Submits Special Rept to Document ISI of SG Tubes at SONGS, Unit 2
ML20065M805
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 04/15/1994
From: Marsh W
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9404260205
Download: ML20065M805 (15)


Text

~..

.)

,f"dM?

Southern California Edison Company 23 PAHKDt STREtif inVINE, CAllFORNIA 92718 April 15, 1994 wat vr;n c uAnso m.,,,,

w.~- n o -- m an um-x-u, n..-

i

)

U. S. Nuclear Regulatory Commission i

Document Control Desk Washington, D.C.

20555 Gentlemen:

Subject:

Docket No. 50-361 Special Report Inservice Inspection of Steam Generator Tubes San Onofre Nuclear Generating Station, Unit 2

References:

1.

PWR Steam Generator Examination Guidelines, Revision 2, Electric Power Research Institute (EPRI) Report Number NP-6201, dated December 1988.

2.

Letter from M. O. Medford (SCE) to Mr. G. W. Knighton (USNRC) dated April 5, 1985.

Pursuant to Surveillance Requirement 4.4.4.5(b) of Appendix A, Technical Specifications to Facility Operating License NPF-10, this report is being submitted to the Commission following the completion of an inservice inspection of steam generator tubes at San Onofre Unit 2.

Eddy current inspection of the steam generator tubing was completed on July 20, 1993. A total of 11,937 tubes (66.0% of the tubes _ in service) in-two steam generators were inspected full length and 32 tubas were removed from service by mechanical plugging.

This inspection significantly exceeded the amount of tubing required to be inspected per Surveillance Requirements 4.4.4.0 through 4.4.4.2, including all prospective C-2 expansions (i.e., _a 3%

sample plus a 6% (25) and a 12% (45) expansion in each steam generator].

The planned inspection programs for both steam generators were fully consistent with industry recommendations in the "PWR Steam Generator Examination Guidelines" (Reference 1).

The programs included inspection of the full length of 100% of the tubing in the central cavity region of the tube bundle where the batwing wear mechanism previously described in Reference 2 is active, and tubes adjacent to tie-rods.

The inspection programs for both steam generators were expanded.. The expansions included local bounding of tubes to be plugged, inspection of the full length of all tubes not in the inspection programs within the past four years, and inspection of all tubes with a motorized rotating pancake coil (MRPC) probe at the. inlet top-of-tubesheet location.

~

9404260205 940415 I

ADOCK 0500 1

gDR

4 i

Document Control Desk In Steam Generator E-088, 5987 tubes were inspected full length.

Two tubes were found with the MRPC probe to have a circumferential indication at the inlet top-of-tubesheet location and were plugged.

One tube was found with the MRPC probe to have axial indications at the inlet top-of-tubesheet, _ and was plugged.

One tube was found with the MRPC probe to have a volumetric indication (i.e., no specific axial or circumferential aspect) at the inlet top-of-tubesheet, and was plugged. One tube was preventively plugged due to tie-rod denting.

Three tubes were preventively plugged due to degradation at a vertical strap support.

Three tubes were preventively plugged due to-degradation at a batwing support.

In Steam Generator E-089, 5950 tubes were inspected full length.

Ten tubes were found with the MRPC probe to have circumferential indications at the inlet top-of-tubesheet location and were plugged. One tube was found with the MRPC probe to have an axial indication at the inlet top-of-tubesheet, and was plugged. One tube was found to be defective due to a 57% throughwall indication one inch above the inlet top-of-tubesheet, and was plugged. MRPC' probe testing of this indication revealed that the indication is axially oriented.

Two tubes were found to be defective, due to greater than 90%

throughwall indications within the explosively expanded region within the tubesheet, and were plugged. MRPC probe testing of these two tubes within the tubesheet revealed that the indications are axially oriented.

One tube in E-089 was found to be defective, due to a 89% throughwall indication at the sixth eggcrate support on the inlet side of the tube, and was plugged. MRPC probe testing of this indication, and an indication in this tube at the fifth eggcrate support on the inlet side of the tube, revealed an axial indication at each of these locations.

One other tube in E-089 had a similar axial indication at the sixth 'eggcrate support on the inlet side of the tube, and it was plugged.

Also, in E-089 two tubes were preventively plugged due to degradation at a vertical strap support. One tube was preventively plugged due to degradation at an eggcrate support. Two tubes were preventively plugged due to degradation at a batwing support.

As required by Surveillance Requirement 4.4.4.5(b), complete results of the recently completed inservice inspection of steam generator tubing are provided in the enclosures. provides the steam generator internal location reference guide.

The eddy current indication locations listed in the remaining enclosures are based upon this guide. provides a list of abbreviations used to describe the indications from MRPC probe testing in the remaining enclosures, l

r.

