ML20091P465

From kanterella
Jump to navigation Jump to search
Forwards Independent Assessment of Underpinning Weekly Rept 38 for 830605-11.Minutes of Daily Meetings Held During Wk Between Members of Assessment Team & Site Engineering,Const & QA Personnel Encl
ML20091P465
Person / Time
Site: Midland
Issue date: 06/17/1983
From: Lucks A
STONE & WEBSTER, INC.
To: Cook R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML17198A223 List: ... further results
References
CON-BOX-08, FOIA-84-96 MPF-38, NUDOCS 8406130063
Download: ML20091P465 (9)


Text

.

m q

panwgyrove.

IMn i.

)

ps

%rz.a i ~ itsifio

+3 0v4' v

I STONE & WEBSTER MICHIGAN. INC.

F";

I 'J F 1 litC k,..[,, {$

P.O. Box 2325. Boston. MASSACHUSETTS 02107

'. :,J i

l v.w United States Nuclear Regulatory Commission June 17,1983

e. ' L1 t,

. E

.t l_

i' ' L Midland Site Resident Inspection Office i

l Route 7 J. O. 14358

}

Midland, MI 48640 Ref. MPF 38 i

Attention Mr.

R. Cook RE: DOCKET NO. 50-329/330 MIDLAND PLANT-UNITS 1 AND 2 I

INDEPENDENT ASSESSMENT OF UNDERPINNING l

REPORT NO.

38 i

A copy of the Independent Assessment of the Underpinning, Weekly Report No.

38 for the period June 5,1983 through June 11, 1983 is enclosed with this letter. Included as attachments, are the minutes of the daily meetings held i

during the week between members of the Assessment Team and Site Engineering, Construction, and Quality Assurance personnel.

If you have any questions with respect to this report, please contact me at (617) 589-2067).

Very truly yours, a.-

A. Stanley Lucks Project Manager Enclosures ASL/pd i

u n

JUN g mg g

8406130063 840517 PDR FOIA RICE 84-96 PDR e-se

4. < g 9

q J. O. No. 14358 Midland Plant Units 1 and 2 Independent Assessment of Underpinning Weekly Report No.'38 June 9, 1983,through June it, 1983 Personnel on Site

. Stone & Webster Michigan, Inc.

W.

Kilker 6/6 -6/11 P.

Barry 6/6 -6/11 B.

Holsinger 6/7 -6/11' Parsons, Brinckerhoff Michigan, Inc.

9 P. Parish 6/6 -6/10 l

f Meetings Attended Date-Represented Purpose r

6/6 Stone & Webster Daily Meetings through Bechtel 6/10 Consumers Power Parsons Actitivies Construction Pier KC11: The pier excavation, lagging and backpacking were completed.

I No groundwater entered the excavation. The subgrade was approved by the RGE and.

the mud mat was placed.

Pier. E'8 :

Steel reinforcement and telltale instrumentation were installed up to the level of the pier hammerhead.

Pier E10: Upon removal of the formwork above El 600 honeyenmbing effects in the concrete were noted in 3 of the pier corners approximately 4 ft down from the. top l-of the pier..All honeycombed concrete was removed and the zones were repaired-L.

with grout. The lower leveling plate was installed.

Pier KC2 The pier excavation, lagging and backpacking were completed to E1530, a depth of 20 ft.

No groundwater entered the excavation.

Pier W 8: The support of the bell area was completed and bottom mat and bell-reinforcing steel were installed. - Concrete was placed for the bell portion of i:

.the pier.

Pier W10: Shaft steel reinforcement was installed and the shaft concrete was placed. The pier lower leveling plate was installed.

SWPS: Work continued on the installation of deep probes,-deep seated benchmarks, and soldier pile casings.

Quality control. Documentation and Records e

-1. Performed a surveillance of the concrete placement at the pier W10.

