional
management attention in order to assure that safety-related wiring
remains in conformance with applicable requirements subsequent to
turnover from construction.
3.
Electrical Equipment Installation
a.
Inspection Scope
Over 30 pieces of installed or partially installed electrical
equipment and associated hardware items were inspected.
Samples
J
were based on system function and safety classification.
The following specific electrical components were inspected in
detail:
(1) Motors
The installation of four motors and associated hardware was
inspected for such items as location, anchoring, grounding,
i
identification and protection.
The motors inspected were:
,
.
II-12
_
_-
-
._ -
_- , _ .
._
. --
__
- - - -
.
.
. _ _
_
- - - - - - - - - -
_ ____
_
_
__.
__
___
-- - _
.
_ - - . - _
__-
_
-
.
_
l
Residual Heat Removal Pump Motor
1AP07EG-1A
l
Residual Heat Removal Pump Motor
JAP 09ED-1B
Low Pressure Core Spray Pump Motor
1AP07EE
High Pressure Core Spray Pump Motor
IE22-S001
(2) Electrical Penetration Assemblies
The following containment penetration assemblies were
inspected:
Power
IEE22E-1C3E
Control
Neutron Monitoring
!
Control
The location, type, mounting and identification of these
penetrations were compared with the installation drawings
and vendor manual.
(3) Circuit Breakers
Circuit breakers for the following Class IE pump motors were
examined to determine compliance with design and installation
l
documents for size, type, system interface and maintenance.
Low Pressure Core Spray
i
Residual Heat Removal Pump 1A
(4) Switchgear and Motor Control Centers
l
The following switchgear and motor control centers were
inspected:
Motor Control Center
l
Motor Control Center
Motor Control Center
4160V Switchgear
4160V Switchgear
4160V Switchgear
(5) Station Batteries and Racks
The 125V battery rooms including the installed batteries,
battery racks and associated equipment were inspected.
The
location, mounting, maintenance and environmental control for
installation of the batteries were compared with the applicable
requirements cnd quality records.
i
125V DC Battery
,
i
125V DC Battery
II-13
,
- . , , . .
- - - ,
-
r-
- . . . - . -
.,----------.,n
- , - - ,.,_-- - - - -
--~-------rm-.
._
_
(6) 125V DC System Equipment
The following equipment comprising portions of the 125V dc
systems were inspected for compliance to design documents
for such items as location, mounting (welds, concrete anchors
and bolting) and proper configuratfor
Battery Charger
Battery Charger
125V DC Motor Control Center
125V DC Distribution Panel
Static Inverter
Static Inverter
(7) Conteql Panels
A number of safety-related electrical control panels were
inspected for compliance to requirements for items such as
location, mounting and type.
The panels inspected were:
Remote Shutdown Panel
Diesel Generator Control Panel
IPL12JA
Diesel Generator Control Panel
1PL12JB
Operator Main Control Panels
(8) Motor Operated Valves
Four motor operated valves were examined in detail.
1E12-F0278
1E12-F047A
The following documents provided the basic acceptance criteria for
the inspections:
S&L Clinton Power Station Specification K-2999, " Electrical
Installation," Amd. 10
BAP 2.10, " Equipment Installation," Rev. 6
BQAI-190-6, " Electrical Equipment Field Verification," Rev. 4.
b.
Inspection Findings
(1) Motors
Motors examined were found to have been installed in accordance
with applicable design criteria.
Nameplate data such as operat-
ing voltage, horsepower and speed were compared with FSAR re-
quirements and found to be acceptable. Maintenance records for
the High Pressure Core Spray pump motor were reviewed and also
found to be acceptable.
II-14
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
._
During the examination of the Low Pressure Core Spray pump motor
NRC CAT inspectors raised questions concerning the adequacy of
materials used to mount the motor to its pedestal. This issue
is discussed further in Section VI, Material Traceability and
l
Control, of this report.
(2) Electrical Penetrations
Penetrations examined were found to be in accordance with
design documents.
Installation and inspection procedures were
thorough, and associated inspection and maintenance records
were detailed and complete.
During the examination of the electrical penetration assemblies
it was noted that a pipe restraint had been welded to the
nozzle of penetration IEE27E.
Discussion with the licensee
regarding this issue disclosed that nonconformance reports (NCR
l
28725 and NCMR 1-0971) had previously been issued to document
this condition and had been dispositioned use-as-is by engi-
neering.
Based upon the information available, NRC CAT
inspectors could not determine whether this activity had
adversely affected the penetration gas boundary or components
.
within the penetration sleeve, or whether the disposition of
'
the nonconformance reports is adequate.
Further evaluation by the licensee is required.
(3) Circuit Breakers
The examination of the selected circuit breakers indicated
that they had been installed and maintained in accordance
with applicable design documents.
Important installation
attributes such as proper alignment and main contact pene-
tration were verified by physical inspection of the equip-
ment and review of construction and startup test records.
(4) Switchgear and Motor Control Centers
Several construction deficiencies were identified in Class 1E
switchgear installations.
The examination of switchgear 1AP09E
disclosed that the switchgear unit had been floor mounted using
American Society for Testing and Materials (ASTM) A-307 bolting
'
materials corresponding to Society of Automotive Engineers
(SAE) Grade 2.
In reviewing the vendor (Westinghouse) manual
NRC CAT inspectors noted that SAE Grade 5 bolting material had
been specified for this installation.
Additionally, the review
of the seismic qualification report for this equipment indi-
cates that Grade 5 bolting materials had been used to mount the
test unit to the shake table for qualification.
This item was discussed with licensee personnel who produced
NCR 24174 which had been issued in December of 1984 to document
this condition.
Subsequently, this item was transferred to
and dispositioned on CPS NCMR 1-0413 in accordance with site
procedures for items turned over to operations.
The disposi-
II-15
.
..
.
-
-__-__-
--
-
tion of the NCMR requires that all of the existing bolting
material be replaced with the specified SAE Grade 5 material.
NRC CAT inspectors noted that the switchgear unit is energized
and provides the Class 1E power feed for many of the plant
systems currently under test.
Consequently, although this
deficiency had been properly identified by the licensee, the
delay in initiating the specified corrective action could ad-
versely affect other plant systems.
During the examination of switchgear 1E22-5004 NRC CAT inspec-
tors noted that watt transducer 1JY-AP778 located inside of
cubicle 1 of the switchgear had burned. Additionally, the trans-
ducer associated wiring and Class 1E field cables located above
the device had also been damaged as a result of the transducer
fire.
Discussions with licensee personnel revealed that MWR B08649
had been issued to document and correct this condition.
A
review of this document indicates that the disposition,
" Procure, calibrate and install new transducer and associated
wiring as necessary," is inadequate in that it fails to
consider damage done to the Class 1E field cables located
in proximity to the device.
Wiring separation deficiencies were also identified inside of
various cubicles of switchgear 1E22-5004.
This item is identi-
fied as part of Potential Reportable Deficiency 81-05 dated
February 5,1982 and specified rework is scheduled to be
accomplished in accordance with the resolution of this docu-
ment.
The examination of switchgear 1AP07E and the motor control
centers selected indicate that they have been installed in
accordance with applicable requirements.
(5) Station Batteries and Racks
i
!
The condition of the 125V battery rooms was found to be clean,
free of debris and in good order.
Although permanent ventila-
tion systems had not been installed, temporary systems were in
place and provided adequate ventilation for the areas examined.
Access to these areas was controlled by keyed entry.
The 125V batteries were examined in detail and found to be
in good condition.
Maintenance activities were reviewed and
in general had been performed in accordance with requirements.
(6) 125V DC System
Inspection of components comprising the 125V de system
disclosed a deficier.cy in the installation of battery chargers
1DC07E and 1DC06E.
Design documents which specify
installation details for this equipment show mounting pad
I
dimensions which differ from the actual field configuration.
'
II-16
_
_ _ _ _ _ _ _ _ _ _ _ _ _ _
_
.
_ _ _ _ _ _ _
_ ____ _
__ .
l
IDC07E - Design Dimensions 48 inches W x 40 inches D
Actual Dimensions 47 inches W x 36 inches D
IDC06E - Design Dimensions 48 inches W x 40 inches D
Actual Dimensions 47 inches W x 38 inches D
l
The review of applicable records indicates $ hat the
l
appropriate design change document had been initiated for the
conditions noted on charger 1DC-06E.
However, technical
justification for the discrepancies identified on charger
1DC-07E was not provided.
As a result of this observation the licensee has issued NCR
l
32598 to document and correct this condition.
l
Other 125V dc system components examined were found to have
been installed in accordance with requirements.
(7) Control Panels
In general, the installation of Class 1E control panels was
found to be in accordance with applicable requirements.
Six
panels were identified which had been mounted using bolts of
indeterminate material type.
The following panels exhibited
this condition:
Switchgear HVAC Control Panel
1PL65JC
Switchgear HVAC Control Panel
IPL65JB
Diesel Generator HVAC Panel
1PL54JA
Shutdown Service Water Panel
1PL53JA
Shutdown Service Water Panel
1PL53JB
Shutdown Service Water Panel
1PL53JC
i
The use of indeterminate bolting materials in safety-related
applications is discussed in detail in Section VI, Material
Traceability and Control, of this report.
During the examination of the Divisions 1 and 2 Class 1E Diesel
Generator Control panels, NRC CAT inspectors noted that physical
identification of the panels was not in compliance with FSAR
requirements for identification of Class 1E equipment.
Name-
plates supplied by the vendor (Stewart & Stevenson) are not of
the color coding required for safety-related Divisions 1 and 2
electrical equipment.
Discussions with the licensee indicate that the requirements of
Specification K-2861, to which these panels were purchased, may
have been implemented prior to the FSAR commitment for color
coding of equipment.
Consequently, these panels had not been
properly identified.
As a result of this observation the licen-
see has issued Field Engineering Change Notice (FECN) 10305 to
document and correct this condition.
II-17
.
.
In addition, the NRC CAT inspectors reviewed a licensee surveil-
lance of vendor panels.
Based on an NRC inspection at another
site, the licensee's QA organization initiated a special surveil-
lance of vendor panels concentrating on those turned over to IP
startup and initially tested.
The surveillance findings indica-
ted a number of problems and resulted in IP QC performing a
broader scope inspection program.
However, the scope of the IP
QC inspection program does not include panels manufactured by
MCC Powers and a number of GE panels.
The NRC CAT specifically inspected a number of panels excluded
from the IP QC program and identified a number of discrepancies:
IPL54JA (MCC Powers)
Separation between non-Class 1E
field installed lighting circuit
and Class 1E vendor wires; minimum
bend radius of Class 1E vendor
wires (subsequently documented on
NCMR 2-0350); mounting bolts of
indeterminate material.
IPL53JA (MCC Powers)
Separation between non-Class 1E
field cable IVH79A and Class 1E
vendor wires; mounting bolts of
indeterminate material.
1PL53JB and JC (MCC
Mounting bolts of indeterminate
Powers)
material.
H22-P028 (GE)
Misidentification of Class 1E
associated vendor wiring as non-
Class 1E; separation between
Class 1E vendor wiring and non-
Class IE lighting and utility
circuits; isolation or analysis of
the interface between Class 1E
associated vendor wiring and non-
Class 1E field wiring.
Subsequently
addressed on Field Deviation
Disposition Request, LH1-3027
Rev. O.
The NRC CAT findings indicate that the scope of the IP QC
inspection program for vendor supplied control panels needs to
be enlarged.
The discrepancies found in the MCC Powers equip-
ment and the GE panel indicate t, hat the 63 panels manufactured
by these two companies originally omitted from the inspection
program should be included.
Inspection attributes, such as the
interface between field wiring and vendor wiring, mounting
details, and minimum bend radius should be added to the QC
inspection program.
(8) Motor Operated Valves
Motor operated valves examined were installed and maintained
in accordance with applicable design documents.
II-18
_-
_- -
_
_
.
~
. . _ . .
_
- -
- - - - .
_ _ - .
. -
..
i
l
I
c.
Conclusions
l
In general, the installation of electrical equipment has been
i
accomplished in accordance with requirements.
However, of concern
j
were the examples of hardware deficiencies which exist in equipment
i
which has been turned over for operation.
l
Items such as internal panel separation and the mounting of
l
1
seismically qualified equipment are concerns which will require
i
additional attention by the licensee.
i
i
4.
Instrumentation Installation
a.
Inspection Scope
i
i
The NRC CAT inspectors selected a sample of 15 completed runs of
instrument piping, comprising about 930 feet, for a detailed
,
j
examination in accordance with specification requirements and
j
isometric drawings.
four instrument racks and ten piping supports were examined for
'
i
conformance with requirements including installed configuration,
mounting details, material conformance, identification, and loca-
l
tion.
Eleven instruments were examined for conformance with requirements
'
for location, mounting details, and instrument type and range.
i
See Table II-4 for a listing of piping runs, supports, racks, and
l
1
instruments included in the sample, and identification of those
j
items previously inspected by BAFV or IPOI programs.
The following documents provided the acceptance criteria for the in-
spections:
f
l
S&L Clinton Power Station Specification K-2883, " Erection of
l
Phase I Piping Systems and Equipment," Amd. 13
BAP 2.6, " Instrumentation," Rev. 7 Change F
f
Applicable design drawings and change documents.
I~
b.
Inspection Findings
l
In general, the installation of instruments, racks, piping runs,
j.
and supports conformed to the appropriate requirements.
However, a
'
number of deficiencies were identified and are discussed below:
,
l
l
(1) The weld symbol for weld number 1 of support 1AB35011G on
!
drawing M-1AB35011G, Rev. B does not indicate the required
fillet weld size.
The licensee subsequently issued NCR 32421
j
to document this condition.
It should be noted that this
i
support had undergone reinspection under the BAFV program, and
,
this drawing deficiency was not identified.
4
!
il
j
11-19
t
!
. - --.~,..._ _ . ,_,,-_ _ .- _
, _..
- ,_. - _ _ . -
._ - - _ ___... - - .. _ ,... ._ . _ _ _ _. - - -
s
(2)
Instrument line RH-919-7C was found bent in two locations (due
to construction traffic in the area) near support 1AB01034G.
The licensee subsequently issued NCMR 2-0338 to document this
condition.
(3) The support clamp for piping run IE12-N015A "LO" on support
1AB02204G was found to be missing.
Further review revealed
that this condition had been previously discovered by the BAFV
program and documented on NCR 80367 and NCMR 1-1005.
(4)
Instruments 1E12-N015C, 1E12-N055C, and 1E12-N056C are mounted
on instrument rack 1E22-P005 using bolts containing no identi-
fication markings on their bolt heads.
The NRC CAT inspectors
observed that all other bolts used to mount instruments to this
and other instrument racks contain markings which identify them
as ASTM A-307 (SAE Class 2) bolts.
The licensee has subsequently
issued NCMR 2-0335 to document this condition.
This NCMR states
that Rosemont Instruction Manual 4302, Rev. 8, Model 1153 re-
quires these bolts to be ASTM A-193, Grade B8, which would indi-
cate that all bolts used to mount instruments to racks are non-
conforming.
Further review by the licensee is necessary to ac-
curately define the material requirements for these bolts.
(5) Three instances were observed of installed instrument piping
in physical contact with other items.
These are:
Instrument line 1MS31AB-3/4 is in contact with 6-inch
diameter pipe 1HG05BA
Instrument line IMS31JB-3/4 is in contact with 3-inch
diameter pipe ISC02DA
Instrument line 1NB05BB-3/4 is in contact with heating,
ventilating and air conditioning duct support P-4010.
In the first two cases, the licensee's Interaction Analysis
Group had previously documented these points of contact on
Potential Interference Reports (PIRs) C-2007 and C-2008, which
have been dispositioned use-as-is by S&L.
Further discussions
with the Interaction Analysis Group reveals that the analysis
supporting the use-as-is dispositions only addresses possible
seismic interaction and may not consider thermal expansion or
movement of either the instrument lines or the pipe involved.
In the third case, discussions with the Interaction Analysis
Group indicates that interactions of this type are considered
to be a generic exclusion to their criteria and, as such, they
are not required to document this on a PIR.
However, following
further discussion with the licensee, NCMR 2-0334 was issued to
document this condition as a construction deficiency instead of
a seismic interaction.
The NRC CAT questions the prudence of
the generic exclusion for such an item.
Identified construc-
tion deficiencies in completed and QC accepted installations
need to be recorded and evaluated in accordance with existing
QA requirements.
II-20
__
.__
Refer to Section III, Mechanical Construction, of this report
for a further discussion of the licensee's Interaction
Analysis Program.
- j
c.
Conclusions
The NRC CAT inspectors determined that, in general, instrumentation,
tubing, and support installations conform to applicable require-
ments.
The activities of the Interaction Analysis Group and
subsequent dispositioning of identified PIRs by S&L require further
review by the licensee.
1
II-21
_
l
TABLE II-1
,
RACEWAY INSPECTION SAMPLE
Cable Tray:
189A(P2E)
188A(P2E)
187A(P2E)
186A(P2E)
185A(P2E)
'
184A(P2E)
183E(P2E)
182A(P2E)
181A(P2E)
18R9(P2E)
1892G(P2E)
1893G(P2E)
16297G(P2E)
1894G(P2E)
1895G(P2E)
16296G(P2E)
16295G(P2E)
16294G(P2E)
16293G(P2E)
16292G(P2E)
16291G(P2E)
16260G(P2E)
16259G(P2E)
16257G(P2E)
1071D(P2E)
1072D(P2E)
1070D(P2E)
10690(P2E)
1068D(P2E)
10670(P2E)
,
i
1063D(P2E)
1064D(P2E)
1065D(P2E)
1066D(P2E)
169D(P2E)
168D(P2E)
167D(P2E)
166D(P2E)
165D(P2E)
164D(P2E)
i
163D(P2E)
162D(P2E)
161D(P2E)
16R1(P2E)
16413K(C4E)
16412K(C4E)
16411K(C4E)
16410K(C4E)
10510K(C1E)
16R9(C1E)
1614B(C1E)
17R12(K1E)
17111C(K1E)
17112C(K1E)
17115C(K1E)
17116C(K1E)
17117C(K1E)
17R55(K1E)
17220C(K1E)
17222C(K1E)
17223C(K1E)
17224C(K1E)
17R80(K1E)
19120D(P3E)
19121D(P3E)
19122D(P3E)
19123D(P3E)
Cable Tray Supports:
Support Number
Drawing Number
1000-0180H3
E26-1000-018-H3
E26-1000-018-CPH
1001-03A-H24
E26-1001-03A-H24
E26-1001-03A-CPH
l
1003-01A-H57
E26-1003-01A-H57
E26-1003-01A-CPH
1005-04A-H44
E30-1005-04A-H44
'
E30-1005-04A-CPH
1004-04A-H2
E30-1004-04A-H2
E30-1004-04A-CPH
1002-01A-H1
E27-1002-01A-H1
E27-1002-01A-CPH
1003-01C-H9
E27-1003-01C-H9
i
E27-1002-01C-CPH
-
!
i
i
!
!
II-22
4
- - - - - -
--,e--.-.
- -
,
n
-
-
- . , ~ , - -
,,
, - --- -
,
,,-,-,.-w,, - - - . . ,-,,,v-
,,,-,-,- - , - , ---- -- - - - .
_
_. _
_
_
I
TABLE II-1 (Continued)
RACEWAY INSPECTION SAMPLE
Conduit Supports:
E26-1003-03A-TCC-2
'
E26-1003-01A-CC-CP-2
E26-1002-04A-CC-17
E26-1002-04A-JS-1
E26-1003-01A-CC-57
E26-1003-01A-WH-3
Conduits:
Conduit No.
Length (feet)
Conduit No.
Length (feet)
C2301
8
C61490
36
- C2305
10
- C61545
29
C2318
19
- C62867
31
- C2319
10
C71191
37
C2341
8
C71192
39
C629
48
- C72183
45
C633
48
- C71365
110
C6404
33
- C71543
46
C6438
23
C71855
50
C6141
52
C9822
43
C61039
17
C9823
43
C61066
27
C9824
43
C61069
28
- C91230
23
C61371
25
C91523
21
C61386
16
C91527
20
C61394
27
l
NOTE:
The (*) indicates conduits inspected under the Baldwin Associates
Field Verification Program.
1
II-23
-_
- - _ _ _ - -
...
. _ _ _ . _ _ . . _ _ .
_
_ . .
.__
_
_.
_ - _
TABLE II-2
SEPARATION FINDINGS
,
j
Raceway segments listed in the A columns do not maintain required separation from
!
the corresponding raceway segments in B columns.
The (*) indicates physical
separation of less than one inch between the two raceway segments.
I
!
Column A
Column B
Column A
Column B
l
C9713(K1E)
IPB999(P2E)
C6207(B)
167D(P2E)
C92709(C18) *
C92757(P1E)
C659(B)
168D(P2E)
'
C92709(C18)
C92758(C1E)
C0357(B)
1065E(C2E)
C73991(C28)
C71191(C2E)
C02522(B)
1065E(C2E)
j
C73991(C28)
C71192(P2E)
C8926(B)
187A(P2E)
1
C71365(C2E)
C73639(K18)
C8133(B)
187A(P2E)
,
'
C71365(C2E) *
C7894 (C1E)
C8578(B)
184A(P2E)
1
)
C71365(C2E)
C71991(K3N)
C8579(B)
184B(C2E)
j
C71365(C2E)
C73218(C28)
C8137(B)
184A(P2E)
{
C71365(C2E) *
C72235(K18)
C8300(B)
183A(P2E)
!
C71991(K3N)
C72030(K28)
C8538(B)
C81649(2E)
j
-C72717(C2E)
C72812(K1E)
C8699(C3E)
1875D(P28)
i
C7891 (C2E) *
C73287(K1B)
C81775(2E)
1833D(P3E)'
f-
C62367(K4E) *
C61069(C2E)
C81777(2E)
1833D(P3E)
C62367(K4E)
C62084(P2E)
C81776(2E)
1833D(P3E)
C62367(K4E) *
C61068(P2E)
C81778(2E)
1833D(P3E)
'
}
C62367(K4E) *
C62100(K18)
C81257(B)
18926(P2E)
l-
C6141 (CIE) *
1PB695(P18)
C0224(B)
1061D(P2E)
i
16300K(C4E)
C61039(C2E)
C0223(B)
1061D(P2E)
j
16300K(C4E)
C61037(C2E)
1068D(P2E)
C0372(B)
j
16300K(C4E)
C61038(C2E)
1068C(C2E)
C0372(B)
!
16300K(C4E)
C62876(C2E)
C72997(1E) *
C72514(4E)
C6947 (P1B)
C6949 (PIE)
C72296(1E) *
C72514(4E)
,
j
C61066(P2E) *
C61364(K1E)
C72297(1E) *
C71570(3E)
j
C61371(C2E)
C6934 (P28)
C71570(3E) *
C72296(1E)
!
C73255(CIE)
IPB7107(DIV.2)
C72888(1E) *
C71541(2E)
i
C71855(K3E) *
17128C(K1B)
C73160(B)
C73666(1E)
l
C6917(B)
16279G(P2E)
1H13-P70GA(1E) 10360A(C1B)
i;
C61364(1E)
C61066(2E)
1H13-P701A(1E) 10347A(C1B)
.
C61374(1E)
16257B(C2E)
1H13-P731F(IE) 10344A(C1B)
!
C61373(1E)
16257A(C2E)
C62382(B)
16390E(C3E)
i
C61258(P28)
C61373(1E)
C62381(B)
16390E(C3E)
'
C6249(B)
161D(P2E)
10602(C1B)
10603K(P2E)
C6303(B)
167E(C2E)
10602B(CIB)
10631A(P1E)
i
I
1
i
a
II-24
_. .. _ _ _ . . _ . _ , _ . _ _ _ _ _ . . _ . _ . _ . _ _ _ _ . . , _ . _ . . . _ . . _ - , - _ . - _ . _ - . ,
TABLE II-2 (Continued)
SEPARATION FINDINGS
Column A
Column B
10632B(C1E)
10603K(P2E)
10603K(P2E)
10632A(PIE)
10611D(P28)
10615K(P2E)
10611E(C28)
10615L(C2E)
10600E(C28)
10632B(C1E)
C1079(B)
10632B(C1E)
10600K-P2E
10632A(PIE)
C6901(P28)
16257G(P2E)
C6901(P28)
16258A(C2E)
C6901(P28)
16258G(P2E)
C6901(P28)
16259G(P2E)1
C0409(B)
C9866(1E)1
10358B(C1B)
1H13-P706F(1E)1
C0409(B)
1992B(C1E)
C9866(B)
C9831(C1E)
C0410(B)
1989B(C1E)
C9713(K1E)
IPB999(P2E)
C9804(B)
1992A(PIE)
C9657(2E)
C9617(B)
'
C9657(2E)
C9615(B)
C74311(B)
C72514(4E)
NOTE:
1These separation deficiencies also involve raceway to cable.
11-25
TABLE II-3
CABLE TERMINATION INSPECTION SAMPLE
PGCC Termination Cabinet 1H13-P743
Cables:
1VD038,
IVD18E,
IVD11F,
IVD03D,
IVD06B,
1VD03C,
IVD06C,
IVH09E,
1VH098,
IVH09D,
IVX218,
IVX188,
1VX09B,
IVX128,
IVY 098,
IVY 088,
1D003C,
1HP21P,
1HP75A,
1HP75B,
1HP75C,
1HP75D,
100798,
ID079A,
1SX750,
ISX75C,
1SX55A,
1SX08C,
1SX03D,
ISX038.
PGCC Termination Cabinet 1H13-P742
Cables:
1VC068,
IVC 088,
IVD05C,
IVD02D,
IVD028,
IVD10F,
1VD18C,
IVD02C,
IVF07J,
IVC 40L,
IVG35K,
IVC 02C,
IVC 45H,
IVC 148,
IVC 45F,
1AP23G,
1DG31G,
1AP23B,
1DG21f,
1AP290,
LAP 21G,
1AP23F,
IAP21M,
IDG31L,
IAP60D,
IAP29C,
1AP29K,
ICC08C,
ICC09C.
PGCC Termination Cabinet 1H13-P741
Cables:
1AP220,
IDG11G,
1AP28E,
1AP228,
1DGG1D,
1AP20G,
IAP22G,
1AP20M,
ICC11F,
ICC14G,
IDG11L,
1AP28K,
ICC14C,
ICC11C,
ICC17L,
ICY 05C,
IRP11E,
ICY 09C.
Diesel Generator IA Control Panel 1PL12JA
Cables:
IDG02A,
IDG020,
IDG11F,
IDG11S,
1DG02B,
IDG11C,
1DG11T,
1DG11E,
1DG11D,
1DG01D,
1DG02F,
1DG04A,
1DG06A,
IDG098,
10G09C,
1DG10C,
1DG108,
IDG05A,
1DG07A,
IDG02C,
1DG02E,
1DG02G,
1DG75E,
10G11R,
1DG75C,
IAP20K,
1AP22J,
1DG08A,
IDG01E,
10G01Q,
IAP20M,
IAP22K,
IDG015,
IDG01Q,
IDG01R.