~

4 M

DocumentbontrolDesk Enclosures 3 and 5 provide a list of eddy current testing indications, including tube _ identification, indication depth for bobbin probe indications, indication description for MRPC probe indications, and the axial location of the indication in the tube. _ Enclosures 4 and 6 provide a list of tubes

- plugged after completion of the inservice inspection.

If you require any additional information, please so advise.

Sincerely, Jbke/$

Enclosures (6) cc: - L. J. Callan, Regional Administrator, NRC Region IV K. E. Perkins. Jr., Director, Walnut Creek Field Office, NRC Region IV J. A. Sloan, NRC Senior Resident, San Onofre Units 1, 2 & 3 M. B. Fields, NRC Project Manager, San Onofre Units 2 and 3 Institute of Nuclear Power Operations (INP0)

?

.Page 1 of 3

~

~

CE MODEL 3410 TUBE SUPPORT DRAWING vH2 vcu vc2 VH1 VH3 VC3 VC1 1

I I

I DDH I

f i

i 00C B

10}l

==

10C 30.75*

E 09C 09H f

30.75*

OBC 08H

=.

30.75*

07H OTC 38' 06H 06C 30*

05H OSC 35' 04H 04C 38' 03H 03C 36*

1 02H 02C a

35*

h 01H 010

- l f

l 20,25' N

J TSC TSH t

23,00*

+

TEC TEH r-I!JLET OUTLET f

6 Page 2 of.3 CLARIFICATION OF TUBING / SUPPORT INTERFACES AB0VE THE 7TH FULL EGGCRATE SUPPORT R0W(S1 TUBING / SUPPORT INTERFACES 120-147 08H.09H.10H.DBH.VHl.VH2.VH3.VSM.VC3.VC2.VC1.DBC.100.09C.08C 115-119 08H.09H DBH.VHl.VH2 VH3.VSM.VC3.VC2.VC1.DBC 09C.08C 84-114 08H.09H DBH VH2.VH3.VSM.VC3.VC2 DBC 09C.08C 83 08H DBH VH2.VH3.VSM.VC3.VC2

'DBC 08C 51-82 08H DBH VH3.VSM.VC3.

DBC 08C 49-50 08H DBH VSM DBC 08C 19-48 DBH VSM DBC 1-18 DBH DBC I

(

Page 3 of 3 J A il 23 a

u

} M f j (:.

p 3

l j:

!'" d (b

)I ' f[

3 n

! ": S 7

i 4

i,,. !wfu L

l*

3 m

s

!+ !k j

! f [5 ll h

f !

f b

z 5so- !b

' f

- )p q%f4

. 1 u

t 7

...;p:

(~

f p g

i l,[

~

y

iji

[ i i g

{

a 3

H g

[*

!i j

P s-as j

.:s 1.

.lpf E

1-

^jj~f jsid j

g q

c f

j 1

E s 1

]

j

'i j

.pg j

p

(

jlj

=

m

..3 b !

j

[ f.

l 1 E

"" l y

a e :L t

p gj

[ j [

d a

M ll

[i l

.... (

[

j g

g g

L iE U

    • '{t

. l I

E l

f

k. [
j s $l$ $f (<.

t,. ae bbbbbbbbbbbbbN b b b b b k h h h h h k kk

- i LIST OF ABBREVIATIONS USED T0-DESCRIBE TME INDICATIONS FROM MRPC PROBE TESTING

' i Abbreviation Explanation of the Abbreviation SCI Single Circumferential Indication i

MCI Multiple Circumferential Indications SAI Single Axial Indication MAI Multiple Axial Indications SVI Single Volumetric Indication (i.e.. no specific axial or circumferential aspect)

)

t e

i F

4 u-CUHULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2

. STEAM GENERATON

88 PAGE:

1 OF 2

2 OUTAGE DATA SET

CURRENT DATE:

02/02/94.

SELECTION VARIABLES: Percent TIME:

12:06:44 EXAM EXTENT CURRENT ROW COL EXP #

LEG PROGRAM ACTUAL EXP CAL PROBE LOCATION VOLTS MIL DEG CH 76 ~54 7,8,5 C

TEC-TEH TEC-TEH 00035 580UL VSH-0.82 0.64 74 <20 2

C TEC-TEH TEC-TEH 00035 580UL VSH+

0.61 1.54 146 30 2

C TEC-TEH TEC-TEH 00035 580UL VC3-0.93 0.69 149 <20 2

C TEC-TEH TEC-TEH 00035 580UL VC3-0.58 0.54 117 <20 2

43 19-7,8 C

TEC-TEH TEC-TEH 00036 580UL 02H+

0.88 0.71 115 <20 1

89 19 7,8 C

TEC-TEH TEC-TEH 00036 580UL DBC-1.49 0.82 106 21 P2 78 22 8

C TEC-TEH TEC-TEH 00011 580UL VC3-0.93 1.08 31 <20 P2 54 28 8

C TEC-TEH TEC-TEH 00001 580UL 05C+ 19,31 0.74 158 <20 1

19 33 8

C TEC-TEH TEC-TEH 00001 580UL 02C+

5.83 0.66 154 <20 1

27 33 8

C TEC-TEH TEC-TEH 00001 580UL 04H+

2.05 1.96 155 <20 1

111 35 2,8,5 C

TEC-TEH TEC-TEH 00021 580UL VSH+

0.00 1.30 143 30 P2 82 38 1,3 C

TEC-TEH TEC-TEH 00011 580UL VC3-0.39 1.13 50 21 P2 21 39 7,8 C

TEC-TEH TEC-TEH 00038 580UL 05C+ 15.64 0.93 147 21 1

11 53 8

C TEC-TEH TEC-TEH 00004 580UL 05C+ 20.23 0.85 148 <20 1

29 57 8,7 H

TSH-TSH TSH-TSH 00077 600RC TSH+

0.00 5.49 19 SCI 6

58 68 C

TEC-TEH TEC-TEH 00006 580UL TSH+

1.60 0.75 145 20 1

46 70 C

TEC-TEH TEC-TEH 00007 580UL TSH+

2.00 1.67 155 <20 1

52 70 7,8 C

TEC-TEH TEC-TEH 00045 580UL VH3+

0.83 0.63 111 <20 2

144 70 7,8,5 C

TEC-TEH TEC-TEH 00046 580UL DBC+

1.82 1.64 120 34 2

123 73 8

C TEC-TEH TEC-TEH 00007 580UL TSH+

0.80 0.98 152 <20 1

69 75 7,8 C

TEC-TEH TEC-TEH 00047 580UL VH3-0.82 0.37 11 <20 2

C TEC-TEH TEC-TEH 00047 5800L VSM+

1.12 0.53 55 <20 2

133 75 7,8 C

TEC-TEH TEC-TEH 00047 580UL DBH+

2.34 0.47 127 <20 2

135 75 7,8 C

TEC-TEH TEC-TEH 00047 580UL DBH+

2.23 1.50 123 30 2

145 75 7,8 C

TEC-TEH TEC-TEH 00047 580UL DBH+

2.20 0.92 52 22 2

101 77 5,8 C

TEC-TEH TEC-TEH 00021 580UL DBH+

1.17 0.92 108 25 P2 119 77 8

C TEC-TEH TEC-TEH 00021 580UL VH2+

0.00 0.82 63 24 P2 146 78 1,8 C

TEC-TEH TEC-TEH 00020 580UL DBC-1.37 1.08 90 28 P2 143 79 7,8 C

TEC-TEH TEC-TEH 00047 5800L DBC+

1.31 1.26 36 27 2

147 81 8,7 C

TEC-TEH TEC-TEH 00082 58)UL DBC-1.85 0.48 40 <20 2

55 83 1

C TEC-TEH TEC-TEH 00010 580UL DBH-2,06 0.73 153 <20 P2 61 83 1

H TSH-TSH TSH-TSH 00002 600RC TSH+

0.18 2.20 101 GVI 4

147 83 1,8,5 C

TEC-TEH TEC-TEH 00020 580UL DBC+

1.21 2.26 120 42 P2 52 84 8

C TEC-TEH TEC-TEH 00010 580UL DBC-1.60 0.54 98 <20 P2 147 89 7,8 C

TEC-TEH TEC-TEH 00051 580UL VC1+

0.58 0.39 99 <10 2

49 93 1

C TEC-TEH TEC-TEH 00012 5800L DBC-1.59 1.02 107 <20 P2 107 93 1,3 C

TEC-TEH TEC-TEH 00012 580UL DBH+

0.00 0.28 27 <20 P2 50 94 8

C TEC-TEH TEC-TEH 0C312 580UL DBC-2.33 0.64 62 <20 P2 147 95 7,8 C

TEC-TEH TEC-TEH 00052 580UL VC1+

0.76 0.85 87 23 2

72 98 C

TEC-TEH TEC-TEH 00013 580UL 02Ch 2.74 0.99 147 24 1

118 102 5,8 C

TEC-TEH TEC-TEH 00014 580UL DBH-2.58 0.56 86 <20 P2 C

TEC-TEH TEC-TEH 00014 5800L DBH+

2.30 0.81 147 23 P2 138 102 5,8 C

TEC-TEH TEC-TEH 00014 580UL DBH-1.30 1.29 153 29 P2 71 103 H

TSH-TSH TSH-TSH 00007 600RC TSH+

0.00 1.26 82 SCI 6

58 108 C

TEC-TEH TEC-TEH 00025 580UL TSH+

3.16 0.73 147 22 1

CONAM NUCLEAR, INC.

