Advises That Mods Per NUREG-0612, Control of Heavy Loads, Will Be Completed by 850701 Rather That 841231,per 830713 Commitment.Mods Will Begin After Refueling Outage 6,to Reduce Excessive Man Loading During Outage
ML20098C764
Person / Time
Site: Pilgrim
Issue date: 09/21/1984
From: Harrington W
BOSTON EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-36, REF-GTECI-SF, RTR-NUREG-0612, RTR-NUREG-612, TASK-A-36, TASK-OR 84-156, NUDOCS 8409270189
Download: ML20098C764 (1)


Text

a SOSTON EDISON COMPANY S00 SOYLETON STREET SOeTON MASSACHUBETTS O2199 WILLIAM D. MARWINGTON September 21, 1984 8ECo Letter No.84-156 Mr. Darrell 6. Eisenhut, Director Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Consission Washington, D.C.

20555 License No. DPR-35 Docket No. 50-293

Subject:

NUREG 0612: Control of Heavy loads

Dear Sir:

By letter of July 13, 1983, Boston Edison (8Eco) transmitted a report to the NRC on the control of heavy loads at Pilgrim Station.

In that letter we comunitted to complete all modifications and procedure emplacements by December 31, 1984.

To reduce excessive plant man-loading during refueling outage #6, and to ensure that the NUREG 0612 modifications would be performed in an optimal manner, we intended to begin the modifications at the conclusion of the outage. The extent of the outage has impacted that plan.

The design of the modifications is nearly complete; however, the design review process and the time needed for material procurement compels us to revise the completion date to July 1, 1985.

Very truly yours, a