ML20100M127

From kanterella
Jump to navigation Jump to search
Forwards Response to NRC 850115 Request for Comments on Fire Protection Policy Steering Committee Rept Encl W/ Generic Ltr 85-01.NRC Effort to Clarify 10CFR50,App R Guidance Supported.Exemption Requests Will Be Submitted
ML20100M127
Person / Time
Site: Vermont Yankee File:NorthStar Vermont Yankee icon.png
Issue date: 04/10/1985
From: Capstick R
VERMONT YANKEE NUCLEAR POWER CORP.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
FVY-85-34, GL-85-01, GL-85-1, NUDOCS 8504170319
Download: ML20100M127 (6)


Text

'

a VERMONT YANKEE NUCLEAR POWER CORPORATION RD 5, Box 169, Ferry Road, Brattleboro, VT 05301

,,,L y,,

g ENGINEERING OFFICE 1671 WORCESTER ROAD April 10, 1985 FRAMINGHAM. MASSACHUSETTS 01701 FVY 85-34 United States Nuclear Regulatory Commission Washington, D. C. 20555 Attention:

Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulations

References:

(a) License No. DPR-28 (Docket No. 50-271)

(b) Letter, USNRC to All Power Reactor Licenses and all Applicants for Power Reactor Licenses, NVY 85-1, dated January 9, 1985, Generic Letter 85-01, Fire Protection Policy Steering Committee Report

Subject:

Vermont Yankee Nuclear Power Corporation Comments on Generic Letter 85-01, Fire Protection Policy Steering Committee Report

Dear Sir:

On January 15, 1985, the Nuclear Regulatory Commission requested (50 Federal Register 2057) public comment on the Fire Protection Policy Steering Committee Report enclosed with Generic Letter 85-01, [ Reference (b)). The Steering Committee was directed to develop recommendations for resolution of certain fire protection issues including (1) the general adequacy of current guidance to the industry on Appendix R, (2) the validity of certain Staff interpretations of Appendix R requirements, (3) the treatment of future technical and schedular exemptions from Appendix R, and (4) the adequacy of the current inspection program. Enclosed with this letter are Vermont Yankee's specific comments and concerns associated with the Committee's Report. This enclosure was previously submitted to Mr. Vic Stello, Jr.,

Deputy Executive Director for Regional Operations and Generic Requirements in response to his request of March 4, 1985.

Vermont Yankee is supportive of the NRC's efforts to clarify 10CFR50 Appendix R guidance and is currently trying to bring this issue to a close for the Vermont Yankee S ation. As part of this effort, we will be submitting to NRR a comprehensive exemption request package for items which are not in literal conformance to Appendix R, recognizing that these requests may need to be revised and/or withdrawn should certain of the Comm8ttee's recommendations be adopted by NRC.

8504170319 850410 9

PDR ADOCK 05000271 F

PDR s\\

o United States Nuclear Regulatory Commission April 10, 1985 Attention:

Mr. Harold R. Denton Page 2 Vermont Yankee appreciates the opportunity to provide consents on the Steering Conunittee Report and assist in NRC's efforts to expedite completion of compliance ~with the fire protection requirements for nuclear power plants.

,s-Very truly yours, VERMONT YANKEE NUCLEAR POWER CORPORATION N

R. W. Capstick Licensing Engineer RWC/tl Enclosure

i Vermont
1. Control Room Fire Considerations (Ref. Encl. 6, Question 3.8.4)
a. Operator Action Prior to Control Room Evacuation The answer to this question states that the only manual action that can be assumed to be taken prior to leaving the control room is reactor trip. Vermont Yankee Alternate Shutdown System was designed assuming MSIV closure in addition to reactor trip. This assumption was considered reasonable, since at Vermont Yankee both actions can be accomplished by actuation of a single switch. Since the Vermont Yankee design has been previously reviewed and approved by the NRC, we find the answerfcontradictory.
b. Post Fire Shutdown Capability

' Although the Steering Committee Report did not address the question of whether fuse replacement is a " repair", this issue has.been raised lLn a more recent NRC Information Notice (IN 85-09) and relates to control: room fire considerations. IN 85-09 states.that, if a control-room evacuation is required, operability of the Alternate Shutdown

' System must exist without repairs', including replacement of fuses.

At Vermont Yankee, we do not consider that a problem exists if fuses in the Alternate Shutdown Circuits are damaged prior to awitchover.-

Because of' closing the MSIV's prior to evacuating the control room, sufficient time would be available to permit fuse replacement before the Alternate Shutdown equipment is needed. Again, since the Vermont Yankee design has been previously approved by the NRC, we find the statement made in IN 85-09 contradictory.

2. Short Circuit Coordination Studies (Ref. Encl. 6, Question 5.3.8)

The answer to this question states that high impedance faults, including simultaneous high-impedance faults below the trip point for the -breaker on each individual circuit, should be considered for all associated circuits-located in the fire area of concern. Such considerations were not previously required and have not been addressed by Vermont Yankee as part of its coordination study. We believe that consideration of high impedance faults goes beyond the design review required by Appendix R.