I

CUMULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2 STEAM GENERATOR

88 PAGE:

2 OF 2

OUTAGE DATA SET

CURRENT DATE:

02/02/94 SELECTION VARIABLES: Percent TIME:

12:06:44 EXAM EXTENT I

CURRENT ROW COL EXP #

LEG PROGRAM ACTUAL EXP CAL PROBE LOCATION VOLTS MIL DEG CH 54 110 6,8 H

TSH-TSH TSH-TSH 00120 600RC TSH+

0.98 4.41 79 HAI 4

C TEC-TEH TEC-TEH 00032 5800L TSH+

1.26 1.95 141 27 1

78 110 6,8 C

TEC-TEH TEC-TEH 00032 5800L VH3-0.83 0.31 64 <20 P2 90 110 6,8 C

TEC-TEH TEC-TEH 00032 580UL VH3+

0.86 0.26 127 <20 P2 53 111 6,8 C

TEC-TEH TEC-TEH 00032 5800L TSH+

1.49 1.32 150 24 1

27 117 8,5 C

TEC-TEH TEC-TEH 00082 580UL VSM-0.87 1.07 45 28 2

C TEC-TEH TEC-TEH 00016 580UL VSM+

0.00 1.87 83 35 P2 112 120 7,8 C

TEC-TEH TEC-TEH 00063 580UL DBC+

0.00 0.89 202 20 2

51 123 C

TEC-TEH TEC-TEH 00018 580UL DBC-0.05 0.25 74 <10 P2 122 124 1,3 C

TEC-TEH TEC-TEH 00019 580UL DBH+

2.03 0.43 87 <.0 P2 73 133 8

C TEC-TEH TEC-TEH 00020 580UL VH3+

0.00 0.47 31 <20 P2 28 134 7,8 C

TEC-TEH TEC-TEH 00062 580UL VSM+

0.84 0.53 46 <20 2

112 144 7,8 C

TEC-TEH TEC-TEH 00066 580UL DBH+

2.12 1.51 113 28 2

15 165 7,8 C

TEC-TEH TEC-TEH 00068 580UL 04H+ 24.38 0.66 152 <20 1

67 165 7,8 C

TEC-TEH TEC-TEH 00068 580UL VH3-0.72 1.08 71 23 2

NUMBER OF TUBES SELECTED FROM CURRENT OUTAGE:

53 NUMDER OF DATA RECORDS SELECTED FROM CURRENT OUTAGE:

60 NO TREND ANALYSIS REQUESTED DATA SELECTION CRITERIA:

Percent: MAI, MCI, SCI,SAI,SVI, O to 100%

REPORT OPTIONS:

Only examination results matching criteria are included MAP OPTIONS:

Plot Variablo = Percent ThruWall Plot data from current examination only CONAM NUCLEAR, INC.

(

M

}

LIST OF TUBES PLUGGED

'1 1

San Onofre Unit 2 Steam Generator E-088 1

J Row Column Reason 76 14 Preventive Maintenance 111 35 Preventive Maintenance 29 57 SCI at TSH + 0.0 inches s

e 144 70 Preventive Maintenance 135 75 Preventive Maintenance 61 83 Preventive Maintenance 147 83 Preventiva Maintenance 71 103 SCI at TSH + 0.0 inches 54 110 MAI at TSH + 0.98 inches 27 117 Preventive Maintenance 45 139 Preventive Maintenance

.q I

h i

?

Enclosurc $

CUMULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2 STEAM GENERATOR

89 PAGE:

1 0F 4

OUTAGE DATA SET

CURRENT DATE:

02/02/94

-SELECTION VARIABLES Percent TIME:

