Forwards Updated Const Status Repts as of 820930
ML20127D493
Person / Time
Site: 05000000, Palo Verde
Issue date: 10/13/1982
From: Fasnacht D
ARIZONA PUBLIC SERVICE CO. (FORMERLY ARIZONA NUCLEAR
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 ANPP-SCM-9149, NUDOCS 8504150330
Download: ML20127D493 (4)


Text

_ - _

ARIZONA NUCLEAR POWER PROJECT

~

Post Office Box 21666 Phoenix, Arizona 85036 ANPP-SCM-9149 October 13, 1982 Chief, Management Information Branch Office of Management and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C.

20555

Subject:

USNRC Construction Status Report Update File:

Subj ect Attached for your use and information is the Construction Status Report Update worksheets for Palo Verde Nuclear Generating Station -

Units 1, 2 and 3, updated through September 30, 1982.

Should you need any additional information, please do not hesitate to call.

D. B. Fasnacht Nuclear Construction Manager DBF/SJS/csw M

Attachments (3) cc:

E. E. Van Brunt, Jr.

G. C. Andognini hh 41l g 840606 KILLEFEB4-367 PDR i

4 C0MSTRUCTION 5TATUS REPORT PAGE HO:

PALO VERDE I' MUCLEAR POWER PLANTS STATUS AS OF 09-30-82 C0N5TRUCTION. S T A T U St APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

08-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-01-83 DEFINED IN CP: (EARLIEST) 06-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-81 (LATEST) 11-01-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATIDH DATE: 12-00-83 CURRENT ESTIMATED PERCENT COMSTRUCTIDH COMPLETE: 97%

COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTINATED ACTUAL ESTIMATED START ART COMPLETION COMPLETION % COMPLETF MOBILIZE APD PREPARE SITE:

0-

- 6 10-00-76 100% ~

rLACE STRUCTURAL CONCRETE:

08-00-76 01-00-81 100%

INSTALL REACTOR PRESSURE VESSEL:

11-00-78 17 J0-78 100%

INSTALL LARGE BORE PROCESS PIPE:

03-00-77 10-00-82 99%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

09-00-78 01-00-83 98%

INSTALL SMALL BORE PIPE:

06-00-78 01-00-83 99%

INSTALL CABLE TRAY:

10-00-77 11-00-81 100%

INSTALL EXPOSED METAL CONDUIT:

03-00-78 02-00-83 96%

INSTALL POWER -CONTROL, INSTRUMENTATIDH AND SECURITY CABLE:

02-00-79 02-00-83 93%

INSTALL ELECTRICAL TERMINATI0HS: '

08-00-79 03-00-83 84%

. CONDUCT REACTOR COLD HYDROSTATIC TEST:

07-00-82 07-00-82 100%

CONDUCT HOT FUNCTIONAL TEST:-

03-00-83 05-00-83 0%

CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

10-00-81 08-00-83 5%

f.'

C0N5TRUCTION STATUS REPORT PAGE NO2 PALO VFRDE 2 NUCLEAR POWER PLANTS

. STATUS AS'0F 09-30-82

'C0N5TRUCTION

$TATU5:

APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:

08-01-84 APPLICANTS CONSTRUCTIDH COMPLETION ESTIMATE AS

. APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

08-01-84 DEFINED IN CP: (EARLIEST) 02-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:

11-00-83 (LATEST) 11-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:

92%

C0tTTENTS REGARDING CURRENT CONSTRUCTIDH STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COr1P ET[

MOBILIZE AND PREPARE SITE:

06-00-/6 06-00-77 1

PLACE STRUCTURAL CONCRETE:

08-00-77 12-00-81 100%

.IMSTALL REACTOR PRESSURE VESSEL:

06-00-80 07-00-80 100%

' INSTALL LARGE BORE PROCESS PIPE:

09-00-78 03-00-83 98%

INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:

10-00-78 07-00-83 86%

INSTALL 5 MALL BORE PIPE:

04-00-79 07-00-83 90%

INSTALL CABLE TRAY:

06-00-78

'03-00-82 100%

INSTALL EXPOSED METAL CONDUIT:

01-00-78 07-00-83 90%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

02-00-81 09-00-83 70%

INSTALL ELECTRICAL TERMINATIONS:

05-00-81 10-00-83 62%

CONOUCT REACTOR COLD HYDROSTATIC TEST:

07-00-83 07-00-83 0%

CONDUCT HOT FUNCTIONAL TEST:

02-00-84 03-00-84 0%

COMnUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD: 06-00-83 08-00-84 0%

I i.

e

I

  • C0NSTRUCTION 5TATUS REP 0RT PAGE NO:

PAID VEiOE 3 '~

HUCLEAR POWER PLANTS STATUS AS OF: 09-30-82 C0N$TPUCTIoN

$TATU5:

APPLILANT'S CURRENT ESTIMATED FUEL LOADING DATE:

11-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:

11-00-85 DEFINED IN CP: (EARLIEST) 11-01-84 APPLICANT'S ESTIMATED FUEL LDADING DATE AT CP ISSUANCE:

11-00-85 (LATEST) 11-01-86 APPLICANT'S CURRENT ESTIMATED C0f1 MERCI AL OPERATION DATE: 05-00-86 CURRENT SSTIMATED PERCENT CONSTRUCTIDH COMPLETE:

47%

COfffENTS REGARDING CURRENT CONSTRUCTION STATUS:

ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % C0ffPLEfr MOBILIZE AND PREPARE SITE:

06-00-76 04-00-79 100%

PLACE STRUCTURAL CONCRETE:

03-00-79 01-00-84 87%

INSTALL REACTOR PRESSURE VESSEL:

04-00-82 05-00-82 100%

INSTALL LARGE BORE PROCESS PIPE:

04-00-79 09-00-84 68%

INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SHUBBERS:

10-00-80 01-00-85 21%

INSTALL SMALL BORE PIPE:

'06-00-80 01-00-85 15 %

INSTALL CABLE TRAY:

04-00-80 03-00-84 54%

INSTALL EXPOSED METAL CONDUIT:

01-00-80 11-00-84 33%

INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:

12-00-82 02-00-85 0%

INSTALL ELECTRICAL TERMINATIONS:

02-00-83 05-00-85 0%

CONDUCT REACTOR COLD HYDROSTATIC TESTr 02-00-85 02-00-85 0%

CONDUCT NOT FUNCTIONAL TEST:

06-00-85 08-00-85 0%

CUHDucT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:

09-00-84 11-00-S5 0%