Special Rept for Inplant Review 92-10:on 920610 No Mention Made on Work List of Vent Path Through SG 1B for Incoming SG Crews.Caused by Deficient Communication.Turnover Sheet Established to Document Existing Vent Path Status
ML20101T944
Person / Time
Site: McGuire, Mcguire  Duke Energy icon.png
Issue date: 07/13/1992
From: Mcmeekin T
DUKE POWER CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
92-10, NUDOCS 9207220118
Download: ML20101T944 (10)


Text

__

_ _ _ _ _ _ _ -. - ~. _ ~

m ll l

(suke l%ter Company T C M,untas McGuire Nulgar Gewatwn ikpartment ilce hesident

!!iOJ llagsrs Irrry had(AfGillA)

(704bi5-600 lluntersville, br!$0iM9h5 (104B754509/n DUKE POWER July 13, 1992 U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555

Subject:

McGuire Nuclear Station Inplant Review Number 92-10 t'

Gentlemen:

Inplant Review 92-10 is being submitted to the NRC as a voluntary special report.

This event is considered to be of no significance with' respect to the health and safety of ths. public.

Very truly yours,.

fYl%If L

-T.C. McMeekin TLP/bcb Attachmont xc:

Mr.

S.D.

Ebneter INPO Records Center Administrator, Region 11 Suite 1500 U.S. Nuclear Regulatory Commission 1100 Circle 75 Parkway 101 Marietta St., NW, Suite-2900 Atlanta, GA 30339 Atlanta, GA 30323 Mr. Tim Reed Mr.-P.K. Van Doorn U.S. Nuclear Regulatory Commission NRC Resident Inspector Office of Nuclear Reactor Regulation McGuire Nuclear Station Washington, D.C.

-20555 r c g,;,

920722013g 920713 i

f gDR ADOCK 05000369~

[

3 PDR

+

,..n

-. - -. ~ - -.

f9+

j 0

McGUIRE SAFETY REVIEW GROUP INPLANT REVIEW REIORT 1.

REPORT NUMBER:

92-10 2.

DATE OF RKVIEW June 12, 1992 Through July 9, 1992 3.

SUBJECT DESCRIPTION: This Inplant Review is being submitted to the NRC as a voluntary special report of the circumstances relating to the incident described on Problem Investigation Report (PIR) 1-M92-0104, Inadequate Vent Path For The Reactor Coolant (NC) System While At Midloop Operation. The specific purpose of the review was to determine the cause of the incident and possible solutions to prevent further problems of the type described by the PIR.

4.

KVALUATION AND OOMMENT: PIR l-M92-0104 documented an incident in which there was not an adequate vent path for the NC system au specified by Generic Letter 88-17.

4.1 Background

Generic Letter 88-17 discusses the loss of decay heat removal during nonpower operation and the consequences of such a Icss.

One of the recommended actions included in this letter is as follows:

" Applicable to Westinghouse and Combustion Engineering Nuclear Steam Supply System (NSSS) designs, implement procedures and administrative controls that reasonably assure that all hot legs are not blocked simultaneously by nozzle dams unless a vent path is provided that is large enough to prevent pressurization of the upper plenum of the Reactor vessel."

The concern stated by the letter is that a pressurization of the NC system can occur as a result of conditions unique to operation with a reduced NC systeta inventory and all hot leg nozzle dams installed. Such a pressure increase could lead to Reactor core voiding and thereby seriously affect plant safety. As a result of the recommendations made by the letter the following procedure changes have been made to insurs that the vent path is maintained during conditions of reduced NC syetem inventory at McGuire.

-~ - ^ - -

e e

DPC/NNS INPLANT REVIEW No.

92-10 PAGR 2 These changes included the addition of appropriate steps and cautions to Operations Management Procedure 2-2, Shift Turnover, and Mechanical Maintwnance procedures MP/1/A/7150/42 and MP/2/A/7150/57, Reactor Vessel Head Removal And Peplacement.

These additions concerned interface between the Control Room Senior Reactor Operator (SRO) and Mechanical Maintenance personnel regarding the vent path as well as tracking of changes in NC system vent status. The char.ges were documented under McGuire Action Directory (MAD) item 1805-017Q, completed in July, 1989.