12:25:37 EXAM EXTENT CURRENT ROW COL EXP#

LEG PROGRAM ACTUAL EXP CAL PROBE LOCATION VOLTS MIL DEG CH 22 2

8,5 C

TEC-TEH TEC-TEH 00000 580UL VSM-0.78 0.70 53 26 P2 48 8

8 C

TEC-TEH TEC-TEH 00000 580UL DBH-1.78 0.45 52 20 P2 13 9

8,7 C

TEC-TEH TEC-TEH 00030 580UL 02C+

6.69 0.79 154 <20 1

54 10 8,7 C

TEC-TEH TEC-TEH 00029 580UL VH3+

0.85 0.51 295 <20 P2 64 10 8,7 C

TEC-TEH TEC-TEH 00029 580UL 03C-1.08 0.40 144 <20 P2 59 13 8

C TEC-IEH TEC-TEH 00000 580UL VH3+

0.52 0.33 17 <20 P2 26 14 8,7 C

TEC-TEH TEC-TEH 00029 5 80;". VSM+

0.82 0.52 47 <20 P2 44 18 8

C TEC-TEH TEC-TEH 00000 580UL VSM-1.16 0.35 67 <20 P2 62 18 1,3 C

TEC-TEH TEC-TEH 00000 580UL VH3+

0.53 0.36 17 <20 P2 53 19 8,7 C

TEC-TEH TEC-TEH 00032 580UL VC3+

0.83 0.40 120 <20 P2 C

TEC-TEH TEC-TEH 00031 580UL VC3+

0.83 0.40 120 <20 P2 77 25 8,7 C

TEC-TEH TEC-TEH 00032 580UL VH3-0.96 0.32 57 <20 P2 91 27 8,7 H

06H-06H 06H-06H 00111 600RC 06H+

0.48 16.64 14 SAI 4

56 28 8

C TEC-TEH TEC-TEH 00002 580UL VC3-0.72 0.27 93 <20 P2 72 28 1,3 C

TEC-TEH TEC-TEH 00001 580UL DBC-0.35 0.39 25 <20 P2 91 29 8,7 H

TSH-TSH TEH-TSH 00043 600RC TEH+ 15.39 13.24 23 SAI 4

C TEC-TEH TEC-TEH 00032 580UL TEH+ 18.48 5.71 58 92 P 1 H

TSH-TSH TEH-TSH 00043 600RC TEH+ 18.93 40.32 28 SAI 4

84 30 8,7 C

TEC-TEH TEC-TEH 00032 580UL 07H+ 27.05 0.88 153 <20 1

91 31 8,4 C

TEC-TEH TEC-TEH 00017 580UL VH2+

0.65 0.31 78 <20 P2 47 33 8

C TEC-TEH TEC-TEH 00002 580VL DBH+

2.46, 0.60 28 22 P2 91 33 8

H 05H-06H 05H-06H 00002 600RC 05H+

0.67 9.03 19 SAI P 1 H

05H-06H 05H-06H 00002 600RC 06H+

0.67 56.43 33 SAI 4

C TEC-TEH TEC-TEH 00002 580UL 06H+

0.79 28.03 47 89 P1 99 33 8

C TEC-TEH TEC-TEH 00002 580UL VSM-0.81.

0.37 67 <20 P2 C

TEC-TEH TEC-TEH 00002 580UL VSM+

0.60 0.33 65 <20 P2 C

TEC-TEH TEC-TEH 00002 5800L VC2-0.98 0.55 70 20 P2 111 33 8

C TEC-TEH TEC-TEH 00002 5800L VH2-0.74 1.19 113 32 P2 94 34 8,4 C

TEC-TEH TEC-TEH 00017 580UL VH2+

0.83 0.41 35 <20 P2 101 35 8,7 C

TEC-TEH TEC-TEH 00033 580UL VH3-0.99 0.26 83 <20 P 2 113 35 8,7 C

TEC-TEH TEC-TEH 00033 580UL VSM-0.62 1.02 59 30 P2 C

TEC-TEH TEC-TEH 00033 5800L VC3-1.02 0.68 154 23 P2 108 38 8

C TEC-TEH TEC-TEH 00003 580UL VH2+

0.38 0.42 57 <20 P2 118 38 8

C TEC-TEH TEC-TEH 00003 580UL 03H-1.22 0.18 154 <20 P2 49 39 8,7 C

TEC-TEH TEC-TEH 00033 580UL VSM-0.68 0.35 117 <20 P2 108 42 8

C TEC-TEH TEC-TEH 00004 580UL DBH-2.57 0.52 98 22 P2 C

TEC-TEH TEC-TEH 00004 580UL DDH+

2.25 0.53 108 22 P2 116 42 8

C TEC-TEH TEC-TEH 00004 5800L 04H+

9.76 0.74 155 <20 1

122 42 8

C TEC-TEH TEC-TEH 00004 580UL DBC-2.80 0.74 118 27 P'2 48 44 8,7 C

TEC-TEH TEC-TEH 00035 580UL VSM-0.76 0.33 53 <20 P2 81 45 8,7 C

TEC-TEH TEC-TEH 00035 580UL 07H+

0.41 0.25 55 <20 P2 l121 45 1,3 C

TEC-TEH TEC-TEH 00005 580UL VC2-0.71 0.79 114 25 P2 C

TEC-TEH TEC-TEH 00036 5800L VC2-0.48 0.68 104 23 P2 C

TEC-TEH TEC-TEH 00005 5800L VC1-0.99 0.42 135 <20 P2 39 47 8,7 H

TSH-TSH TSH-TSH 00057 600RC TSH+

0.01 8.24 33 SCI 6

CONAM NUCLEAR, INC.

i

CUMULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2 STEAH GENERATOR

89 PAGE:

2 OF 4

OUTAGE DATA SET

CURRENT DATE:

02/02/94 SELECTION VARIABLES: Percent TIME:

