ML20069L801

From kanterella
Jump to navigation Jump to search
Suppls 820306 Response to Noncompliance Noted in Item 1 of IE Insp Rept 50-293/81-24.Deadline of 820531 for Revising Maint Requests & Training Personnel Not Met.Compliance Expected by 821201
ML20069L801
Person / Time
Site: Pilgrim
Issue date: 10/12/1982
From: Ballentine J
BOSTON EDISON CO.
To: Starostecki R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
82-268, VP-NO-82-43, NUDOCS 8211180239
Download: ML20069L801 (1)


Text

r O

O

~

BOSTON EDISON COMPANY 800 BoyLsTON STREET ECETON, MAESACHUBETTs 02199 JERE M. SALLENTIN E

!!JI."C."!,,...

October 12, 1982 BECo. Ltr. #82-268 VP-N0 82-43 Mr. Richard W. Starostecki, Director Division of Project and Resident Programs U.S. Nuclear Regulatory Comission Region I 631 Park Avenue King of Prussia, PA 19406 License No. DPR-35 Docket No. 50-293 Supplemental Response to Item of Non-Compliance (50-293/81-24-01)

Reference:

(A) BECo Letter (W. D. Harrington) to NRC R. W. Starostecki, dated March 6, 1982 BECo Ltr. 2.82.71

Dear Sir:

The Reference (A) letter stated, in part, in response to item of non-compliance (50-293/81-24-01), that PNPS Procedure 1.5.3, " Maintenance Requests" would be revised and affected personnel trained by May 31, 1982.

Compliance was not achieved by May 31, 1982 due to the extent of the revisions made to Procedure 1.5.3.

Training for affected personnel has begun and will be completed by December 1, 1982. The revised procedure will be implemented when the training is completed.

The revised MR forms are printed and will be issued concurrent with the revised procedure implementation.

Full compliance will be achieved by December 1,1982.

Should you have any questions regarding this supplemental response, please contact ".

Ver trul

urs, niSE 3

y-o' Comonwealth of Massachusetts)

County of Suffolk

)

,M Then personally appeared before me Jere M. Ballentine, who, being duly sworn,

,Qg did state that he is Vice President - Nuclear Operations of Boston Edison Company, the applicant herein, and that he is duly authorized to execute and file the sub-oo mittal contained herein in the name and on behalf of Boston Edison Comaany and lMQ thatthestatementsinsaidsi;bmittalaretruetothebestofhisknowledgeand I5E belief.

'emo f.

L-My Commission expires:./o/y(/9fg g,[

p0I hotary Publi(