4.2 Description Of Event Prior to the start of the Unit 1 Steam Generator (SG) Tube Inspection Outage, in May of 1992, McGuire Management personnel made a decision to establish a vent path through the Hot Leg of SG ID to avoid having to remove the Reactor Vessel head during the outage. (Reference the attached NC system drawing page 9.)

Discussion of the consequences of this decision was held between Work Control, Operations, and Component Engineering personnel.

However, even though the vent path was discussed prior to the start of the outage and current vent path status covered during daily outage and SG status meetings, no changes to the existing administrative and procedural controls were made to ensure this new vent path configuration would be properly maintained.

On June 10, 1992, Unit 1 wan la midloop operation.

The Component Engineer ir. charge of work then in progress on the Unit 1 SGs made a work list for the SG crews coming in that night.

Included un the list were directions to close the Cold Leg Manway on SG 1B.

The Component Engineer stated that the list was extensive and that he did not expect the SG crews to complete all of the items listed that night.

No mention was made of the vent path through SG 1B on the list At approximately 1730, the Component Engineer performed the daily turnover with the Maintenance Enginaering Support Technician serving as single point contact for the SG crews.

During the course oI the turnovei the Component Engineer received a telephone call notifying him of a personal emergency. Due to this distraction the turnover was cut short and no mention was made of

0.

DPC/KNS INPLANT REVIEW No.

92-10 PAGE 3 maintaining the vent ath turing the turnover.

The Maintenance Engineering Support Technician stated that he was aware of the vent path and had intended to ask about it during the turnover but did not do so due to distractions and the turnovar being cut short.

There was no further interface between the Component Engineer and the SG crews that night Contrary to the expectations of the Component Engineer, all items on the work list were completed that night including replacement of the manway cover for SG 18.

The Maintenance Support Technician stated that he was aware of the vent path being through SG 18, but concluded that the component Engineer must have made appropriate interface with Operations personnel.

This same conclusion was voiced by the Maintenancs personnel who performed the SG manway installation.

All work involving installation of the SG manway cover was performed according to written direction of the Component Engineer and approved station procede es.

At approximately 0100 on the morning of June 11, 1992, Maintenance personnel installed the diaphragm for the manway on SG 18.

This effecticely blocked the 1C system vent path.

At approximately 0530 the Component Engineer arrived on site.

Upon arrival he proceeded to contact the Maintenance personnel involved and discovered that the vent path had been closed. At approximately 0630 ae verified that the manway had been installed.

Concurrently, the Shift Manager and Unit 1 Operations Engineer contacted him with the same conclusion concerning the vent path.

Immediate action was then taken to begin removal of the Hot Leg retzle dam on SG 1A and thereby reestablish the vent path. The vent path was reestablished at approximately 1100 on June 11, 1992.

4.3 Conclusion This incident is assigned a cauue of Management Deficiency due to lack of an adequate policy or procedure to goverr. control of the vent path.

Prior to the start of the Unit 1 TJ Tube Insp~; tion Outage, a

i DPC/MNS INPLANT REVIEW No.

92-10 PAGE 4 decision was made to establish a vent path through the Hot Leg of SG ID.

However, even though the status of the vent path was covered during daily outage and SG status meetings, there was no procedural provision made to insure that control was maintained when the vent path was changed during the outage when the SG manways were reinstalled.

The only procedure sign off for tha vant path was included in vendor procedure 80A9520, SG Nottle Dam Insta11ttien And Removal (Horizontal Suppcrt Frame). No mention was made of the vent path in station procedure MP/0/A/7650/97, SG Primary Manway Removal And Installation Using A Multi-Stud Tensioner.

Therefore, when the vent path was closed off by Maintenance personnel, no method was in place to inform Operations personnel of the change in configuration.

A cause of Inappropriate Action is also assigned because of Deficient Commu ication. The only direction given to the Maintenance personnel by the Component Engineer concerning the vent path was to install the manways on SG 1B.

This was in part due to the ambitious work list generated by the Corponent Engineer on that particular night. The Component Engineer stated that he did not expect that the SG crews would finish the wof list but felt that part of it would be carried t3 the next day when ha would be present.

Because of the personal emergency that night, the turnover was not completed properly. No communication took place during the turnover about the vent path.

Also, although the Maintenance personnel involved knew that the vent path existed, there was not e good understanding of the purpose or safety significance of the vent path.

