ML20080M178
| ML20080M178 | |
| Person / Time | |
|---|---|
| Issue date: | 03/23/2020 |
| From: | Thomas Aird, M'Lita Carr, Mark Fuhrmann, Joseph Kanney, Elena Yegorova Office of Nuclear Regulatory Research |
| To: | Office of Nuclear Regulatory Research |
| T. Aird | |
| Shared Package | |
| ML20080M135 | List:
|
| References | |
| Download: ML20080M178 (21) | |
Text
1 Overview of NRCs Probabilistic Flood Hazard Assessment Research Program 5th Annual PFHA Research Workshop NRC HQ, Rockville, MD February 19 - 21, 2020 Thomas Aird*, Meredith Carr, Mark Fuhrmann, Joseph Kanney, Elena Yegorova Fire and External Hazards Analysis Branch Division of Risk Analysis Office of Nuclear Regulatory Research
Outline
- Objectives
- Key Challenges
- Research Approach
- Selected Projects
- Future Directions 2
PFHA Research Objectives
- Address significant gap in technical basis for guidance for probabilistic assessment of external hazards
- Probabilistic: seismic, high winds
- Deterministic: flooding
- Develop resources, tools and selected guidance
- Support risk-informed licensing and oversight activities associated with flooding hazards and consequences Licensing and oversight in operating reactor program Design basis flood hazard assessments for new facilities
- Readiness for licensing of advanced reactors 3
Key Challenges
- Hazard Curve Development
- Range of annual exceedance probabilities (AEPs)
- Moderately rare to extreme floods
- Multiple flooding mechanisms
- Coincident and correlated mechanisms
- Uncertainty characterization and estimation
- Aleatory (e.g. storm recurrence rates)
- Epistemic (e.g. model structure, parameters)
- Fragility Curve Development
- Information on reliability of flood protection features and procedures is sparse
- Cliff-edge effects 4
Magnitude Load Intensity Failure Probability
Phased Approach
- Phase 1 (FY15-FY19)
- Technical basis research
- Phase 2 & 3 (FY20-FY22)
- Selected draft guidance documents
- Perform pilot studies
- Finalize guidance 5
6 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
7 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
Leverage Available Flooding Information
- Completed (continue with updates/maintenance)
- Application of State-of-Practice Flood Frequency Analysis Methods and Tools (USGS)
- Completed - USGS Scientific Investigation Report
- https://pubs.er.usgs.gov/publication/sir20175038
- Extreme Precipitation Estimates in Orographic Regions (USBR)
- Completed - NUREG/CR report in publication
- Technical Basis for Extending Frequency Analysis Beyond Current Consensus Limits (USBR)
- In progress (completion expected in FY20) 8
- Eastern US Riverine Flood Geomorphology Feasibility Study (USGS)
- Completed - USGS Scientific Investigations Report
- Eastern US Riverine Flood Geomorphology Comprehensive Study (USGS)
-In progress (completion expected FY20)
- Framework for Technical Review of Paleoflood Information (USGS)
-In progress (completion expected FY20)
- Workshop summary: ML19200A281
- Application of Point Precipitation Estimates to Watersheds (ORNL)
-Completed (NUREG/CR report in publication) 9 Leverage Available Flooding Information
10 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
PFHA Modeling Frameworks
- Probabilistic Flood Hazard Assessment Framework Development (USACE)
- In progress (completion expected FY20)
- Structured Hazard Assessment Committee Process for Flooding (SHAC-F) for LIP & Riverine Flooding (PNNL)
- In progress (completion expected FY20)
- Development of SHAC-F for Coastal Flooding (PNNL &
USACE)
- In progress (completion expected FY20)
- Methods for Estimating Joint Probabilities of Coincident and Correlated Flooding Mechanisms for Nuclear Power Plant Flood Hazard Assessments (ORNL)
- In progress (completion expected FY20)
- Task 1 (Literature review) completed
- Task 2 (Critical Assessment of Selected Methods and Approaches) Completed.
11
12 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
Numerical Modeling of Local Intense Precipitation Processes (USGS/UC Davis)
- Completed - NUREG-CR report in publication
- Peer-reviewed papers: Mure-Ravaud, et al. (2019a,b) https://www.sciencedirect.com/science/article/pii/S0048969719306734
- https://www.sciencedirect.com/science/article/pii/S0048969719306291 Quantifying Uncertainties in Probabilistic Storm Surge Models (USACE)
- In Progress (completion expected FY20)
- Task 1 (Literature Review) Completed. ERDC/CHL SR-19-1
- Task 2 (Storm Recurrence Rate Models) Completed. ERDC/CHL TR-19-4
- https://apps.dtic.mil/docs/citations/AD1073835 Erosion Processes in Embankment Dams (USBR)
- Completed - NUREG-CR report in publication Convection-Permitting Modeling for Intense Precipitation Processes (NCAR)
- In Progress (completion expected FY21) 13 Improved Modeling
14 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
- Modeling Plant Response to Flooding Events (INL)
- Completed. NUREG/CR report in publishing
- Effects of Environmental Factors on Manual Actions for Flood Protection and Mitigation at Nuclear Power Plants (PNNL)
- Completed. NUREG/CR report in publication process
- Critical Review of the State of Practice in Probabilistic Risk Assessment for Dams (ORNL, UMD)
- Completed. ORNL report available at https://www.osti.gov/biblio/1592163-current-state-practice-dam-safety-risk-assessment
- Performance of Flood Penetration Seals at NPPs (Fire Risk Management, Inc.)
- Completed. NUREG report in publication process
- Flood Barrier Testing Strategies (INL/ISU)
- In Progress. Public workshop to be held March 12 - 13 15 Reliability of Flood Protection
16 Phase 1 Technical Basis Projects Leverage Available Flood Information PFHA Modeling Frameworks Improved Modeling Reliability of Flood Protection Dynamic and Nonstationary Processes
Dynamic and Nonstationary Processes
- Regional Climate Change Projections: Potential Impacts to Nuclear Facilities (PNNL)
- Year 1 (CONUS) - Complete
- published as a PNNL report (PNNL-24868)
- Year 2 (Southeast US) - Complete
- published as a PNNL report (PNNL-26226)
- Year 3 (Midwest US) - Complete
- published as a PNNL report (PNNL-27452 Rev1)
- Year 4 (Northeast US) - Complete
- published as a PNNL report (PNNL-29079) 17
18 Future Directions for PFHA Phase 1 Technical Basis Projects Phase 2 Pilot Projects Application Inform & update Phase 3 Guidance
19 Future Directions for PFHA Phase 1 Technical Basis Projects Phase 2 Pilot Projects Application Inform & update Phase 3 Guidance
Objective: Synthesize results from technical basis research
- Multiple flooding mechanism contribution to hazard curves
- Quantify key aleatory variabilities and epistemic uncertainties LIP Flooding PFHA Pilot (PNNL)
- Pilot study to inform development of guidance for probabilistic assessment of flooding hazards at NPPs due to local intense precipitation events Riverine PFHA Pilot (USACE/HEC)
Coastal Flooding Pilot PFHA Pilot (USACE/ERDC) 20 Phase 2 Pilot Studies
- Revise guidance documents based on pilots
- Stakeholder & Public Interactions
- Finalize guidance 21 Phase 3 (FY22-?)
Questions?
Contact:
joseph.kanney@nrc.gov Phase 1 Technical Basis Projects Phase 2 Pilot Projects Application Inform & update Phase 3 Guidance