~

L

'j

- 2. Verified the'cortifications of eight-QC inspectors performing welding -

-l

. inspections.

e

.,1

y l-J.O. No'. 14358 Midland Plant Units 1 and 2 iIndependent Assessment of Underpinning, 2

Weekly Report No. 38 3.

Reviewed Contractor's an,d MPQAD's decision to address and correct honeycomb concrete on pier E10.

l 4

Perforded a QA surveilance of Standish Fabrication Shop and selected PQCI's, drawings and specifications to check for current revisions and appropriate change., The findings were compared to the MPQAD document control station and, in turn, to the plant central document control log.

i 5.

Reviewed several welding Inspection Reports for accuracy, j

completeness and timely closure.

l 6.

Reviewed 30 welding Inspection Reports to follow up on the i

procedural, problems, identified in the Assessment Team's NIR No. I t,

,f en inspection of base metal repair.

Observation Construction - Upon discoveryor the honeyecmbed concrete in the pier E10.the i

Centracter implemented tne necessary repair procedure. The inferier concrete was removed, a bending agent applied to the exposed concrete and the voids were grouted. After a cure period the forms were removed revealing that the area had been properly repaired.

I The Team's observation of the lagging, reinforcement and concrete installation.s.

at the various piers under construction indicated that the work was done in accordance with the requirements of the project documu.ts.

The Assessment Team ' observed that the Contractor has decreased the diameter of the Hillibolts'to permit shorter bolt embedmont for bearing plate installations.

This modifidatica should minimize the bolt hole

  • reinforcing bar interference problems that have plagued the work to date. These new bolts were used twice this week without any delay caused by.rebar interference.

Cuality Control. Documentation and Records -

1. The placement and vibration of concrete in Pier W10 was in accordance with project procedures, codes and goed industry practice and produced a well consolidated mass of concrete.
2. Eight welding inspectors names were selected at randem from completed inspection reports and compared to their certification date. All of these checked ha,d performed inspection after the date on their certificate.

3 With reference to $he honeydomb concrore discovered in Pier 10 the Assessment Team reviewed the project specifications and industry code requirements. The project specifications satisfy all of the code requirements. The Team concluded that the Contractor and HPQAD decision not. to write a noncomformance report is correct.

4 The Assessment Team ob,serYed good craftmanship and quality attitude at the Standish Fabricatien Shop. Work area cleanlineds and the storage area meet or exceeded the inten; er. industry codes. The weld rod station

- storage ovens and hermetically seals containers are kept in a locked cage.

g

. m e gen,,,,,w w.,

a

..e,.<.

- + -

s k

d...

r 1

J J. 0, No. 14358 Midland Plant

. Units 1 and 2

-Independent Assessment of Underpinning 3

Weekly Report No. 38

5. The Inspection Report reviewed appeared to be accurate, complete and exhibited a vast improvement for timeliness of the supervisors review and j

closures.

6. The Assessment review of the 30 welding i nspection r eports did not show g

anyfurther indication that required inspections for base metal repair j

being missed, as reported in NIR No. 11.

l

' l Noncomformance Identification Reports

)

All 11 previously identified NIR's have been closed out.

t 5

i i

I 1

v-

, /L /

reject Engine @

Project Manager

?

>=mwAm*.~ns

-+.

~

+e.ww

, ~.

..uun,

.n.__,,,

,Q

,0

t s

Notes of Daily Meeting l

Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan June 6, 1983 Present For:

Consumers Power Bechtel MPQAD_

Stone & Webster i

W. Kilker G. Murray J. Firher J. Gaydos J. Ross j

Purpose j

This meeting is held each day to discusJ ttems regarding the Independent Soils Assessment at the. Midland Plant, Units 1 & 2.

i Discussion i

Item 1 - Status of NIRs 6-8.

~l W. Ki '.<er reported that NIRs 6-8 have been closed-out as acceptable.

R. Sevo stated two of the Quality Action Requests will remain open until the proposed procedure and specification changes are made.