Division 3 Optical Isolator Cabinet IPL49J
Cables:
IMIO5A,
1HP110,
1HP17J,
ISX03E.
Remote Shutdown Panel 1C61-P001
Cables:
1RH55F,
1RH55E,
1RH40D,
1RH40C,
1RH310,
1RH31C,
1RH27D,
1RH27C,
1RH070,
IRH07C,
1RH12D,
1RH12E,
1RH12C,
1RH01G,
IRH01H,
1Ril01C,
1RS02A,
1RH22E,
1RH09F,
1RH09D,
1RH09C,
1RH18D,
1RH18C,
IRH16D,
1RH16C,
1RH61F,
1RH61E,
1RH380,
1RH38C,
1RH63F,
1RH63E,
1SX20C,
ISX20N,
1RH220,
1RH22C,
IRI13E,
IRI13C,
1RIl0D,
IRIl0C,
IRIO3D,
IRIO3C,
IRIO60,
1RIO6C,
1RI26D,
1RI26C,
1RIO5D,
IRIO5C,
IRIO8D,
IRIO8C,
IRI25C,
1RI258,
IRI248,
IRI24A,
IRI27F,
IRI27G,
1NB380,
1RH73L,
IRI12E,
IRI12C,
IRIO9G,
1RIO9C,
IRI24J,
IRI24H,
1RI24G,
IRI24K,
1RSO4A,
1RS06A,
1RS82A,
IRIllD,
IRI11C,
IRIO7D,
IRIO7C,
IRIO40,
IRIO4C,
1RS05C,
1RH13D,
1RH13C,
IRH13E,
IRH17F,
1RH17E,
1RS05B,
1RH10E,
1RH23D,
1RIO2F,
IRI15F,
IRI27J,
IRI27H,
IRI15E,
IRI170,
IRI17C,
1RH37C,
1RH37D,
INB390,
IRS 05A,
1NB35A,
1NB35C,
II-26
TABLE II-3 (Continued)
CABLE TERMINATION INSPECTION SAMPLE
Remote Shutdown Panel 1C61-P001 (Continued)
Cables:
1RI760,
IRI76G,
IRI76E,
IRI76C,
IRI85C,
1RS75A,
1RS768,
1RS76D,
IRI858,
IRI85A,
1RS03A,
ISX59D,
1SX59C,
1RH240,
1RH24C,
1RH33D,
IRH33C,
1RH360,
1RH36C,
1RH500,
1RH50C,
ISX14K,
1SX14L,
ISX14M,
1SX30E,
1SX170,
1SX33D,
1SX37E,
1SX10F,
ISX20Q,
ISX14C,
1SX14F,
1SX14J,
ISX30C,
ISX17C,
1SX33C,
1SX37C,
1SX10C,
1SX11C,
ISX25J,
ISX25Q,
ISX50F,
1SX20J,
1SX50K,
ISX25X,
ISX25V,
ISX110,
1RS80A,
1RS798,
1RS79D,
INB35M,
INB35B,
IRIO2G,
IRIO2F.
4160 V Power Cables in Switchgear
Cables:
1RH02A,
1LP01A,
1HP08A,
1RH27A,
ILP03A,
1HP03D.
11-27
_
TABLE II-4
INSTRUMENTATION INSPECTION SAMPLE
Instrument Racks:
BA
IH22-P026
BA
BA
01
BA
Instrument Pipe Supports:
ISPS-CM096A
-
1AB35004G
BA
1AB35003G
BA
1AB35002G
BA
1AB35011G
BA
1RB31511R
BA
1RB32518G
BA
1RB22538G
BA
1RB21572R
BA
1RB21576X
Instrument Piping Runs:
1PT-CM034/1PT-CH256
BA
1E31-N088C "HI"
1E31-N088C "LO"
BA
1E31-N0888 "HI"
BA
1E31-N0888 "LO"
BA
1E12-N015C "HI"
BA
DI
1E12-N015C "LO"
1E12-N015B "HI"
1E12-N015B "LO"
BA
1E12-N015A "HI"
1E12-N015A "LO"
BA
1821-N078A
BA
1B21-N081A "HI"
1821-N0788
BA
1821-N0818 "HI"
Instruments:
1E31-N0888
1821-N081B
1E12-N0158
1PT-CM034
IPT-CM256
1821-N078A
1821-N0788
1821-N081A
NOTE:
8A indicates inclusion in Baldwin Associates Field Verification.
indicates inclusion in Illinois Power Company Overinspection.
II-28
III.
MECHANICAL CONSTRUCTION
A.
Objective
The objective of the appraisal of mechanical construction was to deter-
mine if installed and Quality Control (QC) accepted mechanical items
conformed to engineering design, regulatory requirements and licensee
commitments.
B.
Discussion
The specific areas of mechanical construction evaluated were piping,
pipe supports / restraints, concrete expansion anchors, mechanical
equipment, and heating, ventilating and air conditioning (HVAC)
systems.
To accomplish the above objective, a field inspection of a
sample of QC accepted hardware was performed in each area.
In
addition, certain programs, procedures and documentation were reviewed
as required to support or clarify hardware inspection findings.
The inspection samples in a number of these areas included items
covered by the Illinois Power ~ Company (IP) Overinspection Program.
Section VII, Design Change Control, of this report provides further
discussion of the IP Overinspection Program.
1.
Piping
a.
Inspection Scope
Piping depicted on the 11 Baldwin Associates (BA) and 3 Reactor
Controls, Inc. (RCI) drawings listed in Tables III-la and b was
inspected by the NRC Construction Appraisal Team (CAT).
In all
cases, piping inspected by the NRC CAT had been previously inspected
and accepted by the responsible QC organizations.
The piping
samples included portions of the High Pressure Core Spray (HPCS),
Low Pressure Core Spray, Reactor Core Isolation Cooling (RCIC),
Reactor Water Clean-Up, Shutdown Service Water, Main Steam Isolation
Valve Leakage Control, Nuclear Boiler, and Control Rod Drive ('RD)
systems.
In addition, some of the NRC CAT samples included piping
covered by the IP Overinspection Program.
Attributes inspected
included configuration (i.e., component orientation and dimensions),
component locations and types, and valve operator orientations.
Pipe support locations and types were inspected against hanger
design drawings to the extent indicated in Table III-1.
Site
construction practice as it affected installed components was
observed and component material specifications were compared to
drawing bills of material on a random basis.
The sample of BA piping selected for inspection included all American
Society of Mechanical Engineers (ASME) pipe classes and ranged in
size from 1 to 20 inches.
The sample included approximately 600
feet of large bore (greater than 2-inch diameter) and approximately
275 feet of small bore (less than or equal to 2-inch diameter)
piping located in the containment, auxiliary, fuel and diesel
generator buildings.
QC verified isometric drawings were used to
III-1
1
perform the inspection.
Subsequently, field data compiled by the
NRC CAT was also compared to walkdown record copies (NRC IE Bulletin
79-14) of piping design drawings to the extent indicated in Table
III-1.
Observations associated with the inspected piping are listed
in Tables III-la and b.
A sample of approximately 125 feet of RCI
piping associated with the insert and withdraw of the CRD was
inspected by the NRC CAT.
The inspection utilized walkdown record
copies of the RCI drawings listed in Table III-lb.
Thirteen piping samples representing approximately 200 feet of pipe
were selected to determine whether ASME requirements for pipe wall
thickness were met.
The measured pipe wall thicknesses were com-
pared against the minimum wall thickness requirement specified by
ASME (12.5 percent below nominal thickness).
Pipe wall thickness
was measured using ultrasonic methods, with personnel and equipment
provided by the licensee.
Circumferential measurements were taken
at the ends and the center of the samples; other measurements along
the length of the pipe were also obtained for those samples in
which a potential for violating minimum wall thickness requirements
appeared likely.
See Table III-2 for the inspection sample and
observations.
The following documents provided the acceptance criteria and back-
ground information:
BA Project Procedure (BAP) 2.14, " Fabrication / Installation of
Items, Systems, and Components," Rev. 10, Change F
BAP 3.2.9, " Piping 'As-Builts'," Rev. O, Change A
BAP 3.6.6, " Control of Welded Temporary Attachments," Rev. O
i
Sargent & Lundy Engineers (S&L) Project Instruction
PI-CP-028, " Field Installation Data Required to Permit
Confirmation of Piping Subsystem Analysis," Rev. 2
S&L Drawing M09-1001N, " Component Support Installation
Tolerances ... " Sheet 1, Rev. N and Sheet 12, Rev. N
S&L Specification K-2882, " Nuclear Safety Related and
Non-Nuclear Safety Related Specifications for Phase II
Piping, Miscellaneous Equipment, and Equipment Erection,"
through Amendment 11
S&L Nuclear Station Engineering Instructions (NSEI) ME-2,
" Interaction Analysis Program," Rev. 0
S&L Project Instruction PI-CP-034, " Interaction Analysis,"
Rev. 4
RCI Quality Assurance Instruction QAI-10-1, " Instruction
for Quality Control Inspection," Rev. 6
III-2
RCI QAI-8-4, " Instruction for As-Built Inspection / Verification
Walkdown," Rev. 5
RCI Document No. RCI-FPC-4, " Friction Clamp for 1" Withdraw
CRD Pipe," Rev. 6
RCI Document No. CLN-TOL-1, "Clinton Field Tolerances,"
through Rev. 3
RCI Document No. CLN-TOL-2, "Clinton Interface Tolerances,"
Rev. 1.
b.
Inspection Findings
In general, the NRC CAT inspected piping conformed to installation
requirements and tolerances.
However, the following observations
and discrepancies warrant additional attention.
(1) Baldwin Associates
Pipe spool 1-NB-751-4 depicted on Drawing NB-751 is routed
through and is in contact with the tube steel support for
electrical box lJB729.
This configuration is in accordance
with the support design drawing, No. E27-1602-038-EIT and
the piping design drawing, No. M27-1602-03B-03BK except
that the current pipe to support steel contact is not
identified by either drawing.
According to BAP 2.14 (Form
JV-734) and BA QC personnel, this contact is regarded as an
interference to be identified during the QC walkdown
inspection.
Also, according to the BA Resident Engineer,
such contact must be identified during preparation of the
as-built drawings.
There was no evidence presented to the NRC CAT inspector
that this pipe to electrical support steel contact was
identified by either the QC inspection or the as-built
walkdown for evaluation by the piping design organization.
Since no similar instances of obvious interference with
piping were encountered by the NRC CAT, this finding is
considered an isolated case which requires appropriate
engineering disposition.
At pipe spool pieces 1-RI-758-3 and 1-RI-758-5A, a temporary
pipe support was not removed at the time of the NRC CAT
inspection.
Procedure BAP 2.14 specifically noted that
removal of temporary supports need not be verified for QC
acceptance of the piping.
BA QC personnel noted that
removal of each temporary support was controlled by the
discipline superintendent and the dismantling was performed
in accordance with BAP 3.6.6.
As discussed with BA QC
however, neither that procedure nor any other presented
to the NRC CAT inspector provided assurance that all
-
temporary supports would be removed.
The NRC CAT is
III-3
concerned that the QC inspection and acceptance of piping
prior to the removal of temporary supports may result in
undetected unacceptable conditions once the temporary
supports are removed, or that if the supports are not
removed, that unanalyzed constraints may be imposed on
the piping.
Various dimensional discrepancies were also noted among
the inspected piping.
Two instances were observed where
the three inch tolerance for fitting to fitting dimensions,
as specified by the piping specification K-2882, had been
exceeded.
As a result of the NRC CAT observations, the
licensee has prepared Nonconforming Material Reports
(NCMRs) addressing the discrepant dimensions.
In related inspection observations, three instances were
noted where dimensions between components, or components
and supports were found to differ from the as-built
dimensions by one inch or more.
Procedure BAP 3.2.9
required that as-built dimensions be checked and recorded
to the closest inch.
The maximum out of tolerance conditions and maximum dif-
ference between as-built and measured dimensions were
two inches for both cases.
The magnitude of these dis-
crepancies when considered with regard to the pipe sizes
involved, are not large.
The NRC CAT did not identify a
large number of discrepancies of this nature, and thus,
does not consider the occurrences of the discrepant con-
ditions to be of significant concern.
(2) Reactor Controls, Inc.
With respect to RCI installed piping, no discrepant conditions
were found by the NRC CAT during the inspection.
However, the
following observations are provided.
During inspection of the CR0 piping, the RCI document
which specified the design of friction clamps used for
axial restraint of withdraw piping was reviewed.
Based
on this review and discussions with RCI engineering and
QC personnel, it was determined that no inspection
tolerance or minimum clearance was specified for the gap
between the clamp halves (ears).
To function as designed,
the clamp must develop bearing between the clamp and pipe
by the controlled application of torque to the clamp bolts.
Contact between the clamp ears would result in reduced
clamp to pipe bearing, and therefore reduced capacity of
clamp restraint in the axial (pipe) direction.
Although
not a QC inspection attribute, RCI stated that the need to
maintain a minimum gap was known and that in all cases,
such a gap was maintained by construction.
III-4
Random inspection of RCI supports by the NRC CAT included
an inspection for a minimum clearance between clamp ears on
approximately 60 axial clamps associated with the CRD
" withdraw" piping.
No cases of contact between the clamp
ears were observed, but several clamp ears exhibited
clearances of only one to two mils indicating that this
attribute may warrant QC inspection.
In conjunction with the inspection of RCI installed
piping, their as-building and stress reconciliation effort
was also reviewed.
As a result, it was observed that
portions of piping associated with the Hydraulic Control
Units (HCU) to which RCI piping interfaced, had not been
walked-down for as-built reconciliation of the RCI piping
since the HCUs had been installed by BA.
Subsequent clari-
fication provided by RCI stated that RCI would incorporate
the piping associated with the HCUs into their walkdown.
Because the previously completed walkdowns did not include
the HCU piping, the need exists for the licensee to assure
that the additional piping is incorporated into the
as-building effort, and to recognize the potential for
deficiencies arising from construction interfaces.
(3) Piping Minimum Wall Verification
With regard to the 13 piping samples selected for minimum wall
thickness verification, none of the samples were found to be
below the specified minimum values.
Only one sample was within
seven mils of the minimum wall thickness limit.
The various
sa.mples ranged in diameter from
inch to 24 inches, and were
,
s'ecified to meet the ASME Boiler and Pressure Vessel Code,
p
"
Section III, Class 1, 2 and MC requirements (as appropriate).
(4)
Interaction Analysis Program
.
In conjunction with the review of piping systems, the NRC CAT
reviewed the licensee's Interaction Analysis Program as it
related to Unresolved Safety Issue (USI) A-17, " Systems
Interaction in Nuclear Power Plants," discussed in the Clinton
Power Station (CPS) Safety Evaluation Report (NUREG-0853).
NSEI ME-2 and Project Instruction PI-CP-034 were the guidance
documents used for the interactions inspection program.
The scope of the program originally considered only the
seismic displacement of components (e.g., piping, supports,
cable trays).
The allowable clearance criteria stated in the
above identified instructions included a built-in incremental
clearance for thermal displacement.
Conditions which violated
the acceptable clearance criteria (under categories identified
in the procedures) were identified on Potential Interaction
Reports (PIRs).
These PIRs were then evaluated for their
acceptability.
III-5
-- -
-
.
-- -
. - _ _
_ -
-
During the initial implementation of the program approximately
4000 PIRs were generated of which only 2 required rework; the
remainder were dispositioned use-as-is.
Based on these results
(Report No. EMD-050518, " Generic Evaluation of Interaction
Between Seismically Designed Components"),
the licensee
-
'
developed exclusions for which certain categories of potential
interactions need not be considered or documented.
In future revisions to the Interaction Analysis Program, the
scope of the program will be expanded to address the thermal
'
effects of piping with respect to the overheating of electrical
l
components due to proximate hot piping, interferences with
!
installation of piping insulation, and interferences with
pipe expansion resulting in piping overstress or interferences
with components.
(The Interaction Analysis Program as it
relates to electrical and instrumentation components, cables
and conduits is discussed in Section II, Electrical and Instru-
mentation Construction, of this report).
The NRC CAT considers the guidance procedures to be difficult
to understand due to their apparent piecemeal compilation and
fragmented incorporation of information.
Further, although the
NRC CAT did not identify any deviations regarding the applica-
tion of the current procedures, observations of hardware
indicate that the program revision will need to ensure the
appropriate identification of thermal clearance violations
for the certain categories of interactions previously excluded.
c.
Conclusions
Piping was found to generally conform to design requirements and
,
specifications.
Site inspection and engineering personnel were
knowledgeable of requirements and responsibilities. No significant
problems regarding construction practice as it affected installed
piping hardware were observed by the NRC CAT.
However, the lack of
control regarding the removal of temporary supports, and the
piecemeal formulation of the program for identification and evalua-
l
tion of potential interferences and interactions warrants additional
attention.
2.
Pipe Supports / Restraints
a.
Inspection Scope
Twenty-six ASME Class 1, 2 and 3, and ten Class D pipe supports /
restraints which represented a variety of types, sizes, systems and
locations were selected for detailed inspection.
These supports /
restraints were inspected for proper configuration, clearances,
member size, location, weld size, fasteners, and damage.
All but
two supports had been QC inspected and accepted.
Included in the
ASME supports sample were two supports / restraints reviewed under the
IP Independent Design Review which was performed by Bechtel Power
Corporation and six supports / restraints reviewed under the IP
III-6
_ . . _ _
_ _ _ _
.
. _ _ ,
__..._ _ . _ __ _ _ __
__
- _ _ _ _ _
._
-
- - - .
_.
. _ -
_
Overinspection Program.
See Table III-3 for a listing of the
inspection sample.
In addition, approximately 70 other supports / restraints were
observed at random in the field for obvious deficiencies such as
loose or missing fasteners, improper clearances or angularity,
improper locking devices, disassembled items, damage and improper
concrete expansion anchor spacing.
Installation traveler packages for the supports were examined and
compared with drawings and change notices to verify that the
required attributes were inspected and that inspections were per-
formed to the latest design documents.
BA Field Verification and IP
Overinspection reports were also reviewed to assess the effective-
ness of the program in this area.
Acceptance criteria for these inspections were contained in the
following documents:
S&L Specification K-2882, " Phase II Piping, Miscellaneous
Equipment, and Equipment Erection," through Amendment 11
S&L Specification K-2884, " Component Supports," through
Amendment 8
S&L Specification K-2884-001, " Basic Engineers Load Capacity
Data Sheet Manual"
S&L Drawing No. M09-1001N, " Component Support Installation
Tolerances ... " Rev. N
S&L Drawing No. M09-1003N, " Component Support Installation
Tolerances ...." Rev. M
IP QAI-710.15, " Component Support Overinspection Checklist,"
Rev. 4
"IP Nuclear Power Construction QA Manual," Appendix A,
Rev. 10
BAP 3.2.5, " Piping Component Supports," Rev. 7, Change B
BA Quality Assurance Instruction BQAI-190-5, " Component
Support Field Verification," Rev. 4
Applicable design drawings and change documents.
!
b.
Inspection Findings
Approximately 94 percent of the nearly 11,300 component supports
(large bore and small bore safety related, and fire protection
j
related) had been installed and QC accepted.
Approximately 65
percent of the 545 Class D (quality inspectable) supports had been
installed and QC accepted.
III-7
I
-.
--
-
- _ - -
.
_
-.
-
- -
--
- - -
-
The inspection activities for pipe support / restraint installation
was controlled by BAP 3.2.5 which included a three phase inspection
program that required the preparation of travelers for each
inspectable support / restraint.
Phase I inspet. tion covers the installation of the support's
primary attachment to the building, and verification of its
location and orientation to the building.
Phase II inspection covers the inspection and verification of
the installed support per the design drawings.
Phase III inspection includes restroking of snubbers, load
stamping of constant spring supports, and setting of variable
spring supports.
In general, pipe supports / restraints were in conformance with the
specified requirements.
The inspection checklists for attributes
used by QC personnel were found to be comprehensive and detailed.
Several discrepancies were identified and are discussed below.
These discrepancies included incorrect modelling and analysis of
certain Class I supports, pipe shear lugs not in contact with the
riser clamp as required by the design drawing, thread length
mismatch between a snubber body and its extension piece, incorrect
substitution of material, and scaffold in contact with or supported
by pipe support / restraint components.
See Table III-4 for a listing
of inspection observations.
Welding deficiencies are discussed in
Section IV, Welding and Nondestructive Examination, of this report.
The lower pipe shear lugs on support M-ISX010285 were not in
contact with the riser clamp as required by the design drawing.
Gaps between the clamp and lugs ranged from 1/32 inch to 3/16
inch.
In addition, one shear lug was observed to be 1-1/4
inches wide when the specified width was 2-1/2 inches.
Engi-
neering documentation authorizing the variation of shear lug
sizes were not provided to the NRC CAT.
NCMR 2-0327 was
generated for this condition.
While this support was inspected
during the IP Independent Design Review performed by Bechtel
Power Corporation, these deficiencies were not identified
during that review.
"
Two Pacific Scientific Arrestor PSA 35 snubbers, for supports
M-1MS31002S and M-1RH080925, were identified by the NRC CAT
inspector as exhibiting a 1/4 inch thread length mismatch
between the extension piece and the snubber body.
The exten-
sion piece was provided by Basic Engineering (BE); the snubber
was provided by Pacific Scientific Company.
This mismatch was
a result of the male threads of the extension piece being
longer than the female threads of the snubber.
Upon
disassembly, it was discovered that the extension piece was
fully seated against the internal dust cover.
The NRC CAT is
concerned that the extension piece could be tighten beyond the
1-1/4 inch depth of the female threads of the snubber body and
push the dust cover into the inertia mass, thus causing the
III-8
malfunction of the snubber.
We are also concerned with the
potential generic implications of this condition on other
supports which use Basic Engineering supplied extension pieces.
The licensee is currently evaluating the extent and signifi-
cance of this condition.
The licensee did not have a construction or QC procedure that
included inspection attributes which would prevent the over-
tightening of these components.
However, as a result of these
observations, the licens:e is in the process of incorporating
the necessary changes into their inspection program to ensure
that such conditions are identified.
Two ASME Class 1 snubber supports were found to have been
modelled and analyzed in a manner contrary to Final Safety
Analysis Report (FSAR) commitments.
According to S&L, supports
M-1NB01003S and M-1NB010025 of the Nuclear Boiler System were
modelled as rigid supports.
The FSAR states that the Nuclear
Steam Supply System (of which the Nuclear Boiler System is
included) shall be modelled as flexible supports.
The NRC
CAT is concerned that this deviation could affect the adequacy
of the design of the supports, and considers that this devia-
tion in design warrants additional attention by the licensee.
The NRC CAT observed that the rear bracket (Part No. BE-410-5)
on support M-1SX01028S did not have an "N"
suffix as part of
the part number.
The "N" suffix was observed on all of the
ASME support components in our sample.
The NRC CAT was con-
cerned about the material traceability aspects of the component
and the significance of the "N"
suffix.
According to the
licensee, traceability is determined by a Receiving Inspection
Report (RIR) number which is etched on each part or assembly.
From the RIR, the part or assembly can be traced to the
purchase order, packing slip, and Certificate of Compliance (C
of C).
Part number BE-410-5 was obtained from the BE parts
catalog which did not list the "N" suffix.
BE-410-5 and
BE-410N-5 were identical parts, thus no specific distinctions
were made between the two.
Safety-related supports / restraints
are required to have C of Cs and RIRs.
These documents are
verified by BE QC, BA vendor surveillance and receiving QC
personnel.
The licensee indicated that these supports will be
reinspected for material compliance under Corrective Action
Request 222 reinspection and verification program.
Based on
this program, adequate traceability appears to be provided.
Evidence of a lack of attention to detail by QC personnel
during their inspections of Class D pipe supports / restraints
was observed by the NRC CAT during the inspection of Class D
seismic supports, even though the inspection checklist for
attributes was thorough in content.
The NRC CAT identified
discrepancies in four of the ten supports selected for detailed
review, such as the unauthorized substitution of shaped steel
with one of a similar shape but smaller size, binding contact
between a pipe clamp and eye nut, and various weld quality
III-9
_ .
~ . .
---
- - -
_ - _ _
- __ -
-
_ .
.-
--
. -_
_
_
,
irregularities.
The NRC CAT reviewed the traveler packages for
these supports and in general, found them to be accurate and
acceptable.
However, the above discrepancies were not iden-
.
'
tified in the traveler packages associated with the supports.
!
'
Numerous instances of wooden scaffold in contact with or supported
by permanent support components were observed.
In one case,
scaffold was supported by a spring can and its support rod.
In
each case, there was no apparent damage to the support compo-
nents when the scaffolding was removed.
The licensee did not have a formalized program which controlled
the erection of temporary scaffold on permanent supports as was
l
evidenced by the numerous observations.
The NRC CAT is con-
l
cerned about the lack of control on the erection of scaffold
and its effects on the hardware, since physical damage is not
restricted to that which is readily visible.
Further, damage
,
to previously QC accepted supports could result in undetected
!
,
unacceptable conditions.
As a result of the NRC CAT observa-
!
tion, the licensee has issued a project memorandum addressing
the erection of scaffolding.
Section II, Electrical and
Instrumentation Construction, of this report also discusses the
support of temporary scaffolding.
l
During the review of piping (Section III.B.1, above), three box type
l
restraints were found not to exhibit the minimum gap requirement
l
between the pipe and the support frame steel.
The S&L M09 series
!
drawings specify minimum pipe to support steel clearances based on
'
system temperatures.
For the Shutdown Service Water piping of
Drawing SX-27, a minimum clearance of 0.015 inches is required.
Furthermore, for any system regardless of temperature, an " air
i
gap" must be maintained.
For the three supports listed in Table
III-la against Drawing SX-27, the required clearance was found not
to exist.
For two of these (supports ISX11014R and ISX11016R),
support frame steel was found to be in contact with the top and
bottom of the pipe such that the requirement to maintain an air
gap was also violated.
As a result of the NRC CAT observations,
BA has reviewed the supports in question and other similar Shut-
down Service Water supports.
Two Nonconformance Reports (NCRs)
addressing a total of six cases, including the three addressed
here, of less than required pipe to steel clearances were written
following this review.
The NRC CAT considers these discrepancies
to be isolated occurrences.
The installation and inspection travelers of six ASME and ten Class
D supports / restraints were reviewed, and were found to exhibit
proper chronological inspection verification and acceptance of
handling, installation processes and sequences.
In addition,
six BA Field Verification packages and IP Overinspection reports
were reviewed and were found to accurately reflect the condition of
i
l
the hardware.
III-10
-
-
.-
_
.
- - - - _ -
- -
-_ _
. _ _ _ _
- - -
.
_ - - _ - _ . -
- - _
- -
!
!
c.
Conclusions
ASME Class 1, 2, and 3 pipe supports / restraints were found to be in
general conformance to design requirements.
Site engineering and
inspection personnel were knowledgeable of procedures, requirements
!
and responsibilities.
Procedures and inspection checklists were
!
thorough and detailed.
