ARIZONA NUCLEAR POWER PROJECT
~
Post Office Box 21666 Phoenix, Arizona 85036 ANPP-SCM-9149 October 13, 1982 Chief, Management Information Branch Office of Management and Program Analysis U. S. Nuclear Regulatory Commission Washington, D. C.
20555
Subject:
USNRC Construction Status Report Update File:
Subj ect Attached for your use and information is the Construction Status Report Update worksheets for Palo Verde Nuclear Generating Station -
Units 1, 2 and 3, updated through September 30, 1982.
Should you need any additional information, please do not hesitate to call.
D. B. Fasnacht Nuclear Construction Manager DBF/SJS/csw M
Attachments (3) cc:
E. E. Van Brunt, Jr.
G. C. Andognini hh 41l g 840606 KILLEFEB4-367 PDR i
4 C0MSTRUCTION 5TATUS REPORT PAGE HO:
PALO VERDE I' MUCLEAR POWER PLANTS STATUS AS OF 09-30-82 C0N5TRUCTION. S T A T U St APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
08-01-83 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
08-01-83 DEFINED IN CP: (EARLIEST) 06-01-81 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
11-00-81 (LATEST) 11-01-82 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATIDH DATE: 12-00-83 CURRENT ESTIMATED PERCENT COMSTRUCTIDH COMPLETE: 97%
COMMENTS REGARDING CURRENT CONSTRUCTION STATUS:
ESTIMATED ACTUAL ESTINATED ACTUAL ESTIMATED START ART COMPLETION COMPLETION % COMPLETF MOBILIZE APD PREPARE SITE:
0-
- 6 10-00-76 100% ~
rLACE STRUCTURAL CONCRETE:
08-00-76 01-00-81 100%
INSTALL REACTOR PRESSURE VESSEL:
11-00-78 17 J0-78 100%
INSTALL LARGE BORE PROCESS PIPE:
03-00-77 10-00-82 99%
INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:
09-00-78 01-00-83 98%
INSTALL SMALL BORE PIPE:
06-00-78 01-00-83 99%
INSTALL CABLE TRAY:
10-00-77 11-00-81 100%
INSTALL EXPOSED METAL CONDUIT:
03-00-78 02-00-83 96%
INSTALL POWER -CONTROL, INSTRUMENTATIDH AND SECURITY CABLE:
02-00-79 02-00-83 93%
INSTALL ELECTRICAL TERMINATI0HS: '
08-00-79 03-00-83 84%
. CONDUCT REACTOR COLD HYDROSTATIC TEST:
07-00-82 07-00-82 100%
CONDUCT HOT FUNCTIONAL TEST:-
03-00-83 05-00-83 0%
CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:
10-00-81 08-00-83 5%
f.'
C0N5TRUCTION STATUS REPORT PAGE NO2 PALO VFRDE 2 NUCLEAR POWER PLANTS
. STATUS AS'0F 09-30-82
'C0N5TRUCTION
$TATU5:
APPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
08-01-84 APPLICANTS CONSTRUCTIDH COMPLETION ESTIMATE AS
. APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
08-01-84 DEFINED IN CP: (EARLIEST) 02-01-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
11-00-83 (LATEST) 11-01-84 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE: 12-00-84 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:
92%
C0tTTENTS REGARDING CURRENT CONSTRUCTIDH STATUS:
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % COr1P ET[
MOBILIZE AND PREPARE SITE:
06-00-/6 06-00-77 1
PLACE STRUCTURAL CONCRETE:
08-00-77 12-00-81 100%
.IMSTALL REACTOR PRESSURE VESSEL:
06-00-80 07-00-80 100%
' INSTALL LARGE BORE PROCESS PIPE:
09-00-78 03-00-83 98%
INSTALL LARGE BORE PIPE HANGERS, RESTRAINTS AND SHUBBERS:
10-00-78 07-00-83 86%
INSTALL 5 MALL BORE PIPE:
04-00-79 07-00-83 90%
INSTALL CABLE TRAY:
06-00-78
'03-00-82 100%
INSTALL EXPOSED METAL CONDUIT:
01-00-78 07-00-83 90%
INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
02-00-81 09-00-83 70%
INSTALL ELECTRICAL TERMINATIONS:
05-00-81 10-00-83 62%
CONOUCT REACTOR COLD HYDROSTATIC TEST:
07-00-83 07-00-83 0%
CONDUCT HOT FUNCTIONAL TEST:
02-00-84 03-00-84 0%
COMnUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD: 06-00-83 08-00-84 0%
I i.
e
I
- C0NSTRUCTION 5TATUS REP 0RT PAGE NO:
PAID VEiOE 3 '~
HUCLEAR POWER PLANTS STATUS AS OF: 09-30-82 C0N$TPUCTIoN
$TATU5:
APPLILANT'S CURRENT ESTIMATED FUEL LOADING DATE:
11-00-85 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
11-00-85 DEFINED IN CP: (EARLIEST) 11-01-84 APPLICANT'S ESTIMATED FUEL LDADING DATE AT CP ISSUANCE:
11-00-85 (LATEST) 11-01-86 APPLICANT'S CURRENT ESTIMATED C0f1 MERCI AL OPERATION DATE: 05-00-86 CURRENT SSTIMATED PERCENT CONSTRUCTIDH COMPLETE:
47%
COfffENTS REGARDING CURRENT CONSTRUCTION STATUS:
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START START COMPLETION COMPLETION % C0ffPLEfr MOBILIZE AND PREPARE SITE:
06-00-76 04-00-79 100%
PLACE STRUCTURAL CONCRETE:
03-00-79 01-00-84 87%
INSTALL REACTOR PRESSURE VESSEL:
04-00-82 05-00-82 100%
INSTALL LARGE BORE PROCESS PIPE:
04-00-79 09-00-84 68%
INSTALL LARGE BORE PIPE MANGERS, RESTRAINTS AND SHUBBERS:
10-00-80 01-00-85 21%
INSTALL SMALL BORE PIPE:
'06-00-80 01-00-85 15 %
INSTALL CABLE TRAY:
04-00-80 03-00-84 54%
INSTALL EXPOSED METAL CONDUIT:
01-00-80 11-00-84 33%
INSTALL POWER, CONTROL, INSTRUMENTATION AND SECURITY CABLE:
12-00-82 02-00-85 0%
INSTALL ELECTRICAL TERMINATIONS:
02-00-83 05-00-85 0%
CONDUCT REACTOR COLD HYDROSTATIC TESTr 02-00-85 02-00-85 0%
CONDUCT NOT FUNCTIONAL TEST:
06-00-85 08-00-85 0%
CUHDucT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:
09-00-84 11-00-S5 0%