Item 2 - Work Status.

1 J. Fisher reported that pier E8 bell and pier E10 shafts were concreted j

l June 3 and June 4, respectively. Piers W10 and W8 are in the process of reinforcies bar installation.

)

Item 3 - Hilti Bolt, Test Program.

J. Ross reported the test program was completed and the data forwarded to Project Engineering for analysis.

f Item 4 - Telltale Detail Change.

J. Fisher reported the lower telltale detail will change for future piers including E/W8 and KC piers. This change will result in a telitale with a free end as opposed to the existing fixed end.

' Item 5 - C$rlson Meter Encasement Change.

J. Ross said the WJE has determined that embedded lifting reinforcement and bolts may be affecting the meter readouts. These bolts and rods will be re-moved for future meter installatiors, item 6 - Discussion of; Layback Grouting.

R. Sevo generated a discussion of grouting of the si' ope laybacks.. J. Fisher said after grout viscosity adjustments on the east side placement, the I

west side placement proceeded quite well.

l

~ Items Requiring Resolution 1

None 4

..l.-

..~--. - ~ -

.,,.. - _ ~.,

s__

q I

i Notes of Daily Meeting Int.ependent Assessment of Underpinning

{

Micland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan June 7, 1983 Present For:

l Consumers Power.

Bechtel MPQAD Stone & Webster G. Murray J. Fisher W. Lydell W. Kilker J. Gaydos P. Barry

. N. Swanberg B. Holsinger Parsens 5

P. Parish Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.

l Discussion I

Item 1 - Construction Aid Guideling.

G. Murray stated that the guideline has been signed out and forwarded to Document Control.

t Item 2 - Fox-Howlett Disassembly Inspection.

J. Fisher said the inspection is being performed on piers under construction ej cn one of every - 100 assemblies as per the ASME' requirement.

Item 3 - Carlson Meter Encasement and Hilti Bolt Test Program N. Swanberg elaborated on the detail change in the encasement that is intended to improve the accuracy of response to applied loads.

Item 4 - Time Delay Requirements on Fox-Howlett Splice Testing N. Swanberg advised that the 24-hour lab hold-time requirement was not intended for the splic.e testing now being performed.

Item 5 - Revised Work Schedule J. Fisher advised that the field construction forces are now on the

" rolling 4-10" time schedule.

9 Item 6 - Pier E10 Concrete Honeycomb In response to a question by W. Kilker, J. Fisher and J.. Gaydos explained

.the conditions that~1ed to the concrete honeycomb effect in 3 corners of pier E10 approximately 4 ft. down from the top of the pier.

J. Fisher'

_ )

explained that-the approved concrete repair procedure would be implemented to do the repairs.

I Items Requirina Resolution-None T

i 97 a-w,s,..

Le:

j '.? : 0

l l

-1 l

p 3,

Notes of Daily Meeting Independent Assessment of Underpinning Midland Plant Units 1 & 2 Consumers Power Company Held at Midland Site Loxation Midland, Michigan June 8, 1983 t, '

Present For:

Consumers Power Bechtel MPQAD Stone & Webster G. Murray J. Fisher R. Sevo W. Kilker J. Gaydos P. Barry N. Swanberg B. Holsinger J. Kelleher Parsons P. Parish Purpose This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2.

{

Discussion Item 1 - Audit Report on U. S. Testing.

W. Kilker reported that according to MPQAD the report will be issued next week.

Item 2 - Carlson Meter Calibration.

N. Swanberg said that the encased Carlsonmeters will be calibrated on-site prior to placement in the piers. -The information 4111 be used by engineering in evaluating the ^ meters in-service response.

Item 3 - Concrete Workability.

P. Barry question &d,why the concrete placed to-date'in the underpinhing work has been at or on the low side of the 3 inch design slump instead of using concrete of up to 5 inches slump, the rejection limit. J. Gaydos replied that the Project Engineering design mix is for 3 inches and that going over this slump is considered an inadvertency. _That is, the intent is to avoid going over slump.