However, the NRC CAT is concerned with the
'
potential damage and generic implications regarding the thread
l
1ength mismatch between snubber assembly components, and concludes
that additional attention is warranted.
We are also concerned that
i
certain Class 1 supports may not be properly modelled and analyzed.
,
l
Class D pipe supports / restraints were generally found to be in
conformance with design requirements.
However, additional attention
to detail by QC personnel during their inspections is warranted.
Observations regarding scaffolding in contact with permanent
!
supports indicates a deficiency in the control of the erection of
l
scaffold.
l
3.
Concrete Expansion Anchors
!
a.
Inspection Scope
Seventy-one concrete expansion anchors on 12 pipe supports /
restraints and 61 anchors on 8 HVAC restraints were inspected for
proper diameter, length stamp, embedment, edge distance, damage,
washers and residual torque (an indication of anchor preload).
In
addition, the length of the expansion anchors were verified by
ultrasonic testing.
The anchors inspected were selected at random
on a variety of systems and ranged in diameter from one-half to one
inch.
Anchors were torqued to the BA or Zack Company (Zack)
specified post installation test torque.
Table III-5 provides a
listing of the anchors inspected.
l
Acceptance criteria for the field inspections were contained in the
i
following documents:
BAP 2.16 " Concrete Expansion Anchors Work," (sic) Rev. 12-5
Zack Procedure FQCP-12. " Inspection of Concrete Expansion
1
Anchors," Rev. 5-3
b.
Inspection Findings
Pipe support / restraint expansion anchors were installed by BA, and
HVAC restraint anchors were installed by the HVAC subcontractor,
Zack Company.
Expansion anchor installations were inspected by the
respective subcontractor QC personnel.
The BA and Zack procedures
were nearly identical in substance.
However, two fundamental dif-
l
ferences existed with respect to inspections.
BA QC inspected and
!
witnessed 100 percent of the anchor bolts installed.
Zack QC
inspected a minimum of one concrete expansion anchor of each
diameter on each anchor plate assembly, or a minimum of one concrete
l
l
III-11
. .
-
expansion anchor in every ten of each diameter, whichever was
greater.
For the NRC CAT inspection the anchor nuts were torqued to the
specified retightening (BA) or testing (Zack) torque.
Fourteen
anchors for pipe supports out of seventy-one tested exhibited
insignificant nut rotation at less than the retightening torque
with a maximum of 1/8 turn (which was within the BAP 2.16 acceptance
criteria).
Seven anchors for HVAC supports out of sixty-one tested
exhibited insignificant nut rotation at less than the testing torque
with a maximum of 1/16 turn.
Since Zack procedures did not specify
any allowable nut rotation, job plans to retorque each of the
affected anchor nuts were issued for the associated anchor plate
assemblies.
All other features inspected by the NRC CAT for both BA and Zack
installed anchors were in conformance with requirements.
c.
Conclusions
Concrete expansion anchors inspected by the NRC CAT were installed
in accordance with design and procedural requirements.
The results
of the torque tests are typical of normal wedge type expansion
anchor installations and do not indicate installation deficiencies.
4.
Heating, Ventilating and Air Conditioning
a.
Inspection Scope
Six HVAC seismic restraints were selected at random and inspected
for location, configuration, member size, weld size and connection
details.
Approximately 150 feet of duct adjacent to the restraints
and others selected at random were examined for proper attachment to
anchors, companion angle size and joint makeup.
Thirteen fire
dampers were inspected for proper installation, operability and
condition.
IP Overinspection documents were also reviewed to assess
the effectiveness of the program in this area.
HVAC concrete
expansion anchor installation was inspected and is discussed in
Section III.B.3, above.
See Table III-6 for a listing of inspected
items.
The following documents provided the acceptance criteria for the
inspection of HVAC hardware installations:
Zack Procedure FQCP-5, " Fabrication and Installation
Inspection," Rev. 8-1
"
Zack Procedure FQCP-10.7, " System Walkdown for Turnover,"
Rev. 2-1
"
IP QAI-710.20 "HVAC Overinspection Checklist," Rev. 4
S&L Specification K-2910, " General HVAC Specification"
!!I-12
.
-
- -
- - -
- - - - - - - - - - - -
- - -
.
S&L PI-CP-024, "Non-Category I Verification Program," Rev. 2
S&L Design Criteria DC-ME-17-CP, " Design Criteria for
Interaction Analysis in Category I Buildings," Rev. 1
Applicable design drawings, duct standards and change
documents.
b.
Inspection Findings
HVAC systems were designed by S&L and detailed on the Zack layout
drawings.
Hardware for fabrication and installation were detai ed
l
on duct fabrication details and hanger details.
The installation and inspection of HVAC seismic supports / restraints
are controlled through the use of " job plans." A job plan is
essentially a traveler which details the activities to be performeo
and the required inspection activities.
Installation and inspection
criteria are delineated on the job plans.
The inspections are
documented on hanger inspection checklists, which then become part
of the job plan package.
In general, the inspected HVAC seismic restraints conformed to
design documents and specification requirements.
One minor brace
angle discrepancy (four degrees out of tolerance) and one minor
dimensional discrepancy were noted.
The duct assemblies exhibited
proper weld stitches to supports and companion angles, placement of
reinforcements, proper fasteners, and in general, conformed to
specified requirements.
However, two documentation related
anomalies were noted for support R-7037.
NCR 911376 recorded stiffener plates missing from its vertical
channel members, and was dispositioned use-as-is.
The NRC CAT
requested the calculations for the support which formed the basis
for the disposition, and upon review noticed that the configuration
used to disposition the NCR differed significantly from that
depicted on the current design drawing.
Subsequent calculations
utilizing as-built information reconfirmed that the use-as-is
disposition was still acceptable.
This same support also had a
Field Engineering Change Notice (FECN) posted against it (FECN
7718) when in fact a nonconformance report should have been
generated.
The FECN changed a weld symbol to match a field
configuration which had been erroneously QC accepted.
Support
R-7037 had undergone IP Overinspection, and the inspection results
were documented on Inspection Report No. H2030 prior to the
inspection by the NRC CAT.
These two anomolies are r.ot significant
in the engineering context and are considered to be isolated
occurrences.
With respect to the licensee's inspection program of Class D
(nonsafety-related) seismic supports and duct, Zack Procedure
FQCP-5 required that the Class D seismic assemblies receive the
same level of inspection as the safety-related seismic Category I
assemblies.
The job plan packages of the Class D seismic supports
III-13
-
which were reviewed by the NRC CAT contained the appropriate
inspection reports.
The concerns of Position C.2 of Regulatory
Guide 1.29, " Seismic Design Classification," have been adequately
considered and implemented by the licensee through the documents
PI-CP-024 and DC-ME-17-CP.
With regard to the 13 fire dampers which were subjected to a release
test, all of the dampers released as designed and provided the
required isolation.
It should be noted however, that Zack and S&L
are currently evaluating the impact of defects in certain fire
dampers described in a 10 CFR 21 notification by the manufacturer of
the fire dampers (Ruskin Manufacturing Company).
This notification,
in part, stated that certain models of fire dampers were found not
to close properly under air flow conditions, and recommended that
the affected dampers be tested under the appropriate flow condi-
tions.
S&L intends to evaluate the functionality of the dampers through
the use of test models.
Test criteria have been developed; modelled
configurations. included horizontal and vertical duct runs, the use
of balancing dampers, and multiple damper configurations.
The
ducting ranged in size from 24x24 inches to 60x50 inches.
The
tests were conducted at the vendor's facilities with the use of an
S&L approved test procedure (XHV-85-41), which was originally
developed by Ruskin Manufacturing Company (415850Y-NIBD-23).
At the time of the NRC CAT inspection, S&L was reviewing the results
of the tests.
c.
Conclusions
The inspected HVAC hardware generally conforms to design require-
ments and specifications, and the 10 CFR 21 notification regarding
fire dampers is receiving adequate licensee attention and followup.
5.
Mechanical Equipment
a.
Inspection Scope
Twenty-four pieces of equipment for seven systems were inspected
for proper configuration, location, condition and bolt size.
Installation documentation for these components were reviewed for
content, clarity, consistency and thoroughness.
IP Overinspection
and BA Field Verification documents were also reviewed in order to
assess the effectiveness of these programs in this area.
Equipment
examined included the Emergency Diesel Generators, Diesel Generator
Day Tanks, and the Standby Liquid Control Pumps.
The NRC CAT
inspector examined documentation for components which were considered
to be completely installed, and those which were still in process.
Equipment which had received final alignment or whose foundation
anchor bolts had been tensioned or torqued were considered to have
been completely installed.
Table III-7 provides a listing of
irsper.ted items.
III-14
-_
..
-__
The following documents provided the basic acceptance criteria for
the inspections:
BAP-2.10, " Equipment Installation," Rev. 10-D
BQAI-190-3, " Mechanical Equipment Field Verification," Rev. 3
i
IP QAI-710.3, " Mechanical Equipment Overinspection Checklist,"
Rev. 1
Applicable equipment details and foundations drawings.
b.
Inspection Findings
Installation inspection reports generally exhibited the desired
sequencing of installation activities and inspections.
However,
BAP 2.10 which governed the preparation of equipment installation
travelers, did not require work to be performed in the sequence in
which they appear in the traveler unless specifically noted.
As
such, any designated QC holdpoint did not disallow the initiation
or completion of work activities (which may fall sequentially later
in the traveler) prior to the sign-off of the QC holdpoint.
Rather,
only a QC verification need be performed for that particular
operation or activity at its completion.
Of the 24 components for which installation documentation was
reviewed, all had been inspected and found acceptable by QC for
those attributes examined by the NRC CAT inspector.
Of these
components, the NRC CAT identified only one discrepancy between
installation requirements and as-installed conditions.
Diesel Fuel
Oil Storage Tank 0001TC was found to be missing washers at the
foundation anchor attachment.
Further, this was the only discre-
pancy identified between the sampled as-installed hardware and
the associated BA Field Verification or IP Overinspection reports.
It was noted however, that five components manufactured by Goulds
Pumps Inc.
(HPCS Water Leg Pump, Residual Heat Removal Water Leg
Pump, RCIC Water Leg Pump and the Control Room Chilled Water Pumps)
appeared to nave been improperly fastened to the foundation anchor
bolts in that the foundation anchor nuts were tightened to a " snug
l
tight plus \\ turn" condition rather than the torque value specified
by the vendor drawings.
For each water leg pump, this potential
discrepancy was originally documented by licensee QC personnel
on NCR 6639.
This NCR was dispositioned use-as-is by the invocation
/
of Field Change Request (FCR) 3477 which specified the snug tight
'
condition "unless otherwise specified." Due to the ambiguous and
imprecise language in both FCR 3477 and NCR 6639, the NCR appeared
to have been improperly dispositioned.
A review of NCR G571, which
dispositioned a similar discrepancy (for the Spent Fuel Cooling
Pumps) in the same manner, revealed that the licensee's position was
that S&L's requirements prevailed over vendor recommendations as the
component installations were governed by S&L drawings and documents.
The NRC CAT thus considers NCR 6639 to have been appropriately dis-
III-15
- _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
positioned and the equipment to have been properly installed.
The
licensee has agreed to provide clarification regarding the tighten-
ing of foundation anchor bolts.
The NRC CAT inspector also reviewed the seismic analyses for the
HPCS, RCIC and Residual Heat Removal Water Leg Pumps, RCIC Pump,
Turbine and Gland Seal Compressor, and the Diesel Generator Day
Tanks for consistency between the foundation anchor bolt material
type assumed in the analyses, and the as-installed material.
No
discrepancies were identified.
During the review of equipment installation travelers, the traveler
package covering the modification of the lube oil system for the
HPCS diesel generator was examined.
Documentation showed a history
of queries by licensee personnel regarding the appropriateness of
the safety classification of the materials to be used during the
modification; nonsafety-related material and components were
purchased for the modification.
These questions arose as a result
of a disparity between a vendor generated Field Deviation
Disposition Request (FDDR LH1-482) which categorized the lube
oil system to have been safety-related, and a General Electric
Quickletter dated March 4, 1985 which stated that the material to
be used in the modification need not be safety-related.
Ultimately, the use of nonsafety-related materials was approved
by the supplier of the HPCS diesel generator in FCR 37073.
The
NRC CAT inspector reviewed documents germaine to this concern and
concludes that the specified use of nonsafety related materials
and components as described in FCR 37073 is consistent with
licensee commitments as evaluated in Section 9.5.7 of the
CPS Safety Evaluation Report (NUREG-0853).
'
c.
Conclusions
Mechanical equipment installations generally conformed to design
and installation requirements.
Equipment travelers adequately
documented work activities.
I
i
III-16
_ _ _ _ _ _ _
,_- _ _ _ _ _____ _ _ - _ _ _ _ _ - _
TABLE III-la
PIPING INSPECTION SAMPLE - LARGE BORE
Baldwin Associates Piping
!
No. of
Support
Drawing
Pipe
Diameter
Locations
Number
Class
(inches)
Inspected
Notes
Observations
Design
As-Built
l
l
HP-2
2
20, 16
15
15
1
10'0" design dwg.
Rev. 10L
dimension measures
9'7"
1
10
5
5
2
Rev. 8G
RI-7
2
6
12
12
Rev. 10M
RI-14
1
4
-
-
3
Rev. 8J
I
3
4, 3
14
14
Rev. SK
l
SX-25
3
8
18
18
4
6'10" as-built
l
Rev. 8J
dimension from
Support 1SX13003X
to upstream elbovi
measures 6'8"
!
!
SX-27
3
8
15
15
4'0" as-built
Rev. 7P
dimension from
Support 1SX11016R
to Support ISX11015X
l
measures 4'1"
Pipe to support steel
minimum gap does not
exist at Supports
ISX11012R, 1SX11014R
and 1SX110016R
III-17
,.
..
..
. _ _ _
-
.
-
.. -
. - .
.
-_ -
__
-
.
I
TABLE III-lb
,
PIPING INSPECTION SAMPLE - SMALL BORE
Baldwin Associates Piping
i
No. of
Support
Drawing
Pipe
Diameter
Locations
,
<
Number
Class
(inches)
Inspected
Notes
Observations
Design
As-Built
.
!
HP-753
2
2, 1
10
5
5
2'6" as-built
Rev. 15
dimension measures
2'7"
15-754
1, 2
1,2
23
0
6
3'9" design dwg.
'
Rev. 12
dimension measures
3'5 "
1
'
NB-751
1, 3
2
-
-
3
Interference between
Rev. 6
pipe and support for
4
"
electric box IJB729
!
not documented for
piping design
-
incorporation
RI-758
2
2
0
0
7
Temporary pipe
Rev. 17
support not
dismantled at two
locations
Reactor Controls, Inc. Piping
.
No. of
'
Support
Drawing
Pipe
Diameter
Locations
Number
Class
(inches)
Inspected
Notes
Observations
Design
As-Built
SA-489
2
1
-
4
8
Rev. 3
j
SA-490
2
1
-
5
8
i
Rev. 5
l
SA-501
2
1k
-
4
8
Rev. 3
i
{
III-18
. _
_ - . - .
, _ - - . . _ _ . . _ , _
. -
.
,
_
_ . . -
TABLES III-la and b (Continued)
PIPING INSPECTION SAMPLE
NOTES
1.
' Piping dimensions inside containment wall not inspected.
2.
Piping dimensions outside containment wall not inspected.
3.
Selected piping components inspected by NR'. CAT - Piping layout not
inspected.
4.
Piping between floor at elevation 737'0" and support M-1SX13004R not
inspected by NRC CAT.
5.
As-built walkdown is not required for all piping shown.
6.
As-built data not inspected.
7.
As-built walkdown not required for piping shown.
8.
Walkdown design data recorded (March 29, 1985) on listed mathematical
model revision inspected by NRC CAT.
III-19
I
.
__
_
_
_
TABLE III-2
PIPE WALL THICKNESS SAMPLE AND OBSERVATIONS
i
Specified Nominal /
Minimum Wall
2
Manufacturer /
Pipe Size /
Minimum Wall
Thickness Measured
(Heat No.)
Schedule
Class
Thickness (Inches)
(Inches)
B&W (59768)
2 /xxs
2
0.552/0.483
0.501
C-W (14-390)
12/40s
1
0.375/0.328
0.434
!
C-W (13-419)
12/80s
1
0.688/0.602
0.715
!
J&L (631675)
12/40
2
0.406/0.355
0.377
J&L (364557)
4/80
2
0.337/0.295
0.316
S
(466139)
1/80s
2
0.179/0.157
0.170
i
S
(465835)
\\/40s
2
0.109/0.095
0.106
S
(462337)
6/40s
2
0.280/0.245
0.267
PSC (60834)
8/80
2
0.500/0.438
0.473
TCS (93563)
3/4/40s
2
0.113/0.099
0.109
USS (L-24722)
6/40
2
0.280/0.245
0.279
1
SF (1-RI-14-5)
4/120
1
0.438/0.383
0.390
24/
MC
1.000/0.875
1.096
NOTES:
IB&W - Babcock & Wilcox Tubular Products Division
C-W - Curtiss-Wright Corporation
J&L - Jones & Laughlin Steel Corporation
S
- Sandvik, Inc.
SF
- Southwest Fabricating & Welding Company, Inc.
PSC - Phoenix Steel Corporation
TCS - Teledyne Columbia - Summerill
USS - U.S. Steel Corporation
,
i
e
1
III-20
- ..
_ - -
. - .
-_
_ _ _ _ _ - _
TABLE III-3
PIPE SUPPORT / RESTRAINT INSPECTION SAMPLE
2
Size
Pipe
S/R Number 1
Type
Class
(Inches)
Location 3
Comments 4
M-1MS32002S Rev. C
C
12
Cont.
M-1MS31002S Rev. C
C
12
Cont.
BA
M-1MS33009S Rev. O
C
12
Cont.
BA
M-1MS31009C Rev. F
Spring
C
12
Cont.
M-1NB01003S Rev. A
A
2
Cont.
M-1NB01002S Rev. 8
A
2
Cont.
M-1NB01008S Rev. C
A
2
Cont.
M-1NB01027X Rev. A
Box
A
2
Cont.
H-1RH-780-4 Rev. 0
U-bolt
B
3/4
Aux.
IP
M-1RH47013G Rev. A
Box
B
1-1/2
Aux.
IP
M-1RH71016G Rev. C
Box
C
1-1/2
Cont.
IP
M-1RH34010X Rev. A
Strut
A
18
Cont.
IP
M-1RH140095 Rev. D
B
8
Aux.
M-1RH14006S Rev. C
B
8
Aux.
TVL
M-1RI14025G Rev. B
Box
B
1
Aux.
M-1RI14018G Rev. D
Box
B
2
Aux.
BA, TVL
M-1RI14002G Rev. D
Box
B
2
Aux.
BA, TVL
M-1RI14015G Rev. E
Box
B
2
Aux.
BA, TVL
M-1RI14001G Rev. G
Box
B
2
Aux.
BA, TVL
M-1SX42021R Rev. F
Strut
C
2-1/2
Aux.
IP, TVL
M-1SX42019R Rev. C
Strut
C
1-1/2
Aux.
IP
M-1SX01048X Rev. F
Strut
C
30
Screen
M-1SX01017R Rev. H
Riser Clamp C
30
Screen
M-ISX01050X Rev. E
Strut
C
30
Screen
M-1SX01028R Rev. J
Riser Clamp C
30
Screen
M-1SX21002G Rev. B
Box
C
2
Aux.
M-1CC06042G Rev. B
Box
D
14
Fuel
TVL*
M-1CC06016X Rev. B
Strut
D
14
Fuel
TVL*
M-1CC12007C Rev. D
Spring
D
3
Cont.
TVL
M-1CC07014R Rev. D
Rod
D
14
Fuel
TVL
M-1CC06035X Rev. A
Strut
D
14
Fuel
TVL
M-1CC07050X Rev. C
Strut
D
14
Fuel
TVL
M-1CY23002G Rev. C
Box
D
3
Aux.
TVL
M-1FWO30145 Rev. C
D
20
Turbine
TVL
M-1HP03024R Rev. C
Rod
D
10
Fuel
TVL
M-1VQ03003R Rev. E
Strut
D
10
Cont.
TVL
III-21
,
TABLE III-3 (Continued)
PIPE SUPPORT / RESTRAINT INSPECTION SAMPLE
NOTES:
1CC - Component Cooling Water
CY - Cycled Condensate
MS - Main Steam
NB - Nuclear Boiler
RI - Reactor Core Insolation Cooling
SX - Shutdown Service Water
VQ - Drywell Purge
2A - ASME Class 1
8 - ASME Class 2
C - Asme Class 3
3 Cont.
- Containment Building
Aux.
- Auxiliary Building
Screen - Screen House
Fuel
- Fuel Building
Turbine - Turbine Building
4BA - BA Field Verification Records Reviewed by NRC CAT
IP - IP Overinspection Records Reviewed by NRC CAT
TVL - Traveler Package Reviewed by NRC CAT
- Not QC Inspected at Time of NRC CAT Inspection
4
1
III-22
. _ _ _ -
TABLE III-4
PIPE SUPPORT / RESTRAINT INSPECTION OBSERVATIONS
From Support Sample
Support / Restraint
Observations
M-1MS310025 Rev. C
Mismatch of thread engagement of BE extension
Extension piece
male threads measured 1-1/2 inches and snubber
body threads were 1-1/4 inches.
Extension
piece was in contact with internal dust cover.
1/4 inch of threading exposed on extension
piece when assembled with snubber body.
M-1MS31009C Rev. F
Scaffold contacting against riser clamp.
M-1MS330095 Rev. D
Exessive debris in W-beam i)1ocks drainage
of water.
M-1NB01003S Rev. A
Incorrect lock wiring.
Not modelled per
FSAR commitment.
M-1NB01002S Rev. B
Not modelled per FSAR commitment.
M-1NB01008S Rev. C
Weld of item 2 to item 3 not welded as
shown on design drawing.
M-1NB01027X Rev. A
Elevation of 2-1/2 x 2-1/2-inch angle is
2-7/8 inches above drawing location.
Thickness of 2-1/2 x 2-1/2-inch angle is not
listed as 3/8 inch on FCR 33320.
M-1RH14006S Rev. C
Zero inch gap on top between telescoping
cylinder and support cylinder of snubber.
1/8
inch gap on bottom between telescoping cylinder
and support cylinder of snubber.
M-1RH140095 Rev. O
Cotter pin not spread.
Loose locknut on
extension piece.
Zero inch gap on top
between telescoping cylinder and support
cylinder of snubber.
1/8 inch gap on bottom
between telescoping cylinder and support
cylinder of snubber.
l
III-23
-
- - _ _ _ _ _ _ _ _
TABLE III-4 (Continued)
PIPE SUPPORT / RESTRAINT INSPECTION OBSERVATIONS
From Support Sample
n:
Support / Restraint
Observations
M-1RI14002G Rev. D
Zero inch clearance between top horizontal
member and pipe.
Pipe not supported by bottom
horizontal member; 0.046 inch clearance between
bottom member and pipe.
M-1SX01048X Rev. F
Sheet 1, item 6 calls for rear bracket
(Ref. Dwg. No. M-1SX01017R)
BE-410-5, no "N"
suffix.
Extra rear bracket
of a BE strut was incorrectly listed on NCR
26414.
M-1SX01017R Rev. H
Support was not listed on NCR 26414 with
reference tc the extra rear bracket shown on
Drawing M-1SX01048X.
M-1SX01028R Rev. J
Bottom lugs were not in contact with riser
clamp.
Gaps measured 1/32 inch through 3/16
inch.
Bottom lug width of 1-1/4 inch did not
meet the design requirements of 2-1/2 inches.
M-1CY23002G Rev. C
1/8 inch grind depth at weld tie-in on east
vert member.
M-1CC07014R Rev. D
Pipe clamp ears binding against eye nut.
Cotter
pin not spread.
M-1CC07050X Rev. C
Undercut on main structural member (Item 6)
greater than 1/16 inch.
Members not welded
as shown on design drawing (Item 6 to Item 7).
Hole in weld of west rear bracket.
M-1CC06042G Rev. 8
Debris between pipe and south vertical support
steel.
Support was not QC inspected.
M-1CC12007C Rev. O
Structural steel shape M4 x 13 was substituted
for a W4 x 13 shape.
3/16" x 3" x 6-1/4"
plate was substituted for two 3" x 3" washer
plates without proper documentation.
III-24
-.
.
,
TABLE III-4 (Continued)
PIPE SUPPORT / RESTRAINT INSPECTION OBSERVATIONS
From Random Sample
i
Support / Restraint
Observations
M-1FC02003R
Scaffold interfering with support.
M-1FP46005
Sway strut in contact with conduit C6513.
M-1HP03024R
Scaffold resting on pipe support.
M-1MS23006C
Scaffold platform resting on riser clamp.
M-1RH14010S
Scaffold in contact with snubber.
M-1RH13036S
Cotter pin not spread on rear bracket.
M-1RH09049X
Loose locknut on pipe clamp.
M-1RH16031X
Nail substituted for cotter pin in rear
bracket of sway strut.
M-1RH07053X
Auxiliary steel for conduit support E-26-1001-
02B-CP-13 is in contact with rear bracket pin
on sway strut.
M-1RH08092S
Mismatch of thread engagement of BE extension
Extension piece
"
male threads measures 1-1/2 inches and
snubber body threads were 1-1/4 inches.
Extension piece was in contact with internal
dust cover.
1/4 inch of threads exposed on
extension piece when assembled with snubber.
M-1SX18022V
Scaffold in contact with spring can.
M-1SX17028X
Rear bracket binding eye bolt of sway strut.
Pipe clamp was 2 inches lower than design
elevation.
WS00520G
U-bolt damaged (nonsafety).
M-1VC02003R
Scaffold interfering with support.
Valve No. 2SX017A
Scaffold interfering with valve.
III-25
-
- ._
a
TABLE III-5
CONCRETE EXPANSION ANCHOR SAMP3.E AND OBSERVATIONS
Number of Bolts
Turned Prior to
Number of Turns
Achieving
to Achieve
Pipe Support
Number of
Retightening or
Retightening or
Drawing (BA)
Bolts - Diameter
Testing Torque
Testing Torque
3
M-IVC 04017X
15-3/4
6
1/12, 1/12, 1/12
1/8, 1/12, 1/32
M-IVC 04001V
4-1/2
0
-
M-1CC06042G
6-1
1
1/16
M-1RI27003G
3-3/4
1
1/8
M-1RIO3017R
8-3/4
0
-
M-ISX75015G
4-1
1
1/16
M-1SX78008R
8-3/4
2
1/32, 1/16
M-1SX77020X
4-3/4
1
1/32
M-1SX21002G
4-1
0
-
M-1SX23008V
4-3/4
1
1/32
M-1RI14001G
2-3/4,
1
1/32
1-1
M-1RI14019R
8-1
0
-
Number of Bolts
Turned Prior to
Nunber of Turns
Achieving
to Achieve
HVAC Support
Number of
Retightening or
Retightening or
Drawing (Zack)
Bolts - Diameter
Testing Torque
Testing Torque
C-3163
6-3/4
3
1/16, 1/64, 1/64
C-3162
6-3/4
0
-
D-4308
15-3/4
1
1/64
C-3211
8-3/4*
1
1/16
C-3151
8-3/4
1
1/64
D-0121
6-3/4
0
-
C-1109-3
4-1
0
-
C-4103
8-3/4
1
1/64
- 0ne anchor bolt is recessed into the nut and one thread of the nut is visible.