L e

...v

3. Circuit Failure' Modes (Ref. Encl. 6, Question 5.3.1)

The answer to this question discusses hot shorts, but does not provide

.any guidance concerning the types :of hot shorts that are considered credible.. A number of utility submittals have documented assumptions relating to this issue and our position is generally consistent with these assumptions. Nevertheless, the NRC has not yet provided a clear definition of what is acceptable. We believe that such definition would be helpful and avoid future problems.

4. " Approved" Fire Protection Program (Enclosure 6, p.2, 43-44)

-Enclosure 6 references an apparent " approved" Fire Protection Program.

NRC has never formally required any approvals of Fire Protection Programs.

This approval requirement does not appear in Appendix R and is considered a backfit.

5. Submission of Changes (Enclosure 6, p.43-44)

Requirements to submit any changes to the fire protection provisions do not appear in Appendix R other than specific conditions requiring exemption.- Enclosure 6 (Section 8.2 - p. 43-44) requires Commission approval of certain changes beyond those required of Appendix R.

6. Engineering Lighting Standards (Enclosure 6, p.28)

~ Enclosure 6 references the Illuminating Engineering Society Handbook as a standard for emergency lighting levels. This is a new requirement not found in Appendix R and constitutes a backfit.

7. Seismic and Fire Criteria (Enclosure 6, Section 2.2, p.41)

This section suggests additional requirements coupling seismic and fire events. Appendix R specifically says that fire protection systems do not.have to consider seismic events. We consider this a backfit.

8. Openings and Solutions (Enclosure 6, Section 8.8,,s.47)

This section provides specific engineering solutions to fire. problems (ex. sealing of conduit at both ends). Utilities and fire protection engineers should be' allowed the flexibility to design appropriate fire protection techniques.

f. ~.C a '

9. Other-Concerns a.-Schedular Exemptions (Ref. Encl. 2, Section A)

We are concerned that the draf t generic letter would not allow further exemptions under.10CFR 50.12,.once the schedule deadlines of 10CFR 50.48 have expired. ^ The door should be lef t open for justifiable exemptions.

b. Revised Inspection Program (Ref. Encl. 2, Section B)

We recommend that proposed inspections be scheduled af ter the new Staff, guidance has been finalized and released to the industry.

Licensees need time to assimilate the' findings of the report,.and the Commission may ultimately modify some the Staff's positions.

c. Quality Assurance Requirements (Ref. Encl. 2, Section D)'

We l disagree with the proposed new requirement that' all fire protection sys tems must meet' GDC-1.

Also, we note that:

(1) Appendix R makes no such statement and (2) the draf t generic letter itself contradicts

this,
d. Fire Damage (Ref. Encl. 3, Section 3)

We believe th' t the term " free from fire damage" is not sufficiently a

well defined and thus remains open to differing interpretations.

A clearer definition would be helpful in avoiding future problems.

e. Fire Protection License Condition (Ref. Encl. 4)

We object to the proposed license condition._ Adequate enforceability exists for fire protection via the General Design Criteria.

Also,-

10CFR 50.59 reviews must be conducted for all proposed modifications.

In this regard, however, we do not believe that 50.59 requires prior -

submittal of a full unreviewed safety question analysis made where no Technical Specification changes'will be necessary.

f. Fire Door Modifications (Ref. Encl. 6,-Question 3.2.3)

The answer to this question in effect introduces the requirement to submit an exemption for any modification to a fire door. We believe that-such a requirement is. unnecessary and some reasonable qualification is needed.

. g. Fire Protection Features NFPA Conformance and NFPA Code Deviations (Ref. Encl. 6, Questions 3.8.1 and 8.9)

We note that answers to these questions introduce a new requirement that systems be designed in accordance with NFPA guidelines and that even minor deviations' be identified in FSAR or Fire Hazards Analysis (FHA). The effort / cost associated with meeting this requirement will be substantial.

t

.,.u.

,h. III G, J'and 0 Exemptions for Future Modifications (Ref. Enci 6, Question 8.3)

' The answer to this ' question. appears to be a new Staff interpretation which requires that future' modifications involving fire protection features _ outside the scope of III G, J and 7 will need to comply

.with the appropriate part of_ Appendix R or qualify for an exemption.

.This could mean that eventually, all parts of Appendix R will apply to all plants, a backfit situation.

1.- It is still-unclear _ what constitutes a basis for an exemption filing.

Unless quickly clarified, VY will' file under previous Staff guidance.

. j.' Vermont-Yankee utilized _the concept of 20' separation zones to break up the Reactor Building into fire zones. No mention is made of this as acceptable guidance even though the approach has been used at other facilities and does make good fire protection engineering sense.

-k. We generally endorse the specific comments found in the February-14, 1985 letter from the Nuclear Utility Fire Protection Group to

-Harold Denton on the Report of the NRC Fire Protection Policy Steering Committee.

l l

i