ML20133H257

From kanterella
Jump to navigation Jump to search
Monthly Operating Rept for May 1985
ML20133H257
Person / Time
Site: Callaway Ameren icon.png
Issue date: 05/31/1985
From: Goodenow R, Miltenberger S
UNION ELECTRIC CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
References
ULNRC-1110, NUDOCS 8508090262
Download: ML20133H257 (6)


Text

MONTHLY OPERATING REPORT DOCKET NO.

50-483 UNIT NAME CALLAWAY UNIT 1 DATE JirNe 10. 19Rs COMPLsTsp BY n n connevow TELEPHONE (114T 676-R460 PART A OPERATIONS

SUMMARY

MAY 1985 Callaway operated at 100% power for the month of May except as noted on Part E and a load reduction on May 25.

On May 25 the load was reduced to 60% due to problems with ' A' Main Feed Pump and a loss of primary speed signal.

1 0

PART B PORV AND SAFETY VALVE

SUMMARY

~

MnNF I

1

(

l l

i CA-#804 05/09/84 QDP-ZZ-04204 d 8508090262 850531 g/ g 7 \\

PDR ADOCK 05000483 Page 1 of 4 R

PDR 1t

Part D OPERATING DATA REPORT 50-483 DOCKET NO.

UNIT Callaway DATE JUNF 10.1985 R. R. GOODENOW COMPLETED 8Y (314) 676-8460 TELEPHONE OPER ATING STATUS MAY 1985 gross MOURS #N REPORTING PERIOD:

744

1. REPORTING PERIOD:

341l MAX. DEPEND. CAPACITY (MWo.Nett:

1120 j

2. CURRENTLY AL,THORIZED POWER LEVEL (MWil:

DESIGN ELECTRICAL RATING IMWo Net):

1171*

  • At stretch reactor power level which is not currently authorized under the o erating license a
3. POWER LEVEL TO WHICM RESTRICTED tlP ANY)(MWo.Neti:
4. REASONS FOR RESTRICTION (IP ANYl:

THIS MONTM YR TO DATE CUMULATivt 728.8 3241.1 3543.6

5. NUMSER OF HOURS REACTOR WAS CRITICAL 0

0 0

6. RE ACTOR RESERVE SMUTDOWN MOURS 721.0 3168.7 3471.2 7

7 MOURS GENER ATOR ON LINE 0

0 0

8. UNaf RESERVE SMUTDOWN *OURS 7

2.351.261 9.744.671 10.746.196

9. GROSS THERMAL ENERGY GENER ATED (MWHI 800.389 3.301.714 1.640.894 to GROSS ELECTRICAL ENERGY GENER ATED (MWM).

761.511 1.110 qqs 1 Asq 358

11. NET ELECTRICAL ENERGY GENERATED IMWM) 98.0%

89.5%

90.3%

12. RE ACTOR SERvlCE F ACTOR j

98.0%

89.5%

90.3%

l

13. REACTOR AV All.ASILITY F ACTOR 96.9%

87.5%

88.4%

l 14 UNIT SERVICE FACTOR 96.9%

87.5%

88.4%

15. UNIT AVAILAslLITY P ACTOR 91.4%

77.1%

78.57 ts. UNIT CAPACITY F ACTOR (Umas MDCI 87.4%*

73.8%*

75.1?*

17 UNif CAPACITY F ACTOR (Umag Demon MWel.

3.1%

4.7%

4.47

18. UNIT FORCED OUTAGE RATE
19. SHUTDOWNS SCHEDULED OVER NEXT S MONTHS (TYPE OATE. ANO OURAflON OF EACMI:

None

20. IF SMUT DOWN AT END OF REPORT PER100. ESTIMATED OATE OF STARTUF:

NA CA d804 05/09/84 Page 3 of 4 QDP-ZZ-04204

o r

Part E DOCKET NO.

50-483 UNil SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Callaway QATE JUNE 10. 1985 R. R. GOODENOW COMPLETED BY REPORT MONTil MAY 1985 TELEPHONE (314) 676-8460 METHOD OF TYPE SHUTTING DOWN F: FORCED DURAflON THE REACTOR OR NO.

DATE S: SCHEDULED (HOURS)

REASON REDUCING POWER CCRRECTIVE ACTIONSN5NTS

~

8 850503 Scheduled 0

B 1

Load reduced to 60% due to maintenance on

'B' Main Feed Pump.

9 850506 Forced 23.0 A

3 Reactor Trip from 100% Power due to loss of ' fain Feedwater Pump

'B.'

LER's 85-024-00 and 85-025-00.

SUMMARY

CA-#804

' 05/09/84 Page 4 of 4 QDP-ZZ-04204

I Part C AVERAGE DAILY UNIT POWER LEVEL 50-483 DOCKET NO.

UNIT Callaway DATE JUNE 10.1985 COMPLETED BY R. R.

GOODENOW TELEPHONE (314) 676-8460 I

l MONTH MAY 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL a

(MWe-Net)

(MWe-Net) l 1

1105 37 1113 1115 1110 jg 2

1108 1111 3

3, 1108 776 20 4

881 1108 5

21 878 1112 6

3 0

1112 7

562 1108 3

24 1024 1071 9

1109 1077 10 26 1102 1107 33 1112 1107 g

12 1110 1106 33 3

1075 1109 3

14 1111 1086 15 31 1112 f

16 l

l 0[

64 Page 2 of 4 QDP-ZZ-04204

9 l

UNION EtscTaic COMPANY CALLAWAY PLANT MAILING ADDRESS:

P. O. sox S20 FULTON. MO. 6 52 SI June 12, 1985 i

Director, Resource Management Nuclear Regulatory Commission Washington, DC 20555 ULNRC-1110

Dear Sir:

DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 FACILITY OPERATING LICENSE NPF-30 MONTHLY OPERATING REPORT MAY 1985 The enclosed Monthly Operating Report for May 1985 is submitted pursuant to section 6.9.1.8 of the Callaway Unit 1 Technical Specifications.

l fOC e

S. E. Miltenberger Manager, Callaway Plant A/C-d%P ET/WRC/RRG/drs Enclosure cc: Distribution attached rE14

'l.

cc distribution for ULNRC-1110 with enclosures Mr. James G. Keppler Regional Administrator Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137 Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 NRC Resident Inspector I

i l

i s

_,._