NCR No. 912167 issued.
.
III-26
-
. . .
---
-
-
.
_
.
_.
_
-
.
TABLE III-6
HVAC INSPECTION SAMPLE AND OBSERVATIONS
Supports / Restraints
Support I.D.
Location
Observations
R5008
Containment
Acceptable.
R7022
Containment
"E" and "X" dimensions were
15/16 inches longer than
that shown on dwg.
R7033
Containment
Brace angle exceeded dwg.
requirements by 4 degrees.
NCR 911376 was dispositioned
using wrong configuration.
C3163
Control Building
Acceptable.
C6335
Control Building
Acceptable.
D4324
Diesel Generator
Acceptable.
Building
Fire Dampers
Damper I.D.
Quantity
HVAC System
OVC42YF
4
Control Building
OVC103Y
1
Control Building
OVC104Y
1
Control Building
OVL68Y
1
Laboratory HVAC
OVL70Y
1
Laboratory HVAC
1VX08YC
1
Switchgear Heat Removal
IVX82Y
2
Switchgear Heat Removal
IVX86Y
2
Switchgear Heat Removal
III-27
-
.
-
.
-.
- - _
TABLE III-7
,
MECHANICAL EQUIPMENT SAMPLE
Diesel Generator Air Start Skid
1DG06SA
Diesel Generator Day Tanks
1DG01TA,B,C
Diesel Generators
1DG01KA,B
Diesel Generator Oil Transfer Pumps
10001PA,C
Diesel Generator Fuel Oil Storage Tanks
10001TA,C
HPCS Diesel Engine
HPCS Water Leg Pump
RHR Water Leg Pump
RCIC Pump and Turbines
1E51-C001, C002
RCIC Gland Seal Compressor
IE51-C002
RCIC Water Leg Pump
Standby Liquid Control Pumps
Control Room Chilled Water Pumps
OVC08PA,8
Switchgear Heat Removal Coolers
IVX01SA,B
RHR Room Coolers
IVYO65,07S
.
4
f
.,
I
III-28
..
. _ . .
._
_
-.
_
_ _ - -
- _ .
- __._ -.
-
-
IV.
WELDING AND NOND5SNUCTiVs EXAMINATION
A.
Objective
The objective of the appraisal of welding and nondestructive examination
(NDE) was to determine if Quality Control accepted work related to
welding and NDE activities was controlled and performed in accordance
with design requirements, Safety Analysis Report commitments, and
applicable codes and specifications.
An additional objective was to
determine if personnel involved in welding and NDE activities were
trained and qualified in accordance with established performance
standards and applicable code requirements.
B.
Discussion
To accomplish the above objectives, welds and welding details for
piping, pipe supports / restraints, field and shop fabricated tanks and
heat exchangers, structural steel installations, heating, ventilating
and air conditioning (HVAC) installations, electrical supports, and
instrumentation and control tubing were inspected.
The inspectedTelds
were selected to provide a representative sample of the licensee's
contractor welding activities in terms of welding processes used,
materials welded and existing weld-joint configurations.
Considerations
such as physical location, difficulty of welding and limited accessi-
bility were also used in sample selection.
NDE activities were appraised through the review of radiographs for
both field and vendor fabricated welds, the review of NDE procedures
and personnel qualifications, the inspection of the calibration status
of NDE equipment, and the witnessing of in process NDE activities.
During the inspection of welds on pipe supports / restraints, the NRC
Construction Appraisal Team (CAT) identified welds which did not have
the weld size specified by the Architect Engineer, Sargent & Lundy
Engineers (S&L).
Undersized welds were found in both skewed and non-
skewed connections on pipe supports.
S&L has evaluated most of the
undersized welds and determined that the welds are adequate for the
intended application.
Undersized weld reinforcements were also found in
nozzle to shell joints (ASME Code Category D joints) on tanks and heat
exchangers.
A detailed discussion concerning these welds is included
in Sections IV.B.1 and 11, below.
The licensee has instituted an Illinois Power Company (IP) Overinspec-
tion Program.
The program provides for additional inspections to be
performed by the Baldwin Associates Field Verification (BAFV) Group and
the IP Overinspection Group.
Section VII, Design Change Control, of
this report provides additional discussion of the IP Overinspection
Program.
The IP Overinspection Program was set up to include inspections of
welds in all of the major areas of plant construction such as electri-
cal, piping, instrumentation, HVAC and structural steel.
The NRC CAT
inspectors inspected eleven pipe supports / restraints which were
inspected under the scope of the program.
In addition two supports
in the electrical, two supports in the instrumentation, two supports in
IV-1
the HVAC and two supports in the structural steel areas were inspected
to assess the adequacy of the welding overinspections.
In the area of NDE, the NRC CAT inspectors reviewed radiographs
supplied by various contractors and vendors.
The NRC CAT inspectors
found radiographs which showed that some welds did not have the
required weld quality or the NDE documentation did not accurately
reflect the current status of the hardware.
A detailed discussion
concerning the welds and their associated deficiencies are provided in
Sections IV.B.1., 9, 10 and 11, below.
The welding and NDE activities were examined in order to ascertain
compliance with the governing construction codes and specifications.
This effort involved the review and inspection of the following
contractors:
Field Activities
1.
Sargent & Lundy Engineers:
Architect Engineer.
2.
Baldwin Associates:
piping installation and piping supports /
restraints, instrumentation installation and instrumentation
supports, fire protection fabrication and installation, electrical
installation and supports, drywell wall field installation and
structural steel erection and modification.
3.
Chicago Bridge and Iron Company (CB&I):
containment liner and
containment penetration fabrication and installation, tank
fabricator.
4.
Bristol Steel Company:
reactor pool and spent fuel pool liner
fabrication and installation, structural steel supplier.
5.
Zack Company (Zack):
heating, ventilating and air conditioning.
6.
General Electric Company:
reactor internals field modification and
installation.
7.
Reactor Controls Inc.:
control drive mechanism piping
installation.
Shop Fabrication
1. Southwest Fabricating & Welding Company, Inc.:
shop fabricated
piping spools.
2. Harnischfeger Corporation:
crane manufacturer.
3. General Electric Company:
nuclear steam supply system.
4. Anchor / Darling Valve Company:
valve manufacturer.
5. Progressive Fabricating Inc.:
pipe sleeve and cylinders supplier.
IV-2
_ _ _ _ _ .
_
. . . -,
.
-
_
.
-
6. Carrier Corporation:
chillers and coolers manufacturer.
7. Pathway:
expansicn bellows supplier.
8. RECO Industries Inc.:
tank fabricator.
9. Posi Seal:
valve bodies supplier.
10. Fisher Controls Inc.:
valve manufacturer.
11. Rockwell:
flow diverters supplier.
12. Lakeside Bridge and Steel:
miscellaneous steel supplier.
13. La Barge:
pipe supplier.
14. Hub:
tube supplier,
15. Yuba Heat Transfer Corporation:
high pressure heater manufacturer.
16. Southern Boiler:
small tanks supplier.
17. Tube Turns:
penetration manufacturer.
18. Spencer Turbine Co.:
blow casing supplier.
19. Chicago Tube and Iron:
tee tubes supplier.
20. Nooter: water storage tank supplier.
21. Guyon Alloys:
tube and fittings supplier.
22. Gould:
valve supplier.
23. Metal Bellows:
bellows manufacturer.
24. Atomic International:
hydrogen recombiner manufacturer.
25. Steward and Stevenson:
air receiver tank supplier.
'
26. W.J. Woolley Company:
containment vessel hatches fabricator
and supplier.
27. G.W. Taylor:
material supplier.
28. Trent Tube:
material supplier.
29. Bingham-Willamette:
pump manufacturer.
The results of the inspection activities involving each of these areas
and contractors are documented in the following sections.
IV-3
..
,
, . _
. . -_.
-
-
_ _ .
. , . .
1.
Pipe and Pipe Support Fabrication
a.
Inspection Scope
(1) Welding Activities
The NRC CAT inspectors reviewed activities relating to
fabrication contracts in the areas of piping system welds,
support / restraint welds, welding procedures, welder
qualifications, NDE procedures, personnel qualifications, and
the review of radiographic film for shop and field fabricated
Field welding involving pipe fabrication was performed
by BA.
Southwest Fabricating and Welding supplied the shop
fabricated piping spools.
The NRC CAT inspected 56 pipe supports / restraints involving
approximately 550 welds in order to verify conformance of
welding to drawing requirements and confirm the visual
acceptability of the welds.
The inspection included 11 sup-
ports consisting of 68 welds, which had been checked under
the IP Overinspection program in order to evaluate the effec-
tiveness of that program.
See Table IV-1 for a listing of
supports subjected to detailed inspection. Additionally,
another 16 supports / restraints involving 400 welds were
visually inspected to verify the quality of the completed
See Table IV-2 for a listing of supports inspected.
The NRC CAT inspection of piping welds consisted of visual
inspection during walkdown of piping systems and inspection of
pipe welds located near the supports / restraints being inspec-
ted.
Approximately 44 piping spools involving 1400 American
Society of Mechanical Engineers (ASME) Class 1, 2 and 3 welds
were inspected.
Twenty-four of those piping spools were
subjected to detailed inspection which included the review of
pertinent QC documentation while the remaining 20 spools were
only visually inspected.
Both field and shop welds were
inspected in order to assure compliance with the requirements
of the ASME Code.
Some of the inspected socket welds were
fabricated by Reactor Controls, Inc. (RCI) in conjunction with
the Control Drive Mechanism piping installation contract.
See
Tables IV-3 and IV-4 for listings of piping spools inspected.
In addition, 75 welding filler metal test reports, 22 welder
qualification test records and 4 welding procedures were
reviewed for compliance with applicable specifications,
procedures and the ASME Code requirements.
(2) Nondestructive Examination Activities
The NRC CAT inspection of NDE activities for the pipe
fabrication area included the review of 62 shop and 75 field
fabricated welds which involved 1815 film.
The field welds
were fabricated by BA and the shop fabricated pipe spools were
supplied by Southwest Fabricating and Welding.
Three welds
involving 28 film supplied by RCI were also reviewed as a part
IV-4
of this inspection.
In addition, 6 NDE procedures and 11 NDE
personnel qualification records were reviewed in order to
verify compliance with the governing codes and specifications.
Six NDE technicians were observed while performing in process
inspections and were evaluated for their ability to follow the
applicable inspection procedures.
Twenty pieces of NDE equip-
ment were inspected for calibration and one quality assurance
NDE procedure was reviewed for adequacy.
b.
Inspection Findings
(1) Welding Activities
'
In general, the inspected pipe and pipe support / restraint
welding activities were found to comply with the governing
codes and specifications.
However, discrepancies were iden-
tified involving undersized welds in both skewed and nonskewed
welded connections.
Forty-six of 950 structural welds inspec-
ted, involving 56 pipe supports / restraints, were found to be
deficient with respect to the specified acceptance criteria.
Forty-four of the welds were undersized, one weld had overlap
and lack of fusion, and another weld had undercut and was also
welded across the beam flange which violated the specification
requirements.
Nineteen of the undersized welds were found on
hanger 1RH051R which had a total of 79 welds.
As a result of
this finding the BA personnel identified and reinspected the
remaining 20 hangers of similar design.
A relatively high
percentage of undersized welds were also found on those han-
gers.
Investigation revealed that the hangers were predomi-
nately shop fabricated by BA and the shop fabricated portion
was not inspected as closely as those welds which were made
during installation.
See Table IV-1 for details. As a result
of this finding the applicant issued Nonconformance Reports
(NCRs) and the welds were determined to be adequate for the
intended application.
Two of the 1400 pipe welds inspected were found to deviate from
the specified acceptance criteria.
The two welds and their
associated deficiencies are listed as follows:
(a) An undersized reinforcing fillet weld between a small-
diameter coupling and spool piece IRH-8-7 was found.
32441 was written as a result of this finding.
(b) Undersized welds were found on socket welds on the 3/4-inch
Schedule 160 piping connections on RCI work.
CRD-185-48 was written as a result of this finding.
In
addition, all pipe of this size and schedule was reinspec-
ted and accepted by the Architect Engineer without repair.
l
Ten percent of the remaining RCI fillet welds were also
l
inspected, and these were found to be of the correct size
since the connecting piping was Schedule 80 or lighter.
i
l
IV-5
._
. .
_
_ _ .
(2) Nondestructive Examination Activities
In general, the inspected NDE activities were found to comply
with the applicable codes and specifications.
However, during
the review of the radiographic film some irregularities were
identified which involved the following two welds:
Field Weld IVQ-B-1
The radiographs for this weld covering view 2-3 were
originally rejected for base metal gouging.
The repair
film did not adequately cover the repaired area.
As a
result of this finding the applicant issued NCR 31598.
Shop Weld IFC-2-13
This weld was reradiographed by BA.
The weld traveler
FC-2-B misidentified weld IFC-2-13 as being weld
IFC-2-13-W-3.
A visual examination of weld IFC-2-13
confirmed that the radiographed weld is IFC-2-13.
As a
result of this finding the applicant issued NCR 31513.
c.
Conclusions
(1) Welding Activities
In general, the inspected welding activities were found to
comply with the requirements of the applicable codes and
specifications.
However, the NRC CAT found structural welds on
pipe supports / restraints which did not meet the weld specifi-
cations.
The welds for these supports were evaluated by the
Architect Engineer and determined to be structurally adequate
for the intended application.
(2) Nondestructive Examination
In general, the inspected NDE activities were found to comply
with the requirements of the governing codes and specifica-
tions.
However, the NRC CAT found welds which were misidenti-
fied and the repair areas did not have adequate radiographic
coverage.
2.
Reactor Internals Modification and Installation
a.
Inspection Scope
Apprvximately 20 feet of welded seam of the outer bank hood replace-
ment of the steam dryer and 6 new tie bar installation welds were
inspected.
In addition, one welding procedure and the qualification
test records for two welders were also reviewed for adequacy.
The
modification work was performed by General Electric Installation and
Services Engineering Division.
IV-6
-
b.
Inspection Findings and Conclusions
No problems were identified in the area of inspected welding
activities.
Activities were found to meet the specified acceptance
criteria.
3.
Electrical Installation and Electrical Supports
a.
Inspection Scope
The NRC CAT inspected approximately 100 field and 60 shop welds in
the area of electrical installation.
Two welding procedures and
the qualification test records for six welders were reviewed.
In
addition, the personnel qualification test records for four welding
inspectors were also reviewed and four inspectors were observed
and evaluated for their ability to follow the visual inspection
procedures.
The welding activities in the electrical area were
performed by BA.
b.
Inspection Findings and Conclusions
No problems were identified in the area of inspected welding
activities.
Activities were found to comply with the applicable
construction codes and specifications.
4.
Instrumentation Tubing Installation and Instrumentation Supports
a.
Inspection Scope
Approximately 110 welds involving 18 instrumentation supports, 2
panels, and 80 tubing welds were visually inspected to ascertain
compliance with the specified acceptance criteria.
Two welding
procedures and qualification test records for six welders were
reviewed.
NDE procedures and qualification records for four NDE
inspectors were also reviewed.
Two visual welding inspectors and
two liquid penetrant inspectors were observed and evaluated for
their ability to follow the applicable inspection procedures.
The
welding in the instrumentation area was performed by BA.
b.
Inspection Findings and Conclusions
No problems were identified in the area of inspected welding and
NDE activities.
Activities were found to comply with the
applicable construction codes and specifications.
5.
Heating, Ventilating and Air Conditioning
Installation and Supports
a.
Inspection Scope
Approximately 140 welds involving 20 supports were inspected for
compliance with the specified acceptance criteria.
Six welding
procedures and the qualification test records for six welders were
reviewed.
In addition, four welding inspector personnel qualifi-
cation test records were also reviewed and two welding inspectors
IV-7
.
_
were observed and evaluated for their ability to follow the visual
inspection procedures.
The welds on four duct pieces, two air
blowers, one air filter and four dampers were also included in this
inspection.
The welding in the HVAC area was performed by Zack
Company.
J
b.
Inspection Findings
During the inspection of Hanger A-0082 a burn through the duct was
observed in the welded joint between the duct and the duct companion
As a result of this finding, Zack Company issued NCR 912085
and the duct will be repaired as required.
c.
Conclusions
In general, the inspected welded activities were found to comply
with the requirements specified by the Architect Engineer.
With
the exception of the minor finding (burn through duct in one
isolated case) the inspected welding activities were found to comply
with the applicable codes and specifications.
6.
Structural Steel Fabrication, Erection and Modification
a.
Inspection Scope
Approximately 150 welds comprising 80 field and 70 shop welds
involving 22 structural beams were visually inspected in order to
,
ascertain compliance with the specified acceptance criteria.
Five welding procedures and the qualification test records for six
welders were reviewed.
Visual inspection procedures and the
qualification test records for five inspectors were also reviewed.
Three welding inspectors were observed and evaluated for their
ability to follow the visual inspection procedures.
The structural
steel field welding was performed by BA.
Rockwell Engineering and
Bristol Steel supplied structural steel to the project.
b.
Inspection Findings and Conclusions
No problems were identified in the area of inspected welding
activities.
Activities were found to comply with the applicable
construction codes and specifications.
7.
Fuel Storage Pool and Refueling Cavity Liner Fabrication
a.
Inspection Scope
The NRC CAT visually inspected approximately 120 feet of welded
seam on the Fuel Storage Pool and the Refueling Cavity Liner.
The
attachment welds for two gusset hooks and two pad plates were also
inspected in order to ascertain compliance with the specified
acceptance criteria.
In the area of NDE the NRC CAT reviewed the
radiographs for 100 feet of welded seam involving 234 film.
The
Fuel Storage Pool and Refueling Cavity Liner fabrication was
completed by Bristol Steel.
IV-8
__.
__
-
-
. _ .
-
.-
b.
Inspection Findings and Conclusions
No problems were identified in the areas of inspected welding and
NDE activities. Activities were found to comply with the
applicable construction codes and specifications.
8.
Fire Protection System Fabrication and Installation
a.
Inspection Scope
Approximately 80 welds involving 10 pipe supports' and 15 pipe welds
,
involving 2 pipe spools were visually inspected.
One welding
procedure and the qualification test records for two welders were
also reviewed for adequacy.
The fire protection installation was
completed by BA.
b.
Inspection Findings and Conclusions
No problems were identified in the area of inspected welding and
NDE activities.
Activities were found to comply with the governing
construction codes and specifications.
9.
Containment Liner and Containment Penetration Installation
a.
Inspection Scope
The NRC CAT visually inspected approximately 50 feet of liner seam,
the welds on one pad plate, the attachment weld for one personnel
hatch, and the attachment welds for two mechanical and two
electrical penetrations.
In the area of NDE, the NRC CAT reviewed
the radiographs for 150 feet of liner seam which involved 450
film.
One radiographic examination procedure was also reviewed as
a part of this inspection.
The containment liner and penetrations
were installed by CB&I.
b.
Inspection Findings
No problems were identified in the area of inspected welding
activities.
However, during the review of radiographs the NRC CAT
inspectors identified 14 spot radiographs which did not meet the
required weld quality.
As a result of this finding, the applicant
performed an evaluation of the affected liner welds and concluded
that the welds are acceptable "as is" because every weld was sub-
jected to and had passed magnetic particle and vacuum box inspec-
tions.
In addition, in 1984, the applicant had reviewed 25 percent
of the fabrication and erection documentation for the containment
liner. The review was conducted by the Authorized Nuclear Inspector
,
'
employed by the Hartford Steam Boiler Inspection and Insurance
Company. Twenty-six minor nonconforming conditions were identified
and no major discrepancies were found.
Based upon these reviews the
applicant has concluded that the overall liner weld quality is
acceptable to maintain the structural and leak tightness integrity
of the containment liner.
IV-9
.
.
_.
__
_
. _ _
_
_
_.
The NRC CAT identified welded seams and their associated deficien-
cies are listed as follows:
Purchase Order (P.O.) 409.27 7-8A-7C
139 porosity
7-8A
146 porosity
7-8B
144 porosity
7-88-7L
145 Incomplete Fusion
513-A-5
142 porosity
P.O. 409.29
9-10B
176 linear indication
9-108
173 alligned indication
P.O. 409.35
11-128-12L 194 crack-like indication
P.O. 409.35
170
219 porosity
16A
10A crack-like indication
16A
4-5 crack-like indication
P."
409.40
517-11-7
280 incomplete fusion
51-B-7
275 aligned indication
P.O. 409.44
C0 Vert.
4-5 I.F. porosity
!
c.
Conclusions
In general, the inspected welding and NDE activities were found to
4
comply with the requirements of the governing codes and
i
specifications.
However, the NRC CAT found spot radiographs which
did not meet the specified weld quality.
The welds were evaluated
by the applicant and determined to be adequate for the intended
application because every weld had passed magnetic particle and
vacuum box testing.
10.
Drywell Wall and Penetrations
a.
Inspection Scope
The NRC CAT visually inspected approximately 40 feet of drywell wall
seam and the attachment welds for one penetration.
In the area of
NDE, the NRC CAT reviewed the radiographs for 220 feet of welded
seam which involved 340 film.
One radiographic examination proce-
dure was also reviewed as a part of the inspection.
The drywell
wall was fabricated by Mississippi Valley Steel Company and the
field installation of the prefabricated assemblies was done by BA.
i
The drywell locks and hatches were installed by CB&I.
.
b.
Inspection Findings
,
No problems were identified in the inspected welding activities.
j
However, during the review of radiographs, the NRC CAT inspectors
identified three welds which did not have the specified weld
quality.
The three welds and their associated deficiencies are
identified as follows:
IV-10
-.
_ _ . - - .
____ _ . -.
.
.
Seam weld No. 16, station 12 located at elevation 707' to 737',
column 173 contained an unacceptable linear indication.
The
weld was fabricated by BA.
NCR 32686 was generated as a
result of this finding.
Seam weld No. 30, film A-8, view F-G contained an unacceptable
insufficient fusion indication.
The weld was fabricated by
Mississippi Valley Steel Company.
NCR 32294 was generated
as a result of this finding.
One weld for P.O. 9993.1 on drywell locks and hatches assembly
1A, weld seam 1-5-4 to 1-5-1, view 0-1 R1 contained an
unacceptable crack-like indication near station mark 1.
The
original film was rejected for a linear indication near station
mark 0 which indicated that the repair film was reversed from
the original film position.
This reversal had prevented the
interpreter from detecting the crack-like indication because he
was looking at the wrong area.
NCR 32597 was generated as a
result of this finding.
The radiographs were supplied by CB&I.
c.
Conclusions
In general, the inspected welding and NDE activities were found to
comply with the governing codes and specifications.
However, three
welds were found to contain unacceptable indications.
As a result
of this finding, the applicant has issued NCRs and the welds will
be evaluated and repaired as needed.
11.
Vendors and Shop Fabricators Other Than Those Previously Addressed
a.
Inspection Scope
The NRC CAT visually inspected six vendor supplied tanks and heat
exchangers.
See Table IV-5 for inspected vendor supplied equipment.
In addition to the welds inspected and listed in Table IV-5, the NRC
CAT inspectors reviewed radiographs related to work performed by 28
vendors which have supplied various equipments and hardware to the
Clinton Power Station project.
A total of 347 feet of welded seam
involving 472 radiographs and 91 welds involving 771 film were
reviewed.
The radiographs for 19 valves involving 408 film, and
the radiographs for 15 spot welds involving 33 film were also
reviewed for compliance with the governing codes and specifications.
b.
Inspection Findings
During the inspection of tanks and heat exchangers supplied by the
vendors listed in Table IV-5, the NRC CAT found that the size of
the nozzle and manway weld reinforcement did not meet the
requirements stated in the vendor drawings.
In addition, the welds
on some of the inspected supports were also found to be undersized.
A total of six tanks and heat exchangers were found to deviate from
the required drawing sizes.
As a result of these findings, the
applicant issued NCRs and this item will be reviewed and disposi-
tioned by S&L.
See Table IV-5 for details.
The NRC has issued
Information Notice No. 85-33 on the subject of undersized weld
IV-11
-
reinforcement in ASME Code nozzle to shell joints.
As a result of
this notice, prior to the NRC CAT arrival, the licensee had inspec-
ted the nozzle welds on ten pressure vessels and tanks.
Nine of the
items were found to have undersized weld reinforcements around the
nozzles.
By the end of the NRC CAT inspection of this area, the
licensee had initiated a complete reinspection of tanks and pressure
vessels supplied by CBI and RECO industries.
In the area of NDE, the NRC CAT inspectors identified irregularities
relating to NDE documentation and radiographs supplied by two
vendors.
See Table IV-6 for details.
c.
Conclusions
In general, the inspected welding and NDE activities were found to
comply with the requirements of the governing codes and specifica-
tions.
However, six tanks and heat exchangers were found to deviate
from the requirements stated in the applicable drawings and
specifications.
In addition, the radiographs and NDE documentation
supplied by two vendors were found to be deficient with respect to
the required quality.
IV-12
.
.
.
. - -
..
TABLE IV-1
LIST OF SUPPORTS WHICH WERE INSPECTED
AGAINST ORAWING REQUIREMENTS
IMS280095 (1)
1MS28012C
1RB21572R
IMS860015
1HP08009X (2)
ISX45003X (3)
1FC03091X (4)
1FC03002R (5)
1HP04019R
1HP04005R (6)
1HP03042S
1RH20007X
1RH19002X
1RH07004X (7)
1RH07003S
1RH16036X
1RH090895
1LP03016S
1FB15018G*
ILP04003R
1R114019R
1RH09011R (8)
1MS07002G (10)
1RH04051R (9)
1RH04035X
1RH04042X (11)
IIA 16002G
ISC01020R
1RT03032R
1RT11047X
1RB13542G (12)
1MS27012S (Partial)
1MS63001G
1FWO1008G
1MS86001S
1MS860105
ISX30003V
1HP03042S (13)
1RH090875 (14)
IMS86007V
1MS86010X
CLN-021-SP11 (17)
CLN-021-SP16
ISX-01028R
ISX-01017R
ISX-01050X
1RH47013G*
H-1RH-780-4* (15)
ISX42021R* (16)
ISX42019R*
1RH34010X*
1RH71018G*
1RH71016G*
1SX52022X*
1SC01020R*
1RB22056G*
NOTES:
,
1.
One fillet 1/32" undersized for full length due to member size.
NCR 31498.
,
2.
Two fillet welds undersized by 1/16".
NCR 31499.
l
I
3.
Two skewed fillet welds undersized by 1/16" for full length.
NCR 31497.
!
!
IV-13
!
i
-_
.- .
_ -
---
._
.