All SG crew personnel interviewed, 1B stated they knew the vent path was being closed when the SG manways were installed but felt the Component Engineer had handled 3

any necessary interf ace with Operations personnel.

Since no procedural or other written guidance existed they depended on the component Engir.eer solely to handle such an interf ace.

A meeting was held on June 15, 1992, to discuss the incident and to establish a course of action for implementing controls to insure an adequate vent path is maintained at all times when the NC aystem is at reduced inventory and hot leg nozzle dams are installed.

Included 17. the meeting were representatives from the operations, Safety Review, Work Control, Nuclear Services, and

O.

DPC/MNS INPLAN'i REVIEW No.

92-10 PAGE 5 Component Engineering groups as well as the Station Manager.

The outcome of this meeting was a commitment to incorporatu procedural sign offs for control Room SRO concurrence when the vent path is changed.

These sign offs will be incorporated in'all proceduren governing SG manway removal and installation as well as the procedures governing removal and installation of nozzle dams.

The Component Engineering group also agreed to establish a written turnover sheet to document the existing vent path to keep the SG crew personnel informed of vent path status. Operations personnel present agreed to insure that adequate turnover of the current vent path was taking place on each Operations shift change.

Operations personnel present also agreed that an evaluation of the use of a graphic reprecentation in the Control Room to display current vent status as an aid to Control Room Operators would be performed.

All of the procedure changes and the written turnover sheet were to be in effect prior to moving any Unit 2 nozzle dams or SG manways since Unit 2 was in a position to begin closing of the SGs.

These controls were put into place on June 17, 1992.

The evaluation of graphic representation of the vent path in the Control Room is still underway by operations personnel.

In addition to these corrective actions, Selected Licensee Commitment (SLC) 16.5.1, Reduced Inventory Operation With Irradiated Fuel In Core, is currnntly under review for incorporation in the SLC Manual for McGuire.

This SLC commitment states that prior to reducing NC system level to less than 60 inches Wide Range, if SG nozzle dams are in use, at least one Hot Leg vent path shall remain open whenever the Reactor vesec1 head is in place. This SLC will provide appropriate guidance for Operations Control Room personnel regarding the vent path. As soon as the SLC commitment in officially incorporated in the McGuire SLC Manual, procedureo MP/1/A/7150/42 and MP/2/A/7150/57 (hes tar Vessel Head Removal And Replacement), MP/0/A/7650/97 (Steam Generator Primary Manway Removal And Installation Using A Multi-Stud Tensioner), and 80A9520 and 80A9526 (Steam Generator Nozzle Dam Installation And Removal Procedure) will be changed to incorporate a reference to the SLC commitment, The procedure changes, turnover sheet, graphic representation, and SLC commitmoit will provide appropriate guidance for all personnel involved with regard to the l

l L

O i

DPC/MNS INPLAliT IGVIEW No.

92-10 PAGE 6 vent path and should prevent recurrence of similar incidents.

PIR 92-104 was written to record a problem with inadequate vent path control while in midloop operations with respect to Generic Letter 88-17.

During this investigation, it was noted that Generic Letter 88-17 states that all Hot Legs should not be blocked simultaneously by nozzle dams unless a vent path is provided that is large enough to prevent pressurization of the upper plonum of the Reactor vessel. The concern as stated is to prevent a condition in which all Hot Legs are blocked by nozzle dams and a subsequent loss of ND results in boJ11ng of the reactor coolant. Once boiling is initiated, steam would begin to collect in the upper plenum of the Reactor vessel and pressure would begin to increase.

ha pressure irareased the coolant in the Reactor vessel would be displaced to tho Cold Legs of the SGs out of the core resulting in uncovering of the core.

At no time during this incident were all SG Hot Legs blocked by nozzle dams. Since three of the four SGs had their nozzle dams removed and manway covers installed, the wcrding of Generic Letter 88-17 was not violated.

However, the scenario described in Generic Letter 88-17 does not address the possibility that loss of ND with no vent path supplied for the NC system and one or more nozzle dams installed could lead to a scenario in which a build up of pressure could cause one of the nozzle dams to blow out.

This wo".ld lead to the Reactor coolant then flashing to steam and rapid uncovery of the Reactor core.

