Text
.
l l
Beaver Valley Power Station hipp n PA 15077-0004
.,g (412) 643-8069 FAX D o Vice P es de t I
Zl*UO'amion October 6,1995 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001
Subject:
Beaver Valley Power Station, Unit No. I and No. 2 BV-1 Docket No. 50-334, License No. DPR-66 BV-2 Docket No. 50-412, License No. NPF-73 Amendment 192 and 75 Administrative Changes
,1 On September 15, 1995, the Nuclear Regulatory Commission issued Technical Specification Amendment Nos.192 and 75 to Beaver Valley Power Station Unit Nos. I and 2, respectively. A review of Amendments 192 and 75, " Quadrant Power Tilt Ratio,"
has been completed, and it is requested that the attached six pages be reissued to correct the following typographical errors.
BV-1 Amendment 192:
_P_a.ge Change 3/43-6 In Action 7.b, replace "their" with "other."
B 3/4 2-7 In Action b, replace " Action a" with " ACTION a."
BV-2 Amendment 75:
Page Channe 3/42-9 In Action e, replace "show QPTR" with "show a QPTR."
3/43-6 In Action 3.a, replace "increaing" with " increasing."
B 3/4 2-7 In Action a, replace " Time" with " time."
B 3/4 2-9 In SR 4.2.4.a, add "high" before "neudon flux."
This request follows the discussion between our NRC Project Manager and a member of the Duquesne Light Company staff on September 25,1995. Issuance of these changes is requested by November 1,1995, to allow implementation of the subject
. amendments on November 10,1995.
Sincerely, 1SOG21 9510130282 951006
>MS PDR ADOCK 0500 4
George S. Thomas c:
Mr. L. W. Rossbach, Sr. Resident Inspector Mr. T. T. Martin, NRC Region I Administrator Mr. D. S. Brinkman, Sr. Project Manager
.h I
-