ML20064D977
| ML20064D977 | |
| Person / Time | |
|---|---|
| Site: | Fort Calhoun |
| Issue date: | 11/19/1982 |
| From: | William Jones OMAHA PUBLIC POWER DISTRICT |
| To: | Seidle W NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| Shared Package | |
| ML20064D948 | List: |
| References | |
| LIC-82-368, NUDOCS 8301040802 | |
| Download: ML20064D977 (2) | |
Text
~
t O
Omaha Public Power District 1623 HARNEY a OMAHA, NEBRASMA 68102 E TELEPHONE 536-4000 AREA CODE 402 November 19, 1982 LIC-82-368 Mr. W. C. Seidle, Chief Reactor Project Branch 2 U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, suite 1000 Arlington, Texas 76011
Reference:
Docket No. 50-285
Dear Mr. Seidle:
Completion Schedule for the Fort Calhoun Station Drawing Update Effort Omaha Public Pcwer District responded to IE Inspection Report 81-15 by letter dated August 27, 1981.
Specifically, the District's response to Unresolved Item 8115-04 provided our plan for eliminating the Fort Calhoun Station drawing updating backlog by December 31, 1983.
The purpose of this letter.is to provide the Commission with a status of the work completed to date and to update the expected completion schedule.
Since August, 1981, the District has made significant progress toward meeting the goal of updating all Fort Calhoun Station drawings to I
an "as-buil t" condi tion. A Document Update Team (DUT), consisting of six personnel experienced in nuclear power generation, has been formed to provide a dedicated, systematic approach for completing this task.
To date, the DUT has expended several thousands of hours in reviewing l
modification documentation, investigating and field verifying modifi-cation packages, and marking applicable drawings to reflect the present plant condition. These marked-up drawings are then sent to an engi-neering draf ting group, which has significantly increased staffing for this effort, for final updating.
Utilizing this approach has proven to be very effective, but the total time required to complete a modifi-cation package has proven to be greater than anticipated. Upon realizing this trend, the District decided to revise our drawing updating approach and implement the following actions:
(1) The DUT staffing will be increased by adding three more full-time designers / engineers and one part-time engineer.
(2) The DUT will review as many of the remaining modification packages as possible between now and the 1983 refueling outage to identify those modifications that require field verifications in areas that are normally inaccessible during 8301040802 821229 PDR ADOCK 05000285 P.
Mr. W. C. Seidle LIC-82-368 Page Two power operation. Scheduling and completion of these field checks can then be completed during the upcoming 1983 re-fueling outage.
Inaccessible modifications that require further verification or are not field checked during the 1983 outage will be verified during the 1984 refueling outage.
(3)
During the review of the modification packages detailed above, the District will also identify those modifications that impact overall plant safety (e.g., fire protection and safety-related system modifications).
The verification and inclusion of these modifications in the Fort Calhoun Station drawings will then be given the highest priority, since these changes have the most significance.
The District will continue to allocate the necessary resources for completing this drawing effort in a timely manner.
Progress has been achieved in this large task, but the District estimates two refueling outages will be required to ensure all inaccessible modifications are field checked and walked down as necessary.
Based on a schedule that necessitates two refueling outages for completion, the District now expects to complete the drawing update effort two months after com-pletion of the 1984 refueling outage, which is tentatively scheduled during the spring of 1984.
Until all Fort Calhoun Station drawings are completely updated in 1984, Standing Order G-47, " Control Room Drawings", provides an interini measure to ensure control room P&ID's and electro-mechanical drawings 0
utilized by plant operators are maintained current and identify all design changes to systems and equipment resulting from plant modifi-cations.
Additionally, the revised program approach detailed above will ensure the most important drawing revisions are completed first.
Sincerely,
\\,/hy\\t/d
?
' v i.,/
6 W. C. Jones Division flanager Production Operations WCJ/TLP:jmm cc:
LeBoeuf, Lamb, Leiby & flacRae 1333 New Hampshire Avenue, N.W.
Washington, D.C.
20036 Mr. L. A. Yandell, NRC Senior Resident Inspector
m-m+
1-r-g 9-r---
#