Therefore, this incident did serve to point out a weakness in control of the vent path while nozzle dams are installed, and the corrective actions implemented should prevent recurrence of similar incidents that could have safety significant implications.

4.4 Safety Evaluation During the time period the vent path was closed, there were no emergencies or perturbations to the NC system or to the other systems that are necessary to maintain the NC system in a stable and controlled condition during reduced inventory conditions.

No abnormal level or temperature changes took place.

A 1.'

instrumentation and alarms associated with monitori.g of the NC system were operable. Operations personnel in the Control Room were continuously monitoring parameters associated with the NC

s.

e OPC/MNS INPLANT REVIEW Mo 92-10 pta, '

3tua at that time and would have been able tc take appropriate ll ion to mitigate arv transient associated with the NC system.

In the event of a loss of ND system flow, Operations personnel have been able to utilize procedure AP/1/A/5500/19, Loss of

.oi Sleat Removal or De:my Heat Removal System Leakage.

'his would have directel Operations personnel in the actions to reestablish ND sy5cem flow or establien i

I

9t?

cooling means to prevent Reactor Core damage.

This 4

ps also insuren that Containment closure reqv'.temente ara ted tu prevent release of radioat
ive material to the d

6.

' int in the event any Reactor Core damage should occur.

he h.- :'th and saf ety of the poulic and on-site personnel were not afrected by th.t incident.

y

)

y

.,y I N ef=

5.

N RRECTIVE ACTIONS

w.,

Imniediate 1)

SG Crew personnel began action to remove the Hot Leg nozzle dam from SG 1A.

Subcoquent? '. )

co - :er: Engineering personnel incorporated procederal sign offs for Control Room SRO concurrence whenever she vat.. path is changed in procedures governing SG manway removal and installation as well

[

as procedures governing removal and installation of nozzle dams.

2)

Component Enginaering personnel estat?.ished c written turnover sheet to document the existing vent path to keep SG Crew personnel informed of the vent path status.

3)

Operations eersonnel verified adequate turnover of the vent path status was being performed by Operations Shift pereonnel.

Committed:

1)

Operations personnel will evaluate the use of a graphic representation in the Control Room to display current vent path status as an aid to Control Room

y I

o-DPC/MNS INPIANT REVIEW No.

92-10 PAGE 8 Operations personnel.

2)

Regulatory Compliance Group personnel will ensure that SLC 16 S.1, Reduced Inventory operation With Irradiated Fuel In Oore, 10 incorporats into the McGujre SLC Manual.

3)

Component Engineering personnel will change all procedures governing reactor vessel head removal and replacement, SG primary manway removal and replacement, and SG nozzle dam installation and removal to incorporate a reference to SLC 16.5.1.

4)

The McGuire Human Performance Enhancement Systems (HPES) Coordinator in conjunction with McGuire Management personnel will evaluate the use of Human Factors training for McGuire Staff personnel to aid in the decision making process used during development of policies and procedures used at McGuire involving safe operating practices.

l l

1

REACTOR COOLANT SYSTEM g=

"A", "C", AND "D" STEAM GENERATORS HAVE N0ZZLE DAHS INSTALLED IN BOTH THE HOT LEG AND THE COLD LEG FOR WORKING.

' AESSURtzEn STEAM GENERATOR HOTE: The itpresented S/G-has HOT LEG nozzle dam lef t out.

It's. COLD LEG nozzle dam.is-in~ stalled. The~ other thre-5/Gs have both nozzle. dams installed. This' q

-j allows HC System level to be raised as indicated such that Mid-Loop operation is not necessary.

The required Hot leg vent path is'through the U_ tubes of the represented S/G and out it's reroved Cold

\\,

..4-WATER w Leg side manway, SG TUBES LEVEL

.~_

[

7 SO MANwAy3 MOTOR VESSEL HEAD D.

h. 3 STALLED

_(

b "E^m.on vrsit )

FIMOVED MAGOR

~-

-3._. _._._..._

HO,T, LEO l;lHOTW..- ~'.. '

,' '._~_[ ____ _ _,:Co m LEG '._

.... COOLANT

~

PUMP l[,' '

coto tEO

_RHR

~

RHR (outi

"$lE DAM-tea,I

-S b '.

CORE s

CROSSOVER LEO

1 L v g

E g

- ~

g N

f

@~:.

~ a khk 3-=

g.S

-