12:25:37 EXAM EXTENT CURRENT ROW COL ZXP#

LEG PROGRAM ACTUAL EXP CAL PROBE LCM (ON VOLTS MIL DEG CH 87 49 8,7 C

TEC-TEH TEC-TEH 00036 580UL VII2 +

0.57 0.35 24 <20 b 129 49 8,7 C

TEC-TEH TEC-TEH 00036 5800L VH1+

6.62 0.66 176 <20 1

74 54 8

C TEC-TEH TEC-TEH 00008 580UL 04H+ 24.22 0.63 146 <20 1

C TEC-TE!! TEC-TEH 00037 580UL 04H+ 24.42 0.65 153 <20 1

118 54 8,7 C

TEC-TEH TEC-TEH 00037 580UL VH1-O.84 0.32 117 <20 P2 101 63 8

C TEC-TEH TEC-TEH 00011 580UL VC2-1.30 0.44 132 <20 P2 44 64 8,7 H

TSH-TSH TSH-TSH 00064 600RC TSH+

0.11 6.71 97 SCI 4

1 88 64 8,7 H

TSH-TSH TSH-TSH 00043 600RC TSH+

0.97 2.52 93 SAI 4

C TEC-TEH TEC-TEH 00039 580UL TSH+

1.17 1.62 124 57 1

133 65 8,7 C

TEC-TEH TEC-TEH 00040 5800L DBC-2.58 0.27 33 <20 P2 143 67 8

C TEC-TEH TEC-TEH 00012 580VL DBH-1.90 0.49 154 20 P2 C

TEC-TEH TEC-TEH 00012 580UL DBH+

2.10 0.61 88 22 P2 143 69 8

C TEC-TEH TEC-TEH 00012 580UL 10H+

1.23 0.57 137 22 2

50 70 8,7 C

TEC-TEH TEC-TEH 00073 580VL 08H+

0.94 0.41 53 <20 P2 52 70 8,7 H

TSH-TSH TSH-TSH 00069 600RC TSH+

0.12 1.51 153 SCI 4

138 70 8

C TEC-TEH TEC-TEH 00012 580UL DBH+

0.57 0.26 19 <20 P2 31 71 8

C TEC-TEH TEC-TEH 00073 580UL DBH-2.05 0.48 120 <20 P2 C

TEC-TEH TEC-TEH 00073 580UL DBC-1.34 0.43 45 <20 P2 141 71 8

C TEC-TEH TEC-TEH 00013 5800L DBli+ 27. 53 0.41 109 <20 P2 58 72 8

C TEC-TEH TEC-TEH 00097 5800L DBC-1.96 0.50 126 <20 P2 143 73 8

C TEC-TEH TEC-TEH 00013 580UL DBC-1.64 0.15 107 <20 P2 145 73 1,8 C

TEC-TEH TEC-TEH 00013 580UL VC1-0.74 0.27 81 <20 P2 C

TEC-TEH TEC-TEH 00013 580UL DBC-1.69 0.27 158 <20 P2 44 76 8

C TEC-TEH TEC-TEH 00074 580UL DBC-1.21 0.44 157 <20 P2 54 78 C

TEC-TEH TEC-TEH 00015 580UL 04H+

8.43 0.57 146 22 1

72 78 C

TEC-TEH TEC-TEH 00015 5800L VH3-0.60 0.70 36 24 P2 76 78 C

TEC-TEH TEC-TEH 00015 5800L VC3+

0.71 0.44 93 <20 P2 119 79 8

C TEC-TEH TEC-TEH 00015 5800L VH3+

1,48 0.17 163 <20 P2 60 80 8

C TEC-TEH TEC-TEH 00089 580UL VH3+

0.65 0.41 135 <20 P2 145 81 8

C TEC-TEH TEC-TEH 00108 580UL VH1+

0.91 0.38 105 <20 P2 52 84 8

C TEC-TEH TEC-TEH 00016 580UL DBH+

1.96 0.34 72 <20 P2 147 85 8,7 C

TEC-TEH TEC-TEll 00044 5800L DBC-1.77 0.43 12 <20 P2 146 86 8,7 C

TEC-TEH TEC-TEH 00087 5800L DBH+

1.98 0.86 154 29 P2 56 88 1,3 C

TEC-TEH TEC-TEH 00016 580UL VSM-0.77 0.56 102 <20 P2 68 88 C

TEC-TEH TEC-TEH 00016 580UL TSH+

1.20 0.59 148 21 1

82 88 1

C TEC-TEH TEC-TEH 00016 580UL DBH+

0.00 0.32 59 <20 P2 63 89 8

11 TSH-TSH TSH-TSH 00072 600RC TSH+

0.23 2.59 233 SAI 4

147 89 8,7,5 C

TEC-TEH TEC-TEH 00044 580UL DBH+

2.20 1.74 85 38 P2 3

C TEC-TEH TEC-TEH 00044 5800L DBC+

1.60 0.88 103 26 P2 l

62 90 8

C TEC-TEH TEC-TEH 00018 580VL VC3+

0.89 0.37 278 <20 P2 125 91 8

C TEC-TEH TEC-TEH 00018 580UL 03H+ 27.69 0.79 157 <20 1

127 93 1,3 C

TEC-TEH TEC-TEH 00018 580UL 03H+

0.91 0.33 121 <20 P1 147 93 1,8 C

TEC-TCH TEC-TEH 00018 5800L VC1+

1.01 0.55 145 <20 P2 54 94 8

C TEC-TEH TEC-TEH 00019 5800L VSM+

0.92

'O.52 204 <20 P2 C

TEC-TEH TEC-TEH 00019 5BOUL VC3-0.49 0.29 146 <20 P2 CONAM NUCLEAR, INC.