TABLE IV-1 (Continued)
LIST OF SUPPORTS WHICH WERE INSPECTED
AGAINST DRAWING REQUIREMENTS
.
4.
Two fillet welds 1/32" undersized.
NCR 31493.
5.
One fillet weld 3/4" undersized for full length.
NCR 31496.
6.
Two 1/4" fillet welds 3/32" undersized due to fit-up gap.
NCR 31495.
7.
One fillet weld 1/16" undersized.
NCR 31494.
,
8.
Four obtuse angle skewed welds and one right fillet weld undersized for
full length 1/16".
NCR 31542.
9.
Nineteen of 79 fillet welds 1/32" undersized.
NCR 31572.
10. One fillet weld undersized by 1/16".
NCR 31541.
11.
Obtuse angle fillet weld 3/32" undersized.
NCR 31574.
12.
Obtuse angle fillet weld 1/8" undersized due to too small attaching plate.
NCR 31573.
13.
Three fillet welds 1/16" undersized.
14.
Two obtuse angle fillet welds 1/8" undersized.
NCR 31611.
15. Weld surface has overlap and lack of fusion.
16.
Undercut in excess of 1/32" in two places, unspecified welding across flange.
NCR 31599.
17.
Obtuse angle fillet weld undersized.
IV-14
._
_
_
_
_.
. _ . . _
-
_
_
_
._
_ _ _ - _ _ _ _ _ _ _ _ _ -
-
!
l
!
!
!
TABLE IV-2
LIST OF SUPPORTS WHICH WERE SUBJECTED TO VISUAL INSPECTION ONLY
1RB22144G
1CC50041G
1RB22111G
l
1FWO30115
1RB22106G
IIA 16002G
i
1RIl00095
1RB22056G
1RF07001G
ILP09005G
1RH40011X
1RH40013G
1FB15015G
1FB15006G
1FB15008G
1FB15018
1
IV-15
.
.
_ _ _ _ _ - - _
_ _ _ _ ___ _ _ _ _
_-_
__
TABLE IV-3
e
LIST OF PIPING WHICH WAS SUBJECTED TO VISUAL INSPECTION ONLY
Item
Description
Pipe Size (in.)
Material
G003-A-1
24
Carbon Steel
i
Component Cooling
10, 12
Carbon Steel
12
Carbon Steel
Shutdown Service Water
18
Carbon Steel
Fuel Pool Cooling
14
Stainless Steel
Fuel Pool Cooling
8
Stainless Steel
Fuel Pool Cooling
14
Stainless Steel
1RH-8-7 (1)
24
Carbon Steel
24
Carbon Steel
24
Carbon Steel
4
Carbon Steel
18
Carbon Steel
Shutdown Service Water
18, 24
Carbon Steel
Shutdown Service Water
12
Carbon Steel
Reactor Isolation
4
Carbon Steel
Reactor Isolatinn
4
Carbon Steel
Reactor Isolation
4
Carbon Steel
Reactor Isolation
t
Carbon Steel
Reactor Isolation
4
Carbon Steel
Reactor Isolation
4
Carbon Steel
IV-16
. _ _ _ ___
_.
. _ _ - _ _ - _ _ _ _ _ _ _ _ _
____
TABLE IV-4
PORTIONS OF PIPING SYSTEMS VISUALLY EXAMINED AND
FOR WHICH DOCUMENTATION WAS REVIEWED
Item
Description
Pipe Size (in.)
Material
G003-A-1
24
Carbon Steel
G004-A-1
24
Carbon Steel
G005-A-1
24
Carbon Steel
l
Reactor Isolation
4
Carbon Steel
Reactor Isolation
4
Carbon Steel
Reactor Isolation
4
Carbon Steel
Reactor Isolation
4
Carbon Steel
l
Reactor Isolation
4
Carbon Steel
j
Reactor Isolation
4
Carbon Steel
l
Reactor Isolation
4
Carbon Steel
20
Carbon Steel
18
Carbon Steel
12
Carbon Steel
i
12
Carbon Steel
12
Carbon Steel
12
Carbon Steel
l
12
Carbon Steel
20
Carbon Steel
Lugs
Carbon Steel
Lugs
Carbon Steel
Lugs
Carbon Steel
Lugs
Carbon Steel
IFW-1-7L
Lugs
Carbon Steel
Lugs
Carbon Steel
IV-17
. ..
..
.
_ _ _ _ _ _ _ _ _ _ _ _ . .
c
TABLE IV-5
VENDOR SUPPLIED TANKS AND HEAT EXCHANGERS
-
WHICH WERE VISUALLY INSPECTED
ITEM
MANUFACTURER
Standby Liquid Control Tank 1C41-A001 (1)
Boeing Corporation
Fuel Oil Storage Tank 10001TC (2)
RECO Industries, Inc.
Fuel Oil Day Tank 1DG01TC (3)
RECO Industries, Inc.
Accumulator Tank 1821-A003E (4)
RECO Industries, Inc.
Fuel Pool Cooling Heat Exchanger 1FC01AA (5)
Yuba Heat Exchanger Corp.
Fuel Oil Storage Tank 1D001TA (6)
CB&I Corporation
NOTES:
(1) Five nozzle reinforcing fillet welds undersized.
NCR 32365.
(2) One nozzle reinforcing fillet weld and support fillet welds undersized.
NCR 32364.
(3) Undersized fillet welds on supports.
NCR 32363
(4) Two nozzle reinforcing fillet welds and support welds undersized.
NCR 32361.
(5) One nozzle reinforcing fillet weld undersized due to overgrinding, and
support fillet welds undersized.
NCR 32362.
(6) Nine nozzle reinforcing fillet welds undersized, manway reinforcing fillet
welds undersized, support fillet welds undersized, head-to-shell mismatch in
excess of that permitted by the Code and weld surface quality
unacceptable.
NCR 32573.
IV-18
TABLE IV-6
VENDOR RADIOGRAPHS REVIEWED
Valve
Spot
Feet of
Contractor
Pumps
Film
Notes
20
450
Yuba Heat Transfer
30
60
Progressive Fabricating
40
105
RECO Industries
26
32
Pathway
36
52
Harnischfeger
16
12
Anchor / Darling
5
160
(1)
Rockwell
2
14
Lakeside Bridge
22
54
(2)
& Steel
Carrier
6
9
La Barge
45
37
Southern Boiler
15
10
Tube Turns
6
12
2
44
Spencer Turbine Co.
13
22
Chicago Tube and Iron
4
32
Nooter
15
33
Guyon Alloys
6
9
HUB
1
2
Gould
2
53
Atomic International
6
63
Metal Bellows
10
68
Steward and Stevenson
40
32
'
IV-19
ll
.
_
-
TABLE IV-6 (Continued)
VENDOR RADIOGRAPHS REVIEWED
Valve
Spot
Feet of
Contractor
Pumps
Film
Notes
Posi Seal
7
106
W. J. Wooley
12
19
G. W. Taylor
52
40
Bingham-Willamette
3
45
Trent Tube
30
20
NOTES:
(1) Film stuck together indicating that film was improperly packaged.
(2) Reader sheet for piece mark 2-1-1 showed rejections for cracks and other
indications.
The original film also showed rejections.
The final acceptable
film was not identifiable as being of the same area.
Further investigation
indicated that a slot in the area of interest was welded, ground smooth and
re-radiographed.
The final radiographs were identified and determined to be
acceptable.
IV-20
.-
-
_ _ _ .
-
- - .
. . .
._ .
--
V.
CIVIL AND STRUCTURAL CONSTRUCTION
A.
Objective
The objective of the appraisal of civil and structural construction was
to determine by evaluation and review of Quality Control (QC) accepted
work and documentation whether civil and structural construction areas
were completed in accordance with regulatory requirements, Safety
Analysis Report commitments, and project specifications, drawings and
procedures.
B.
Discussion
The specific areas of civil and structural construction evaluated were
concrete, reinforcing steel configuration, cadwelds, structural steel
installation, high strength bolting, structural fill, and diesel genera-
tor exhaust silencer supports.
A major part of the installed structural
steel inspection sample was previously inspected by the Illinois Power
Overinspection (IPOI) Program.
For concrete, reinforcing steel configuration, structural steel install-
ation, high strength bolting, und diesel generator exhaust silencers,
a physical or hardware inspection and a QC documentation and field
procedures review were conducted.
For cadwelds, concrete pours, and
structural fill, a review of QC documentation and field procedures was
performed.
1.
Reinforced Concrete Construction
a.
Inspection Scope
Reinforced concrete construction areas inspected by the NRC
Construction Appraisal Team (CAT) included reinforcing steel
configuration, activities for a concrete placement, and general
concrete surface quality.
These areas were checked for conformance
with Sargent and Lundy Engineers (S&L) design drawings and specifi-
cations.
General concrete quality was examined from surrounding
areas of completed concrete construction for conformance to site
specifications.
For the reinforcing steel configuration inspection, the upper layers
of exposed rebar projecting from the east face of the base mat along
plant wall lines 200 and 202 and between the D wall line and the
south exterior wall line of the Diesel Generator Building wall were
reviewed for conformance to applicable drawings and specifications.
One in process concrete placement for the personnel access hatch
door to the drywell was observed by the NRC CAT.
These observations
occured from the time of mixing of the concrete at the site batch
plant to completion of the placement of the concrete in the steel
formwork.
Observations were made for slump tests, length of time
required for concrete placement, and preparation of concrete
cylinder test specimens.
V-1
_ _ _ .
.
QC documentation and appropriate field procedures were reviewed for
six concrete pour travelers and three cadweld travelers.
The QC documentation reviewed for six concrete pour travelers and
associated concrete pour package numbers are given in Table V-1.
Records reviewed and associated with the concrete placements
included concrete pour pre placement checklist, concrete pour
placement and testing checklist, and report of concrete cylinders.
The reviews checked the forms for adequate completion by the QC
inspectors, the existence of senior QC inspectors' signature for
evaluation of completed forms, and acceptable coverage of attributes
by the documentation.
For the cadweld QC documentation and field procedures review, the
following cadweld travelers were covered:
CCW No. 3.
Records were reviewed to identify whether the cadweld
work was properly inspected before and after each cadweld was
performed and whether each cadwelder was adequately tested.
In
addition, the qualification records for 10 cadwelders (operator ID
Nos. 6, 15, 16, 17, 19, 20, 27, 30, 46, 48) in cadweld traveler CCW
No. 1 were reviewed to determine if they were properly qualified to
perform cadwelds of each splice position, bar size and grade.
The requirements and acceptance criteria for reinforced concrete
construction were obtained from the drawings listed in Table V-2 and
the following specifications and procedures:
S&L Specification K-2938, " Concrete Mix Design," Rev. 3, dated
April 14, 1981
S&L Specification K-2944, " Concrete and Grout Work," Rev. 26,
dated July 13, 1984
Baldwin Associates Project Procedure BAP 3.1.1, " Concrete,"
Rev. 13, dated October 3, 1984
BAP 3.1.5, "Embedments/ Reinforcing Steel /Cadwelding," Rev. 10,
October 3, 1984
b.
Inspection Findings
Two areas were identified by the NRC CAT where the concrete place-
ments did not meet site criteria in the AD wall line at elevation
724'.
Debris and rags were found embedded in the wall.
It was also
identified that the 2-inch shake space between the containment and
the adjacent structures had been violated.
Two areas were identi-
fied by the NRC CAT inspectors where concrete had encroached into
.
'
the 2-inch shake space between the containment and the adjacent
structures.
The licensee reinspected the rest of the shake space
and identified 26 additional locations where the 2-inch shake space
clearance requirements had not been met.
Nonconformance Report
(NCR) 31579 was issued on this deficiency.
l
The six concrete pour travelers were found to meet procedure
requirements and demonstrate proper QC inspection.
V-2
-
In the top steel reinforcement of the concrete base mat on the 200
line and 202 line, one area was identified where the number and
spacing of the rebar were not in accordance with the design drawing,
but were in accordance with the shop drawings approved by S&L.
31949 was written and the condition was evaluated and accepted by
S&L.
Visual inspection ,equirements before and after the cadwelds were
performed were met.
The 10 cadwelders reviewed for qualification
requirements were found to be properly qualified for cadwelding
the appropriate bar size and grade and splice positions.
Two discrepancies were found in the cadweld traveler packages
reviewed. One discrepancy was a noncompliance with the cadweld
tensile testing requirements in the Final Safety Analysis Report
(FSAR) and specifications.
Appendix B, paragraph B.2.3.4 of the
FSAR states "Sg srate sampling and testing cycles were established
for cadweld oplices in horizontal, vertical, and diagonal bars, for
each bar grade and size, and for each splicing operator." However,
the cadweld records showed that separate sampling and test cycles
were established for cadweld splices in each position, bar size and
grade for each shift (instead of for each cadweld operator).
This discrepancy was previously identified by Baldwin Associates
(BA) in NCR 31282 written on May 18, 1985.
The S&L disposition for
NCR 31282 was to use-as-is because the specification requirements
had been met.
However, the NRC CAT does not consider that the
requirements of Paragraph 4.4.1(a) of the mechanical splice speci-
fication were met.
The same sampling plan is provided in the FSAR.
It appeared that S&L's resolution was based on a general observation
of the records and not a complete review of the records.
Therefore,
the disposition of NCR 31282 is considered inadequate.
The concern of the NRC CAT with this discrepancy is that one or more
operators may have been tested at less than the required frequency.
Since the cadweld tensile test sampling schedule was based on each
shift, rather than individual cadwelders, there could be deviations
from the required testing frequency stated in the FSAR.
The FSAR
requirements in Appendix B, paragraph B.2.3.4 for tensile testing
frequency for each operator states:
Separate sampling and testing cycles were established... for
each splicing operator as follows:
a.
One production splice out of the first ten splices
b.
one production and three sister splices for the next 90
production splices, and
c.
one splice, either production or sister splices for the
next subsequent units of 33 splices.
At least 1/4 of the
tested number of splices tested were production splices.
V-3
The cadweld records do not easily permit a reconstruction of the
testing information to determine if the testing requirements were
met.
However, a tabulation was made of the tensile testing
frequency for production splices of the three cadweld travelers
reviewed by the NRC CAT.
Results of the tabulation are shown in
Table V-3a and V-3b.
Table V-3a shows four operators (I.D. Nos. 6, 16, 20, 30) whose
sampling did not meet the requirements of one production splice out
of the first ten splices.
Table V-3b shows 13 additional operators
(I.D. Nos. 28, 35, 38, 45, 48, 49, 50, 51, 61, 62, 67, 68, 72) whose
sampling did not meet the testing requirements.
The other discrepancy was found in the Cadweld Test Cycle Log.
The
Cadweld Test Cycle Log was to record the sequential order in which
the cadwelds were performed.
However, numerous instances were found
where cadwelds were not in sequential order.
Table V-4 shows
numerous cadweld sequential discrepancies based on the dates
obtained from the cadweld inspection check-off sheets for 17 Cadweld
Test Cycle Log sheets.
The remaining Cadweld Test Cycle Log sheets
contain over 20 other instances of improper ordering of cadweld
production splices.
c.
Conclusion
The general concrete construction quality seems adequate.
documentation in the completed concrete pour travelers appeared
adequate.
Procedures followed by site craft for the single
in process concrete pour work observed by the NRC CAT appeared to be
proper.
The rags found in a completed concrete placement and the 28
locations with concrete in the shake space between the containment
and adjacent structures will require appropriate management atten-
tion.
Records reviewed for cadweld work performed indicated that the
frequency of tensile test sampling for many cadweld operators was
not satisfied.
S&L's corrective action was not adequate.
2.
Structural Steel Installation
a.
Inspection Scon
Installed and QC accepted structural steel were inspected by the NRC
CAT.
A major part of the NRC CAT inspection sample was covered by
the IP0I Program.
Attributes inspected by the NRC CAT were member
size, configuration, and high strength bolted connection configura-
tion.
High strength bolt friction and sliding connections were
tested by using a calibrated torque wrench to determine whether the
bolts were properly installed.
Most of the friction bolt connec-
tions and all of the bolted sliding connections had been inspected
by the IPOI Program.
The samples used in the structural steel verification for correct
member size and configuration are described in Table V-5.
A total of
59 structural steel members and 27 connections were inspected by the
V-4
-
.-
-. _
.
.
_
. _ .
_-
-
_.
_
NRC CAT.
Samples were taken from areas previously covered by IP0I
except for the framing to the Hydraulic Control Unit in Area 3 of
the Containment Building.
Section VII, Design Change Control, of this report discusses
deficiencies identified with the IPOI documentation for structural
steel beams.
Four of the beams refered to in that section with
documentation deficiencies were inspected by the NRC CAT to deter-
mine if the hardware quality had been affected.
This sample was
part of the inspection sample in Table V-5.
The location, size, and number of the three different kinds of high
strength bolts for friction connections that were checked for
installation torque are shown in Table V-6.
A total of 287 bolts
were tested for minimum installation torque.
Test torque values of
IPOI were used for the NRC CAT inspection.
The sample of sliding connections tested is described in Table V-7.
A total of 15 bolts spread over five connections were tested for
maximum installation torque.
The requirements and acceptance criteria for structural steel
installation are included in the drawings listed in Table V-8 and
in the following specifications and procedures:
S&L Specification K-2947, " Furnish Structural Steel," Rev. 3,
dated June 22, 1983
S&L Specification K-2948, " Erect Structural Steel," Rev. 9,
dated March 9, 1984
BAP 3.13, " Structural Steel Erection," Rev. 11, dated October
22, 1984.
b.
Inspection Findings
Detailed findings of the erected structural steel member and con-
nection inspection are provided in Tables V-5, V-6 and V-7.
The
'
comments portion of the tables contain an explanation of whether the
inspection sample had been covered by IPOI.
Of the 59 members reviewed, there was one discrepancy found during
the structural member size and configuration inspection.
Modifica-
tion 1AC for Detail 27-615 on Drawing S27-1458 requires a 7/8-inch
A36 side plate, continuous between the centerlines of Beams 2D and
2E, which had not been installed.
The beam had previously been
inspected and accepted by IPOI.
This seemed to be an isolated case
rather than a program deficiency.
The licensee indicated a complete
reinspection of the beam would be performed, followed by an NCR.
No hardware deficiencies were identified for the sample of four
beams associated with the IPOI documentation discrepancies discussed
in Section VII.B.3.
V-5
.--
_ _ .
_
_ _ _ _ _
Of the 251 friction connection bolts tested by the NRC CAT and
previously by IP0I for minimum installation torque, only 2 bolts
were found to be under-torqued.
Of the 36 fixed connection bolts
tested by the NRC CAT, but not within the inspection sample of IP
OI, seven bolts were found under minimum acceptable installation
torque including one just hand-tight.
Installation torque for the bolts of the sliding connections was
defined as snug-tight.
Procedures provided to the craft to ensure
the bolts were installed in a manner which may prevent the sliding
connections to perform as intended were insufficient.
A sample of
the bolting for two of the five sliding connections checked by the
NRC CAT were found to be over-tight.
S&L was asked to evaluate this
condition. The subsequent response was considered inadequate by the
NRC CAT and requires further evaluation.
The floor grating inside the Containment Building was observed to
not be fastened to the structural steel.
The NRC CAT is concerned
that the grating could become a missile under high energy pipe
break conditions.
The licensee responded that the grating will be
fastened to the structural steel with clips, but that the grating
could still become a missile if subjected to the forces of high
energy break conditions.
This matter was discussed with and will be
referred to the NRR Auxiliary Systems Branch for review.
Another observation by the NRC CAT was that the structural steel
within the Containment Building was coated with inorganic zine which
could generate hydrogen gas during a loss of coolant accident.
The
licensee stated that the amount of zinc in the Containment Building
is being calculated and systems are being sized in consideration of
the hydrogen gas that could be generated.
Therefore, the NRC review
of the calculations and system sizing criteria may be performed at
a later date.
c.
Conclusion
The IPOI Program on the structural steel installation appears to be
satisfactory with two exceptions.
The inadequate implementation of
the IPOI Program criteria resulted in not including the Hydraulic
Control Unit (HCU) framing in the scope of the IP0I Program.
Furthermore, the installed torque of some of the high strength bolts
of the friction connections of the HCU structural steel not included
in the IPOI Program was found inadequate.
The evaluation by S&L of
the identified condition of the sliding connections did not address
the NRC CAT finding and the technical concern of additional loads
due to over-tightened bolts.
3.
Structural Fill
a.
Inspection Scope
The NRC CAT inspectors reviewed daily earthwork logs between June 3,
1976 and June 13, 1976 for the safety-related Class B structural
fill for the main power block structures.
Also, the following NCRs
were reviewed:
NCR S-S-S-0006, NCR 174, and NCR 1650.
V-6
. _ _ _
-.
-_
_.
The requirements and acceptance criteria were included in the following
documents:
S&L Specification K-2942, " Earthwork," Amendment 9, dated
July 13, 1984
U.S. Testing Company Procedure QCP-10 " Testing Procedures for
Earthwork," Rev. O, dated February 9, 1977 and Rev. 9, dated
January 2, 1985
Fruin-Colnon " Compaction Test Section Report," dated April 1976.
b.
Inspection Findings
The daily earthwork logs were reviewed by the NRC CAT inspectors.
A discrepancy was identified with the lift thickness requirements in
the structural fill records.
Of the 15 compaction placement records
reviewed, 7 did not record the lift thickness used in placing the
fill.
Section 2.5.4.5.1.5 of the FSAR states " Type B material used
as structural fill to support foundation loads was placed in near
horizontal lifts not exceeding 12 inches in loose thickness."
Further, the applicable compaction test report also recommends that
the fill be placed in 12 inch lifts.
The NRC CAT review of the
structural fill records do not indicate that the FSAR commitment was
satisfied.
Approximately one-half of the records reviewed did not
indicate any lift thickness measurement.
In other records the lift
thickness was listed as 12 to 14 inches.
The dispositions for the three NCRs were questioned by the NRC CAT.
Nuclear density test data was used to accept fill placements where
the sand cone test data had failed.
This was contrary to the
project specification. Also, structural fill was placed over areas
that had not been QC accepted.
Some of these areas were not
accepted for as long as two years; thus indicating untimely correc-
tive action.
The following is a brief review of the three NCRs referenced above.
NCR S-5-5-0006 was written by BA on June 11, 1976 to cover
apparent errors in the correlation factor between sand cone
tests and nuclear density tests for covered fills placed
between May 29,1976 and June 10, 1976.
As part of S&L's resolution of this NCR, S&L found that the
perceived reduction in the correlation' factor had been cal-
culated incorrectly and that the 73 test locations in question
were in accordance with the design requirements.
The S&L
disposition also indicated that all soil tests reports in
question were checked by BA QC and spot checked by S&L.
This
check supposedly included all sand cone test data (approx-
imately 367) up to May 24, 1976, correlation factors and all
nuclear density test data.
V-7
l
NCR 174 was written by BA on January 21, 1977 to cover failed
sand cone tests between May 17, 1976 and August 19, 1976 and
represented 45 zones (100x100x1 feet) in the structural fill.
These areas of structural fill were accepted based on the
results of the nuclear density tests.
However, three of the
failed sand cone tests were performed prior to May 24, 1976 and
should have been evaluated as part of NCR S-S-S-0006.
Sand
cone test SC 320 performed on May 17,1976 was voided because
the results were " unreliable." A second sand cone test, SC 364
performed on May 24, 1976, had a relative density of 65.3
percent.
This was 20 percent below the acceptance criteria.
On November 1, 1978 NCR 1650 was issued and stated that 16
zones placed between April 29, 1976 and May 17, 1976 did not
meet the specification requirements for frequency of testing
before additional fill was placed.
This deficiency should have
been identified by the prior review of all soil test reports
accomplished under NCR S-5-5-0006 and NCR 174.
The 16 zones were accepted by S&L on the following basis:
Deviation in portions of the documentation does not
necessarily dictate nonconforming physical properties in the
fill.
Zones in question were constructed with procedures similar to
procedures used to construct the rest of the fill.
Average density of the fill is greater than that required by
specification.
Small isolated confined pockets low in the fill will not
influence the overall performance of the fill.
The daily earthwork logs and the basis for the disposition of the
NCRs reviewed by the NRC CAT inspectors are not considered adequate
for the following reasons:
The applicable specifications and procedures were changed four
times during the placement of the fill.
These revisions may
not have been sufficiently addressed by S&L's resolution of the
NCRs.
Some of the records did not show lift thicknesses used.
In some
cases incorrect lift thicknesses were used.
The evaluation performed for the NCRs did not adequately
address the discrepancies found by the NRC CAT with the
apparent omissions in data for evaluations performed of soil
test data.
V-8
_.
-
- .
-_
. .
. . . _
t
The acceptance of failed sand cone test data based on nuclear
density test data was inconsistent with the specifications.
The intent was to have the less reliable nuclear density test
data supported with direct, sound sand cone test data and not
,
vice versa.
Based on our limited review, there was no indication of the
size of unacceptable fill pockets.
c.
Conclusion
The licensee's program of corrective actions did not result in a
timely, comprehensive evaluation and appropriate disposition of
known deficiencies in the testing and placement of structural fill
for the period reviewed by the NRC CAT.
The deficiencies found in
the lift thickness of structural fill were also not identified or
addressed by the corrective action taken.
Therefore, current
corrective action to ensure the adequacy of the structural fill
requires additional management attention.
4.
Diesel Generator Exhaust Silencer Supports
a.
Inspection Scope
Installed torque values were checked for the sliding connections
,
'
of the support pedestals of the diesel generator exhaust silencers.
Installation procedures required the nuts to be hand tight.
b.
Inspection Findings
From the testing of the exhaust silencer support sliding connection
bolts, only one of the bolts were hand tight.
Installed torque
values found by the NRC CAT are shown in Table V-9.
c.
Conclusion
An evaluation should be made concerning the over-tightened condition
of the bolts.
These bolts should not prevent the exhaust silencers
from sliding as designed for thermal growth.
!
V-9
- - - - -
_
. - _ . _ _ _- - - _ _
.-
._.
- _ - _ -
. _ - _
__
-- _ _
- --
- _
_ _
._. -- - - - _ _ _ .
VI.
MATERIAL TRACEABILITY AND CONTROL
A.
Objective
a
The objective of this portion of the inspection was to examine trace-
ability and control of material and equipment and to determine the
'
adequacy of the licensee's program relative to these activities.
B.
Discussion
The approach to perform the inspection was to identify and select
samples of various types of installed material and equipment for
examination.
Some samples of installed material that were not
!
accessible, such as rebar, were selected from records.
The samples
also included uninstalled material that had been QC inspected, such as
protective coating materials, located in warehouses or shops.
A total
,
of 293 samples were examined.
The following Baldwin Associates Project Procedures (BAP) provided the
,
'
acceptance criteria for this inspection:
BAP 1.5, " Material Identification," Rev. 11, dated December 18,
1984; Change D, dated May 23, 1985
BAP 2.3, " Receiving and Issuance," Rev. 12, dated July 26,
1984; Change F, dated April 25, 1985
BAP 2.3.2, " Transfer of Material IP to BA," Rev. O, dated
April 19, 1985
- BAP 2.8, " Material Upgrading," Rev. 8, dated October 26, 1984;
Change A, dated March 28, 1985
- BAP 2.19, " Welding Filler Material Procurement, Storage and
Control," Rev. 3, dated June 19, 1984; Change B, dated December
18, 1984; Change C, dated May 31, 1985.
