ML20065C918
| ML20065C918 | |
| Person / Time | |
|---|---|
| Site: | Grand Gulf |
| Issue date: | 09/15/1982 |
| From: | Mcgaughy J MISSISSIPPI POWER & LIGHT CO. |
| To: | James O'Reilly NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| References | |
| 10CFR-050.55E, 10CFR-50.55E, AECM-82-2-001, AECM-82-2-1, NUDOCS 8209240341 | |
| Download: ML20065C918 (2) | |
Text
~,,
,e MISSISSIPPI POWER & LIGHT COMPANY Helping Build Mississippi P. O. B O X 164 0, J A C K S O N, MIS SIS SIP PI 3 9 2 05 September 15,19$M
_g JAMES P. McGAUGHY, JR A5SinfANT v1CE Ps4ES# DENT
(/)
v.
m p
Of fice of Inspection & Enforcement M
U. S. Nuclear Regulatory Commission
}g Region II got
- 9 101 Marietta Street, N.W.
Suite 3100
- y Atlanta, Georgia 30303 3
Attention:
Mr. J. P. O'Reilly, Regional Administrator Dea r Mr. O'Reilly:
i
SUBJECT:
Grand Gulf Nuclear Station Unit 2 Docket No. 50-417 License No. NPF-13 File 0260/15525/15526 PRD-82/28, Final Report Unit 2, Hille r Actuators AECM-82/2-001 Ref e rence: AECM-82/274, 6/11/82 On May 12, 1982, Mississippi Power & Light Company notified Mr. F. S.
Cantrell, of your office, of a Potentially Reportable Deficiency (PRD) at the Grand Gulf Nuclear Station (GGNS) construction site.
The deficiency concerns the failure of drywell, containment, and secondary containment isolation valves to close on a loss of air.
This deficiency is reportable under the provisions of 10CFR21 and 10CFR50.55(e) for Unit I and 10CFR50.55(e) for Unit 2.
All applicable information was given in our previous report.
It also stated that corrective actions for Unit I would be completed by August 1, 1982. These have not been completed at this time but will be prior to exceeding 5% power.
Our Architect / Engineer has issued Non-Conformance Report (NCR) 6418 to track l
corrective actions for Unit 2.
All corrective actions should be complete prior to Unit 2 fuel load.
l l
Yours truly,
/'
i
/
(A-l<
sf
.~
y KDS:dr cc:
See page 2 l
l 8209240341 820915 PDR ADOCK 05000417
, I POk".N. )
~~
S pon Member Middle South Utilities System l--6' J2_
.s.
o.
Mr. J. P. O'Reilly AECM-82/2-001 NRC Page 2 cc:
Mr. N. L. Stampley Mr. R. B. McGehee Mr. T. B. Conner Mr. Richard C. DeYoung, Director Office of Inspection & Enforcement U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Mr. G. B. Taylor South Mias. Electric Power Association P. O. Box 1589 llattiesburg, MS 39401