)

i i

l i

CUMULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2 STEAM GENERATOR

89 PAGE:

3 OF 4

OUTAGE DATA SET

CURRENT DATE:

02/02/94 SELECTION VARIABLES: Percent TIME:

12:25:37 EXAM EXTENT CURRENT FOW COL EXP#

LEG PROGRAM ACTUAL EXP CAL PROBE LOCATION VOLTS MIL DEG CH 59 95 8

C TEC-TEH TEC-TEH 00044 580UL DBC-0.80 0.44 26 <20 P2 91 95 8,7 H

TSH-TSH TSH-TSH 00074 600RC TSH-0.04 10.34 20 SCI 4

117 95 8,7 C

TEC-TEH TEC-TEH 00053 580UL DBC+

0.72 0.48 102 <20 P2 147 95 8,7 C

TEC-TEH TEC-TEH 00059 580UL DBH+

1.63 1.40 72 32 P2 88 96 8,7 H

TSH-TSH TSH-TSH 00074 600RC TSH+

0.00 12.31 17 MCI 4

89 97 8,7 H

TSH-TSH TSH-TSH 00074 600RC TSH-0.04 8.25 13 SCI 4

56 98 C

TEC-TEH TEC-TEH 00019 580UL VSM+

0.77 0.32 106 <20 P2 112 98 1,3 C

TEC-TEH TEC-TEH 00020 580UL 03C-0.17 0.42 131 <20 P2 49 99 8

C TEC-TEH TEC-TEH 00020 5800L DBH-2.02 0.39 18 <20 P2 51 99 8

C TEC-TEH TEC-TEH 00020 580UL VSM-0.95 0.40 77 <20 P2 99 99 8,7 H

TSH-TSH TSH-TSH 00075 600RC TSH-0.11 12.74 26 SCI 4

78 100 8,7 H

TSH-TSH TSH-TSH 00075 600RC TSH-0.13 12.55 24 SCI 4

126 100 8,7 C

TEC-TEH TEC-TEH 00058 5800L 10H-1.00 2.38 86 41 P2 146 100 8,7 C

TEC-TEH TEC-TEH 00058 580UL DBH+

2.13 0.68 156 20 P2 36 102 8

C TEC-TEH TEC-TEH 00020 580UL DBC-0.65 0.13 4 <20 P2 69 103 C

TEC-TEH TEC-TEH 00021 580UL TSH+

4.33 1.44 157 <20 1

38 106 8

C TEC-TEH TEC-TEH 00021 580UL VSM-0.56 0.22 128 <20 P2 50 108 3

H TSH-TSH TSH-TSH 00109 600RC TSH+

0.06 2.72 88 SCI 6

56 108 3

C TEC-TEH TEC-TEH 00021 580UL VSM+

0.00 0.28 73 <20 P2 106 108 8

C TEC-TEH TEC-TEH 00021 580UL VC2-0.61 0.28 76 <20 P2 99 109 8,7 C

TEC-TEH TEC-TEH 00057 580UL VSM-1.12 0.48 54 <20 P2 141 109 8

C TEC-TEH TEC-TEH 00025 580UL VH3-0.17 0.67 48 26 P2 40 112 8

H TSH-TSH TSH-TSH 00081 600RC TSH+

0.00 3.98 11 MCI 4

44 112 8

C TEC-TEH TEC-TEH 00026 5800L VSM-0.81 0.36 161 <20 P2 124 114 8

C TEC-TEH TEC-TEH 00056 5800L TSc+

5.92 0.80 156 <20 1

14 116 8

C TEC-TEH TEC-TEH 00097 580UL 07H-0.20 0.44 94 <20 P2 126 118 8

C TEC-TEH TEC-TEH 00024 580UL 06C+

0.85 0.47 13 <20 P2 55 123 C

TEC-TEH TEC-TEH 00028 580UL VH2-0.92 0.32 55 <20 P2 j

95 123 C

TEC-TEH TEC-TEH 00024 580VL VH2-0.91 0.44 146 <20 P2 C

TEC-TEH TEC-TEH 00024 580UL VH2+

0.17 0.22 23 <20 P2 l

127 123 1,3 C

TEC-TEH TEC-TEH 00023 5800L 08H+ 26.27 1.38 160 <20 1

134 124 8,7 C

TEC-TEH TEC-TEH 00046 5800L VC3+

0.62 0,28 64 <20 P2 122 126 1,3 C

TEC-TEH TEC-TEH 00023 5800L VH1+

1.11 0.t B 138 22 P2 81 127 8

C TEC-TEH TEC-TEH 00028 5800L VSM-0.54 0.54 151 20 P2 l

C TEC-TEH TEC-TEH 00028 580UL VC3-0.82 0.81 133 26 P2 74 128 5

C TEC-TEH TEC-TEH 00102 58412 VSM-0.85 0.92 76 28 P2 C

TEC-TEH TEC-TEH 00028 580UL VSM-0.40 0.92 41 28 P2 95 129 8,7 C