Items Requiring Resolution None i

s.

!?'

a

+

k'

. ~...

-~

~L 0 e

r

.-....m

.~..

Notes of Daily Mes

)

Independent Assessment of Underpinning Midland, Plant Units 1 & 2 Consumers Power Company Held at Midland Site Location Midland, Michigan June 9, 1983 Present For:

Consumers Power Bechtel MPQAD Stone & Webster R. Wieland J. Fisher R. Sevo P. Barry N. Swanberg V. Verma J. Gaydos Parsens M. Blendy P. Parish I

D. Lavelle Purpose i

This meeting is held each day to discuss items regarding the Independent Soils Assessment at the Midland Plant, Units 1 & 2 Discussion 1

Item 1-Carslon Meter Correlation, t

l Four concrete encased Carlson meters were sent to WJE in Chicago for i{

- correlation testing to ensure that the meters would be available for placement in pier E8.. Other Carlson meter encasement correlations will 3

be performed on-site by U.S. Testing.

Item 2 - Pier E8 Progress.

_ f Carlson meter encasement correlation testing is the critical item necessary

}

for pier E8 concrete placements. Tell-tale fabrication and QC availability for rebar welding inspection are also required tocomplete the work.

Item 3 - Pier W10 Bell Tolerance.

P. Barry requested a clarification discussion on a condition that led to correcting the bell dimension on pier W10 during rebar placement.

J. Fisher-explained that the bell. dimension tolerance deviation on pier W10 was noticed because of inadequate clearance for mat reinforcement and caused by jacking an additional soil support plate at the center of the bell span.

This jacking caused the plate to curl at the edges and reduced inside clearance. Resolution was made by trimming the excavation as necessary and jacking at the plate edges as well as the center.

Items Requiring Resolution

-* None - - -

. ~. -..

4 J

l l

  • .+

,+-A

.4.%.m.

..wwee.,

..m.<-

,w.,

e,..

u.,,,

>+

. s

~ - -_

t

. i

~N Notes of Daily Meeting l

Independent Assessment of Underpinning I

Midland Plant Units 1 & 2 4

Consumers Power Company Held at Midland Site Location Midland, Michigan June 10, 1983 s

Present For:

Consumers Power Bechtel MPQAD Stone & Webster G. Murray J. Fisher P. Barry J. Gaydos W. Kilker B. Holsinger Parsons P. Parish k-i Purpose This meeting is held each day to discuss items regarding the Independent i

Soils Assessment at the Midland Plant, Units 1 & 2.

}

l Discussion

)

Item 1 - Carlson Meter Calibration.

)

J. Fisher reported that Project Engineering has requested that all Carlson-1 l

Meter encasements be load calibrated prior to insertion in the respective piers.

j Item 2

" Road-Map" Meeting.

].

l J. Fisher announced that next week the Subcontractor will conduct a " road-map" discussion on the installation of the NS bulkhead at Pier E/W8 and excavation methodology of two mass excavation areas.

Item ConcreteAgitation.

In response to discussions held on-site earlier this week concerning requirements for constant cone.=ete agitation ('in the delivery truck), P. Barry stated that the Assessment Team had reviewed code requirements, project documents and site 2-practices. The Team agrees with the owners' position that the applicable ASTM and ACI codes do not require constant agitation of the mixed concrete prior to placement. With respect to site practices, the Assessment Team's observations of numerous concrete placements over the past 6 months indicate that, in general, the delivery truck drums are maintained at slow rotation speed. Only on rare occasions have the drums been stationary and then for only very short periods of time.- The' Assessment Team feels.the present site practice meets the intent of the codes, project documents, and good construction practice.

' Items Requiring Resolution None 9

l 4

.--u-w d s.

- me.-

-u

-.-.e.

.- y

. % ; e+ v. m + -+

'. =. - ~

s+-

s

-