An inspection of installed material and equipment was conducted in the
plant to select and verify markings on various samples such as equipment
(mechanical, electrical and instrumentation), pipe, supports / restraints
'
and weld joints.
Other samples were inspected in warehouses or shops.
Table VI-1, Summary of Samples, indicates the types and quantities of
,
materials examined.
Table VI-2, Weld Filler Material Compliance,
contains a list of the 17 weld filler material samples selected.
1.
Material Traceability and Control
a.
Inspection Scope
A total of 293 samples were selected and examined for traceability
to applicable drawings, specification, procurement, records,
j
certified material test reports, certificates of compliance, heat
l
numbers or other required documentation.
VI-1
4
--~..-----w-
- --,--- ,. . .,
,~,
-,,-----,--,,---.-,----,--,-r-
. - -
, - - - - ,
, , - , .
b.
Inspection Findings
In general, it was found that the traceability and control of
material at the site was satisfactory, with the exception of a lack
of traceability for certain fastener materials. The following
observations were made by the NRC Construction Appraisal Team (CAT)
inspector:
(1) Manual and computerized records were used to control the
identification and status of material and equipment at the
site.
(2) Seventeen samples of weld filler materials listed in Table
VI-2 examined for traceability and compliance with specifi-
cations and codes were found to be acceptable.
Twenty-three
weld filler material holding ovens ir, two issue stations were
examined and found to meet requirements for temperature control
and the thermometer calibration records. The holding tempera-
ture of 18 loaded portable ovens in the issue stations was
measured using a pyrometer, and were found to be within the
established temperature range. Approximately 100 portable
ovens in use were examined, and only two were found to be not
operating satisfactorily. The heater indicator lights on these
two ovens were not lit, and rods were warm to the touch but
lower than 125 F, the specified temperature.
The light of one
unit lit when the power plug was moved in the outlet.
The
other oven was checked at the issue station and found to be
operating properly.
The problem was identified as a loss
of power at the work station.
(3)
Indeterminate American Society for Testing and Materials
(ASTM) A-36 steel plate material, which had been reported to
the NRC as a potential 10 CFR 50.55(e) deficiency (55-84-18),
is being stored in a segregated outside storage area.
The
area is roped off and clearly marked to show that this material
is on HOLD.
(4) The inspector observed subdividing of stock materials by
warehouse personnel.
Prior to making the cut in steel plate
and structural steel, the identification marking was trans-
ferred to each piece cut from the stock.
l
(5) Material and equipment listed in Table VI-l were examined for
!
traceability and control. Most items examined were found to
have the required material traceability; however, some
deficiencies were found regarding the traceability and control
for large motor mounting bolts and other fastener materials as
follows:
Mounting bolts used in the transition piece between certain
large pump-motor units as listed below are not traceable
and do not have required washers. Documentation identifies
that American Society of Mechanical Engineers (ASME)
SA-193, Grade 87 bolts are to be used between the transi-
VI-2
-_.
__- __
. _ _ _
. _ .
_ _ _ _
._
-
- -
-.
tion piece and the pumps. Documentation does not identify
the grade of bolts to be used between the transition piece
and the motors. ASME SA-193, Grade B7 bolts were installed
between the transition piece and the pumps.
Society of
Automotive Engineers (SAE), Grade 5 bolts were installed
between the transition piece and the motors.
The supplier,
General Electric Company, stated in a telephone conversa-
tion to the licensee (to be followed up by a letter) that
SAE, Grade 5 bolts were adequate for this application.
Additional investigation is required to confirm the proper
bolts required for this application. However, no Noncon-
forming Material Report (NCMR) was issued by the licensee
during the NRC CAT inspection regarding the use and dis-
position of SAE, Grade 5 bolts.
The pump motcr units
inspected and the NCMRs issued for the omission of washers
only, are as follows:
Low Pressure Core Spray Pump:
lE21-C001 - NCMR 2-0330
High Pressure Core Spray Pump:
lE22-C001 - NCMR 2-0331
Residual Heat Removal Pump:
lE12-C002
Bolts installed to hold the Fuel Pool Cooling Pump motors
1FC02PA and 1FCO2PB to the skids are unmarked or incon-
sistently marked and of indeterminate material. ASTM A325
bolts are required.
As a result of this NRC CAT finding,
the licensee issued NCMR 02-0340 to initiate corrective
action.
Bolts installed to hold the Reactor Core Isolation Cooling
Pump 1E51-C001 to the skid are marked SAE, Grade 5 where
ASME SA-193, Grade B7 is specified.
The turbine (lE51-C002)
hold down bolts are unmarked and indeterminate.
The
coupling end requires American Iron and Steel Institute
(AISI) GR 4037-4140, and the governor end requires ASTM
A108-Gil70. As a result of these NRC CAT findings, the
licensee issuea .NCMR 02-0347 to initiate corrective action.
Nuts on clamp bolts at the lower end of a number of spring
can hangers in the recirculation piping are not properly
traceable. As a result of this NRC CAT finding the
licensee issued Nonconformance Report (NCR) 71314 to
initiate ccrrective action.
The load pin on hanger lLP02004V is an ASME Section III,
Class 2 pin used in a Class 1 application. As a result
of this NRC CAT finding the licensee issued NCR 32360 to
initiate corrective action.
Mounting bolts for HVAC control panel cabinets were
unmarked and of indeterminate material. Refer to Section
II.B.3.b(7), of this report, for details.
(6) ASME piping, tubing and welded joints inspected were marked
with the necessary traceability markings, except for a
VI-3
j
_
1/2 x 3/8 inch pipe-to-tube weld adapter in an instrument
tubing run.
The travelers for installation of this adapter
identified an incorrect Receiving Inspection Report (RIR 886)
which should have been RIR 6886.
The licensee issued NCR
32336 to correct documentation associated with this adapter.
(7) While inspecting the Control Rod Drive Mechanism, the inspector
noted that direction control valve No. 123 had an arc strike
which burned a hole through the solenoid housing.
The licensee
issued NCMR 2-0246 to initiate the necessary corrective action.
(8) Unmarked bolting materials, without manufacturer's identifica-
tion, for non-ASME applications are purchased safety, commercial
grade, with certificates of conformance.
This material and
documentation are receipt inspected by Illinois Power Company's
Quality Control before releasing for construction.
c.
Conclusions
In general, except for certain fastener hardware, the material
traceability and control program was considered to be satisfactory.
Lack of traceability was found for fastener materials, particularly
for some vendor supplied pump-motor and pump-turbine assemblies
mounted on skids.
Also, deficiencies were found in traceability for
fasteners on certain hangers and HVAC control panel cabinets.
2
VI-4
- - . - ___
. _ - _ . _ - .
_
__.-.
-
_._
_ _ - ,---
-
_ - - _ -
_
. -_
TABLE VI-1
SUMMARY OF SAMPLES
Item
No. of Samples *
Equipment
14
Pipe
22 (L)
Tubing (Weld Joints)
19 (L)
Steel-Structural
18 (L)
Steel-Rebar
3 (L)
Steel-Tube
19 (L)
Hangers / Supports / Restraints
4 (L)
Embedments
16
Valves
7
Mounting Bolts & Nuts
40
Weld Filler Material
17 (L)
Weld Joints
17
Electrical Cable (Reels)
24 (L)
Fasteners (Sets)
36
9 (L)
Unistrut
5 (L)
Raceway
6 (L)
1 (L)
TOTAL
293
- (L) = Lots
VI-5
.__g
_
.a
..__m
a__
-
_a
2:v+-
- - .
a
m--._.-_u
1
_.
TABLE VI-2
WELD FILLER MATERIAL COMPLIANCE
Material
Heat No./
Compliance
Designation
Material ID
Comments
E7052
065094
Acceptable
E70S2
32470
Acceptable
,
E7052
065162/065163
Acceptable
E308-16 3/32
616385
Acceptable
E308-16 5/32
6MSB Mix 12
Acceptable
E308-16 3/32
49986
Acceptable
E308-16 1/8
0A0369
Acceptable
I
E309-16 3/32
0A10742
Acceptable
E316L-16 3/32
01353
Acceptable
E316L-16 1/8
02754
Acceptable
i
E502-16 1/8
432LO491
Acceptable
E502-16 3/32
421P4461
Acceptable
E7018XLM 3/32
402A9061
Acceptable
E7018XLM 1/8
22340
Acceptable
E7018 1/8
40461
Acceptable
.
E7018 3/32
LOT 28112
Acceptable
'
E7018 3/32
28296
Acceptable
!
i
VI-6
i
_.
..-,- - .
.- .
-.
-__ _
. . _ _ , - _
. _ _ . . _ . , _ - - - - _ _ _ - - _ _
. .
.. -.-
VII.
DESIGN CHANGE CONTROL
A.
Objective
The primary objective of the appraisal of design change control was to
determine whether the design and other related documents and activities
which defined the installation and inspection of the as-built configu-
ration, were controlled in accordance with regulatory requirements,
Safety Analysis Report commitments and approved licensee, engineer, con-
structor and vendor procedures.
B.
Discussion
The governing regulatory requirements for this appraisal are detailed in
10 CFR 50, Appendix B, Criterion III, " Design Control," and Criterion
VI, " Document Control." These requirements are elaborated in Regulatory
Guide (RG) 1.64, " Quality Assurance Requirements for the Design of
Nuclear Power Plants," Rev. 2, dated June 1976, and American National
Standards Institute (ANSI) Standard N45.2.11-1974, " Quality Assurance
Requirements for the Design of Nuclear Power Plants." The licensee's
commitment to comply with RG 1.64 is stated in Chapter 17 of the Clinton
Power Station (CPS) Nuclear Power Plant Final Safety Analysis Report
(FSAR).
In the area of design charge control, the NRC Construction Appraisal
Team (CAT) inspectors reviewed controlled documents which defined the
installation and inspection of completed structures and hardware, and
which defined or referenced design changes to in process or completed
structures and hardware.
The NRC CAT inspection also reviewed the
Baldwin Associates (BA) installation and inspection program and the
Illinois Power (IP) Overinspection program.
For each of these areas,
NRC CAT inspectors conducted interviews with responsible personnel,
reviewed drawings, procedures, specifications, change documents and
reports, and reviewed installed and inspected structures and hardware.
IP provided responses for the majority of the NRC CAT findings
documented in this section of the report. Where the IP response was not
considered sufficient to resolve the NRC CAT finding, this is speci-
fically noted.
1.
Control of Design Documents
a.
Inspection Scope
The following documents provide the basic acceptance criteria for the
inspection:
Sargent & Lundy Engineers (S&L) General Quality Assurance (QA)
Procedure GQ-3.07, "Sargent & Lundy Drawings," Rev. 6, dated October
21, 1981
S&L General QA Procedure GQ-3.12, " Project Status Reports," Rev. 4,
dated August 24, 1984
VII-1
. _-__
S&L General Quality Assurance Program Topical Report SL-TR-1A,
Rev. 6, dated April 22, 1983
BA Quality Assurance Manual, Rev. 15, dated April 5, 1985
I
BA Project Procedure BAP 2.0, " Document Control," Rev. 13,
Change B, dated April 5, 1985
BAP 2.0.1, " Instructions for Maintaining Project Procedures /
Specifications / Drawings," Rev. 2, Change B, dated January 31,
1985
IP Nuclear Power Construction Quality Assurance Manual, Rev.
12, dated March 12, 1985
IP Nuclear Power ASME Quality Assurance Manual, Rev. 5, dated
March 5, 1985
IP Records Management System Standards No. 2.05, " Standard
for the Maintenance of Distributed Documents," Rev. 1, dated
March 7, 1985
IP Nuclear Planning and Support Department (NP&S) Procedure No.
2.51, " Document Control Procedure," Rev. O, dated June 11,
1985.
NRC CAT inspectors interviewed engineering and construction personnel
engaged in the distribution and control of S&L design drawings and
specifications, BA design installation drawings, BA installation
and inspection procedures, and vendor drawings.
b.
Inspection Findings
The primary intent of this review was to assess the adequacy of the
design document control program implemented by the constructor,
Baldwin Associates, for ensuring that correct S&L or BA design
documents were utilized for installation.
This review was conducted
at the BA Document Control Center (DCC), the BA resident engineering
(RE) offices in the civil and structural, piping and pipe support,
and electrical disciplines, and at the BA Field Document Center
(FDC).
(1) The DCC distributes procedures, specifications, design drawings
and associated change documents which are controlled in
accordance with the BA QA Manual, BAP 2.0, " Document Control,"
and BAP 2.0.1, " Instructions for Maintaining Project Proce-
dures/ Specifications / Drawings."
Section 5.3 of BAP 2.0.1 requires that recipients of amendments
and addenda to specifications check all transM tted documents
for accuracy against the DCC transmittal, update the speci-
fication in accordance with the transmittal instructions,
replace superseded pages, verify that all change documents
identified on the transmittal as outstanding are filed in front
VII-2
- -
- -
,
-
--
-
- --
.
-
.
.
-
. - - - -
- - _ - _ _ .-
of the specification, and sign, date and return a copy of the
I
transmittal to the DCC.
Section 5.4 of BAP 2.0.1 requires that recipients of change
documents issued against specifications check the documents
for accuracy against the DCC transmittal, revise the speci-
.
fication in accordance with transmittal instructions, remove
,
affected specification sheets or forms and destroy or return to
!
DCC as directed, file the change documents in the front of the
'
specification, and sign, date and return a copy of the trans-
mittal to the DCC.
Section 5.5 of BAP 2.0.1 requires that recipients of change
documents [ Field Change Requests (FCRs), Nonconformance Reports
(NCRs), Engineering Change Notices (ECNs), and Field Engi-
neering Change Notice (FECNs)] issued against a drawing, check
the documents for accuracy against the DCC transmittal, update
the change documents block to reflect the change document
numbers, maintain a file of open change documents, and sign,
-
1
date and return a copy of the transmittal to the DCC.
Section 5.7 of BAP 2.0.1 requires that recipients of revisions
to procedures check the documents for accuracy against the
DCC transmittal, remove superseded forms or procedures and
insert new or revised procedures or forms in accordance with
transmittal instructions, and sign, date and return a copy of
the transmittal to the DCC.
'
,
I
While BAP 2.0.1 controls the transmittal, distribution and
'
receipt of changes to specifications, procedures and drawings,
the overall status of all change documents outstanding against
'
a given specification or drawing is provided by the Document
Management System (DMS), a computer data base which is updated
by DCC as required by Section 5.1.4 of BAP 2.0.
Sections 6.4.2 and 6.4.3 of the BA QA Manual mandate a computer
data base which maintains accountability and current status of
all documents received or issued at the site including design,
fabrication and installation drawings, design specifications,
change documents and work packages and travelers.
There are
i
currently two computer data bases in use at the CPS which
i
address this requirement:
DMS, which lists active change
documents issued at the site against the corresponding speci-
fications and design drawings, and Construction Management
Information (CMI), which lists all design change documents and
the affected design drawings and specifications.
A Traveler
Tracking System (TTS), which is a subset of CMI, lists the
status and location of traveler documents, and can optionally
reference the associated design and change documents.
IP is
now in the process of developing a computer data base system to
'
l
provide for better tracking and integration of data in these
'
computer data basis systems.
4
1
]
VII-3
- - - -
(2) Tables VII-1 and VII-2 list the drawings, specifications and
procedures selected for review, as well as the BA locations
where copies of these controlled documents were accessed.
For
this documentation sample, the following information was
accessed:
the S&L transmittal letters, the DCC transmittal
documents, the DMS computer data base lists of the active
change documents posted against each drawing and specification,
and the index to the latest revisions of the BA installation
and inspection procedures.
Controlled copies of the drawings, specifications and proce-
dures listed in Tables VII-1 and VII-2 were reviewed in the RE
offices and the FDC to check that specifications were properly
amended and that no superseded materials were present, and that
the change documents posted with the specifications were
consistent with the DMS computer data base listings of active
change documents for those specifications.
Drawings were
checked to confirm that the latest revision of the drawings
were with the stick file and that the active change documents
listed in the change documents blocks by authorized BA
personnel were consistent with the change documents listed in
I
the DMS computer data base.
The BA installation and inspection
procedures were checked to confirm that the latest revisions to
,
the procedures were posted, and that no superseded materials
were present.
The NRC CAT inspectors identified three categories of defi-
ciencies during the course of this review:
the presence of
superseded or voided portions of specifications and procedures,
or inconsistencies between procedures; discrepancies between
the active change documents listed in the DMS computer data
base for a given specification and the change document
included with that specification; and discrepancies between the
active change documents listed in the OMS computer data base
for a given drawing and the change documents included on the
change documents block.
(3) The NRC CAT inspectors documented the following discrepancies
relative to superseded or voided portions of specifications and
procedures, inconsistencies between procedures, and of one
instance of drawing illegibility:
A superseded copy (dated March 4, 1985) of the S&L Document
Index System Foreign Document Report was on file at BA
civil / structural (C/S) RE.
This document is distributed by
BA DCC as received on site from S&L.
Distribution of this
!
document is not controlled in accordance with BAP 2.0 and
its presence without stamping as an uncontrolled item could
result in the RE's inappropriate use in preparation of work
packages.
The BA C/S RE-12 controlled copy of the BA Project Proce-
j
dures Manual contained superseded copies of BAP 1.1 and BAP
t
2. 0.1.
BAP 2.11 contained an Attachment A that was not
l
VII-4
.
formally listed as an attachment in the procedure.
BAP
2.41 was incorrectly filed under tab number 2.40, but BAP
2.40 was not on the distribution list for that controlled
copy.
A superseded copy of BAP 3.1.8 was incorrectly
!
filed under tab number 3.1.4; however, the current revision
of BAP 3.1.8 was correctly filed.
FDC files CL-series drawings on aperture cards.
The five
CL-series drawings listed in Table VII-2 were requested for
review.
The aperture caros identified the correct revision
numbers for the drawings, but were stamped "0RIGINAL DRWG.
NOT LEGIBLE FOR MICROFILM." Blowbacks of the cards con-
firmed drawing illegibility.
An examination of the
full-size sepias at DCC indicated that one of the five
sepias could not be legibly reproduced.
Whether the
illegible sepia was used in producing drawings included
with a traveler needs to be verified and the affect of its
use on construction determined.
Amendment 5 to the FDC copy of S&L specification K-2947
and Amendment 11 to the FDC copy of S&L specification
K-2948 had not been incorporated into the specifications.
Voided pages were not removed.
The BA Traveler Preparation Review Group (TPRG) copy V-530
of S&L specification K-2882 contained a superseded copy of
seven page Attachment 322.
BAP 2.1.6 was filed with the TPRG copy of the BA Procedures
Manual, although shown deleted in the table of contents.
BA QA Manual, subsection 6.5.3.1, requires that design
change documents be " posted and distributed by the Document
Control Center to the affected drawings or work controlling
documents as noted on the design change document." BAP
2.0.1, subsection 5.5, requires the recipient of a change
document to maintain a file of open change documents.
However, BAP 2.0, subsection 5.1.3 was revised on April 5,
1985 to note that stamp affixed change documents will no
longer be distributed directly to the holders of the
affected documents.
This revision of BAP 2.0 is incon-
sistant with the current requirement of the BA QA Manual.
The interim IP response provided during the NRC CAT inspec-
tion does not adequately address this finding.
,
(4) The following discrepancies were documented between the active
change documents posted in the DMS data base for a given
specification and the change documents posted with that
specification.
I
FCR 35687 was not filed with the FDC copy of S&L speci-
l
fication K-2947, but was listed in DMS.
IP indicated
'
that FCR 35687 is stamp affixed.
IP will correct DMS to
list this change document as stamp-affixed.
VII-5
"
The following change documents were listed in DMS but were
not filed with the TPRG, V-530 copy of S&L specification
K-2882:
ECNs 4511, 4822, 4832, 4853 and 5234; FCRs 1847,
26283, 26754, 28060, 30783 and 37478, and NCR 29249.
IP indicated that the DMS listing of the ECNs is correct,
and that copies will be posted with the specification; FCR
1847 is a stamp-affixed change document.
IP will correct
DMS to list FCR 1847 as stamp-affixed.
DMS correctly lists
the remaining FCRs and the NCR as outstanding against the
specification, and copies of these change documents will be
posted in the specification.
The following change documents were filed with the TPRG,
V-530 copy of S&L specification K-2882, but were not listed
in DMS:
ECHs 3634, 3929, 3954, 3960, 3996, 4017, 4061,
4265, 4281 and 4291; FCRs 17682, 19020, 20351, 20605,
20667, 20687, 20742, 21243, 21404, 21770, 21899, 22227,
22578, 22607, 22666, 22677, 22678, 22867, 23129, 23193,
23360, 23640, 24317, 24407, 24559, 24654, 24682, 24655,
24940, 25431, 28071, 30185, 30328, 31502 and 36345; FCR
24416 was filed with the specification, and is not
stanp-3ffixed, but is listed in DMS as a stamp-affixed
change document.
IP indicated that the ECNs and FCRs
listed above had all been superseded or incorporated, and
have been removed from the specification.
IP will
correct DMS to list FCR 24416 as not stamp-affixed.
The following change documents were listed in DMS but were
not filed with the TfRG, V-460, (P/DRFT) copy of S&L
specification K-2882:
ECNs 4832, 4853, 4858, and 4943;
FCRs 1847 and 34643, and NCR 29249.
IP indicated that DMS
correctly lists the ECNs as active against the specifica-
tion, and copies of these change documents will be included
with the specification.
IP will correct DMS to list FCR
1847 as a stamp-affixed change document.
IP indicated
that DMS correctly lists FCR 34643 and NCR 29249 as active
against the specification, and copies of these change
documents will be posted with the specification.
The following change documents were filed with the TPRG,
V-460 (P/DRFT) copy of S&L specification K-2882, but were
not listed in DMS:
ECNs 4380, 4469 and 4895; FCRs 22867,
24317, 28071, 30328 and 36345; FECNs 6639, 7529 # (stamp-
affixed) and 9478.
FCR 24416 which was filed with the
specification and was not stamp-affixed, was listed as
stamp-affixed in DMS.
IP indicated that the ECNs, FCRs
and FECNs listed above were all superseded change docu-
ments, and will be removed from the specification.
IP will
correct DMS to list FCR 24416 as not stamp-affixed.
The following change documents were listed in DMS, but
were not filed with the FDC, V-300 (FDC/R) copy of S&L
specification K-2882:
FCRs 1847, 6480 and 22962, and FECN
8778.
FECN 6639 and FCR 1874 were filed with the speci-
VII-6
.
- -
-
fication but were not listed in DMS.
IP will correct DMS
to list FCR 1847 as a stamp-affixed change document.
IP
indicated that DMS correctly lists FCRs 6480 and 22962, and
FECN 8778 as outstanding against the specification, and
copies of these change documents will be posted with the
specification; FECN 6639 is a superseded change document;
and FCR 1874 is incorrectly posted with the specification.
Due to the results of the review of TPGR, V-460 and TPGR,
V-530 copies of specification K-2882, a followup review of
a third copy of the five controlled copies of this specifi-
cation was performed.
A new DMS printout was accessed and the 104 active design
change documents listed (all nonstamp-affixed) were
checked against the change documents filed with the TPRG,
V-460, (D-6) copy of specification K-2882.
All change docu-
ments were on file, with one exception:
NCR-0114 (one of
seven active NCRs).
Approximately 200 pages associated with
Amendment 11 to the specification were also audited, using
the S&L transmittal listing the pages to be voided or
inserted.
There were no deficiencies identified.
IP's response to NRC CAT findings for the initial two
copies (V-460 and V-530) of specification K-2882 reviewed
noted that these copies have been permanently returned to
Document Control and the third copy (06/V-460) will now be
used as the sole reference of the Piping Department.
Further, the licensee indicated that a full time Document
Control clerk has been assigned the responsibility for
maintaining the controlled documents of the Piping Depart-
ment.
The following change documents were listed in DMS but were
not filed with the TPRG, V-460, (D-6) copy of S&L speci-
fication K-2884:
ECNs 4683; FCRs 29144 and 32822, and NCR
70021.
FCR 24317 was filed with the specification, but was
not listed in DMS.
IP indicated that DMS correctly lists
the ECNs, FCRs and the NCR as outstanding against the
specification, and copies of these change documents will be
posted with the specification; FCR 24317 is a superseded
change document and will be removed from the specification.
FCRs 27508 and 27545 were listed in DMS but were not filed
with the FDC copy of S&L specification K-2999.
NCR 51358
was listed in DMS but was not filed with the specification.
FCR 7113 had been removed from the file of change documents
posted with the specification.
IP did not provide an
interim response during the NRC CAT inspection.
FECN 5081 was filed with the V-465, E/McGUIRE copy of S&L
specification K-2999, but was not listed in DMS.
IP did
not provide an interim response during the NRC CAT
inspection.
VII-7
-
-
.
.
_ -_-____ - ___ - __-___-__-_
.
.-
(5) The following discrepancies were documented between the active
change documents posted in the DMS data base for a given
drawing, the change documents posted with the drawing, and the
change documents listed on the change documents block:
FCR 32933 is listed on the change documents blocks of the
C/S RE copies of BA drawing CL1-27-S-136 and S&L drawing
S27-1001-03B, but is not listed in DMS.
IP indicated that
FCR 32933 was superseded by FCR 37573 and removed from DMS
on May 22, 1985.
The transmittal receipt returned to
DCC is dated May 24, 1985.
The change documents blocks
were therefore not updated in a timely manner.
FCR 35968 is listed on the change documents block of the
C/S RE copy of S&L drawing S27-1003-03A, but is not listed
in DMS.
IP indicated that FCR 35968 was superseded by FCR
37971 and was removed from DMS on May 25, 1985.
The
transmittal receipt returned to BA DCC is dated May 28,
1985.
The change documents block was therefore not updated
in a timely manner.
NCR 29699 is listed on the change documents block of the
C/S RE copy of S&L drawing S28-1002-02A.
DMS lists NCR
29699 as stamp-affixed.
IP indicated that DMS correctly
lists NCR 29699 as stamp-affixed.
The change document
should not be posted on the change documents block.
FCR 25139 is not filed with the FDC copy of S&L drawing
S29-1422, but is listed in DMS.
IP indicated that:
DMS
correctly lists FCR 25139 as outstanding against the
drawing, and that a copy of the change document will be
posted with the drawing, the FCR is incorporated in both
travelers (53369 and S3370), and there is no impact on
hardware.
FCR 32686 is not filed with the FDC copy of S&L drawing
M09-1001N, but is listed in DMS.
IP did not provide an
interim response for FCR 32686 during the NRC CAT inspec-
tion.
ECN 3332 and NCR 5351 R/3 were listed in DMS but were not
t
listed on the change documents block of the BA Start-Up
Field (SU-F) office copies of S&L drawings M-1SX01017R,
sheets 1 and 2.