TEC-TEH TEC-TEH 00054 580UL 04C+

5.91 0.84 155 <20 1

119 129 1,3 C

TEC-TEH TEC-TEH 00023 5800L VH2+

0.59 0.17 128 <20 P2 78 130 8,7 C

TEC-TEH TEC-TEH 00052 580UL VSM-1.15 0.25 144 <20 P2 85 133 8

C TEC-TEH TEC-TEH 00028 5800L VH2-0.66 0.31 95 <20 P2 80 136 8,5 C

TEC-TEH TEC-TEH 00028 580UL VH3-0.94 0.80 71 26 P2 C

TEC-TEH TEC-TEH 00102 58412 VH3-0.93 0.81 81 26 P2 62 140 8,7 C

TEC-TEH TEC-TEH 00060 580UL VSM-0.72 0.39 40 <20 P2 68 140 8,7 C

TEC-TEH TEC-TEH 00060 5800L TSH+

3.62 0.44 124 23 P1 CONAM NUCLEAR, INC.

~,.-

CUMULATIVE REPORT 06/93, SOUTHERN CALIFORNIA EDISON, SAN ONOFRE, UNIT 2 STEAM GENERATOR

89 PASE:

4 OF 4

OUTAGE DATA SET

CURRENT DATE:

02/02/94 SELECTION VARIABLES: Percent TIME:

12:25:37 EXAM EXTENT CURRENT ROW COL EXP#

LEG PROGRAM ACTUAL EXP CAL PROBE LOCATION VOLTS MIL DEG CH 66 144 8,7 C

TEC-TEH TEC-TEH 00076 5800L VH3-0.80 0.43 108 <20 P2 74 156 8,7 C

TEC-TEH TEC-TEH 00087 580UL VSM-0.89 0.46 120 <20 P2 49 157 8

C TEC-TEH TEC-TEH 00079 580UL VSM-0.87 0.91 54 28 P2 C

TEC-TEH TEC-TEH 00102 58412 VSM-0.78 0.81 63 26 P2 69 159 8,7 C

TEC-TEH TEC-TEH 00080 580UL 07C+

6.26 2.09 165 <20 1

77 159 8,7 H

TSH-TSH TSH-TSH 00099 600RC TSH-5.69to-6.02 0.86 0 SAI 4

C TEC-TEH TEC-TEH 00080 580UL TEH+ 19.29 5.99 41 91 P1 H

TSH-TSH TSH-TSH 00099 600RC TSH-2.01to-4.17 1.67 O

SAI 4

70 160 8,7 C

TEC-TEH TEC-TEH 00080 580UL VSM+

2.71 1.02 158 <20 1

74 160 8,7 C

TEC-TEH TEC-TEH 00080 580VL VH3-0.84 0.44 104 <20 P2 NUMEF9 OF TUBES SELECTED FROM CURRENT OUTAGE:

120 NUMFER OF DATA RECORDS SELECTED FROM CURRENT OUTAGE:

145 NO TREND ANALYSIS REQUESTED DATA SELECTION CRITERIA:

Percent: SCI,MAI, MCI,SAI,SVI, O to 100%

REPORT OPTIONS:

only examination results matching criteria are included MAP OPTIONS:

Plot Variable = Percent ThruWall Plot data from current examination only i

1 i

l CONAM NUCLEAR, INC.

~

5./

j

< c. ;

LIST OF TUBES PLUGGED San Onofre Unit 2 Steam Generator E-089 Row Column Reason 91 27 SAI at 06H + 0.48' inches 91 29 92% Indication at TEH + 18.48-inches 91 33 89% Indication at 06H + 0.79 inches 111 33 Preventive Maintenance 113 35 Preventive Maintenance 39 47 SCI at TSH + 0.01 inches 44 64 SCI at TSH + 0.11 inches 88 64 57% Indication at TSH + 1.17 inches.

52 70 SCI at TSH + 0.12 inches 63 89 SAI et TSH + 0.23 inches 147 89 Preventive Maintenance 91 95 SCI at TSH - 0.04 inches 147 95 Preventive Maintenance i

88 96 MCI at TSH + 0.00 inches 89 97 SCI at TSH - 0.04 inches 99 99 SCI at TSH - 0.11 inches 78 100 SCI at TSH - 0.13 inches 126 100 Preventive Maintenance 50 108 SCI at TSH + 0.06 inches 40 112 MCI at TSH + 0.0 inches 77 159 91% Indication at TEH + 19.29 inches