Forwards Insp Rept 50-445/85-11,Const Insp Repts 50-445/85-11 & 50-446/85-06,Comanche Peak Response Team Activities Insp Repts 50-445/85-11 & 50-446/85-06 on 850622-0831 & Notices of Violation & Deviation
ML20133M717
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 10/11/1985
From: Denise R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
Shared Package
ML20133M720 List:
References
NUDOCS 8510280217
Download: ML20133M717 (3)


See also: IR 05000445/1985011

Text

.

In Reply Refer To:

OCT U M

Dockets:

50-445/85-11

50-446/85-06

Texas Utilities Generating Company

ATTN:

Mr. W. G. Counsil

Executive Vice President

400 North Olive Street, Lock Box 81

Dallas, Texas 75201

Gentlemen:

This refers to the inspection conducted by Mr. T. F. Westerman and other

members of the Region IV Comanche Peak Group during the period

June 22-August 31, 1985, of activities authorized by NRC Construction

Permits CPPR-126 and CPPR-127 for the Comanche Peak Steam Electric Station

(CPSES), Units 1 and 2, and to the discussion of our findings with

Messrs. R. E. Camp and J. C. Kuykendall, and other members of your staff at the

conclusion of the inspection.

Areas examined during the inspection included operations, construction, and

Comanche Peak Response Team activities. Within these areas, the inspection

consisted of selective examination of procedures and representative records,

interviews with personnel, and observations by the inspectors.

These findings

are documented in the enclosed inspection report.

During this inspection, it was found that one of your activities was in

violation of NRC requirements.

Consequently, you are required to respond to

this violation, in writing, in accordance with the provisions of Section 2.201

of the NRC's " Rules of Practice," Part 2, Title 10, Code of Federal

Regulations. Your response should be based on the specifics contained in the

Notice of Violation enclosed with this letter.

During this inspection, it was found that certain of your activities appeared

to deviate from commitments made to the NRC.

These items and references to the

commitments are identified in the enclosed Notice of Deviation.

You are

requested to respond to these deviations in writing.

Your response should be

based on the specifics contained in the Notice of Deviation enclosed with this

letter. As part of your response to Item A in the Notice of Deviation, please

identify all members of the Comanche Peak Response Team (CPRT) and Senior Review

Team with previous CPSES involvement, along with the documented evaluation which

sets forth the basis for acceptance of their objectivity as defined in

Section VII of the CPRT Program Plan.

Two unresolved items are identified in paragraphs 3 and 5.h of Appendix E of

the enclosed inspection report.

TA

l

RIV:CPSES

C:CPSESf

D:DRSP

D:CPP

b

i

IBarnes/1w

TFWesterman

RPDenise

VSNoonan

X li /85

n / if /85

p / /85

j? / N/85

8510200217 851011

DR

ADDCK 050

5

I

,

Texas Utilities Electric Company

-2-

We have also examined actions you have taken with regard to previously

identified operations inspection findings.

The status of these items is

identified in paragraph 2 of Appendix C of the enclosed inspection report.

The responses directed by this letter and the accompanying Notices are not

subject to the clearance procedures of the Office of Management and Budget as

required by the Paperwork Reduction Act of 1980, PL 96-511.

Should you have any questions concerning this inspection, we will be pleased to

discuss them with you.

Sincerely,

Origina! Signed Dy:

Rkhard P. 0cn63

R. P. Denise, Director

Division of Reactor Safety

and Projects

Enclosures:

1.

Appendix A - Notice of Violation

2.

Appendix B - Notice of Deviation

3.

Appendix C - NRC Operations Inspection Report

50-445/85-11

4.

Appendix D - NRC Construction Inspection Report

50-445/85-11

50-446/85-06

5.

Appendix E - NRC Comanche Peak Response Team Activities Inspection Report

50-445/85-11

50-446/85-06

cc w/ enclosures:

Texas Utilities Electric Company

ATTN:

J. W. Beck, Manager,

Licensing

Skyway Tower

400 North Olive Street

Lock Box 81

Dallas, Texas

75201

Texas Radiation Control Program Director

. - - -

- - - - -

-,

..

.=

-

- _ _

. . - - . -.

.

-. .-

.-

_

_

.

.

.

.

,

,

bcc to DMB (IE01)

,

bec distrib. by RIV:

  • RP8
  • MIS System

4

  • RRI-OPS
  • RSTS Operator
  • RRI-CONST
  • R&SPB
  • T.

F. Westerman, CPTG

R. Denise, D/DRSP

V. Noonan, NRR

R. Martin, RA

S. Treby, ELD

Juanita Ellis, Pres.- CASE

J. Taylor, IE

Renea Hicks, A/ Atty General, EP Div.-TX

R. Heishman, IE

  • RIV File
  • D. Weiss, LFM8 (AR-2015)
  • w/766

i

i

i

l

. _ . -

, . . .

_

_

.

-

. .

_

._

.

-