It appears that ECN 3332 has already been
incorporated into the drawings.
IP indicated that ECN 3332
should not be outstanding against the drawing, and DMS will
be corrected.
IP did not provide an interm response on NCR
5351 R/3.
FCR 27389 is listed in DMS but was not listed on the
change documents block of the BA SU-F copy of S&L drawing
M-1SX01048X.
IP indicated that DMS correctly lists FCR
27389 as outstanding against the drawing.
The transmittal
receipt returned to BA DCC is dated August 29, 1984.
The
change documents block was therefore not properly updated.
VII-8
____________
-
ECN 3332 is listed in DMS but was not listed on the change
documents block of the SU-F copy of S&L drawings M-2SX01028R,
sheets 1 and 2.
It appears that ECN 3332 has already been
incorporated into the drawings.
IP indicated that ECN 332
should not be outstanding against the drawing, and DMS will
be corrected.
(6) NRC CAT inspectors reviewed the IP audit program to determine
whether the discrepancies identified in the construction design
change control area had previously been addressed by IP audit
personnel.
Sections 18 of the IP Nuclear Power American Society of
Mechanical Engineers (ASME) QA manual and the IP Nuclear Power
Construction QA manual define the requirements for a planned
system of periodic audits to verify compliance with the quality
assurance program at CPS.
The IP audit program is also discussed on page IV-30 of IP
report, Results of Quality Programs for Construction of Clinton
Power Station, with Appendices, NRC Docket No. 50-461, dated
February 1985.
Appendix B of that report summarizes each of
the IP QA audits of the BA and IP organizations that were
scheduled and performed for the period 1982-1984.
Table VII-3 lists the sample of IP audits of activities
reviewed by the NRC CAT inspectors.
The activities reviewed by
IP, as well as audit findings, indicate that a number of the
NRC CAT inspection design document control findings in this
report were similar to those previously identified by IP.
For
j
example, IP audit report Q31-83-8, dated July 28, 1983, audit
finding PD-1, noted that BA procedures did not describe the
activities associated with the use and updating of the DMS,
CMI or Aquarius (a historical file) computer programs.
IP
audit personnel also documented discrepancies between these
computer programs, and documented additional discrepancies when
these computer programs were compared to the specific design
documents and the Document Review and Record cards.
This audit
finding was closed by IP on May 23, 1985.
In another example,
IP audit report Q31-85-02, dated April 4, 1985, audit finding
10-1 noted seven procedure updating discrepancies in nine
copies of BAP QC piping and mechanical field office manuals.
,
Therefore, IP has implemented an audit program to verify
compliance with the design document control provisions of the
quality assurance program at CPS.
However, based on NRC CAT
findings, IP audit program corrective actions were not
effective since the acti^n -taken did not provide for the
prevention of the excest.ve deficiencies identified by the NRC
CAT.
VII-9
--
_ _ _ _
_ _ - _ ..
c.
Conclusions
Design document control is generally acceptable for the overall
scope of items sampled with the exception of the high rate of
discrepancies identified in certain areas.
These included the
updating of procedures for the one sampled copy of a project pro-
cedures manual, and the discrepancies between the active change
documents listed in the DMS computer data bases against two con-
trolled copies of piping design specification K-2882 and the change
documents physically posted with each copy of the specification.
In
addition, examples of other discrepancies were identified such as:
the timeliness of updating change document blocks or design change
documents to be listed in DMS, the presence of an illegible sepia
drawing at DCC, and the inconsistency of the revision of BAP 2.0
with the BA QA Manual.
The examples of discrepancies identified by the NRC CAT - as cur-
rently present in the controlled project procedures and in the
listing of design change documents for controlled specifications,
drawings and their DMS computer data bases - are similar to the
deficiencies previously identified in those areas by IP QA audits
and, in part, by NRC Region III and Resident inspectors.
Therefore,
the effectiveness of IP corrective action was apparently inadequate
.
IP interim responses to NRC CAT findings in this area generally
indicated that the causes of the individual discrepancies in design
change or procedure document control will be determined and that
corrective action would be taken.
IP needs to address the generic
implications of NRC CAT findings for the types of discrepancies
identified in the the project procedures manual and specification
K-2882.
2.
Control of Design Change Documents
a.
Inspection Scope
The following documents provide the basic acceptance criteria for
the inspection:
,
IP Corporate Nuclear Procedure (CNP) 3.03, " Nonconforming
l
Material Report," Rev. 4, dated July 18, 1984
l
IP Nuclear Station Engineering Department (NSED) Procedure
D.8, " Handling Clinton Power Station Field Change Requests,"
Rev. 4, dated September 27, 1984
IP NSED Procedure D.9, " Handling Clinton Power Station
Field Problem Reports," Rev. 3, dated July 17, 1984
IP NSED Procedure D.12, " Preparation and Control of Field
Engineering Change Notices," Rev. 1, dated November 19,
1984
VII-10
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _
IP CPS Procedure D.7, " Handling Clinton Power Station
Nonconformance Reports," Rev. 6, dated February 28, 1985
IP Nuclear Power Construction Quality Assurance Manual,
Rev. 12, dated March 12, 1985
IP Nuclear Power ASME Quality Assurance Manual, Rev. 5,
dated March 5, 1985
IP Records Management System Standards No. 2.05, " Standard
for the Maintenance of Distributed Documents," Rev. 1,
dated March 7, 1985
IP NP&S Procedure No. 2.51, " Document Control Procedure," Rev.
O, dated June 11, 1985
S&L General QA Procedure GQ-3.07, "Sargent & Lundy Drawings,"
Rev. 6, dated October 21, 1981
S&L General QA Procedure GQ-3.13, " Engineering Change
Notices," Rev. 6, dated October 21, 1981
S&L General QA Procedure GQ-3.15, " Approved Procedural
Deviations," Rev. 1, dated January 26, 1981
S&L General QA Procedure GQ-4.01, " Procurement Specifica-
tions," Rev. 10, dated August 15, 1983
S&L Project Instruction PI-CP-003, " Processing a Baldwin
Associates Field Change Request or Nonconformance Report,"
Rev. 13, dated May 31, 1984
l
S&L PI-CP-004, " Control of Clinton Engineering Change
Notice (ECN)," Rev. 10, dated November 7, 1984
"
j
S&L PI-CP-021, " Processing an Illinois Power Company Field
Problem Report," Rev. 5, dated November 7, 1984
S&L PI-CP-022, " Control of Clinton Field Engineering
Change Notices (FECN)," Rev. 5, dated October 5, 1984
l
!
S&L PI-CP-046, " Processing an Illinois Power Company
l
Nonconforming Material Report (NCMR)," Rev. 2, dated
l
October 10, 1984
'
BA QA Manual, Rev. 15, dated April 5, 1985
BAP 1.0, "Nonconformances," Rev. 16, dated March 28, 1985
BAP 1.2, " Field Change Requests," Rev. 12, Change C, dated
November 19, 1984
BAP 2.0, " Document Control," Rev. 13, Change B, dated April
5, 1985
VII-11
_ _ _ _ _ _ _ _
-
BAP 2.0.1, " Instructions for Maintaining Project Proce-
dures/ Specifications / Drawings," Rev. 2, Change B, dated
January 31, 1985.
NRC CAT inspectors interviewed engineering and construction person-
nel engaged in the distribution and control of design change
documents.
b.
Inspection Findings
Site issued design change documents are processed through the DCC
and distributed, with the recent exception of stamp-affixed change
documents, to all locations which maintain controlled copies of the
affected drawings and specifications, and to all affected travelers.
DCC updates the DMS computer data base to indicate that a given change
document has become active against a drawing or specification, and
copies of all active change documents are maintained with drawings
and specifications.
New travelers are issued, or supplements to
existing travelers are issued, to incorporate newly-issued change
documents which impact in progress or completed structures and hard-
ware.
Change documents must be referenced on, and physically
attached to, these work packages.
As previously noted, TTS, the
computer data base which lists the status and location of traveler
documents, does not currently mandate that active change documents
be listed in TTS.
As a consequence, travelers affected by a given
design change document could not always be readily identified.
This
is not consistent with the requirements of Section 17.4 of the BA QA
manual, which commits BA to an index system for records to be
maintained in the Documents Record Center which will ensure the
rapid and orderly identification and retrieval of records.
NRC CAT inspectors selected the 24 design change documents listed
in Table VII-4.
In majority, the sample was selected from the change
document discrepancies the NRC CAT inspection had documented in Sec-
tion VII.B.1.b.(4) above, for a number of the controlled specifica-
tions available to REs for use in the preparation of work packages.
The review was primarily performed to assess the extent design change
documents not properly included with the specification may not have
been implemented in work packages prepared by REs utilizing those
specifications.
IP was requested to provide the NRC CAT with an
example of documentation which substantiated the intended disposition
of each of the 24 selected change notices.
The NRC CAT review of
the documentation provided by IP assessed the actual disposition of
each design change document for its incorporation in a work package,
i.e., either an amendment to a specification, procedure or a purchase
order, or supplement to a traveler.
The NRC CAT review identified
the following discrepancies:
BA equipment installation traveler RH-024 does not appear to
have been revised to incorporate FCR 27508.
The change docu-
ment is dated August 25, 1984, and waives the provisions of
American Welding Society (AWS) D1.1, paragraph 8.2.3 for
qualification for weldability of American Iron and Steel
Institute sAISI) C1010 to C1025 sheet steel.
The change
VII-12
79--
-
.
document requires that specification K-2999 be amended to
incorporate this waiver.
DMS still lists FCR 27508 as out-
standing against the specification.
ECN 5282, dated June 3, 1985, allows the use of ASME Code
Case N-413, Minimum Size of Fillet Welds for Linear Type
Supports,Section III, Division 1, Subsection NF.
Box 7 of the
change document was marked in error as it indicates
that an FSAR revision is not required.
However, the IP letter
S-5454 dated May 22, 1985, which is referenced in the ECN,
indicates that IP will draft an amendment to the CPS FSAR for
the use of this code case.
NRC's letter of April 30, 1985 to
IP indicates that the referenced code case may be used at the
CPS.
FCR 27545 documents HVAC and electrical attachments welded
to structural steel that were fireproofed without prior appli-
cation of a galvanox coat.
The FCR requires that specifica-
tions K-2910 and K-2999 be revised to permit a direct appli-
cation of CAFCOTE H fireproofing directly over welds which are
clean and free from slag and debris.
The original nonconform-
"
ing welds should have been documented on an NCR for an evalua-
tion as to their acceptability.
This review resulted in identifying only one instance where the
change document (FCR 27508) was not referenced on the appropriate
traveler revision, and two other apparent discrepancies in docu-
mentation.
However, the sample of change documents listed in Table
VII-4 is not considered sufficiently large to confirm the actual
implementation of all design change control discrepancies identified
by the NRC CAT.
The NRC CAT also could not confirm that the sample
of work packages provided for review were prepared through the RE
use of the TPRG V-530 and V-460 copies of the K-2882 controlled
specification found to contain an excessive number of deficiencies
in omitted design change documents.
Further, the NRC CAT followup
review of a third copy of the five controlled copies of Specifica-
tion K-2882, found only one such deficiency.
This indicates that
travelers prepared by use of this third specification most likely
would implement the design change documents not included with the
V-530 and V-460 copies of the K-2882 specification.
Therefore, the
results of the verifications of the sample of work packages provided
for NRC CAT review may not be representative of the disposition of
the excessive change notice discrepancies identified in two of the
five K-2882 specifications initially examined by the NRC CAT inspec-
tor.
c.
Conclusions
The program for control of design change documents was generally
determined to be in accordance with site procedures, with one
exception.
The exception pertains to an inconsistency between the
program instructions for TTS and the Index System of records.
TTS
instructions allow that active design change documents need not be
VII-13
listed in TTS for a given traveler.
This option for TTS does not allow
for the ready identification of travelers affected by a given change
notice.
On the otherhand, the Index System for Records is required
to be maintained in a manner which will ensure the rapid and orderly
identification and retrieval of records.
It is noted that IP's
current effort to integrate data in DMS and CMI into one data
system should resolve this inconsistency in procedural requirements.
For the sample of 24 change documents and related implementing
documents examined by the NRC CAT inspectors, all but one of the
change documents was verified to be implemented as intended in a
work package, i.e., either an amendment to a specification, proce-
dure, or purchase order or supplement to a traveler.
However,
the NRC CAT findings also indicated that IP corrective action, as
discussed in Section VII.B.1.c above, is warranted.
3.
Illinois Power Company Overinspection Program
A consideration of the NRC CAT's selective examinaticns discussed in
most sections of this report was to include examination of a sample
of installed hardware that had been subject to the IP Overinspection
Program.
The IP Overinspection Program was implemented in response to a
series of stop work actions imposed in 1981 and 1982 due to iden-
tified deficiencies in the implementation of the BA QA Program for
construction of various areas of CPS.
The IP Overinspection Program
provides two levels of additional inspection in the functional work
areas subject to the prior stop work actions.
The two adcitional
levels of inspection of work previously inspected by BA QC include a
sample inspection conducted by the BA Field Verification (BAFV)
Group and a subsequent sample inspection by the IP Overinspection
(OI) Group.
The intent and scope of the IP Overinspection Program
is summarized on pages V-1 and V-2 of 1P Report "Results of Quality
Programs for Construction of Clinton Power Station", with Appen-
dices, NRC Docket No. 50-461, dated February 1985.
As noted
therein:
The purposes of the Overinspection Program are to verify
that the structures, systems, and components within the
scope of the program are properly installed and to provide
IP with assurance that BA is performing installation and
inspection work that satisfies the applicable req,sirements
of codes, standards, drawings, and specifications.
These
objectives are accomplished by performing additional inspec-
tions of completed and inspected work, whether performed
before issuance of stop work actions in 1982 (old work)
or after the stop work actions were lifted (new work).
The
inspections conducted under the Overinspection Program are
in addition to those normally performed as part of the QA
Program for CPS.
Therefore, the Overinspection Program is
a supplement to the QA Program and not a substitute for it.
VII-14
,
. .
._
Inspections in the IP Overinspection Program focus on installation
of safety-related, augmented class D (radioactive waste), and fire
protection items in the following areas:
large and small bore
piping, mechanical equipment, structural steel, heating, ventilating
and air conditioning, electrical hangers, electrical conduit and
raceways, electrical terminations, electrical equipment, and
electrical and mechanical instrumentation.
Since the IP Overinspection Program supplements the BA QC program
and is not a substitute for that program, the NRC CAT inspectors
in the area of design change control reviewed the BA installation and
QC inspection work packages in addition to the IP Overinspection
Reports for the hardware sample listed in Tables VII-5 through
VII-7.
Other NRC CAT examinations of hardware previously inspected
by the IP Overinspection Program are discussed in the other sections
of this report.
a.
Inspection Scope
The following documents provide the basic acceptance for the
inspection:
BA Quality Assurance Manual, Rev. 15, dated April 5, 1985
BA Quality and Technical Services Organization Chart,
dated March 8, 1985
BA Quality Control Training and Qualification Manual,
Rev. 9, dated September 26, 1984
BAP 3.1.3, " Structural Steel Erection," Rev. 11, Change B,
dated May 17, 1985
BAP 3.2.5, " Piping Component Supports," Rev. 7, Change D,
dated May 13, 1985
BAP 3.3.6, " Electrical Raceway Support Installation," Rev. 10,
dated May 17, 1985
BAP 3.3.10, " Cable Tray Installation and Traveler Processing,"
Rev. 6, Change E, dated May 21, 1985
BAP 3.6.3, " Repair of Welds, Material and Items," Rev. O,
Change C, dated April 17, 1985
BAP 3.6.5, " Visual Inspections of Weldments," Rev. O,
Change B, dated March 26, 1985
IP Nuclear Power Construction Quality Assurance Manual,
Rev. 12, dated March 12, 1985
IP Nuclear ASME Quality Assurance Manual, Rev. 5, dated
March 5, 1985
VII-15
l
J
.
IP Nuclear Power Program Organizational Chart, dated
January 15, 1985
IP Quality Assurance Instructions QAI-710.01,
"Overinspection Program," Rev. 5, dated March 20, 1985
IP (AI-710-08, "0verinspection Sample Plar..," Rev. 3, dated
<
April 26, 1985
IP QAI-710.12, " Structural / Auxiliary Steel Oserinspection
Checklist," Rev. 7, dated February 22, 1985
IP QAI-710.13, " Mechanical Equipment Overinspection
Checklist," Rev.1, dated January 13, 1984
IP QAI-710.14, " Piping / Valves / Instrumentation
Overinspection Checklist," Rev. 4, dated November 15, 1984
IP QAI-710.15, " Component Support Overinspection
Checklist," Rev. 4, dated August 27, 1984
IP QAI-710.18, " Electrical Raceway Support Overinspection
Checklist," Rev. 2, dated February 21, 1985
IP QAI-710.19, " Electrical Raceway Support Overinspection
Checklist," Rev. 2, dated February 21, 1985
NRC CAT inspectors interviewed engineering and construction person-
nel engaged in the preparation and contro? of BA installation and
inspection work packages and IPOI reports.
b.
Inspection Findings
Inspection findings for this review are categorized as discrepancies
in computer data bases, BA installation and inspection work pack-
ages, or in IPOI reports.
(1) As described in Section VII B.1.(b).(1) above, there are
currently two basic computer data 'ases in use at CPS:
DMS,
u
which lists active change documents issued at the site against
the correspcnding design drawings, and CMI, which lists all
design change documents and the affected design drawings and
specifications.
TTS, which is a subset of CMI, lists the
status and location of traveler documents, and can optionally
reference the associated design and change documents.
The NRC CAT inspectors documented several discrepancies in
these computer data bases during the course of this review
of the use and relationship of the computer data with the
work packages prepared for BA installation and inspection
and IP Overinspection activities.
These include:
VII-16
TTS lists the incorrect design drawing revision numbers for
the design drawing referenced in IPOI reports M-3330 and
M-3338.
A systematic weakness in DMS is it does not reference
the work packages and travelers associated with the S&L
structural steel design drawings.
A systematic weakness in TTS is it does not reference
th? design drawings associated with electrical cable tray
support travelers.
(2) There is no uniform relationship between the hardware detailed
on a design drawing and the number of BA work packages and
travelers prepared by each construction discipline to document
the installation and inspection of that hardware.
As an
example, there is generally one-to-one correspondence between
the design drawing and the traveler for pipe and cable tray
supports, while for structural steel there are numerous work
packages and travelers associated with each structural steel
design drawing.
Structural steel inspections were documented
on either inspection forms, vendor drawings or welding
travelers depending on whether the steel was vendor fabri-
cated, field fabricated, bolted or welded.
The NRC CAT inspectors note that the current computer data
bases program does not readily relate the associated design,
fabrication, installation and inspection documents.
Since
there is no current correlation in DMS between the structural
steel design drawings and the associated work packages and
travelers, some documentation proved difficult to access and
audit.
For example, BA required approximately one week to
access the welding travelers associated with the steel beams
listed in Table VII-5.
Other NRC CAT inspectors indicated that
documentation proved difficult to access in their areas as
well.
However, the requested work packages and travelers were
eventually accessed and, in general, were properly documented.
The NRC CAT inspectors noted a number of documentation discre-
pancies in the BA installation and inspection work packages.
These included an incorrect Receiving Inspection Report number
for a steel beam listed in a support traveler
(E26-1003-01A-H48, Rev. 11), an incorrect inspection attribute
indicated on two of three pre-inspection checklists filed with
a hanger traveler (E27-10002-018-H33), BA QC inspection forms
for several steel beams do not reference the correct revisions
,
of the S&L design drawings, a steel plate listed on the bill of
materials but not used on the hanger drawing, and inconsist-
ancy in documentation relative to the use of the surveyors'
reports for verification of pipe support locations and Form
JV-718 for verification of electrical hanger locations in
containment.
VII-17
.
-
.
.-
-
(3)
Illinois Power performed overinspection activities in accoi'd-
ance with a series of overinspection checklists which defined
the attributes to be inspected for a specific piece of hard-
ware.
This list of attributes was generally a subset of the
attributes that had been BA QC inspected for that piece of
hardware.
The NRC CAT noted a number of generally minor documentation
discrepancies in the IP0I reports reviewed.
These included
reports (S-0399, S-1490, M-3351, M-3329, E-3920) which
referenced an incorrect drawing number, or drawing or revision
number, an incorrect building elevation, or an incorrect FECN;
two reports (M-3349, E-3762) which did not document an inspec-
tion attribute or included the wrong form; and one report
(E-3623) which documents an incorrect drawing revision as being
used for the inspection.
In addition an inconsistency similar to that discussed in
Section VII.B.3.b.(2), above, relative to surveyors' reports
was found.
QAI-710.18 requires location of electrical hangers
be verified to design drawings and Form JV-718 is used as the
documentation of the verification, while QAI-710.15 does not
require independent verification of pipe support locations in
containment, but does require that the surveyors' report to be
attached to the verification checklist.
As noted in Section III, Mechanical Construction, and Section V,
Civil and Structural Construction, of this report, the NRC CAT
physically inspected a sample of hardware associated with the IPOI
report work packages reviewed.
This included four of the steel
beams listed in Table V-5 and six of the pipe restraints listed in
Table III-3.
The purpose of the field inspection was to substan-
tiate the technical content of the IPOI reports, including the
affect of a number of the apparent documentation discrepancies on
the installation.
No deficiencies in the installed hardware were
identified.
c.
Conclusions
For the overall scope of documentation items sampled during tnis
NRC CAT review, the documentation of BA installation and inspec-
tion work packages and of IPOI reports, except for discrepancies
noted, is generally adequate.
The majority of the discrepancies documented for this review are
considered minor in nature.
The two systematic weaknesses in the
computer basis (DMS and TTS) are considered to contribute to the
difficulty IP was having with the timely access of documentation.
The NRC CAT review of the approximately 400 documentation attributes
for the 25 IPOI reports examined found that the reports were
generally well documented relative to the overinspection conducted,
with some exceptions.
In majority, the exceptions related to
documentation discrepancies which apparently had a minor effect on
VII-18
- -
.
- - -
.
..
. ..
.
.
. . _
_ - . - . . _ -
- - .
.-
-
!
the overinspection conducted.
However, these errors in documenta-
tion indicate that a more critical management review of the infor-
mation recorded on the IPOI reports should be performed.
I
a
)-
i
i
I
,
,
4
f
F
,
4
i
r
l
VII-19
i
t
,
. - . - . - - , - - .
, - - , - , _ , - _ . , - - . , - - -
,a.
, . , -
- , - , - , _ , _ -
- . . - - - - - - , - - -
, - - - - - - - - , ~ , , . , - - -
.
.-
.
- _.
._
.
- ._ .
- - .
- -
. - _
.
P
k
TABLE VII-1
SPECIFICATIONS AND PROCEDURES REVIEWED
i
Document ID
Location (s)
.
S&L Spec. K-2882, Rev. 11
BA Traveler Preparation Review Group (TPRG) (3 copies)
!
BA Field Document Center (FDC)
!
S&L Field Design Office
(to confirm filing of ECN 4832)
S&L Spec. K-2884, Rev. 8
BA TPRG
l.
BA FDC
.
S&L Spec. K-2944, Rev. 27
BA Civil /Struc. (C/S) Res. Eng. (RE)
1
BA FDC
a
!
S&L Spec. K-2947, Rev. 5
BA C/S RE
BA FDC
S&L Spec. K-2948, Rev. 11
BA C/S RE
i
BA FDC
S&L Spec. K-2999 Rev. 11
BA Electrical RE (2 copies)
BA FDC
,
t
Baldwin Project Procedures
BA C/S RE
(various revisions.)
BA TPRG
i
,
1
5
i
VII-20
4
v
e
e,-
..,.-----.n
- . - ,
,.e...
- ._-, ,.
- -- ,- -, .
- - - -.-,
-_.,.-.---c
.
_
TABLE VII-2
DRAWINGS REVIEWED
Document ID
Location (s)
S&L Dwg. S26-1705, Rev. E
BA C/S RE & BA FDC
S&L Dwg. S26-1710, Rev. N
BA C/S RE & BA FDC
S&L Dwg. S26-1407, Rev. Y
BA C/S RE & BA FDC
S&L Dwg. S27-1001-03B, Rev. AH
BA C/S RE & BA FDC
S&L Dwg. S27-1002-01A, Rev. AY
BA C/S RE & BA FDC
S&L Dwg. S27-1003-03A, Rev. AM
BA C/S RE & BA FDC
S&L Dwg. S27-1004-04A, Rev. AB
BA C/S RE & BA FDC
S&L Dwg. S27-1005-04A, Rev. AD
BA C/S RE & BA FDC
S&L Dwg. S28-1002-02A, Rev. S
BA C/S RE & BA FDC
S&L Dwg. S28-1003-05A, Rev. T
BA C/S RE & BA FDC
S&L Dwg. S28-1100-07C, Rev. K
BA C/S RE & BA FDC
BA Dwg. CL1-27-5-132, Rev. 4
BA C/S RE &
BA Dwg. CL1-27-5-136, Sheet 12, Rev. 2
BA FDC (aperture cards) &
BA Dwg. CL1-27-S-136, Sheet 25, Rev. 2
BA DCC
BA DWG. CL1-27-S-136, Sheet 37, Rev. 1
BA Dwg. CL1-27-5-141, Sheet 18, Rev. 1
S&L Dwg. M09-1001N, Sheet 1, Rev. N
BA TPRG &
S&L Dwg. M09-1003N, Sheet 1, Rev. M
BA FDC
S&L Dwg. M09-1004N, Sheet 1, Rev. L
S&L Dwg. M-1SX01048X, Rev. F
S&L Dwg. M-1SX01017R, Rev. H, Sheets 1&2
S&L Dwg. M-INB010035, Rev. A
S&L Dwg. M-1NB01027X, Rev. A
S&L Dwg. M-1CC06042G, Rev. B
S&L Dwg. M-1RB24010G, Rev. C
S&L Dwg. M-1SX01050X, Rev. E
S&L Dwg. M-1SX01028R, Rev. J. Sheets 1&2
!
!
VII-21
- -
_
_
-_
1
TABLE VII-3
IP AUDIT SAMPLE
IP Audit
Report No.
Organization Audited
Q31-83-8
Baldwin Associates (BA) Quality Assurance
Q31-84-01
BA Quality & Technical Services
Q31-84-02
BA Procurement
Q31-84-03
BA Piping / Mechanical
Q31-84-04
BA Document Review Group
Q31-84-05
BA Electrical Department
Q31-84-07
BA Field Verification
Q31-84-09
BA Document Control Center (DCC) and
Nonconformance Review Group
Q31-84-10
' BA Systems Release and Completion
Q31-85-01
BA Electrical Reinspection Program
Q31-85-02
BA Quality Control & Technical Services
Q31-85-04
BA Quality Engineering Systems, Quality
Engineering Procedures and DCC
Q31-85-05
BA Procurement, Receiving and Audits Sections
,
VII-22
TABLE VII-4
CHANGE DOCUMENT SAMPLE
Change
Required
Implementing
Document
Description
Disposition
Document
ECN 3332
Add Note to two support
Revise support drawings
Traveler Nos. H-SX-2-C,
drawings
to incorporate note
H-SX-3-D
ECN 4291
Modification to ECN 4061
Revise Paragraphs 326.7c,
Generic
d of Specification K-2882,
Revise Dwg. M06-1000,
Sheet 12
ECN 4683
Correct typographical
Revise Paragraph 302.4a
Generic
error in ECN 524
of Specification K-2884
ECN 4822
Clarifications to Spec.
Revise Attachment 311.3
Clow Painting
BA-K-2882-29
of Specification K-2882
Procedure
EPS 30-69-721
ECN 4832
Response Spectra Data for
Revise Article 305.4 in
Generic
valves and actuators
Attachment 311.3 of
Specification K-2882.
ECN 4853
Clarification of shop
Revise Attachment 311.3
Clow Painting
painting requirements for
of Specification K-2882
Procedure
valves installed in
EPS 30-69-721
containment b1dg.
ECN 4943
Purchase and installation of Revise Attachment 311.2,
IP P0 X-19490, dated
nuclear safety-related
add Sections 327 and
dated April 3, 1985
heat tracing fo- CM and PR
Attachment 327 to
systems
Specification K-2882
ECN 5263
Update list of Class D
Revise Attachment 302.50
Traveler No. 1WOLC6303
support listed in Attach-
of Specification K-2882
ment 302.50
ECN 5282
Allow use of Code Case N-413 Revise Attachment 110.1 of Generic
for component supports
Specification K-2884
NCR 29249
Use as-is dispositio,of
S&L Concurrence
Traveler No. DG-2
pipe minimum
Supp. 15
NCR 51358
Use as-is disposition of
Revise Specification
Traveler No. IVH25B
control cable mechanical
K-2999
connection
l
VII-23
l
I
TABLE VII-4 (Continued)
CHANGE DOCUMENT SAMPLE
Change
Required
Implementing
Document
Description
Disposition
Document
NCR 7002
Superseded by DR 5935;
S&L Concurrence
N/A
DR 5935 superseded by
10283; NCR 10283
documents use as-is
disposition for anchor
bolt which does not
project beyond nut
FCR 21404
Incorporate '81 Addenda to
Revise Paragraph 118 of
Traveler No. RR-759-A
ASME Code for Minor Attach-
Specification K-2882
FCR 21899
Revision of purchase
Revise Article 319.2 of
BA P0 C49800
requirements for copper
Specification K-2882
refrigeration tubing
FCR 27389
Snubber substitution for
Incorporate design change
Traveler No. H-SX-2-C
two supports
drawings
FCR 27508
Material clarification and
Revise Specification
Traveler No. RH-024
weld qualification infor-
K-2999
has not reference to
mation
FCR 27389.
FCR 27545
Use as-is disposition of
Revise Specification
Generic
fire proofed HVAC and
K-2910 and K-2999
electrical attachment weld
to structural steel without
galvanex
FCR 28060
Material substitution for
Revise Paragraph 118 of
Baldwin Purchase
SA 307 GR A bolts and nuts
Specification K-2882
Order No. C48811
FCR 29144
Clarification of safety-
Revise Specification
Generic
related requirements for
K-2884
exempt items per NF-2121(b)
from basic engineers
FCR 30783
Material substitution for
Revise Specification
Midway Industrial
primer and finish for
K-2882
Contractors Form
interior of diesel oil
storage tanks
FCR 32822
Clarification of hanger
Revise Specification
Generic
support ID
K-2884
VII-24
1
TABLE VII-4 (Continued)
CHANGE DOCUMENT SAMPLE
Change
Required
Implementing
Document
Description
Disposition
Document
FCR 38578
Installation modifications
S&L Concurrence
Traveler No. CS1655
to beam connections due to
field interference
FCR 36538
Clarification of installa-
Revise Paragraph 313.5
Traveler No. VG-3-8
tion and inspection require- of Specification K-2882
ments for Class O penetra-
tion assemblies
FCR 36245
Hanger stiffener cannot be
Revise Hanger Drawing
Traveler No. H-RR-995-F
installed due to inter-
1RB13521G
ference
VII-25
_ _ _ _ _ _ _
TABLE VII-5
STRUCTURAL STEEL IPOI SAMPLE
DI Report
Elev.
Bristol
No.
Bldg.
(Ft.)
S&L Drawing
Bristol Drawing
Piece Mark
S-0826
Aux.
800
S26-1004-01A, Rev. F
F-02710, Sheet 5-8, Rev. 0
5-8B6
S-0399
Fuel
800
526-1004-02A, Rev. F
Baldwin Detai1*
S2520A
S-0825
Aux.
800
S26-1004-01A, Rev. F
F-0271D, Sheet 5-6, Rev. 0
5-683
S-0862
Aux.
800
S26-1004-02A, Rev. H
F-0271D, Sheet 5-9, Rev. 1
5-9B5
S-1460
Contain.
778
527-1003-03A, Rev. AH
F-0271A, Sheet 3-14, Rev. 1
3-1483
S-1462
Contain.
778
S27-1003-03A, Rev. AH
F-0271A, Sheet F3-11, Rev. 2
F3-11B1
S-1464
Contain.
778
S27-1003-03A, Rev. AH
F-0271A, Sheet F3-5, Rev. 2
F3-5B8
S-1472
Contain.
778
S27-1003-03A, Rev. AH
Fab. Detail Per FCR 11690*
--
S-1486
Contain.
778
S27-1004-01A, Rev. AA
F-0271A, Sheet F5-16, Rev. 1
F5-16BA
S-1490
Contain.
803
S27-1004-01A, Rev. AB
F-0271A, Sheet F5-13, Rev. 1
F5-13B1
,
OSite Fabricated
VII-26
l
.
- .
_ - -
-.
-
. -
- _ _ _ _ _ - - . -
-
TABLE VII-6
PIPE SUPPORT IPOI SAMPLE
DI Report
Elev.
S&L Drawing
No.
Bldg.
(Ft.)
C1
(Support No.)
Traveler No.
M-2590
Contain.
737
A
M-1RH34010X, Rev. A
H-RH-20I, Rev. 3*
M-3155
Control
737
C
M-1SX52022X, Rev. A
H-SX-22K, Rev. 1FR*
M-3328
Contain.
755
B
M-1RH71016G, Rev. C
H-RH-767-U, Rev. 1*
M-3329
Aux.
737
B
BA Dwg. H-1-RH-780-4, Rev. 0
H-RH-780-D, Rev. IFR
M-3330
Contain.
755/762
B
M-1RH710185, Rev. E
H-RH-767-CC, Rev. 4
M-3338
Contain.
755
C
M-1RB22056G, Rev. B
H-RH-947H, Rev. 1
M-3349
Contain.
828
8
M-1RH22035X, Rev. F
H-RH-29F, Rev. 2
M-3351
Fuel
712
C
M-1SX42019R, Rev. C
H-SX-138, Rev. 15
M-3354
Aux.
708
B
M-1RH47013G, Rev. A
H-RH-764-L, Rev. 1*
M-3421
Fuel
712
C
M1SX42021R, Rev. F
H-SX-13P, Rev. 7*
RTraveler Not Reviewed
!
,
!
t..
L
VII-27
1
L
TABLE VII-7
ELECTRICAL CABLE TRAY HANGER IPOI SAMPLE
01 Report
Elev.
BA Drawing
No.
Bldg.
(Ft.)
(Hanger No.)
Traveler No.
E-3762
Contain.
755
1002-018-H24, Rev. 04
E27-1002-018-H24, Rev. 5
E-3920
Aux.
781
1003-01A-H47, Rev. 04
E26-1003-01A-H47, Rev. 8
E-3921
Aux.
781
1003-01A-H48, Rev. 02
E26-1003-01A-H48, Rev. 12
E-4010
Contain.
768
1002-01B-H33, Rev. 04
E27-1002-01B-H33, Rev. 5
E-4541
Control
800
1004-04A-H10,
E30-1004-04A-H10, Rev. 23
Sheet 1, Rev. 03 &
Sheet 2, Rev. 01
01 Report
Elev.
No.
Bldg.
(Ft.)
S&L Drawing
Traveler No.
E-3623
Control
800
1004-00A-CPR, Rev. E
RT425, Rev. 6
1942, Rev. Y
(Items 10510K, M, N)
- SCI - Seismic Category I
VII-28
.
VIII. CORRECTIVE ACTION SYSTEMS
A.
Objective
The corrective action systems and related activities were examined to
determine whether measures were established and implemented to assure
that nonconformances and other conditions adverse to quality were promptly
identified and corrected.
B.
Discussion
An examination was made of the licensca's program for identification and
control of corrective actions, including review of sample documents and
inspection of some material and equipment for verification of actual
corrective actions in the plant.
The following procedures by Baldwin Associates (BA) and Illinois Power
Company (IP) protided the acceptance criteria for this inspection:
- BA Project Procedure (BAP) 1.0,
"Nonconformance Report (NCR),"
Rev. 17, dated May 24, 1985
IP Nuclear Station Engineering Instructions (NSEI) ME-2,
" Interaction Analysis Program," Rev. O, dated March 4, 1985
IP Quality Assurance Procedure QAP-115.02, " Nonconforming
Material Report (NCMR)," Rev. 4, dated February 8, 1985
- QAP-116.04, " Reporting of Deficiencies per 10 CFR 50.55(e),"
Rev. 4, dated February 14, 1985
QAP-116.05, " Evaluation and Reporting of Defects and Noncon-
formances per 10 CFR 21," Rev. 2, dated June 20, 1983
- QAP-116.06, " Project Trend Analysis Program," Rev. 7, dated
May 15, 1985
QAP-116.07, " Management Corrective Action Requests (MCAR),"
Rev. 7, dated February 14, 1985
QAP-116.08, " CPS Condition Report (CR)," Rev. 5, dated July 27,
1984
IP Startup Administrative Instruction SAI-7, " Control of Condi-
tions Adverse to Quality," Rev. 5, dated February 25, 1985
- IP Startup Administrative Procedure SAP-1, " System Subsystem
Turnover," Rev. 12, dated July 18, 1984
- SAP-2, " Construction Work Requests," Rev. 13, dated December 20,
1984
SAP-6, " System Release and Return," Rev. 5, dated December 7,
1984
VIII-1
_ - _ _
SAP-9, " Maintenance Work Requests-Startup Group," Rev. 5 dated
August 24, 1984
SAP-20, " Preventative Maintenance," Rev. O, dated March 30, 1984.
1.
Corrective Action Measures Inspection
a.
Inspection Scope
A review was performed of applicable portions of the Quality
Assurance (QA) program and procedures.
A total of 231 samples
of corrective action documents including Nonconformance Reports
(NCRs), Nonconforming Material Reports (NCMRs) and Condition Reports
(CRs) were reviewed.
Five material and equipment samples were
inspected for verification of corrective actions in the plant. Three
samples of risk releases were selected for field verification of
control and status of work on material and equipment to correct
the deficient condition involved.
Also, 26 samples of corrective
action documents which identified documentation revisions to show
as-built conditions for their disposition, were reviewed to verify
that the required documentation revision had been completed.
Samples were selected to cover various disciplines and activities.
The activities included the normal program activities of BA, Zack
Company, IP and the additional activities of BA Field Verification
and IP Overinspection.
Open items requiring corrective action after turnover from BA to IP
were also reviewed.
Corrective actions dispositioned use-as-is were evaluated to
determine if sound engineering was used for the disposition.
b.
Inspection Findings
In general, it was found that satisfactory procedures were in place
for corrective action systems to identify and correct conditions
adverse to quality at the site.
Except for a high rate of errors
found in a limited sample of open items identified in the IP Startup
Punch List, the corrective action measures were found to be accept-
able.
The following details the NRC CAT inspector's findings:
(1) With approximately 80 percent of the systems turned over to IP,
more than 6000 open items are identified on the IP Startup
Punch List Tracking System.
The document packages for four
open items were selected for a detailed review by the NRC CAT.
The criteria used for the sample selection was that the item
was identified as an open item and corrective action was required.
Discrepancies were found in the posting of documents against
two of the open items which prevented the open items from being
closed although the work had been accomplished.
Because of the
high percentage of problems identified in this small sample, two
additional sample packages were selected for review.
Problems
were identified in both of these additional packages.
The high
VIII-2
-_ --_
.-
- -
..
percentage of open item packages with problems identified by
the NRC CAT inspector indicates that additional management atten-
tion to this matter is required.
The packages examined are as follows:
>
ISA0069 Install Permanent Cable Between E21-N049 and JB
BA #61 -- Satisfactory
ISA0009 Change Wiring of NSIV-LC Valves -- Satisfactory
DGA0349 Division II Overhaul, Rust on Cylinder Liner, NCR
,
17583 -- Unsatisfactory, See Table VIII-1
LPA0109 Water Leg Pump Seal Piping Discrepancies
ILP-1P2 -- Unsatisfactory, See Table VIII-2
DGA0153 Lube Oil Strainer Element Opening --
Unsatisfactory, See Table VIII-3
ISA0074 1E32-F008 Torque Switch Not Working in the Closed
Position -- Unsatisfactory, See Table VIII-4
(2) Manual and computerized records were used to track the status
and to trend nonconformances.
(3) Work had been completed and inspected for five samples
selected which required rework to correct a nonconformance.
(4) Three samples of the nonconformance documents reviewed
permited work to continue on a conditional release before a
final disposition could be made.
The corrective action docu-
ments were still open and were controlled through the project's
nonconformance program.
(5) The appropriate revisicns to design documents for a sample of
26 corrective action reports which identified document revi-
sions to show as-built conditions for their disposition, were
found to be posted or incorporated into the design documents.
The only exception was three documents identified on an NCR
which had not been completed at the time of the NRC CAT
inspection.
(6) Sections II.B.3.b(2), V.B.1.b and V.B.3.b of this report iden-
tify NCRs dispositioned use-as-is without providing sufficient
documentation to substantiate compliance with requirements.
Section III.B.4.b of this report identifies the use of an FECN
when an NCR was required by project procedures.
(7)Section VII.B.1.b(7) of this report identifies ineffective
corrective actions for IP QA audit program findings for the
area of design document control.
The NRC CAT inspectors found
similar deficiencies in the same area previously identified by
IP QA audits.
VIII-3
.
-_
_
- - -
-.
. _ _ _
.-
- . _ . . - . .
t
(8) Documentation reviewed for NCRs written due to BA Field Veri-
fication and IP Overinspection findings, was found to be satis-
factory.
c.
Conclusion
The corrective action system was found to be generally acceptable
except for the following:
"
Lack of control of entries into the IP Startup Punch List after
turnover of systems for startup testing.
The number of problems
found with the limited NRC CAT sample of open items reviewed
indicates that this matter requires additional management
attention.
Failure to apply effective corrective actions in the area of
document control for IP QA audit findings.
Disposition of nonconformances use-as-is without providing
a basis to substantiate this disposition.
VIII-4
TABLE VIII-1
REVIEW 0F OPEN PUNCH LIST ITEM DGA0349
DIVISION II OVERHAUL, RUST ON CYLINDER LINER, NCR 17583
Documents
Issued /Date
Comments
NCR 17583
Identified light rust bloom on number 6 cylinder liner
(5/2/84)
of 16 cylinder diesel, 1DG01KB.
This NCR was superseded
by NCMR 1-0809 (4/15/85) which is not identified on the
punchlist.
IP NSED investigated rust problem on all DGs
(memo Y-72291) under NCR 17583, recommendation was to
" rework" and the position taken, "the rust will be
removed, after turnover, during disassembly of the
engine to replace power assembly lower seal by
mechanical maintenance."
MWR B02134
Work request to inspect engine turbocharger via the
(4/1/85)*
inspection ports, for 16 cylinder engine.
General
maintenance and inspection, visual inspection performed.
MWR B02133
Work request to remove power assembly and perform work
(4/1/85)*
as per instruction provided, for 16 cylinder engine.
General maintenance and inspection activities.
MWR 802135
Work request to replace viscous damper as per
(4/1/85)*
instructions provided, for 16 cylinder engine.
Maintenance work.
MWR B02138
Same as MWR 802133, except for 12 cylinder engine.
(4/1/85)*
MWR B02139
Same as MWR B02134, except for 12 cylinder engine.
(4/1/85)*
MWR 802140
Same as MWR B02135, except for 12 cylinder engine.
(4/1/85)*
NCMR Q-01-08290
Written as the result of Condition Report, CR 1-85-04-054
(4/19/85)
which identified what the inspector believed to be a
flaw in the weld area of the upper water jacket for
cylinders 8 and 9 of the 12 cylinder engine.
Engineering
investigation and evaluation found this condition to be
normal.
NCMR Q-02-018900
Written to identify scoring of connecting rod bearing
(4/26/85)
surface, cylinders 1-9 of 16 cylinder engine, found
while performing MWR 802135.
MWR B17342
Work request for pressure test of 12 cylinder engine
(5/2/85)
cooling water system per instructions provided.
- Written 10/29/84, and, while not applicable to this subject item, were entered
4/1/85.
VIII-5
-- -_
_
_ -
-
-
. _ _ _ _ _ _
. _ - _ -
.
._-
_
. -_
_
TABLE VIII-l (Continued)
REVIEW OF OPEN PUNCH LIST ITEM DGA0349
DIVISION II OVERHAUL, RUST ON CYLINDER LINER, NCR 17583
Documents
Issued /Date
Comments
MWR B17351
Same as MWR B17342, except for 16 cylinder engine.
(5/22/85)
MWR B17364
Work request to replace 12 cylinder, engine AMOT valve
(5/28/85)
element housing bolts per disposition of NCMR 2-0216.
Problem:
Of the twelve corrective action documents identified for
punch list item DGA0349, only NCR 17583 appears to be
related to the item description.
NCMR 1-0809 which
should have been identified, is missing.
The initially
identified open item has not been closed out.
VIII-6
i
TABLE VIII-2
REVIEW 0F OPEN PUNCH LIST ITEM LPA0109
WATER LEG PUMP SEAL PIPING DISCREPANCIES ILP-1P2
Documents
Issued /Date
Comments
NCMR Q-00-02400
Unrelated NCMR entered in error and not removed from
(12/16/83)
punch list.
Related NCMR is Q-01-02400.
FPR 3288
Identified that pump IE21-C002 was different from the
(8/27/84)
other pumps in that seal injection piping was missing.
CR 1-84-09-00400
Identified seal bypass piping on LPCS pump 1E21-C0002
(9/6/84)
was missing.
NCR 021710
Identified the nonconformance.
(9/6/84)
NCMR Q-01-02400
Replaced NCR 021710 for corrective action control
(10/2/84)
after turnover.
CWR 11334
Work request to install seal by pass piping.
(11/3/84)
021710, not NCMR Q-01-02400, identified the nonconfor-
mance.
This work request was closed out 1/14/85.
Problem:
Work has been completed, NCR 021710 has been closed
out.
NCMR Q-01-02400 has not been closed out and is
preventing this open item from being closed out.
l
l
!
I
VIII-7
_ . _ -
_ __
_
.
. . .
-__
_-_
_
_
TABLE VIII-3
REVIEW OF OPEN PUNCH LIST ITEM DGA0153
LUBE OIL STAINER ELEMENT OPENING
Documents
Issued /Date
Comments
MWR B00183
Identified provisions for the diesel generator lube
(9/18/84)
oil flush.
CR 1-84-10-540
Identified lube oil strainer had manufacturer's defect.
(10/19/84)
NCMR Q-01-052100
Identified the nonconformance with disposition to scrap
(1/9/85)
defective strainer and replace with a new strainer.
FDDR LH1-5151
Provided GE's disposition for NCMR Q-01-052100.
(1/15/85)
MWR B03584
Prepared to replace strainer.
Note:
This work had been
(3/5/85)-
performed under MWR B00183 which was never closed out.
MWR 803584 was closed out because the work had been
previously completed.
-Problem:
MWR B00183 is still identified as an open item of the
punch list, preventing this item from being closed out.
VIII-8
_
l
TABLE VIII-4
REVIEW 0F OPEN PUNCH LIST ITEM ISA0074
1E32-F008 TORQUE SWITCH NOT WORKING IN THE CLOSED POSITION
Documents
Issued /Date
Comments
MWR 807829
Repair of identified problem with new Torque switch.
Switch was replaced 4/17/85 and documentation closed
out 4/19/85.
Nonconformance, spectacle flange, 1E32-D307, paper work
(3/2/85)
indicated that an ASME Class NF flange was being used
where a Class NC flange is required.
CWR C013430
Was prepared to replace the flange with an ASME NC
l
(3/28/85)
flange as required.
Problem:
Tne NCR and CWR were initially entered into the punch
l
list tracking system under ISA0074.
The operator deleted
l
the problem descripticn but did not delete the NCR and
CWR.
ISA0074 was then reused for MWR B07829 with the NCR
and CWR identified as documentation related to the open
item.
All the work for the MWR has been completed.
The
licensee had made the necessary corrections and removed
this item from the open punch list prior to the NRC CAT
inspection exit meeting.
l
I
!
VIII-9
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
ATTACHMENT A
A.
Persons Contacted
The following list identifies licensee representatives and NRC personnel
present at the exit meeting, and licensee discipline coordinators and key
individuals contacted during the inspection for each area.
1.
Exit Meeting
a.
Licensee and Contractors
G. Bell
D. Hall
M. Pacy
W. Connell
R. Heider
D. Selva
H. Daniels
S. Johnson
D. Shelton
G. Gandsey
W. Kelley
H. Victor
W. Gerstner
A. King
J. Wilson
l
J. Green
L. Osborne
S. Zabel
b.
State of Illinois
R. Hubbard
A. Samelson
S. Swartz
c.
NRC and Consultants
T. Chan
J. McCormack
R. Serb
A. DuBouchet
T. McLellan
B. Siegel
G. Georgiev
0. Mallon
R. Smeenge
T. Gwynn
W. Marini
W. Sperko
J. Harrison
E. Martindale
S. Stein
R. Heishman
J. Nemoto
J. Taylor
D. Johnson *
M. Peranich
R. Warnick
H. Livermore
!
2.
Licensee Coordinators and Contacts
Area
Name
Team Leader
G. Bell
D. Shelton
l
D. Hall
l
Electrical and
E. Bailey
R. Kennedy
Instrumentation
D. Gilbert
L. Ratliff
B. Johnson
Mechanical
D. Adams
K. Danner
B. Buffie
R. Kennedy
1
L. Clark
A. Sherwood
L. Combs
B. Taylor
- Institute of Nuclear Power Operations observer
AA-1
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
______
Welding and NDE
J. Carson
T. Wilmoth
Civil and Structural
T. Parrent
K. Smith
Material Traceability
J. Gruber
Design Change Control
G. Buffington
J. Greene
R. Collins
S. Lyons
W. Connell
Corrective Action Systems
T. Warnick
l
In addition to the above personnel, numerous other inspectors, engineers
I
and supervisors were also contacted.
B.
Documents Reviewed
The types of documents listed below were reviewed by the NRC CAT members
to the extent necessary to satisfy the inspection objectives stated in
Section I of tnis report.
References to specific procedures, specifica-
tions, and drawings are contained within the body of the report.
1.
Final Safety Analysis Report
2.
Quality assurance manual
3.
Quality assurance procedures and instructions
4.
Quality control procedures
5.
Administrative procedures
6.
General electrical installation procedures and specifications
7.
General instrumentation installation procedures
8.
General piping and pipe support installation procedures and
specifications
9.
General mechanical equipment installation procedures and
specifications
10.
General concrete specifications
11.
As-built drawings
12. Welding and NDE procedures
13.
Personnel qualification records
14.
Material traceability procedures
15.
Procedures for processing design changes
AA-2
16.
Procedures for document control
17.
Procedures for controlling as-built drawings
18.
Procedures for processing nonconformances
.
AA-3
\\.
ATTACHMENT B
GLOSSARY OF ABBREVIATIONS
AISC - American Institute of Steel Construction
AISI - American Iron and Steel Institute
ANSI - American National Standards Institute
ASME - American Society of Mechanical engineers
ASTM - American Society for Testing and Materials
AWG
- American Wire Gauge
AWS
- American Welding Society
BA
- Baldwin Associates
BAFV - Baldwin Associates Field Verification
BAP
- Baldwin Associates Project Procedure
BE
- Basic Engineering
80M
- Bill of Materials
BQAI - Baldwin Associates Quality Assurance Instruction
- C
- Degree Celsius
CAT
- Construction Appraisal Team (NRC)
CB&I - Chicago Bridge and Iron Company
- Concrete Expansion Anchor
CHI
- Construction Management Information
- Clinton Power Station
CR
- Condition Report
C/S
- Civil / Structural
- Control Rod Drive
CWR
- Construction Work Request
dc
- Direct Current
DCC
- Document Control Center
DMS
- Document Management Systen
- Engineering Change Notice
F
- Degree Fahrenheit
FCR
- Field Change Request
FDC
- Field Document Center
FECN - Field Engineering Change Notice
FSAR - Final Safety Analysis Report
- General Electric Company
- Hydraulic Control Unit
HPCS - High Pressure Core Spray
HVAC - Heating, Ventilating and Air Conditioning
- Office of Inspection and Enforcement (NRC)
IEEE - Institute of Electrical and Electronic Engineers
IP
- Illinois Power Ccmaany
IPCEA - Insulated Power Ca)le Engineers Association
IP0I - Illinois Power Company Overinspection
k
- One Thousand
LPCS - Low Pressure Core Spray
- One Thousand Circular Mils
MWR
- Maintenance Work Request
NCMR - Nonconforming Material Report
- Nonconformance Report
NP&S - Nuclear Planning and Support
NRC
- United States Nuclear Regulatory Commission
NSED - Nuclear Station Engineering Department
AB-1
NSEI - Nuclear Station Engineering Instructions
PGCC - Power Generation Control Complex
- Project Instruction
PIR - Potential Interaction Report
PSA - Pacific Scientific Arrestor
PSAR - Preliminary Safety Evaluation Report
- Quality Assurance
QAI - Quality Assurance Instructions
QAP - Quality Assurance Procedure
- Quality Control
RCI - Reactor Controls, Inc.
RCIC - Reactor Core Isolation Cooling
RE
- Resident Engineer
- Regulatory Guide (NRC)
RIR - Receiving Inspection Report
SAE - Society of Automotive Engineers
S&L - Sargent & Lundy Engineers
SSW - Shutdown Service Water
SU-F - Startup Field Office
TPRG - Traveler Preparation Review Group
TS
- Technical Services
-
TTS - Traveler Tracking System
USI - Unresolved Safety Issue (NRC)
V
- Volt (s)
AB-2
_ _ . _ .
- . _
_
_ _
_
_
_
. _ _ _ _ , _ _ .
__.
r-
_ic
,
!
NRC Form 8-C
(4-79)
NRCM O240
COVER SHEET FOR CORRESPONDENCE
Use this Cover Sheet to Protect Originals of Multi-Page Correspondence.
i
!
i
l
\\